Sec 1
Sec 1
Section - 1
Technical Specification
D01d Setp.2020
TABLE OF CONTENTS
ELECTRICAL SPECIFICATION
1.0 SCOPE
3.1 General
3.3 3.3
3.14 Interface
3.19 Nameplates
3.20 Grounding
3.21 Accessories
3.22 Drawings
5.0 TESTS
3.1 General
3.4
3.10
PART 4:
5.1 General
5.4Antenna
5.5 Tower
PART 5: 33/0.416kV Auxiliary transformer
PART6:
6.1 General
6.2 48VSystem
6.3 Deleted
PART 7:
PART 8 : Cables
9. 1 General
10.1 General
10.4 Sitetest
Civil Specification
1. General
1.1.5
1.1.6
1.1.7
1.1.8
1.2
1.2.1 General
1.2.3 Stripping of
1.3.1 General
1.3.2Excavation
for Foundation
1.3.3
1.3.4
1.4.1 Materials
1.4.2 Workmanship
7
1.5.1 General
1.8 Concrete
1.8.2
1.8.11
1.8.13 Admixtures
1.8.14 Plant
1.8.17 Workability
1.8.18
1.8.19 Placing
8
1.8.20
1.8.21 Vibrators
1.8.22
1.8.23
1.8.24
1.8.25 Curing
1.8.36 Reinforcement
1.8.39
1.10.1 General
9
1.10.3 Gates
2. Architectural Works
2.1 General
2.3 Materials
2.4 Signage
2.5 Masonry
2.7 Roofing
2.14 Carpentry
2.17
2.18 Furnishings
3. Building Services
3.1 General:
10
3.5.1 General
3.5.4 Cables
3.5.6
3.7 n
3.8.1 General
3.8.6
3.9.1 General
3.9.2 Scope of Supply and Services
3.9.3 Equipment Requirements
3.10 Building Arrangements
3.11 Plumbing Services
3.11.1 General
3.11.3
3.11.5
3.123.12
3.13.1 Conditioning
11
3.13.2 ,
3.13.4
3.13.1 General
3.14.6 Training
3.14.7 Documentation
12
ELECTRICAL SPECIFICATION
1.0 SCOPE
This MOE Specification specifies the minimum technical requirements for design,
engineering, manufacture, inspection, testing and performance of Metal-enclosed Gas
Insulated Medium Voltage Switchgear with 33 kv equipment intended to be used in the
system of the MOE ,IRAQ.
The contract shall include all works and materials needed in each substation in accordance
with the contract and shall include but not limited to the following:
o Earthing system
o Recommended spare parts( Optional Work, will be supplied upon Owner request).
13
2.0 APPLICABLE CODES AND STANDARDS
The latest revision/amendments of the following Codes and Standards shall be applicable for the
equipment/material:
2.7 IEC 60073 Basic and safety principles for man-machine interface, marking
and identification-coding principles for Indication Devices and
Actuators
2.8 IEC 60112
2.11 IEC 60480 Guidelines for the checking and treatment of Sulphur
Hexafluoride(SF6)
14
2.13 IEC60947-1 Low-voltage Switchgear and Control gear – General rules
2.16 IEC62271-100 High-voltage Switchgear and Control gear Part 100: High-
voltage alternating-current circuit-breakers IEC 62271-101
High-voltage Switchgear and Control gear-Synthetic
Testing
3.1 General
The switchgear shall be natural cooled SF6 gas insulated metal-enclosed type with
modular design for indoor service and shall be of manufacturer's standard design
which meets or exceeds the requirements of this Specification in all respects.
3.2 :
The service and climatic conditions under which all equipment are required to
operate satisfactorily are as follows:
15
No. Item Description Specificatio
n
Maximum outdoor peak- in
shade(for +55 °C
Level
5 Barometric Yearly average 0.101 MPa
pressure
Rain fall (Annual Maximum 500 mm
6 Minimum 50 mm
Total Rainfall) Maximum in one day 72 mm
Yearly average 150.8 mm
Sand and Average number of dust storms 21.5
7
Thunder Average number of thunder 15
Storms
16
3.3 Raying
400V
No. Item 33kV system system
1. Rated voltage 36 kV 440V
400V
2. Nominal voltage 33kV ±10%
3. Number of phases 3 3
4. Frequency 50Hz 50Hz
Impulse with stand
5. voltage
for bushing 170kV N.A
for winding 170kV N.A
for neutral 170kV N.A
Power frequency
withstands test voltage
6. (for 1 min.)
for bushing 70kV 3kV
for winding 70kV 3kV
for neutral 70kV 3kV
7. Rated breaking capacity 25 kA 35kA
8. Short time current 25kA/3 sec 35kA/1 sec
Rated voltage and nominal discharge current of lightning arresters
On phases N.A
9. On neutral N.A
Minimum creepage
12. distance of insulator and N.A
bushing
Earthed
through
Zigzag
transformer 4 wire
13. located at with
Earthing system remote neutral
132/33kV solidly
Substation earthed
to limit the
earth fault
current to
1000A.
3.3.2
in the Data Schedule.3.3.3 All equipment and components of the switchgear including bus
17
support insulators shall be free of partial discharges when operated at rated voltage.
3.3.4 . Degree of
Protection to all SF6 gas enclosed compartments shall be IP65 and for all air insulated
compartments it shall be IP4X as per IEC 60529.
3.3.6 Each switchgear panel shall be provided with hinged front door(s) with lock(s). Rear
shall be with hinged door fastened with bolts instead of lock(s) or removable bolted panel
cover. Cable compartment front access shall be with door and lock or bolted removable panel
cover.
3.3.7 The cable compartment enclosure design shall allow clear access to the cable termination
compartment. The entry of primary cables to the enclosure shall be from the rear bottom of
the switchgear. Adequate clearance shall be provided to permit high voltage testing of
the complete installation and of individual cables.
3.3.8
caused by the internal fault in the switchgear, the hot gas or vapor produced by internal arc
shall not endanger the switchgear operators and shall not enter into adjacent panels thereby
preventing spreading of the fault. If required, integrated arc duct shall be provided to direct
gas/vapor away from operators and prevent solid particles from uncontrolled spreading.
The pressure surge shall be cooled in the absorber before its release into the switchgear room.
3.3.9 All ventilation louvers shall be vermin -proof and shall be provided with filter to
minimize ingress of dust.
3.4.1 The switchgear assembly shall be of single bus bar type and suitable for extension at both ends
without cutting and drilling. Welding is also prohibited for field assembly of the cubicles. It
shall be possible to dismantle and remove any middle panel from the switchgear line-up
without dismantling/removing the adjacent switchgear panel.
3.4.2 Each switchgear feeder panel shall consist of bus bar, disconnector, earthing switch, circuit
breaker, current transformer, voltage transformer (if specified), cable compartment, low
voltage compartment with control devices, protection devices as per the protection
requirement and gas monitoring system.
3.4.3 Bus bar, circuit breaker, disconnector and earthing switch shall be
sf6 Each element shall be in independent modules
(Independent compartment) and safe to touch and fully ensure operational security and
personnel safety under all normal and fault conditions. Combination of disconnector and
earthing switch (3-position switch) in one module or busbar, disconnect and earthing switch
in one module shall also be considered Gas
compartments other than specified above may be accepted if the manufacturer proves with
adequate documents that the equipment have superior quality, equivalent or better electrical
18
and mechanical properties in comparison with the other design. The switchgear design shall
have proven that the design will withstand the service conditions of IRAQ Distribution
system as stipulated in specification.
3.4.4 Current transformer and voltage transformer are installed outside the gas zone.
3.4.5 Circuit breaker, disconnector and grounding switches shall be operated from the front of the
panel and shall be accessed from outside of enclosure.
3.4.6 Doors and panels shall have sufficient thickness and rigid to support devices, and doors
shall be easy to open and close.
3.4.7 The door of the low voltage compartment shall have a door stopper to hold the door in the
“open” position.
3.4.8 The switchgear enclosure and the internal barriers shall be adequately rigid and able to
withstand short circuit stresses and arc-proof tests as per IEC 62271-200 of identical switchgear
units.
3.5.1 The main bus conductors and connections shall be made of electrolytic grad copper.
Vertical sections (tee-off droppers) shall be connected to the main busbar by means of sub-
busbar. Interconnection of main busbars in each switchgear panel shall be plug-in type or
equivalent means for easy installation.
3.5.2 Bus bars shall be single phase enclosure with independent SF6 gas insulated module with
provision for extending at either end without the need for cutting or drilling the copper bar.
3.5.3 Provision shall be made to allow the thermal expansion of the busbar conductors due to
normal load current and short circuit currents.
3.5.4 The bus bar and its connections shall be able to withstand the mechanical stresses under
the specified short circuit conditions.
3.6.1 Power circuit breakers shall be single throw, vacuum type fixed and suitable for local and
remote control. The circuit breakers shall comply with IEC 62271-100 or ANSIC37.06.
3.6.3 The circuit breaker shall be single pole or three pole and designed for simultaneous three
(3) poleoperation.
3.6.4 Live parts of circuit breaker shall be in SF6 gas compartment and operating mechanism
shall be accessible from outside the gascompartment.
3.6.5 The circuit breaker operating sequence (operating duty cycle) shall be O-0.3s-CO- 15s-CO
19
as per data schedule.
3.6.6 The operating mechanism shall be of the motor-charged spring-operated stored energy
type suitable for rapid/fast auto-reclosing of the circuit breaker.
3.6.7 The operating mechanism shall employ a 48V DC motor to charge the closing
spring(s) that retains this stored energy until a closing operation is made. The motor shall
operate satisfactorily at voltage ranges between 40V DC and 60 V DC. The energy
storage capability of the mechanism must be sufficient for an O-CO operation at rated
short circuit current or at related required capabilities specified in Data Schedule.
Recharging of closing spring shall occur automatically as soon as the closing spring is
released.
3.6.8 Means for manual spring charging shall be provided with the circuit breaker both in the
"Open" and "Closed" positions. The spring charging motor DC circuit shall be
automatically cut off during manual charging or suitable means of protection shall be
provided to the manual charging mechanism to ensure the safety of operator during the
restoration of power supply.
3.6.9 The operating mechanism shall be electrically and mechanically "trip free". Anti- pump
features shall be provided.
3.6.10 each circuit breaker shall be provided with one (1) closing coil and one (1) electrically trip
coils.
3.6.11 The control power supply to trip and closing coil circuits shall be provided with isolating
switch. One auxiliary contact of this switch shall be wired to alarm when the switch is in
open position. Both positive and negative poles of the close coil shall be switched.
3.6.12 Circuit breakers shall be designed so that they cannot be closed unless the closing spring
is fullycharged.
3.6.13 Each circuit breaker shall be provided with a visible mechanical position indicating
device. The device shall be positively driven in both directions to show whether the
breaker is in the "open" or "closed" position and shall be identified with color coding
"Green" and "Red", respectively with white lettering. Similar positively driven indicating
device shall be provided to indicate the state of the spring. It shall indicate "SPRING
CHARGED" when the spring is in a condition to close the breaker and "SPRING
DISCHARGED" when the spring is not in a condition to close the breaker.
3.6.14 The circuit-breaker and its operating mechanism have to perform the number of
breaking operations at rated current and at rated short-circuit current without
maintenance per relevant IEC or ANSI standards. Each circuit breaker shall have a
mechanical 5-digit operation counter which is not possible to reset and shall be
readable from the front of the switchgear.
3.6.15 Each breaker shall be provided with minimum „four NO‟ and „four NC‟ potential-free
auxiliary contacts, mounted on the breaker for remote interlocking service. In addition
„four spare NO‟ and „four spare NC‟ contacts shall be provided on each breaker for use
onSER (Sequence of Events Recorder) and SCADA. Minimum contact rating shall be 10
A at 48 V dc. Contact surfaces shall be of a metal, which is not subject to oxidization
leading to an increase in contact resistance. They shall be mounted so as to be readily
accessible for maintenance and designed to facilitate inspection, cleaning and
adjustment.
20
3.6.16 Thenumberofoperation for circuit breaker shall be 10000 for incomer and 20000 for
outgoing feeder.
3.7.2 The disconnector and grounding/earthing switches shall be three (3) pole gang operated,
no-load break and single stroke type, shall generally comply with the requirement of
IEC62271-102.
3.7.3 Live parts of disconnector and grounding/earthing switch shall be in SF6 gas
compartment and operating mechanism shall be accessible from outside the gas compartment.
3.7.4 Disconnector shall be of class “M2” minimum and grounding/earthing switch of class “E2”
minimum as per IEC62271-102.
3.7.6 The spring charging motor DC circuit shall be automatically cut off during
recharging or suitable means of protection shall be provided to the manual operating
mechanism to ensure the safety of operator during the restoration of power supply. Once
initiated, the motor mechanism shall complete an open or close operation without requiring
the initiating contact to be held closed.
3.7.7 Motor operated Disconnector/earthing switch shall have manual operation facility.
3.7.8 -reflex
type insulated rod.
3.7.9 Grounding switch shall be with manual/motor drive having full short circuit fault making
capability.
3.7.10Disconnector and grounding/earthing switches shall have mechanical position indicator for
the main contact open and closed position, directly coupled to the driving shaft. The marking
shall be in white letters as “Open” or “O” on a green background and “Closed” or “C” on a
red background. Position indication shall be visible without the need to open switchgear
compartment doors.
3.7.11Disconnector and grounding switches shall be provided with pad-locking facilities to permit
locking both in open and closedpositions.
3.7.12Integral grounding switches shall be provided for incoming and outgoing feeders and bus
bars. Grounding/earthing switch and disconnector switch shall be provided on both sides of
bus-section circuitbreaker.
3.8.2 /termination shall be done by cable socket and plug. The terminations shall
be suitable for copper.
3.8.3 Cable size up to 400 mm2 shall be able to terminate in the cable box. Provision shall be
made for connection of two or more cables per phase as per circuit capacity (viz. incomer,
feeder, etc.).
3.8.4
primary injection with bus bar live are to be provided.
3.8.5 The height of the plug-in connection point shall be minimum 700 mm from cable box bottom
plate for clear access for cable installation and cable testing.
3.8.6 -
magnetic material. The bottom plate for outgoing feeder panels shall be of two pieces with
holes drilled for entry of cable. The bottom plate for incoming and station service
transformer panels shall be of a simple piece without any holesdrilled.
3.8.7 Incoming / outgoing cable support and clamps, earthing busbar and fixing facility for other
accessories such as Voltage Transformer, current Transformer & lightning arrester shall be
provided in the cable compartment.
a. The mechanical and thermal current ratings of CTs shall be coordinated with the
momentary and short circuit current of the associated circuit breaker, respectively.
b. Switchgear shall be delivered with all CT secondary windings shorted out. All CT
secondary leads shall be wired out to terminal blocks. The secondary windings of each CT
shall be rated as specified in Data Schedule and shall be connected to the ground bus by
a direct copper connection, via a removable link at one point only.
c. Relaying and metering accuracy class for standard burdens shall be as specified in Data
Schedule.
d. Primary and secondary terminals and polarity shall be marked per applicable standards.
22
a. Voltage transformers (VTs) shall be of standard three (3)-winding type for the voltage class
of the switchgear and shall have voltage marked. They shall have a voltage factor of 1.2
1.9 for 8 hours, ratio and accuracy class for standard burden as specified in
Data Schedule.
d. VTs shall have two (2) secondary windings. Secondary circuits of all VTs shall be
protected by miniature circuit breakers (MCB). MCB's shall have auxiliary contacts for
alarm indication. All secondary leads shall be terminated in the terminal blocks in low
voltage ecompartment.
e. Provisions shall be made for disconnecting the secondary circuit of VT when the primary
circuit is disconnected. Provision shall also be made for momentary grounding of the
primary winding during the disconnecting operation to remove any residual charges
from the windings.
3.10 SF6 Gas system Requirements
3.10.3 The switchgear module/compartment shall be fully gas tight. The sealing system shall
ensure effective protection against ingress of moisture, dust and other contaminants into gas
compartments. All gas compartments shall contain suitable agentto absorb moisture and any
other decomposition products of SF6 gas.
3.10.4 Each compartment shall be provided with safety devices (bursting disc) activated by
overpressure.
3.10.5 the Relative Leakage rate of SF6 gas in each gas compartment shall not exceed 0.5% per year.
3.10.6 The GIS enclosure shall be sectionalized for each equipment into modular units or
compartments, separated by solid gas barriers with an effective sealing system. Each gas
compartment shall be provided with self-closing non-return valves for sampling and
testing, sampling and testing ,evacuation and refilling of SF6 gas without evacuation another
section or loss of gas. Preferably busbar shall be segregated for each panel.
3.10.7 Gas barrier and sealing system shall have adequate mechanical strength to withstand the
dynamics forces caused by short circuits and effects of internal arc faults as well as maximum
pressure differential that could exist between adjoining compartments.
23
3.10.8 SF6 gas in each individual compartment shall be monitored by suitable temperature-
compensated pressure gauges (gas-density continuous monitoring) switches/relays to
monitor the loss of SF6 gas. The dial of the pressure gauges shall be graduated to read
pressures and colored green, yellow and red to indicate normal, Alarm Stage 1 (non-urgent)
and Alarm Stage II (urgent) pressure conditions respectively. The gas- density monitors shall
be capable of being calibrated with the monitored equipment in service. The indicator shall
be visible and readable from finished ground level. Each pressure switch shall be provided
with two convertible potential-free auxiliary contacts for two-stage alarm initiation. The
alarm contacts shall be wired to the annunciator. It shall be possible to test and replace each
pressure gauge and the density switch/relay with the GIS in service.
3.10.9 At each gas compartment, provisions shall be made for connecting moisture measurement
instrument and the gas service cart. The moisture content in the gas shall not exceed 150
ppmv (parts per million per volume) in circuit breakers and 250 ppmv in other
equipment. Provision for disconnection of gas pipelines shall be incorporated. 100µm or
smaller sintered stainless steel particles filter disk, suitable for pressure involved shall be
installed at the gas serviceconnection.
3.10.10 All piping for SF6 gas and its fittings shall be made of copper, brass or stainlesssteel.
3.10.11 A colored diagram with legends showing various gas compartments, monitoring system
etc. together with normal and alarms ranges shall be mounted on the switchgear.
a. The initial complete filling of SF6 gas for the assembly, if required and in addition, any
gas lost during installation and commissioning procedures.
The Low voltage compartment of the switchgear shall be provided, as applicable, with the
following:
1. One (1) Local/Remote selector switch. Provision shall be made for locking the switch in
eitherposition.
2. One (1) circuit breaker control switch. The switch shall have three position (trip- normal-
close) with a spring return to normal and padlocking facility in the normal position. The control
switch shall follow the convention of closing the circuit breaker in the clockwisedirection.
3. Indicator lights shall be LED type to indicate the breaker status asfollows:
24
-Red: breaker closed, one for each trip coil adjacent to the control switch
-Green: breaker open, one for closing coil adjacent to the control switch
For outgoing and station service feeder panels only, the red and green lights shall be wired in
series with the trip and close coils, respectively to supervise the status of each coil. For incomers and bus
tie breakers, the red and green light indications shall be achieved through the breaker auxiliary switches.
The healthiness of the breaker trip coils shall be monitored via the trip circuit supervision relays which are
located in the control room.
4. One (1) 230 Vac LED light. the light shall be controlled by toggle and door switch . switch shall
be identified with engraved or embossednameplate
7. Lot, Nameplates
8. Lot, Relays and Relay manufacturer's test blocks. SCADA Interposing Relays for Trip and Close.
10. Indication lamps in addition to specified shall be provided on the front of transformer and
feeder panels and connected through capacitor voltage dividers to monitor thecable circuits
dead or live.
3.12 Relays, Meters and Instruments
3.12.1 Relays, meters and instruments shall be located in a low voltage compartment of the same
feeder breaker panel while for the other breaker panels, they shall be installed in separate relay
and control panels, outgoing
3.12.2 All protective relays shall be mounted in racks. If relays cannot be rack mounted they may be
flushmounted.
3.12.3 Target indicators shall be provided on all relays performing protective or tripping functions.
Relay contacts shall beself-aligning.
3.12.4 All meters shall be switchboard fixed-type and flush or semi-flush mounted. Accuracy class
of all digital meters shall be 0.2 per IEC Accuracy class of all revenue meters shall be 0.2.
3.12.5 Themetersshallbefittedwithdustandmoistureproofcoversandshallhavenon- .
Analog meters shall have 240°scale and dimensions 96 x96mm.
3.12.6 Meters, instruments and indicating type transducers shall have test facilities separate from
protective relays, so that testing and calibration can be done without equipmentoutages.
3.12.7 Upper edge of protective relays and meters shall be no higher than 2.2m to allow convenient
maintenance, inspection, target reset, and testing from groundlevel.
3.12.8 All accessories such as DC/DC converters and transducers shall be located inside the panel.
3.12.9 For outgoing and station service feeder panels, each indicating light shall have a current
25
limiting resistor to facilitate replacing the bulb without activating the respective trip/close coil.
The rating of the resistor shall be selected to provide adequate illumination of the lamp at
normal operating conditions. Shorting of the lamp terminals shall not damage the resistor itself
or blow the control circuit fuses (or trip the control circuit MCBs) considering that maximum
DC control voltage is limited to 110% of its nominal rating this shall be met by restricting the
current passing through , the trip coil to less than 25% of its minimum pick-up current.
3.12.10 The trip, close and spring charge circuit MCBs shall be located at the switchgear in the LV
compartment.
3.12.11 All switchgear MCBs shall have normally open auxiliary contacts. Each breaker shall have
its MCB contacts connected in series with the TripCircuit1 located on that breaker.
Any MCB operation shall de-energize the breaker DC supervision relay and provide analarm.
3.12.12 In substations, with Substation Automation IEDs shall be installed in the LV compartment.
Control and Protection requirements, Communication protocol etc. shall be as per relevant
Material specification, IECstandards.
3.12.13 33kVlow
voltage compartment, the effective protection equipment for each circuit should be as
indicated at the Single Line Diagram.
Note: The protection setting parameter should be fully separated from the SCS setting program system .
The Over Current and Earth Fault relays shall be from the numerical inverse definite minimum
(I.D.M.T.L) in the accordance with IEC 60225-151, Current / Time characteristics of all relays
shall cover the normal inverse, long inverse, very inverse, extremely inverse, instantaneous and
definite time characteristics. Cable sealing boxes and/or glands shall besupplied.
Auxiliary wiring, Relays, IED for RTU or SCS, port to region DCC, control switches, alarm lamps
and indicating instruments shall be provided with the switchboard.
Means shall be provided to continuously supervise the integrity of the circuit breaker tripping
circuits and to give alarm in case of having any fault in this circuit.
All protection systems shall be provided with an integral local operator interface facility to enable
communication with the relay without the use of external equipment. Any facilities provided for
connection to an external computer shall be an additional feature to the local operatorinterface.
Load shedding devices shall trip outgoing feeders if frequency of system falls under 50Hz. The protection
consists of definite time lag under frequency relay, with at least four independent
45- 50Hz in 0.1Hz step, with time lag of 0-5 sec. of precision
electronic type relay. The relays should be connected to voltage transformer section of 33kV busbars.
Four Independent load shedding busbars corresponding to each “ stage 1”, “stage 2”, “stage 3” and “stage
4” shall be provided to send tripping pulses to all circuit breakers of feeders connected to the respective
busbar of the stage. The outgoing feeders shall be provided with a selector switch in the tripping circuit of
each circuit breaker to permit to put the load shedding out of service for that respective circuit breaker.
26
When microprocessor based multi functional numerical protection relays are used, the protection of main
incoming feeder shall be provided two independent protection relays, i.e., a main protection relay and a
back-up protection relay which are each operated independently on a separate microprocessor.
Recommended setting of each protection relay shall be submitted for approval and contractor shall set
approved setting values into each relay at factory.All protection systems shall be provided with an
integral local operator interface facility to enable communication with the relay without the use of external
equipment. Any facilities provided for connection to an external computer shall be an additional feature to
the local operator interface
3.13 External Cabling
a. The cable entry shall be through the bottom plate of the cable box exactly below the
terminationpoint.
c. Terminal plugs for power cables shall be suitable for use with copper conductor
material.
a. All external control cables/wires shall be brought to the panel from the bottom, unless
otherwisespecified.
b. Control cables/wires shall enter the panel through suitable cable glands to prevent
contact with sharp metal edges. The gland-plate assembly shall be vermin proof.
3.14 Interface
Control wiring connections between stationary structure and removable element, if any, shall be
provided with self-coupling contacts or manual plug and receptacle for disconnection. The male contacts
shall be placed on the removable element while the female receptacles on the stationary structure.
Secondary isolating contacts shall be so positioned or designed to prevent the danger of electric shock
when disconnected.
3.15.1
to protect the equipment, operator and service personnel from the dangers of mal-
operation. CB, DS and ES shall be provided with adequate number of auxiliary contacts for
interlocking purposes without the use of contact multiplying relays.
3.15.2 Grounding switches shall be mechanically and electrically interlocked with associated
disconnect such that closing operation of grounding switch shall not be possible unless the
related disconnect is in openposition.
Bus bar grounding switch shall be interlocked with the incoming circuit breaker and bus
section breaker as well as with all outgoing breakers on the respective bus side, such that
27
losing operation of grounding switch shall not be possible unless all associated circuit
breakers and disconnectors are open and vice versa, the associated circuit breakers and
disconnectors closing operations shall not be possible unless the bus bar grounding
switch is open.
3.16 DC Control Power
Unless otherwise specified, the nominal DC control voltage for closing and tripping of all circuit breakers
shallbe48
at voltage ranges between 40 VDC and 60
ranges between 40 VDC and 60 VDC.
satisfactorily at voltage ranges between 40 V dc and 60 dc. Voltage dropping resistors shall not be used in
the trip coil and closing coil circuits.
DC circuits: Generally Grey (Trip circuits shall be provided with Red ferrule at the terminal block)
unless MOE specified.
VT circuits: Generally Red unless MOE specified (fitted with R, Y, Bsleeves). Alarm
circuits :Blue
1 Core; Black
1 Core; (Usage limited to grounding conductor) Green or Green with Yellow
stripes
3.17.3 All wiring shall be made without splices. - stranded flexible and
shall be terminated with size 1 hooked crimps or ring type terminals as applicable. Spade
type, pin type or boot lace type crimp terminals are not acceptable.
3.17.4
resistant. If a common termination is required between terminal blocks, preformed wire
jumpers or manufacture‟s own shorting bar can be used. Compatible end stops, end
plates, barriers and terminal block identifiers shall be used. Groups of
28
terminal blocks shall be identified using engraved labels. The comparative tracking index of
terminal blocks shall be at least 500 as per IEC 60112 or equivalent standard.
Each CT circuit shall be provided with a disconnect table ground link. Opening of the link
shall enable all CT and relay wiring to be tested clear of ground. There shall be only one
ground link per CT circuit.
The termination between the ground bus bar and the isolatable link shall be numbered C90
for Overcurrent CT, M90 for Metering CT.
CT terminals shall be grouped by function and then sub-grouped by phase. Each phase
shall be labeled by appropriate labels attached to the terminal blocks. Each complete CT
shall be identified by function and reference number. Where a CT has
, such as S1, S2, S3; the CT terminal block shall have four
(4) terminals: S1, S2, S3 and ground.
The shorting bar shall cover the four terminals of each phase. The bar shall be grounded
through the grounding terminal block. The other end of the bar shall be held by an
insulated screw.
Adjacent to the CT terminal blocks two end stops shall be located with an appropriate label
mounted between them. Each stop shall have formed holes that shall be used to store the
CT shorting screws.
3.17.7 All tapping of dual-ratio CTs shall be terminated at the terminal blocks which shall be
clearly marked to designate the CTs phase and ratio in use.
3.17.8 All VT circuits shall be provided with sliding link type terminal blocks to facilitate isolation
of VTs from the circuit to perform voltage injection tests. These terminal blocks shall be
clearly marked with phase, function, core number and ratio.
3.17.9 Not less than ten percent (10%) spare terminals shall be provided on each terminal block.
3.17.10
terminal blocks for future use. At least two (2) spare (1 NO + 1 NC) contacts of lockout
relay shall be wired to the terminal block for future use.
3.17.11 All wiring internal to the switchgear assembly shall be laid in accessible wiring troughs
throughout the entire length of the switchgear assembly. Internal wiring between the
breaker and the LV compartment shall be bundled and neatly formed. There shall be no
29
wiring run as single cores through grommets. The AC wiring shall be bundled separately
from DC wiring in the same raceway. Signaling cables shall be shielded type and run in a
separate raceway and shall be separated as far as practical from all LV power cables and at
right angle to such wiring when the spacing is less than 300mm.
3.17.12 Cable supports shall be provided for wiring run directly to instruments or devices. Wiring
extensions from raceways or bundles to instruments and devices shall be neatly formed,
securely tied or clamped and supported to the switchgear framework. Bends in the wiring
shall be carefully made in such a manner that the insulation is not damaged.
3.17.13 Wiring for lights, space heaters and convenience outlets may be run in the same raceway in
individual panels and in rigid or PVC jacketed flexible conduits between panels. Wiring of
meters/relays mounted on doors shall be mechanically protected.
3.18.2 Each device shall be permanently identified to correspond to the device identification
symbol utilized on the wiring diagrams. This identification shall be adjacent to the
terminals of the device. Standard relay device numbers shall be provided for protective
relays. For switchgears phase conductors when viewed from operating side, the phase
designation shall be R, Y, B from left to right, from front to back and from top to bottom. For
reinforced substations the three phases shall be designated as per the existing system.
3.19 Nameplates
3.19.1 Switchgear assembly shall also bear a nameplate permanently and legibly markedin
62271-200 or equivalent ANSI
Standards, plus the following additional information:
3.19.3 The nameplate for the switchgear assembly and the circuit breakers shall be made of
30
stainless steel of adequate size to indicate the function of the panel. The nameplate shall be
fastened by stainless steel screws or rivets. Other nameplates for CTs, VTs etc. may be made
of non-corrodible material rather thanPlastic.
3.20 Grounding
3.20.1 An un-insulated electrolytic copper grounding bus sized for the rated short circuit current
and running the entire length of the switchgear assembly shall be provided. Provision shall
be made for extending the ground bus at either end without the need for cutting or drilling
the copper bar.
3.20.2 Two (2) solder less type ground connectors shall be provided on the ground bus, one on
each end section of the bus. The ground connectors shall be suitable for a bare copper
ground conductor 120mm² thru240mm².
3.20.3 All hinged doors and panels shall be properly bonded by unspliced flexible wire or 10mm²
Cubraids.
3.21 Accessories
3.21.1
protective relay test set and portable test equipment for meters, and(2) laptop including
software and communication cable.
3.21.2 200A.
3.21.3 A suitable box or container shall be supplied for storage of test plugs.
3.21.4 Crank lever or equivalent device for manual charging of the spring-operated stored energy
closing mechanism of the circuit breaker, disconnector and earthing switch.
3.21.5 Any special tools required for circuit breaker maintenance and relay adjustments.
3.21.6 Gas handling devices such as:
31
• Earthing set (if required)
3.22 Drawings
Manufacturer shall at least provide the following drawings of size „A3‟ (minimum):
3.22.1 .
3.22.5 .
3.22.7 Component List of Switchgears with sub-supplier (make) and country of manufacture.
4.1 General
a) Switchgear shall be compact, simple for operation with highly secured performance.
b) Switchgearshallbesuitabletooperateatambienttemperaturevaryingfrom -10°Cto
55 °C, under dusty, dry climate out-door conditions as given in (01DMS-01)
c) Switchgear shall comply to the Specifications of MOE and relevant IEC Standards
The Manufacturer shall provide the following along with his bid proposal, in addition to
the requirements stipulated in the Purchase Order or Contract documents:
(b) Technical literature, brochures and list of users in the electric utility sector.
(c) Complete type test reports/certificates of all major equipment.
(d) A declaration from the Manufacturer that the bid proposal is in accordance with the technical
Specifications and associated MOE, material Standard Specifications. Otherwise the
Manufacturer must state clearly any exception or deviation items from MOE Standards, these
guideline Specifications and drawing plans and the reasons for exceptions or deviations.
The base design phase is a period of 4-6 weeks of preliminary design following the issue of
32
Purchase Order or award of Contract Six(6) MOE for
review and comments at the base design review meeting which will be held by the MOE four (4) weeks
after the receipt of the base design package.
c) Literature (specifications, manuals, brochures, drawings and completed Data Schedules) of the
following materials, as a minimum, but not limited to:
1) Switchgear.
2) Relays.
3) Instruments.
4) Control Panels.
5) CTs/PTs.
2) AC and DC auxiliary supply design with sizing of auxiliary transformer, batteries, chargers, etc.
following the base design phase, other detailed/manufacturer drawings shall be submitted by the
Manufacturer for approval by MOE. The list of detailed drawings to be submitted for approval shall be
mutually agreed to between the Manufacturer and MOE.
4.5
The Manufacturer shall submit to MOE, a monthly progress report on the manufacture of the
switchgear.
a) Design.
b) Procurement of Components.
33
c) Testing and Commissioning.
d) Overall Completion.
The format shall be mutually agreed to between the Manufacturer and MOE.
4.6
Factory Tests
1) General
Before any item of equipment is packed or delivered from the manufacturer's factory, all tests itemized
inClause3.13 to prove compliance
with the requirement of the Specifications. According to the Owner practice; qualified/well known
international third party inspector (or company) should witness all factory tests. This third party should
be hired by the Contractor after the approval of the Owner. The Owner may attend the factory acceptance
tests along with the international third party hired inspector. All tests shall be carried out in accordance
with IEC requirements and the approved test procedures.
All measuring, testing instruments and devices used for the testing of the equipment should be
accredited by a valid calibration certificate and issued from a well-recognized firm.
All results of tests shall be approved by Owner. In the event an additional test requested by the Owner or
its representative indicates Noncompliance with the terms of the Contract, the Contractor shall, at his own
expense, make all necessary repairs and perform additional test(s) required to ensure compliance with the
terms of the Contract.
Acceptance of shipment of the equipment after the satisfactory factory test shall be given from the Owner.
The Contractor shall provide Form of Release Note to the Owner for signature.
The approval of the tests, acceptance of the test certificates or waiving of witnessing tests by the Owner
shall not relieve the contractor from his contractual obligations
All costs and expenses associated with such tests and inspections shall be borne by the Contractor. 2)
The Contractor shall give access a e (3) Owner‟s staff and/or his
week excluding travelling days of major equipment at manufacturer's factory. All costs related to the
travelling (air tickets and transportations), residence, meals, pocket money and any other expenses are
deemed to be included.
34
(c) One (1) .
Routine, type and special tests shall be carried out in accordance with IEC 60076 for Transformers.
The Tender shall submit Type Test Report on same type and rating of switchgear to be applied for
this project in accordance with IEC 62271-200,IEC
A notification of the exact date, time and place of the test to be attended as well as all necessary
information shall be given to the Owner and/or his assigned representative in writing not later than four
(4) weeks prior to the date of the test.
The Contractor shall compile all factory test results, test certificates, type test records etc. into a test report
for each item of the equipment. The test report shall include sufficient information such as the subject of
the test, project name, contract number, document number and the test date. The factory test report shall
be countersigned by the independent third party and the owner witnessed the test. One (1) copy of the test
report or its draft shall be handed over to each person witnessing the test.
Four(4) execution of
each test. The delivery of the equipment shall be subject to Owner approval to the test reports.
After completion of all factory tests, the Contractor shall bind all test reports, test certificates, type test
records etc. properly into books of A4 format and submit four (4) sets of the bound factory test reports to
Owner in addition to two soft copies of the full factory test reports .
Rectification of Deficiencies
All deficiencies revealed during the tests shall be rectified by the Contractor under the approval of
the Owner. The components or parts to have been rectified shall bere-tested.
All costs and expenses for rectification and re-testing shall be borne by the Contractor. Tests at
the Site
The Contractor shall carry out the Site acceptance Test & Commissioning in the presence of the
Owner.
4.7. Training
The Contractor shall be required to train the Owner‟s staff at the factory during the contract period.
This is to enable the Owner‟s technicians and skilled personnel to gain skill and experience in the
techniques required for maintain the works. All costs associated with the training are deemed to be
included in the contract price.
35
(a) One (1) (8) membere of Remote Terminal Unit System (RTU) for two (1)weeks
Note: the breakdown for the coast of training each member should be mentioned in case of changing the
number of trainees during the contract negotiations
Upon com , the Manufacturer shall submit eight (8) sets of record books containing the
following documents as a minimum:
• Complete set of Manufacturer‟s drawings and catalogs with identified parts for each device and other
essential information for MOE cataloging and ordering replenishment parts
Note: All documents in item (d) shall be originals.
Manufacturer shall provide recommended spare parts list required for O & M of switchgear
without including as part of bid.
All equipment and materials under the contract shall be guaranteed for 18 months (and limited to
24 months maximum) (TOAC).TOAC
will be issued from Owner after completion of the inspection of all contractual equipment and installation
work for a complete and ready Substation for energization.
The warranty shall cover manufacturer's technical defects which might be caused from design, materials,
workmanship, installation and deviations from the latest IEC or EN (or BS & DIN) , and ITU- T, IEEE
standard.
It does not cover defects arising from the Owner‟s faulty maintenance or operation, or from alterations
carried out without the Contractor‟s consent in writing, or from repairs carried out improperly by Owner..
36
The Contractor shall be responsible for any loss or damage arising from careless packing or
protection up to the place of final destination. After completion of the inspection and tests at the factory
each item shall be packed for export shipment by using wood boxes.
The Contractor shall provide a clear means of identification for items concerning each individual
substation, and is requested to propose specific color to be painted on the upper corners of each package
in order to facilitate distinguishing the materials. Equipment and material items belonging to each
individual substation shall not be mixed with items belonging to other substations.
The method of packing shall be such as to protect all of the items against excessive corrosion or dampness,
and shall afford adequate protection against breakage or other injury, or loss due to breakage of cases or
crates from the time shipped at the factory until finally installed at the substation.
Each crate of package shall contain a packing list and the copies in triplicate shall be forwarded to the
Owner prior to delivery. All items of materials shall clearly be tabulated for easy identification on the
packing list.
All cases and packages shall be clearly marked on the outside to indicate the total weight, to show where
the weight is bearing and the correct position of the slings and shall bear an identification mark allocating
them to the appropriate shipping documents.
Cases or packages which cannot be marked as above shall have tags made of metal or other durable
materials with the necessary marking on them.
The shipping mark shall bear typically the following information in sequence and in a frame
commensurate with size of package:
Port of destination:
Dimension:
4.12 Delivery
4.12.1. General
The Contractor shall deliver all equipment and materials in such time to meet the contractual completion
date.
The Contractor shall notify the delivery information to the Owner and each notification shall include:
The Contractor shall at his responsibility inspect the cargo at site upon arrival and shall report in writing
the particulars, quantities, conditions, damages if any, of the delivered cargo to site. This
(7) . The Contractor is responsible to arrange all
needed equipment and labor for unloading, unpacking for detailed inspection at substation site.
4.12.2
The Contractor shall be responsible for inland transportation of equipment and materials from the
unloading port to designated substation site.
The Contractor shall furnish insurance for inland transportation to the site with some security guards, if
required. Such cost shall be included in the Contract Prices.
5.0 TESTS
5.1 All equipment shall be tested in accordance with the latest applicable IEC
a. All type tests prescribed in the applicable IEC Standards shall be performed on the first
unit of every new design, rating or size of the corresponding equipment to be supplied
to MOE, in accordance with the table below.
b. Arc-proof test shall also be performed on an identical switchgear panel including bus
bars and cable boxes in accordance with Annexure A of IEC62271-200.
c. Certified test reports of type tests performed on identical equipment acceptable to MOE
may be submitted for review and acceptance in lieu of the required type tests above.
5.1.2 ( ) Tests
a. All routine tests prescribed as per the compliance standard to the equipment (IEC
Standards) shall be performed on the corresponding equipment in accordance with the
table below and test reports shall be submitted for review and acceptance.
b. Routine test reports from original manufacturer of all circuit breakers, instrument
transformers, disconnect switch and grounding switches shall be submitted for review
anda cceptance.
5.1.3 The site test shall be performed on the gas insulated metal – enclosed equipment and it
component in accordance with relevant IEC recommendation & MOE commissioning Test
procedure.
38
Part 3: REMOTE TERMINAL UNIT
39
- General
All equipment supplied under this Specification shall conform to the latest editions of the
International Electro technical Commission (IEC) Specifications, ISO Standards, IEEE Standards,
International Telecommunications Union (ITU) Specifications and the General Technical
Specification. Equivalent national standards may be acceptable subject to approval by the
Employer.
RTU supplied should have a proven track record of satisfactory operation in similar
environments, proof of certification / registration by leading power utilities for use in their power
networks will be advantageous to the contractor during tender evaluation, The RTU shall include
the last updated protocols including (IEC 60870-5-103, Modbus (TCP/IP,Serial), Profibus, SPAbus,
DNP3 (TCP/IP, Serial), IEC 61850 hardware & software) for downstream communicate with IEDS,
and IEC 60870-5-101 and IEC 60870-5-104 for upstream communication with DCC.
In addition the required license for RTU (PLC/Archive, HMI)
3.1.1 Introduction
Remote Terminal Unit (RTU) Required to be installed in substation with last updated technology .
They are required together digital and analog input data representing various Substation states
and to send digital and analog input data to control various items of Substation. The RTU shall
transfer input data to, and receive output data from, the Master Station (MS) located at the DCC
via communication media, as part of the overall SCADA system. The Contractor shall be
responsible for the design, supply and installation , commissioning and integration with the
existing DCC, including all protocols ( IEC60870-5-103, Modbus (TCP/IP,Serial),,Profibus, SPAbus,
DNP3(TCP/IP,Serial),, IEC 61850 ,IEC60870-5-101,IEC60870-5-104) In additionthe required license
for RTU/SCS (PLC/Archive, HMI),and communications as required.
Itis essential that the Contractor carries out tests to demonstrate that the full SCADA facilities are
available over the communication interfaces and that the implementation of the standard protocols
at the existing DCC .
40
The standard RTU software shall be capable of supporting, but not be limited to, the following
basicfunctions:
a. Control functions commanded by the DCC ORRTU/HMI.
b. Alarm and event queue mechanism for DCC &RTU/ HMI interrogation of changes ofstatus.
c. The alarm queue reporting mechanism shall take high priority over the event queue reporting
mechanism.
d. Secure tele-command using the select/check/execute mechanism with OPEN , CLOSE ,
RASIE TAP position , LOWER TAP position , RESET alarm commandoutputs,Be
programmed to carry out specific functions (automation functions, interlock function,
switching functions).
f. Multiple RTU/HMI communication at different protocols and configurable baud rate, and
Communication with intelligent Elections Devices (IED).
g- Archiving facility must besupported.
h- support for future to connect with HMI System (Option).
The alarms shall be assigned with priority levels at the RTU and transmitted according to
priority or alternatively as soon as the alarms are received, whichever method is standard. The
standard method employed shall be fully described.
The occurrence of an alarm or an event shall be arranged for transmission to the RTU/HMI at
the earliest opportunity. Alarms or events occurring during a transmission of measurements
shall be arranged for insertion at the next convenient point in the message cycle. Further details
shall be provided describing the message cycles employed for methods where priority
assignments are implemented at the RTU (e.g. arranging multiple alarms with different
priorities). The RTU shall have the capability of automatic start-up and initialization following
restoration of power after an outage without need of RTU/HMI intervention.
The following clauses set out the functional requirements of the RTU.
3.1.3 DesignPrinciples
The RTU shall be designed to achieve a high level of availability, reliability and safety
in operation. The design shall be _fail safe_ such that failure of any component shall
result in all functions affected by the failure defaulting to a defined _safe_ state. It
shall be fault tolerant such that the failure of any single component within the overall
system shall not affect the ability of the remaining healthy components in the system
to continue to operate normally and for its functionality to remain available. Essential
functionality i.e. that required for the continued overall operation of the RTU shall be
tolerant to single component failures. This may be achieved, for example, by using
dual redundant hot/standby arrangements or by automatically re-distributing the
functionality over the remaining operational components so that loss of any one
component does not result in the loss of any functionality. The system shall
continuously monitor its own health and produce alarms for all detected failures.
These alarms shall become part of the Facility List of data to be returned to the MS
and, as far as possible, by lighting _fault_ warning LEDs on the affected equipment
itself, e.g. on individual circuit cards. There shall be no cases in which undetected
failures could occur anywhere within the overall RTU.
The equipment and the enclosures mounted in shall be designed to facilitate ease of
maintenance, particularly fault-finding and replacement of components, e.g.
replacement of rack mounted circuit cards as far as possible, and consistent with safe
operation, it shall be possible to _hot swap_ components such as I/O cards.
41
The equipment shall be robust, suitable for the operating environment in which it is
installed and require minimal maintenance. Each sub-system within the RTU shall be
designed to meet an overall availability of at least 99.98% based on a Mean Time To
Repair (MTTR) of 8 hours. The Contractor shall provide a Functional Design
Specification that will allow the Employer to review and approve the facilities being
provided in the RTU, and on which the testing documentation can bebaseHardware
The design of all RTU equipment shall be such as to ensure satisfactory operation in an
electrically hostile environment typical of high voltage electrical installations and Redundant (
double power Supply & Communication Main Unit option ).
The RTU proposed for this contract should have a proven track record of satisfactory operation
in similar environments. Proof of certification / registration by leading power utilities for use in
their power networks will be advantageous to the tender during tenderer evaluation.
The RTU shall comprise microprocessor based equipment with its software (firmware) resident
in non-volatile memory. It shall be readily possible to update the software (e.g. by PROM
replacement) to alter or extend the RTU functionality.
The equipment may be either of single board design or of rack mounted modular construction.
All computer equipment shall be supplied with a real-time multi-tasking operating system
which conforms to a recognized industry standard and not unique to one manufacturer.
Interconnecting cables shall be made via substantial, secure plugs and sockets, which shall be
mounted in accessible positions and clearlylabeled.
A technical description of each item of equipment, together with evidence to show that the
stated guaranteed reliability figures are supported by actual service conditions, shall be supplied
with theTender.
3.1.4 Software
The software shall be of modular construction, developed using structured design techniques
and written in a commonly used programming language. Where possible standard library
software shall be utilized. The contractor shall identify all standard proprietary software and
any software specially developed for this project.
The application software shall ensure the secure execution of RTU functions, and support to
Protocols IEC60870-5-103, Modbus (TCP/IP,Serial),Profibus, SPAbus, DNP3 (TCP/IP,Serial),,
IEC 61850 , IEC 60870-5- 101 and IEC60870-5-104 and PLC/Archive and HMI system included to
software techniques .
All software programs for RTU/HMI should be free license.
42
-The maximum system capacity and system loading shall not be less than 200% of the Specified
system capacity.
-In addition to the agreed Facility List, approximately 20% spare for each type of input/output
signals shall be provided within the contract . These spare facilities shall be fully fitted and pre-
wired.
-The design shall provide future expansion, modification and testing with the minimum of
disruption to existing facilities.
3.1.5 Performance
The RTU shall process all information required to be transmitted to the DCC & HMI and have
it available for transmitting within less than two seconds of any change occurring in Substation.
The RTU shall be capable of handling all alarms and status changes occurring during avalanche
conditions without loss of anydata.
3.1.6 Electrical andEnvironmental
The electrical and environmental conditions to be applied shall be those within the
associated power station or substation contract specification.
RTU cabinet shall support temperature sensor to detect temperature alarm connect to
digital input.
Environmental conditions:
-Temperature:-10 to 70ºc
-Relative humidity: 5……95% ( non condensing).
Each analog input shall be terminated with transient voltage protection components. In case of
overload, the input circuit shall not sustain any deterioration of its characteristics.
3.2.4 Pulseaccumulators
The RTU shall be capable of counting and storing the number of pulses generated by metering
equipment external to the RTU. The metering equipment will provide isolated normally open or
normally closed contacts. The pulse counter shall be incremented one count for each cycle of the
input (pulse) until the end of the configured metering period that count shall be stored. The
pulse counter shall be capable of accepting pulses at a rate of ten counts per second. The RTU
shall be capable of responding to commands (Freeze, Reset, Freeze and Reset) generated
internally within the RTU at a regular time, and shall support the use of external reset pulses for
accumulators, and the RTU shall be able to accumulate any (impulse) occurring while the
counter is being read it to avoid losing input counts.
The count shall be “frozen” (transferred to a buffer register) when commanded by the master
station or when commanded by locally generated contact inputs, also it can freeze and reset. The
RTU shall be capable of storing a series of accumulator values, in the even
of loss of communication to master station for a period not less than three days and
subsequently transmitting them upon request. The metering or counting period should be
configurable and possible to down load remotely a minimum count of 2 *24 (i.e. 24 bit binary
number) shall be capable of being held by the accumulator.
The Bidder shall describe his method for ensuring the value recorded at the master station(s)
corresponds precisely with the value indicated by the pulsing instrument.
Pulse counting inputs shall be provided as either a separate input module or using digital inputs.
3.3 TimeTagging
Certain status signals may be configured for local time tagging to be applied at the RTU.
These events shall be reported to the DCC/RTU with a time tag embedded in the message. RTU
shall have the capability to time tag events and alarms to a resolution of 1 ms or better. To
complement this feature, the RTU clocks shall be synchronized to enable system wide
comparisons to be made on the alarms and events recorded by different RTU s. The
synchronization shall be achieved by providing periodic time synchronization from the DCC to
all RTUs or, alternatively, directly from a GPSreceiver.
If the data link from the DCC to the RTU fails or GPS fail, the RTU shall continue to perform
time tagging from its internal clock until the data link is restored and the clock is corrected to
compensate for any time drift. The contractor should define the total drift time.
The Tenderer shall provide details of the following:
(a) Time tagging resolution at theRTU.
(b) Method of synchronizing the RTU's real time clock to the master clock from DCC or HMI in
case DCC communication fail to the RTU.
(c) Method of transmitting time tag information with event data to the master station. (d)Means
of selecting events for time tagging and the maximum number definable at eachRTU.
(e)Method of handling overflows of SOE data at the RTU.
45
3.4 Control Outputs:
General
The RTU shall generate signals to implement the commands issued by the DCC/HMI, such as
circuit breaker open/close, tap changer raise/lower, reset alarms etc. These signals shall be in
the form of pulses whose duration can be configured by commands from the DCC/HMI. The
period of the command pulse shall be configurable between 0.5 and 60 seconds to allow for
circuits with synchronizing facilities. The command timer shall reset immediately after the
command is executed or the synchronizing is cancelled.
To afford a high degree of command security against data corruption in the communication
systems, command outputs shall be designed to provide _select and execute_ operation.
The RTU shall be equipped with a control disable switch (Remote/Local) to disconnect power to
all digital output relays, and shall be wired to a contact input in the RTU to report status of
disable switch toSCADA.
Under normal operation, transformer tap changers will be controlled by automatic voltage
regulating (AVR) relays, at the substation.
When selected to supervisory control, it shall be possible for raise and low commands or RCO
set points to be issued to the tap changers from the DCC/RTU.
The raise and low commands shall not require an execute action by the operator (Two Step
command).
Feedback of command execution will be by an associated change in the indicated tap position etc.
The RTU shall perform checks to ascertain the integrity of its processor(s), memory and
input/output cards. The results of these checks shall be made available to the DCC on demand.
The checks shall include:
(a) A watchdog mechanism to isolate the processor from the output cards if the RTU ability to
drive outputs is compromised. The action of outputs when isolated by the watchdog shall be
selectable in sets of eight orless.
(b) A digital output connected (logically) to a digital input to confirm the integrity of digital input
and outputfunctions.
(c) An Analog output connected (logically) to an Analog input to confirm the integrity of Analog
input and outputfunctions.
A pre-settable input source shall be used where the RTU is not fitted with Analog output
facilities. The following conditions shall be included:
(a) RTU faulty - evidence fromwatchdog.
(b) Command output faulty - evidence from monitoring
circuit (c)Set point output faulty - evidence from
monitoringcircuit.
The detailed design of the communication arrangement shall be agreed with the Employer's
Representative before implementation.
(d)Input/output card faulty.
46
(e)Power supply faulty.
(f) RTU high temperature.
(g)VFT low receive level.
(h)RTU transmit buffer overflow.
(i)Where dual communication routes or duplicated modules are employed the RTU shall
annunciate failures to the master station.
(j) IED communication networkfail.
(k)Input signal faulty: The RTU shall be capable of detecting a faulty input signalthat
is changing state with an abnormally high frequency. Upon detection of a fault condition the
RTU shall suppress further reporting of the signal. The RTU shall automatically reinstate normal
reporting upon detection of clearance of the fault condition; this shall be accompanied by an
appropriate fault clearance message to the DCC.
The RTU shall be designed and equipped to communicate with the master station via the
available communication links either directly or indirectly. The Contractor is responsible for
providing all necessary equipment required to achieve such connections. Where available, the
Contractor shall provide direct digital links between the RTU and Master Station. Otherwise, the
Contractor shall provide communication equipment, as specified elsewhere in this specification.
RTU may have capability to support simultaneous communications with multiple independent
master stations (Tenderer shall put a separate price for such facility if that shall make a price
impact). The communication error at one master station shall not affect communications to other
master station. Assignment of communication protocols to master station shall be configurable
via software using RTU configurationsystem.
47
3.7.2 Interface with intelligent Elections Devices(IED)
Each RTU shall be capable to communicate with minimum 32 intelligent electronic devices
(IEDs). The communication interfaces provided shall conform to EIA RS 485.
Or EIA RS232 or Ethernet port, The baud rate of communication port(s) shall be configurable to
accommodate high data transmission.
- The RTU can acquire data from remote Intelligent Electronic Devices such as smart meters and
numerical protective relays in conjunction with conventional inputs/outputs (I/O)
-The RTU should have all necessary hardware / software to provide an optical interface , or any
serial interface to the IEDs and numerical protection relays, or through a serial communication
links. All necessary fiber optic cables, fiber optic modems, termination boxes, plastic pipes
needed to laid and installed into existing cable duct, as well as all works related to connection to
master slave RTU will be the contractor responsibility.
-RTU should have Annunciator Device for Transformers protection alarms.
The Contractor can provide suitable numeric devices which are implemented in a similar
environment to Iraq. The SCS can be combined with the protection system, as an Integrated
Protection and Control System. In this case, the following sections of the specification can be
treated as functional requirements that may be delivered in a different way.
The SCS shall be designed to achieve a high level of availability, reliability and safety in
operation.
The design shall be „fail safe‟ such that failure of any component shall result in all functions
affected by the failure defaulting to a defined „safe‟ state. It shall be fault tolerant such that the
failure of any single component within the overall system shall not affect the ability of the
remaining healthy components in the system to continue to operate normally and for its
functionality to remain available.
Essential functionality i.e. that required for the continued overall operation of the SCS shall be
tolerant to single component failures. This may be achieved, for example, by using dual
redundant hot/standby arrangements or by automatically re-distributing the functionality over
the remaining operational components so that loss of any one component does not result in the
loss of any functionality. The communication links between components within the overall SCS
48
shall be regarded as essential functionality and the SCS must continue to operate with full
functionality if any single communication link is out ofservice.
The system shall continuously monitor its own health and produce alarms for all detected
failures. These alarms shall be presented in the alarm lists on the operator workstation and, as
far as possible, by lighting „fault‟ warning LEDs on the affected equipment itself, e.g. on
individual circuit cards. There shall be no cases in which undetected failures could occur
anywhere within the overall SCS, including within the communication links between the
components of the system.
The equipment and the enclosures it is mounted in shall be designed to facilitate ease of
maintenance, particularly fault-finding and replacement of components, e.g. replacement of rack
mounted circuit cards. As far as possible, and consistent with safe operation, it shall be possible
to „Hot swap‟ components such as I/Ocards.
The equipment shall be robust, suitable for the operating environment in which it shall be
installed and requires minimalmaintenance.
Each sub-system within the SCS shall be designed to meet an overall availability of at least 99.98
per cent based on a Mean Time To Repair (MTTR) of 8 hours.
4.1.2 SystemArchitecture
The SCS shall be based on a distributed architecture complying with the relevant IEC
Standards. The proposed configuration of the equipment and the availability and security
provided by the proposed architecture shall be described fully in theTender.
The SCS shall typically comprise the following components:
•Master Control Unit (MCU).
•Bay Control Units (BCU).
•Operator Workstation.
• Local Area Network(LAN).
•Communication Links to Off Site Control Systems
SCS monitor and control shall be done from remote points, e.g. from operator workstation in the
substation control room and from remote SCADA system at DCC.
The SCS shall be located in the substation control room and shall be fed from an uninterruptible
power supply source to ensure continued operation following loss of main power supply.
The SCS shall be provided with, but not limited to the following details of facilities by the
Tenderer systemsubmission.
(a)Display of the substation single line diagram and individual feeder diagrams with status
Indication. (b)Indicate in the diagram substation status, voltages, currents, frequency,
together with power factor, active and reactive power flows. High/Low limit excursions of
measured shall be alarmed and programmable ( according to the point list ).
(c)Acquire, display substation events, individual feeder and substation equipment alarms with
date and timestamp
(d)Acquire status, with plausibility checks, of the circuit breakers, disconnections and earthing
switches.
(e) Be capable of performing sequential control functions, such as auto-reclosing of breakers,
taking feeders in/out of service, load shedding and loadcurtailment.
49
(f) Provide switch interlocking such that the operation of primary substation is prevented unless
specified conditions are met. Interlocking functionality shall be available at bay and substation
level. (The hard-wired interlocking scheme as specified shall also be provided and the SCS
Scheme shall provide an additional guard facility to ensure safe operation, based on the same
logic).
(g) Perform supervised operations (Close/Open) on circuit breakers, busbar and line
disconnections.
(h) Perform check synchronization functions. (The hard wired check synchronizing relays and
associated scheme as specified shall also be provided and the SCS scheme shall provide an
additional guard facility to prevent closing out ofsynchronism).
(j) Perform reporting of acquired data in user-defined formats (numerical and graphical logging)
Including data from tariff metering. This data shall also be suitable for transmission in text
format to another device for further dataprocessing.
(k) Read relay settings, measured values and evaluate stored data.
(m)Storage of process data in managed files for future use. (n)Resetting
of electrical trip lockoutrelays.
(p) Record station external ambient temperature and humidityperiodically.
(q) Receive and process commands from the DCC, process and transmit status, measurements
And alarms to the DCC. It shall be possible to generate summary data to send to the DCC
(r)Provide access security to both operational and administrative functions, separately, by
username and password.
(s)Be self-supervising, display its own system alarms and hardware status.
4.1.4 Commands
-All commands available at the substation in (SCS) shall be capable of being operated at the
DCC.
-All command sequences shall be performed using a select before execute routine.
-There shall be a maximum time out between the selection step and execution with the
command sequence being cancelled if the execution is not performed within that time. -Prior to
the execution of any command, the software shall perform a check to validate that the user has
the authority to execute the command. Authority violations shall be indicated to the operator via
a message on the VDU.
A „cancel‟ key and/or poke point shall be provided to allow termination of any command
sequence before it is executed.
50
4.1.5 Alarm and IndicationHandling
All alarms and indication changes annunciated in the SCS shall be treated in the same way i.e. as
an Event.
Two types of alarms shall be supported, these being fleeting and non-fleeting. The alarm
type shall be configurable on a point-by-pointbasis.
Two types of indication shall be supported, these being single point and double point.
Single point indications shall be used where no intermediate state needs to be
identified. The indication type shall be configurable on a point-by-point basis.
All events shall be brought to the attention of the operator. The operator shall have the facility to
accept events individually or as a page of events at a time
When an event occurs, the workstation audible alarm shall sound and the appropriate entries
shall be highlighted in the event list. Indications of changes of Substation state shall flash the
Substation symbol on the SCS diagram and alarms shall flash the “Alarm” symbol adjacent to
the Substation.
Silencing events shall not inhibit the annunciation of further events or constitute an
acknowledgement of the event.
The HMI shall provide for supervise of the following from the DCC (according to
the point list):
Close/open of all circuit breakers and disconnectors.
All measurement signals for Feeder and transformer MW, MVAr, kV and
A, MWh and P.F, Busbar (phase to phase) voltage &Busbar frequency.
Acceptance of all active alarms incoming from a substation.
Local/Remote selector switch.
Local or remote control in service.
Resetting of all electrically reset trip relays.
4.1.8 Trends
The HMI shall be capable of displaying any Analog value in graphical form to show the trend
of the value over a selected time period. The trend display shall have adjustable x and y axis,
indicate up to 10 analog values using real-time or historical data from theData Logging
The SCS shall incorporate long-term data logging facilities for all Analogs, digital and other
internally generated signals, Any Analog or digital value defined on the SCS shall be available
for storage and subsequent re- call,All signals shall be scanned periodically and updated values
or digital status changes stored. Date and time tags shall be allocated to each signal.
51
Data shall be stored for up to three months on a suitable storage medium for subsequent re-call
at a later date. An alarm shall be given to the operator when the storage of data approaches 90%
of the full capacity of the storage medium. In this case an automatic storing is performed if the
storage media is available. All data shall be capable of being archived and retained (individually)
for future reference. The operator shall have the facility to recall data held in the data logger
memory or from archives over a specified period of time. The information may also be restricted
to specific SCS data points. The requested information may be presented on the operators
workstation either in tabular form or as selected variables on a trenddisplay.
It shall be possible to compare on the same display, trends, real-time data and historical data
from the archives. This shall not affect the operation of the on-line data logging. The Operational
log shall record when required, the following information:
(a) Status changes.
(b) Onset and clearance of all alarms with facilities for distinguishing between the types ofalarms,
e.g. urgent, non-urgent, group, individual, etc.
(c) Control operations (both successful andunsuccessful).
(d) Operator actions such as alarm limit changes, tagging, hand-dressing, removal of parameters
from scan, inclusion of new parameter into scan, log on, log off,etc.
The operation log shall be available as a VDU list of sufficient size to allow the display of
information covering 5000 alarms/events.
4.1.9 HandDressing
The single line diagram will contain variable elements, some of which are updated automatically
by the application and some that are hand-dressed by the operators e.g. Substation where remote
indications are not available. Hand-dressed data shall be suitably indicated by a symbol or tag.
The hand-dressed changes shall be inserted in the databaseinstantly.
The system must recognize an attempt by the operator to make an invalid hand-dressing
operation and this should be blocked, with a suitable error message being displayed on the
screen.
4.1.10 OperatorInterface
The design of the operator interface shall be based on standard software packages and provide
Windows, Icons, Menus and Pointer (WIMP) style of presentation and use interaction with the
system.
All user actions shall be initiated using the pointer/keyboard and standard „windows methods.
The system shall provide facilities for the display of the entire substation single line diagram as a
single display along with other displays for specific purposes, as required.
Pan, zoom and windowing facilities shall be provided to allow the operator to navigate through
the displays and adjust the level of displayed detail to that appropriate to the task they are
performing. To ensure the interpretation of information from displays is intuitive and not
confusing to the operators all displays and lists shall be constructed following a consistent
overall design philosophy. For example, all lists shall display in the same manner with new
entries always being added to the top of the list or to the bottom of thelist.
The software shall also guide the user, step-by-step, through each sequence by identifying,
preferably via a visual technique on the workstation, the remaining valid entries.
Any invalid entry shall be detected by the software, ignored and an explanatory message
displayed on the VDU. It shall then be possible to continue the sequence with a valid entry.
52
4.1.11 System OperatingPoints
The substation will normally be manned, but also it will be monitored/ controlled when
selected from the Distributed Control Centre via the Substation Control System (SCS).
It shall be possible to operate Substation in the following ways: -
• Supervisory & Controlled - from theDCC
•Remotely - from the substation control room
• Local – from the Local ControlCubicle
•Maintenance – from the Local Control Cubicle.
For maintenance purposes only. The design of the Substation Control System (SCS) and substation.
substation shall be such that control of any item of Substation is only possible from one control point at any
particular time and the transfer of control between these points shall be achieved without affecting the safe
operation, monitoring or control of the substation.
As a minimum, the system software shall be capable of supporting many different levels of user,
e.g. operator, engineer and system manager, etc. For example:
(a) Operators would be responsible to control and monitor the substation using the
facilities of the Substation Control System(SCS).
(b) Engineers would be responsible for any fundamental changes made to the Substation
Control System (SCS) software orconfiguration.
(c) System managers would be responsible for the system security, back-up and database
maintenance.
The availability of functions to each user shall be configurable, allowing the user‟ s area of
responsibility to be defined.
The maximum number of different user levels supported and the degree of configuration
available of each level shall be stated in theTender.
4.1.13 SystemCapacity
The design shall meet the following general requirements with regard to capacity and
expandability. The HMI shall be designed, delivered and commissioned with sufficient capacity
for performing the requirements of this specification. .
The SCS shall be equipped with control, indication and measurement functions required by the
Scope of Work.
The maximum system capacity and system loading shall not be less than 200% of the specified
system capacity, including the specified future expansion.
In addition to the facilities detailed in the Facility point List, approximately 10% spare
input/output capacity shall be provided within the contract (this figure shall be confirmed at the
specific site survey in agreement with the Employer‟ s Representative). These spare facilities shall
be fully fitted and prewired to the Bay Control Units.
The design shall provide for future expansion, modification and testing with the minimum of
disruption to existing facilities.
A minimum of 30% of the future expansion capacity shall be demonstrated during the FAT.
53
4.1.14 SystemPerformance
The (SCS)scanning and polling frequencies shall ensure the following overall performance. If
better performance is necessary to ensure satisfactory operation of certain (SCS)functions, the
Tenderer shall state this.
The (SCS)shall process, enter into the database and update all relevant displays currently on view
within less than one second of a change occurring at a Bay Control Unit input. This time shall
include for any calculation or other processing required to enter derived or compiled information
into the files, logs, reports or displays.
The (SCS)shall also process all information required at the DCC (e.g. status, measurements and
alarms) and have them available for transmitting to the DCC with less than two seconds of a
change occurring at a Bay Control Unit input.
The System shall give priority to commands such that commands issued from an operator‟s
workstation shall have confirmation of action (from the Bay Control Unit) displayed within four
seconds of issue from the workstation (not including the time taken for Substation to operate).
A fault on a HV switchgear bus bar (resulting in the generation of multiple alarms).
4.2 SoftwareRequirements
4.2.1 General
The contractor shall identify all standard proprietary software and any software specially
developed for this project.
The application software shall ensure the secure execution of (SCS)functions.
The operator workstation software shall run under a well proven, widely used, industry standard
and internationally supported operatingsystem.
4.2.2 Real-timedatabase
A real-time database shall be maintained within the (SCS)system. A general check shall be
initiated at configurable intervals to retrieve all data points from the remote I/O to ensure validity
of databaseentries.
The real-time database shall be open and the data dictionary published.
The real-time database shall support the import/export of data via standard interfaces such as
SQL, ODBC, etc.
Engineering facilities shall be provided for database and graphic display creation and
modification for the operator workstation.
Facilities shall be provided so that the operator workstation can be used as engineering console to
modify and configure the overall (SCS)system. It shall be possible to prepare modifications in
advance and implement them with minimal disruption to the running system.
4.2.4 Dataprocessing
In the event of detection of the failure of I/O components, indications and alarms from the
previous successful scan of the failed I/O shall continue to be displayed on the operator
54
workstation. However, facilities shall be incorporated to indicate to the operator that the relevant
data is not presently being updated.
The system shall have the ability to differentiate between status changes resulting from operator
actions and apparently spontaneously occurring actions, the latter drawing
attention to the operator via an audible alarm and highlighting the status change on the
workstation. The processing of Analog signals shall include:
(a) Scaling for display in engineeringunits.
(b) Alarm supervision between adjustable limits, e.g. Low Alarm, Low Warning, High Warning
&HighAlarm.
(c) Devising values such as summated powerflows.
4.3 HardwareRequirements
4.3.1 General
There must be a minimum two RS232/485 ports Separate and tow Ethernet port for high data
transfers. All hardware and software requirements shall be available to support communication
ports of the SCS.
The SCS shall support for at least four most common standard communication protocols to
communicate upstream (T104 & T101 ) (master control center) or downstream ( IEC60870-5-103,
Modbus(TCP/IP,Serial),,Profibus, SPAbus, DNP3(TCP/IP,Serial),, IEC 61850 , and PLC system)
(IEDs or slave RTUs, Network.)
The RTU/HMI protocols shall be non-propriety for use, so the contractor shall provide all the
details and parameter settings for each protocol used through (upstream or downstream or
network) communications MOE shall be authorized to disclose the (SCS)protocol to third
partysuppliers.
The Tenderer shall provide details in their Tender of the SCADA communication protocols
supported by their system.
The rights to access the (SCS)indications and controls from remote systems shall be
programmable within the (SCS)for each communications link connected to the (SCS).
The power supply for this equipment shall provide an 8 hour standby capacity such that it is
able to continue to communicate and exchange control and data with the DCC in the case of
mains failure e.g. ac source or charger failure.
55
Digital Inputs
Substation alarms and indications shall be derived from IEDs.
The change of state of a digital input shall be time tagged to a resolution of 1 ms for Sequence of
Events (SOE) reporting and shall be generated from a real time clock synchronized by Master
SCADA.
AnalogInputs
Analog inputs shall be capable of processing standard voltage and milliamp current inputs
continuously (0,5,4,10,20 mA) & (0,5,10,20V).
CommandOutputs
Command outputs shall be designed to provide “select and execute” operation. The period of the
command pulse shall be configurable between 0.1 second and 25.5 seconds. The command pulse
timer shall reset immediately the command is executed or cancelled.
Pulse CountingInputs
Pulse counting inputs shall be provided as either a separate input module or using digital inputs.
The accumulative values must be treated as instant Analog values for the purposes of the
equipment at the DCC reading the data.
The operator workstation shall be rugged, industrial type units and shall be equipped with a
high resolution color visual display unit (VDU), alphanumeric keyboard and pointing device
(mouse/trackball). It shall be possible to increase the number of VDUs per workstation to two or
three, although one will be provided under this contract.
The visual display unit (VDU) shall be fitted with high quality Light Emitting Diode splay (LED)
to ensure good resolution and clarity of information in all areas of the screen.
The VDU shall have power on/off switch and indicator along with brightness, contrast and any
other necessary controls.
. On workstation with more than one VDU, it shall be possible to freely move the pointer
over the contiguous screen area.
The workstation shall be provided with adequate memory for the required tasks with 25 per
cent sparecapacity.
A highly reliable mass storage device shall be provided in each workstation sized to satisfy
the requirements of the operating system, applications software and anticipated stored data
plus 40 per cent spare capacity.
The workstation shall be supplied with a DVD-RW drive/writer/re-writer for loading
software and backing-up/restoring software and data.
The operator workstation shall be equipped with a low level audible alarm. The operator
workstation shall be fully configured and set into operation by the
Contractor. The design and layout of the screen displays shall be approved by the
Engineer.
56
HMI specifications
Industrial PC inside RTU Cabinet
OS : Windows Last Version
Processor : Intel Core i7
Memory : 16 GB – DDR4
HDD : 2xHDD 1T 24x24
With DVD-RW , Keyboard , mouse and two speakers.
Description LED Monitor
Type: 23” screen
Dimensions (W x H x D) approx.: 546mm x 427,5mm x 210mm
Interfaces/ Network adapter: VGA or DVI
Max Resolutions :1920 x 1080
Inverter 110VDC to 220VAC ( charging Time 8 hour ) to connected with the Battery System in
side Substation.
Microsoft office with License Key .
Antivirus software with License Key.
57
The protection system shall be able to withstand the temperature requirements for storage and
transportation and shall be tested to the following requirements: -
IEC 60068-2-1 with severity class -25°C, 96 hours IEC
60068-2-2 with severity class 70°C, 96hours.
4.4.1.2 Relativehumidity:
The protection system shall operate correctly with a relative humidity of 95 per cent
4.4.1.3 Enclosure:
The RTU Cabinet shall meet the requirements of the tests detailed in IEC 60529 with
classification IP51 (dustprotected)..
4.4.2 MechanicalEnvironment
4.4.2.1 Vibration:
The protection system shall meet the requirements of the tests detailed in IEC 60255-21-1
with severity class 1.
4.4.2.2 Shock andBump:
The protection system shall meet the requirements of the tests detailed in IEC 60255-21-2
with severity class 1.
4.4.2.3 Seismic:
The protection system shall meet the requirements of the tests detailed in IEC 60255-21-3
with severity class 1.
4.4.3 ElectricalEnvironment
4.4.3.1 DC auxiliary energizingquantity:
The protection systems dc auxiliary energizing voltage of 48 V (nominal).
operating voltage range is 38V to 60 V , Numeric protection systems shall meet the
requirements of IEC 60255-11 with interruptions to the dc auxiliary energizing quantity of 10
ms.
4.4.3.2 Frequency:
The standard rated frequency 50 Hz.
The nominal range frequency -5% to +5 %.
4.4.4 Insulation
Rated insulationvoltage:
The rated insulation voltage of circuits connected to current transformers of high impedance
relays shall be 1000 V. All other circuits shall have an insulation voltage of 250 V. All open
contacts of the protection system shall withstand a voltage of 1000 V
58
Dielectrictests:
The protection system shall comply with the dielectric test requirements of IEC 60255-5. The
test voltage shall be selected according to the rated insulation voltage of the circuits being
tested form Series C of Table 1 of IEC 60255-5.
Impulsevoltage:
The protection system shall comply with the impulse test requirements of IEC 60255-5 with
test voltage of 5 kV.
ElectromagneticCompatibility
The requirements of this section of the specification are specifically applicable to numeric
protection systems. The requirements may also be applied to some electro-mechanical relays
that are very sensitive or of high speed, at the discretion of the Engineer.
1 MHz burstdisturbance:
The protection system shall comply with the requirements of IEC 60255-22-1 with severity
Class III.
Electrostaticdischarge:
The protection system shall comply with the requirements of IEC Publication 60255-22-2
with severity Class III.
Radiated electromagnetic fielddisturbance:
The protection system shall comply with the requirements of IEC 60255-22-3 with severity
Class III. The test shall be carried out by using Test Method A and by sweeping through the
entire frequency range 27 MHz to 500 MHz.
Fast transient disturbance:
The protection system shall comply with the requirements of IEC 60255-22-4 with severity
level IV.
ElectromagneticEmissions
The protection system shall comply with IEC 60255-22-25.
4.4.4 PowerSource
The Substation Control System (SCS)components in the substation control room shall be
powered by:
-Inverter fed from the Substation volt battery charger 48VDC, (preferable)
This solution shall comprise an inverter, static by-pass switch and manual maintenance by-pass.
The Contractor shall state the increased battery capacity required to support the control room
equipment such that an 8-hour standby capacity for the Substation Control System (SCS)is
maintained.
-UPS system, and this shall comprise a rectifier/charger with maintenance-free sealed batteries,
inverter, static by-pass switch and manual maintenance by-pas
59
5 Maintenance ,Spare&Training
5.1 MaintenanceFacilities
The RTU/HMI design shall facilitate first line fault location and maintenance to be readily
performed on site.
Maintenance equipment shall include an engineer's portable test unit. The test unit shall enable
all the RTU/HMI functions to be tested on site, with the RTU/HMI in both off-line and on-line
states. It shall provide an indication of the presence and location of any detected RTU fault.
Safeguards shall prevent the activation of RTU control outputs with the test unit connected and
the RTU in the on-linestate.
A master station emulator is required to facilitate the testing of RTU communications.
The emulator shall provide a means of interrogating the RTU, via its normal communications
line, and of monitoring and interpreting responses. It is preferred that a portable PC-based unit
is supplied, that is capable of providing both the MS emulation and local testing facilities
specified above.
A comprehensive description of all available RTU/HMI maintenance facilities, including any
functions available for remote diagnosis of RTU's from the MS, shall be included in the
Tender.
5.2 Maintenance andSpares
The intended maintenance strategy for the RTU/HMI is that the Employer shall be able to:
(a) Perform _first-line-maintenance_ of all subsystems, i.e. be able to locate faulty hardware
components and replace them with spare parts with the faulty parts being returned to the
original equipment supplier for repair orreplacement.
(b) Analyze and define software faults and protocol interface problems withDCC.
(c) Re-configure and extend the RTU / HMI facilities with minimal assistance being necessary
from the original equipment supplier, including updating databases, modifying and building
new display screens and adding new equipment and devices to the RTU / HMI . Spare parts
for the RTU /HMI shall be provided to support the maintenance strategy described above,
particularly bearing in mind the _turnaround time_ to repair/replace faultycomponents.
(d) The Contractor shall supply diagnostic software, which monitors and individually tests each
of the components of the RTU demonstrating all the capability of RTU. The diagnostics shall
provide comprehensive user interaction and printoutcapabilities.
The Tendered shall include an itemized and individually priced list of recommended spare
parts in their contract. It is anticipated that this list would include at least one item of each
hardware component used within the RTU/HMI for use in first-line-maintenance (or 10% of
the components for components that occur in larger numbers within the system, e.g. I/O
cards). Any special tools, including software, and hardware (e.g. lap-topcomputers).
60
Maintenance tools shall also be itemized( Digital Multi meter ,phase sequence, cable maker label machine,
Electronic tools kit , PC networking tool kit UTP cable tester , USB/RS232 converter ,USB/RS485 Converter
, RS232/485 converter ). In order to assist in the ordering of spare parts, the Contractor is required to
recommend a spares holding to cover the first two years, following the end of the Warranty Period, and to
provide a costbreakdown.
The Contractor shall not have access to spares held by the Employer during the Warranty Period. The
maintenance philosophy which will be adopted will generally be for fault-finding to card level and module
replacement, with the faulty modules being either scrapped, if damaged beyond repair, or returned to the
Contractor for repair, as appropriate.
The Contractor shall operate a module repair and replacement scheme, details of which shall be provided
with the Tender, including turn round times.
The Contractor shall base the list of recommended spare parts on the above maintenance philosophy.
This list shall be submitted as an optional price and shall include a cost breakdown. Prices for the
supply of spares shall include all associated charges, and shall remain valid for orders placed withinthe
currency of the WarrantyPeriod.
The Employer shall be at liberty to order quantities of spare parts at variance with those listed by the
contractor. The prices shall remain valid for any such variation of quantities, unless stated otherwise in the
Tender.
The cost of spare parts shall not be used to calculate the cost of any variations to the Contract. The spare parts
recommended shall be identical functionally, electrically and mechanically, to the corresponding parts in the
equipment supplied under the Contract and shall be suitably packed and clearly marked, ready for reception
at the Employer's stores. Any special handling instructions shall be clearly marked on the packages.
The Contractor is required to maintain the capability of supplying material for the overhaul and
maintenance of the System for a period of fifteen years from the handoverdate.
The Contractor shall supply equipment lists of the recommended spare parts that include the names and
addresses of the individual manufacturers of the listeditems.
The Tenderer shall provide prices for a recommended spares holding on a unit basis, as an option for
selection by the Employer, at any time up until the end of the Warranty Period. The Contractor shall
guarantee the availability of spare parts to the Employer, at a reasonable cost, as follows:
(a) The Contractor shall maintain an adequate stock of spare parts for a minimum period of ten years (or
until the end of the equipment's specified life) after the product has been removed from quantity
production, declared obsolete or officially removed fromsale
(b) Where a component, which is not under the Contractor's control, has become unavailable, it is the
responsibility of the Contractor to offer a compatible alternative at reasonablecost.
(c) Design improvements or changes made to a product during its production run shall be
carefully assessed such that component interchange ability shall not beaffected.
The Tenderer shall provide a spare parts list for (HMI) to operate for a minimum of five years after Taking
over of the Works.
33
5.3 Testing
5.3.1Approach toTesting
The testing philosophy for the RTU/HMI shall ensure that the equipment functionality and site
specific facilities are thoroughly exercised and validated at the Contractor's premises before
delivery, and that the site specific facilities are confirmed during commissioning.
The site specific data requirements shall produce in the form of an Overall Facility Schedule and
this shall be agreed with the Employer. This shall be used as a basis for testing the site specific
aspects of the RTU. The test methodology shall complement the design methodology and the
two shall be developed in parallel.
Since the RTU will be made up of common components and facilities, Type Tests shall be
performed to confirm that the non-site specific, functional facilities are acceptable. Factory
Acceptance Testing shall be carried out on each site specific configuration on test equipment
similar to the site target equipment and configured to represent the site target configuration.
The principle of testing shall be that, at stages throughout the work, formal tests shall be
performed and recorded against written test specifications, to provide a high level of
confidence to the Contractor and the Employer that subsequent stages can precede.
The responsibility for specifying, conducting and recording tests shall be with the Contractor,
but all aspects must be to the satisfaction of the Employer. The degree to which the Employer
intervenes in the process will depend upon the level of confidence built up during the project.
This document does not constitute a Test Specification or Test Procedure for any part of the
system; rather it sets out the stages at which tests are required and the subjects, location and
purpose of each stage. All Test Documentation for all tests shall be written by the Contractor
and submitted to the Employer for approval at least 12 weeks before they are first used.
Inspection of incoming goods and components, and subassembly testing, shall be undertaken
by the Contractor in accordance with the procedures set out in the Contractor's own
QualityPlan.
5.3.2 Responsibilities
The Contractor's responsibilities shall include but not be limited to requirements to:
(a)Produce written test plans, schedules, procedures, method statements, test record
sheets and procedures for fault reporting, for alltests.
All test documentation associated with a subsystem or system test shall be submitted for
approval by the Employer at least 12 weeks prior to the commencement of the associated test.
(b) Ensure that all test documentation associated with any testing has been approved by the
Employer prior to the commencement of the correspondingtesting.
(c) Provide the equipment, test equipment, test software, personnel and facilities to conduct
the tests.
(d) Successfully carry out all tests according to the approved test procedures and correct any
errors, with subsequent re-testing of functions that may be affected by the correction, prior to
the witnessed acceptance tests.
34
(e) Provide facilities for the Employer to witness any Factory or othertests.
(f) Produce permanent records of all test progress and results in a formal systematic
manner. (g)Carry out all remedial work and re-testing found to be necessary in order that
the equipment should pass thetests.
Each of the above responsibilities shall be discharged to the satisfaction of the Employer, but
approval by the Employer shall not imply any diminution of the Contractor's responsibilities.
It is expressly the responsibility of the Contractor to satisfy himself that items _supplied by
others' are in a satisfactory condition for the Contractor's tests to beconducted.
The Contractor shall provide all equipment and services required for testing, including, but not
limited to:
(a) Type Test and site specific facility test bedequipment
(b) Laboratory test instruments ( Protocol Simulator free license ,Omicron tester ,phase rotation
indicator , current injector).
(c) Special test equipment, emulators, simulators and test software, to permit full testing of
System functions and performance (in particular a means of connecting to or emulating the
DCC MasterStation)
(d) Other items of the System, specified elsewhere as being part of the Contractor's supply,
even if not part of the Subsystem under testConsumables.
(e) All test instruments shall be subject to routine inspection, testing and calibration by the
Contractor. All test instruments shall be subject to approval by the Employer and, if required by
the Employer, shall be calibrated at the expense of the Contractor by an approved standards
laboratory prior to being used during thetesting.
5.3.4 TestingStages
Inspection of incoming goods and components, and subassembly tests, shall be performed in
accordance with the Contractor's Quality Plan. Software production and integration testing
shall also be performed in accordance with the Contractor's QualityPlan.
The RTU shall be subject to acceptance testing as specified in this document. The stages of
testing to be performed at higher levels shall be based on the following:
(a) Type Testing To check that the operation of all of the RTU facilities perform in accordance
with the Contractrequirements.
Type Testing shall be performed on test equipment at the factory similar to the site target
equipment and configured to represent the largest target site configuration. The Tests shall,
exercise and prove the correct operation of all of the functions of the RTU, using simulation
where necessary, including the interface for connection to the Distribution Control Centre
SCADA system. The Tenderer shall state how they will undertake the Type Tests of the RTU in
their offer.
(b) Factory Acceptance Testing(FAT)
To check that site specific aspects of each RTU performs in accordance with the Contract
requirements.
35
Factory Acceptance Testing (FAT) shall be performed on test equipment at the factory similar
to the site target equipment and configured to represent the site target configuration.
The FAT shall exercise and prove the correct operation of all of the site specific functions of the
RTU, using simulation where necessary, including the interface for connection to the
Distribution Control Centre SCADA system. The Tenderer shall state how they will undertake
the FAT of the RTU in theiroffer.
(c) Site Acceptance Testing (SAT shall done by contractor) To check that the totality of the
equipment supplied under the Contract performs in accordance with the Contract
requirements and interacts correctly with equipment supplied by others and interfaces
correctly to the Works. Site Acceptance Testing (SAT) shall be performed with the complete
RTU installed on site (RTU supply from Contractor & RTU supplied from other vender ) with
all interfaces to the substation connected and functional and be conducted after thesuccessful
completion of the Contractor's own testing of the system. The SAT shall exercise and prove
the correct operation of the functions of the site RTU, including all the testing of all facilities
between the Distribution Control Centre and RTU. The Tenderer shall state how they will
undertake the SAT of each RTU in their offer.
(d) 500 Hour Trial Period (following System SAT) Each RTU shall be subject to a 'hands on' test
period to demonstrate the reliability, stability and robustness of theRTU.
The Contractor shall provide, as part of the Programmed of Work documentation, a master
plan showing the scheduled dates of testing and shall provide updates to this plan, when any
changes are known, at least 6 weeks in advance of thetests.
The Contractor shall advise the Employer in writing of the actual date of commencement of
every test at least 10 working days before the commencement.
The Employer shall have the right to witness any tests whether conducted at the Contractor's
premises or elsewhere. Records of every test, whether witnessed or not, shall be taken by the
Contractor and copies sent to the Employer within 3 weeks of completion of the tests.
5.3.6 Test Procedures and ResultSheets
The Contractor shall prepare test procedures and result sheets for all tests. The Contractor
shall also prepare a cross reference listing to show that all of the requirements of the
Functional Design Specification have been included in the tests.
Separate test procedures and result sheets shall be provided for factory and site acceptance
tests. All test procedures and result sheets will be subject to review and approval by the
Employer.
Test result sheets will be retained as part of the permanent QA record for the RTU.
5.3.7 Contractor's PriorTests
The Contractor shall successfully complete a prior run of all tests, using the test procedures
and result sheets described above, before the commencement of the formal tests.
Any revisions to the test documents found necessary as a result of the prior testsshall be made
before the commencement of formal tests.
Test results from the prior tests shall be made available to the Employer, on request, to
indicate the readiness of the equipment for testing to commence.
5.3.8 Conduct of theTests
The Contractor shall conduct the tests in accordance with the approved test procedures and
36
shall enter the results in the result sheets.
For each test, the Employer will determine whether the test has passed or failed. In general,
the test will be considered to have failed ifeither:
(a) The result of the test is not in accordance with the expected result described in the test
procedure,or
(b)The result of the test is in accordance with the expected result described in the test
Procedure but some other unexpected or unexplained event occurred which the Employer
considers to be afault.
Full use shall be made during the tests of operator manuals and other documentation provided
by the Contractor to provide a series of tests of their accuracy. The Employer may refuse to
allow the commencement of the testing if this documentation is not available at the test site.
5.3.9 Failures
The Contractor shall correct all faults found during testing, and shall arrange for the test to be
repeated. The test shall only be repeated when the fault has been remedied and the equipment
demonstrated to be functioning correctly.
Where remedial measures involve significant modifications that might, in the Employer's
opinion, affect the validity of earlier tests, then the Contractor shall repeat the earlier tests and
obtain satisfactory results before repeating the test in which the fault was first identified.
The Employer shall have the right to order the repeat or abandonment of any test in the event
that results demonstrate that the equipment is significantly non-compliant with the Contract
requirements, without in any way prejudicing his rights.
The Employer shall have the right to suspend any test in the event that errors or failures have
become unacceptable. The Employer shall also have the right to suspend any test in the event
of a fault being detected by the Contractor but not reported to the Employer within 24 hours.
In this event, the suspension shall remain in effect until reporting has been brought up to date
to the satisfaction of theEmployer.
5.3.10 FaultCategories
The Employer will allocate a category to each fault, which shall determine the future tests
required. Test categories shall be as defined in the Table at the end of this section.
The Contractor shall correct and re-test every fault detected during the tests.
The Contractor shall maintain a fault log throughout each series of tests. Every fault detected
during the tests will be entered in the log, together with the actions taken to clear and re-test
the fault.
The fault log will be retained as part of the permanent QA record for the RTU.
For each hardware failure that occurs at any stage of testing, the Contractor shall investigate the
failure and prepare a report on its cause(s) and design implications. The report shall clearly
show: (a)The most likely cause of the failure
(b) An analysis of any stress that may have been caused to other components of the equipment
being tested as a result of the failure.
37
(c) Whether the failure is a result of any component operating outside its design
range (d)Whether any design changes should be made to avoid further failures.
All such reports will be retained as part of the permanent QA record for the RTU/HMI.
38
Table -1 Fault Categories:
Category Definition
0 An item recorded as a fault during testing, and subsequently considered to be a
normalacceptable occurrence. Testing may continue.
1 Minor fault. An event not affecting the functionality being tested in that session.
Testingmay continue.
2 Repeatable fault not affecting the functionality being tested in the session. Testing
maycontinue at the discretion of the Engineer.
3 Repeatable fault affecting the functionality being tested in the session. The fault
must berectified before re-test of the affected test session.
Testing may proceed on other sessionsif permitted by the Engineer.
4 Major fault affecting the functionality being tested in the session. The fault must be
rectified before recommencing testing.
5 Non-repeatable fault affecting functionality being tested in the session. The action
taken
will depend on the severity of the fault. Discussion is needed to establish the most
appropriate course of action.
6 Documentation error or deficiency. The error will usually be amended during the
test and
the test will continue. The documentation shall be corrected before the tests are
considered complete.
7 Deficiency in the ability of the test or test equipment to demonstrate the function
being
tested in the session. Discussion is needed to establish the most appropriate action,
which will usually result in a more appropriate test being devised, by the
Contractor and the function re-tested using that new test. The test documentation
shall be updated to include the new test procedure.
8 Other fault not covered above, but requiring explanation and, in some cases,
correction
5.4 Documentation
Documentation for the RTU /HMI shall be provided in line with the general provisions
specified in the relevant power station or substation Tender documentation. The
documentation shall include the complete functional specification of all hardware and
software and complete maintenance and user manuals for both hardware and software. In
particular, the maintenance documentation shall include detailed fault finding flow charts to
assist with first line maintenance of all subsystems and the user manuals shall provide
detailed instructions on system configuration such that the Employer may reconfigure and
extend the RTU facilities without assistance being necessary from the original equipment
supplier. Complete and original copies of all software programs, operating system, protocols
analysis and parameters setting, drivers, data bases, catalogs, maintenances documents,
tools, and emulators etc shall be provided as hard copy and as a soft copy on CD all
inEnglish.
5.5 Training
39
Training of the Employer's maintenance personnel shall be provided in line with the general
provisions specified in the relevant power station or substation or (master control center)
Tender documentation to enable them to safely and competently maintain the system to the
levels described. It is anticipated that a limited number of formal structured training courses
will be provided for both hardware and software for the Employer s specialist engineers,
working alongside those of the equipment supplier at the equipment supplier s factory in
RTUs and HMI equipments. In addition, _on the job_ training shall be provided tothe
Employer‟s local maintenance staff, on the first line maintenance aspects of the equipment.
This may take place during the site commissioningstages.
Details of the training available shall be provided by the Tenderer, including the type of
Training (basic or advanced), the no. of trainee shall be ( 3 ) trainer. All expenses associated
with the training including international and local travel, hotel accommodation and meals
and sundry expenses for all the trainees shall beincluded.
5.6 On SiteTraining
The Contractor shall do On site training for the same trainees after finishing the
installation work and before SAT, the contractor shall provide the ON site training details
to MOE.
1. Interposingequipment
General
All power system measurement transducers for the measurement of MW, MVAr, voltage,
current and frequency shall be software configurable type and plug-in type (possible to replace
it without affecting the continuous of the current circuit) and individual transducers shall be
enclosed and mounted in sheet steel cubicles. The location of these cubicles will be subject to the
site survey but there is a preference for a centralized arrangement. Transducers shall provide
continuous dc Analog output signals from continuous ac Analog inputs. Transducers shall
include all necessary circuits for signal amplification and forscaling.
Transducers for MW and MVAr measurements shall correctly compound the voltage and
current inputs to provide bi-directional output related to active and reactive power flow.
Transducers for MW and MVAr measurement shall be suitable for three phase unbalanced
load. The scale of the measured voltage should range more or less by 10% of the rated input
voltage.
Power system measurement transducers shall provide galvanic separation between the
primary current, voltage transformers and the intelligent transducer shall be provided for the
measurement of MW, MVAr, voltage, current and frequency for sites with most faulty
40
Transducer.
Test terminal blocks shall be provided with all transducers to permit injection testing of
individual transducers, without interference to the continuous operation of other apparatus
connected to the same current and voltage transformers.
Isolation links shall be provided for current transformer circuits which automatically short
circuit the current transformer output.
Overloads
Each current input shall be capable of carrying 200 per cent rated current continuously
and withstanding ten times the rated current for 5 seconds. Each voltage input shall be
capable of carrying 120 per cent rated voltage continuously and withstanding twice the
rated voltage for10 seconds. The output shall be limited so as not to exceed 1.6 times
nominal full range output current.
The open circuit output voltage shall not exceed 25 volts dc. Transducers shall be
protected against over current and over voltage.
Burden
The burden imposed on the primary current transformer, at full rated input shall not
exceed 1 VA per transducer. The burden imposed on the primary voltage transformers at
full rated input shall not exceed 3 VA pertransducer.
Preference shall be given to transducers which offer burdens significantly lower than the
values specified in this document.
41
Output
The output shall be linear in respect to the measured value with ranges of (0-5, +/-5, & 4
to 20 ) mA. Transducers shall be designed to operate into any load impedance between 0
and 2000 ohms, maintaining measuring accuracy to IEC 688 (Class 1.0).
Responsetime
The response to achieve a final steady value for any step change of 90 per cent of input
range shall not exceed 1 second.
Powersupply
Preference will be given to transducers which derive auxiliary power from the measured
voltage input. An auxiliary dc supply will be available from the RTU dc power supply
system.Attentionisdrawntothefluctuatingnatureofthedcvoltage.Variationsofbetween
+20 and - 15 per cent of nominal voltage shall not cause any detectable inaccuracies.
45
SmartMeter
Control interposingrelays
The control interposing relays shall provide a means of operating the electrical control
circuits of switchgear(circuit breakers and disconnectors), transformer tap changers, etc by
means of light current signals from the RTUs.
The control signal will be in the form of a pulse of short duration but to ensure high
reliability, all control interposing relay coils and contacts shall be continuously rated. The
relays shall have a high degree ofreliability.
The relays shall provide double pole switching. One contact per pole is the nominal
requirement but series or parallel arrangements of contacts for each pole will be considered.
Status indication repeatrelays
The status repeat relays shall each be provided with a minimum of three sets of contacts,
each set arranged to close while the relay coil is energized. The rating of repeat relay coils
shall not exceed 2Watts.
Contacts shall be designed to conduct load currents of less than 5 mA and also be
suitable for infrequentoperation.
I/O Modules.
Input/output (I/O) instruments provide inputs and outputs to data acquisition devices,
programmable logic controllers (PLC), and other computerized machinery.As data
acquisition products, I/O modules are involved in processing inputs from sensors, timers,
relays, and solid-state circuits to monitor, analyze, or control processes. I/O modules may
provide inputs and outputs for devices that lack them or may act as expansion modules to
increase a DAQ board's inputcount.
The module senses the DC input voltage and converts it into a True (ON) or False (OFF)
logic signal.
46
2. CABLES
General
The Contractor shall provide a list of all of the cables supplied for the
control &Measurements and telecommunications equipment together with
the following details:
-Quantity of each type of cable
-The type and construction of each cable e.g. size and number of cores/pairs,
insulation, screening, armoring, sheathing.
-Manufacturer.
-Type of termination e.g. specific plugs, sockets and connectors.
-Price per meter for additional quantities of cable.
-Cross Section area for CT & VT with Smart Meter & Transducer.
RTU Cabling
All cables for measurements should be multi-core, stranded copper, twisted pair
shielded, numbered and overall shielded. All cables for status indication and alarms are
to be multi- core, twisted. stranded copper, numbered shielded overall. Cross section of
multi-core cables for measurements, status indication and alarms should be not less than
1.5 seq.mm. All cables for control purpose should be multi-core, stranded copper,
numbered, overall shielded, cross section should be not less than 2.5 seq.mm.
The Contractor shall supply and install all necessary cables between the equipment in his
scope of supply, and between the RTU and the Data Acquisition System Cabinet marshaled
Substation interface connections. The interface point for Substation to communications
equipment cabling shall be agreed with the Employer.
TERMINALBLOCKS
Terminal blocks shall be having provision for disconnection (isolation), with full-depth
insulating barriers made from molded self-extinguishing material. Terminal blocks shall be
appropriately sized and rated for the electrical capacity of the circuit and wire used. No
more than two wires shall be connected to any terminal. Each analog input signal, digital
status input, and digital output signals shall require two terminals per point plus a common
shield termination for each cable. All terminal blocks shall be suitably arranged for easy
identification of its usages such as CT circuits, PT circuits, analog inputs, status inputs,
control outputs, auxiliary power supply circuits, communication signals etc,Disconnecting
type connectors shall be used forCT
47
Laptop (industrial laptop for Maintenance):-
The weather sensor shall be supplied along with necessary accessories (e.g.
tripod, stand, clamps etc.) for installation/ fixing of sensors, signal/power
cables etc.
All the information listed in this document, prepared to be in general form and can be
customized according to the system requirements and scope of the work and defined
communication, depending on the fact that the smart meter is part of the AMI system.
1. General Description:
Energy Smart meter should be provided with the metering ability, andtwo- way
communicationfacility.
CT/VT energy smart meters, designed for requiring precise measurements and
revenue transactions for indirect connection network used by different voltage level
substation's Feeders. It provides a highly accurate energy and demand metering system with
a comprehensive information shown on an extended temperature large display. Multiple
communication options ensure easy integration with AMI and SCADA Systems, and to be
remotely managed from main data collectioncenter.
2. EnvironmentalConditions:
-Ambient temperature:
+55C° about 6 hours a day
Highest max. (In the shade)
Lowest min. -10 C°
Max. Yearly average +30 C°
-Sun Temperature:
Black Object under direct
Sun shine may attain a temp. of: 85 C°
-Air Humidity:
Max . 92% at 40 C°
Min. 12%
Yearly average 44%
-Altitude:
From sea level up to 1000m
3. TechnicalR requirement:
Standards: The mart meters are designed in conformance with the following
electricity s
standards:
Electricity metering equipment (a.c.)- General
-IEC 62052-11, 31 requirements, tests and test conditions, Part 11 &
31: Metering equipment
-IEC62053-21 Electricity metering equipment (a.c.)-
Particular requirements, Part 21: Static
meters for active energy (classes 1 and2)
- IEC62053-22 Electricity metering equipment (a.c.)-
Particular requirements, Part 22: Static meters for
active energy (classes 0,2S and 0,5S).
- IEC62053-23 Electricity metering equipment (a.c.)-
Particular requirements, Part 23: Static
meters for reactive energy (classes 2 and3)
- IEC62056-21 Electricity metering-Data exchange for
meter reading, tariff and load control, Part 21:
Direct local exchange.
- IEC62056-46 Electricity metering-Data exchange for
meter reading, tariff and load control, Part 46: Data
Link Layer using HDLC-protocol.
-IEC62056-52 Electricity metering-Data exchange for
meter reading, tariff and load control.
- IEC62056-51 Electricity metering-Data exchange for
meter reading, tariff and load control, Part 51:
Application layer protocols.
- IEC 62056-61 Electricity metering-Data exchange for meter reading,
tariff and load control, Part 61: OBIS Object
IdentificationSystem.
The smart energy meters have many features including those related to (AMI and SCADA)
functions as follows:
Measurement:
Local
5. Firmwareupgrade:
Firmware can be updated locally by optical port as well as remotely upgraded in accordance
with the DLMS/COSEM identification System and Interface Classes.
6. Anti-Tampering:
- The meter should be sealed to avoid any type of tamper and illegal use, with no
hardware interface or componentexposed.
- Various anti-tamper events such as terminal cover/ top cover opening, magnetic
fields disturbance and neutral current unbalanced can be detected.
- When these events happen, alarm will be triggered and corresponding events will
berecorded.
- Stored p r o g r a m s and r e g i s t e r s should have full tamper and fraud protection.
- Meter should detect terminal cover removal in power cutSituation.
7. Calendar andClock
- Calendar and clock are related to a time control and management system. All data
related to date and time, including leap years and the deviation of the local time to
generalized time reference (Greenwich Mean Time (GMT)), are controlled by this
module. Time deviation between local time and standard time could vary
withseasons.
- Real time clock has 0.5s per day accuracy according to IEC 62054-21. This clock
could be synchronized with HES (Head-End System) byremote communication.
- Display format for date information is “DD/MM/YY” and for time is
“HH/MM/SS".
- In case of power outage, the calendar clock will be powered by an internal super-
capacitor and then by battery whose minimum standby life is over 15 years without
any user‟soperations.
- If the battery is failed or in low level voltage, low battery icon on LCD screen will
flash and this event will berecorded.
- Load surveys and event logs will always use local time for the date stamp.
- If the time is changed for DST (Daylight Saving Time) start or end, the meter
conducts TOU metering function the adjustedtime.
8. Time of Use(TOU):
9. Billing:
10. Security:
- Multi-Level Security passwordprotection.
- Energy and Power load profiles: more than 120 continuous day‟s data with
configurable interval of both total import and total export energy with configurable
channels issupported.
- Daily load profile: more than 120 of continuous day‟s data of daily total import and
total export energy/power with configurable channels is supported.
12. EventRecord:
- The meter supports more than 20 kinds of event record with time
Standardeventlog:upto150entriesoftherecentstandardeventslog
(i.e.poweron,poweroff,clockcalibration,clockfailure,andbattery failure)
aresupported.
- Tamper detection log: up to 150 entries of recent tamper detection event log (i.e.
terminal cover and top cover opening, magnetic fields disturbance, and
communication log-in failure) aresupported.
13. LED:
- LEDs for active energy to be available (fixed imp./ kwh), reactiveenergy (fixed
imp./ kvarh) and alarm signaloutput.
14. Display:
-The meter Display shall be with good contrast and wide viewing angle for easy meter
readout. It shall have a wide operating temperature range.
- Not lessthan 8 digits display for datadisplay.
- Intuitive graphical display including vector diagram and waveformsfor
Consumption.
-The content of dis0play shall be clearly an indication of the nameplate of the meter.
15. Test:
-Routine test:
The tests should be carried out and pass according to latest issue of IEC standard for
each unit of the production and for all types of meters.
-Type test:
All meter types must pass type test according to latest issue of IEC standard.
- Acceleration LifeTest:
All meters and modems should pass Accelerated life testing.
16. Drawings andDocuments:
-Complete set of drawing of the energy meters with dimension clearly market.
-Type and origin of component and manufacturer.
- Documents of all type of tests should beprovided.
DLMS conformance and certificate shall beprovided.
Conformance and certificate that the meter have the ability to integrate in most market
leading softwarepackages
-Catalogues and technical data and literature consist of the following:
• Usermanual.
• Technicalmanual.
• Electrical and electronic diagram for each type ofmeters.
• The troubleshooting for each type ofmeter.
• All software and data base of themeter.
• All the above documentation should be provided in three copiesin English language as well
as in form computer disc(CD).
Note:The required communication system (UHF or WiMAX) to be specified by client prior to the contract
agreement, and it should be according to the existing communication media of DCC.
General
The applicable frequency band and frequency shall be confirmed by Owner/ client during
Design stage.
The Contractor shall aware/study the existing system and to be incorporated to his design if
necessary.
The contractor shall consider the space for equipment to be installed in the future at
substations other than Baghdad.
The communication system shall include the transceiver, terminations, coaxial cables,
antenna, tower (the height of tower should be determined according to the design) and
lightning protection device.
The required equipment shall be fully suited for the existing wireless communication system
at the Contractor‟s responsibility.
The wireless system shall be capable of supporting data interfaces complying with ITU-T
G.703, ITU-R, IEEE, IEC , V.11, V.24, V.28, V.35, and X.21.
The wireless system shall be powered from 230Vac (an output of UPS AC distribution panel).
The power supply input to individual items of the wireless system shall be individually
fused.
For all substations, expansion space for wireless system including Antenna shall be
provided.
RemoteTerminals
Communication system in Iraqi substations can be classified into two types according to the
current operating wireless communication systems of DCCs in different governorates. The
contractor shall be responsible for the design, supply, installation and test which required for
the correct interfacing of the RTU equipment with the existing DCC, including all protocols
and communications as required. The Remote Terminals can be classified into the following:-
Wireless UHFSystem
The remote terminals of the wireless UHF system shall be of a digital type, and shall have:
a) Radio transceiver/receiverunits.
b) Interfaces.
Asynchronous RS232 interfaces forRTU.
RS485 interfaces.
2- wire telephone interfacesline
4-wire E&M signalinginterfaces.
Ethernet interfaces (Min. 100BaseT).
Data rate: to be according to the design PMP or PTPlink.
c) Telephonehandset.
d) Alarmindications.
e) Network managementinterface.
A 1+1 transceiver hot standby redundant configuration for ensuring minimum down
time in case of equipment failures shall be provided. Hot standby is the configuration
where the two transmitters and the two receivers operate at the same frequency. The
transceivers are connected to the antenna by a passive combining network, with one
transceiver operational and the other on hot standby.
The main and standby units shall be powered by independent power supplies for full
hot standby operation. Any failure of the operating transmitter shall produce
automatic switch-over to the standby transmitter and initiation of an alarm. The two
receivers are operating at the same time the information is taken for the best received
signal.
The system shall be capable of providing proper performance throughout the life
expectancy of the substation.
WiMAXSystem
The remote terminal of WiMAX secure and reliable system according to IEEE 802.16 fixed
sites shall be provided and shall have:
The contractor shall provide the design of communication system which should satisfy the
following features:
High operational security and reliability of communication link in harsh environments
with availability of 99.999%.
High quality transmission in accordance with the ITU-Trecommendations.
Simple operation and faultdiagnosis.
The Contractor shall undertake specific testing to demonstrate the connection and
compatibility of the Wireless WiMAX system including (remote terminal and switches
devices) with the existing wireless system,and existing Network Management System
(NMS)in DCC.
5.3. Antenna
Antenna of UHF system shall be of the type “Yagi” and shall be constructed from
stainless steel or hot dipped galvanized steel parts finished with suitable corrosion
resistant paint.
For WiMAX system, the antenna (wireless TCP/IP data terminal) for harsh industrial
environments to be provided, the antenna and radio terminal should be compatible
with currently operating communication system ofDCC.
Highly reliable out door data terminal with flexible architecture to meet PMP and PTP
deployment in extreme location.
Hardened aluminum case with stainless steel components and integrated MIMO antenna.
-40 to 75 °C operating range using dynamic and thermal dissipation.
Antennas shall be mounted on the top of the provided tower wherever possible and
shall be able to withstand all weather conditions on site. All antennas and feeder cables
shall be equipped with protection devices to ensure that no damage occurs to the radio
system during lightningstorms.
The antenna gain shall be 10 dBi or more.
Cable for Antennafeeder.
Antenna feeder cables terminals and all accessories required to complete the installation
shall be provided and correctly fitted. The antenna feeder cable shall be armored and
compatible with the radio equipment supplied and the operating frequencies used. To
get the radio connected to the antenna for UHF system, an LDF4 type coaxial cable with
surge arrestor, grounding kit and all required accessories should be provided. While for
WiMAX system an Ethernet PoE cable (shielded, high flex Ethernet cable) up to 91m
(300ft) Ethernet cable should be provided.
The contractor shall provide cabinet for installing communication equipment (Radio
terminal unit, switches, etc), the cabinet should be located in substation control room
nearby RTU. The cabinet shall satisfy IP54 or more.
Power Supply
The radio system shall be designed to operate from a 48 Vdc supply. The equipment
shall have protection against transient voltages and operate without degradation in
performance for a supply voltage variation stipulated in the Technical Schedules.
All interconnection cabling from the equipment to power source and any necessary
devices to protect the radio equipment from damage in the event of overload shall be
provided as part of this Contract.
The power supply input to individual items of equipment comprising the radio
system shall be individually fused.
The power supply system shall be designed with enough capacity to ensure the
operation of all communication equipment in the site which includes (Radio devices,
Switches, phones and Tower Warning lights, etc).
The power supply for communication equipment shall provide an 8 hour standby
capacity such that it is able to continue to communicate and exchange control and
data with the DCC/ SCADA Master Station in the case of mains failure of the source
of supply e.g. mains or chargerfailure.
Tower
The contractor should provide the communication design for connecting the substation
with DCC.
The height of the tower should be according to the design and take into consideration the
obstacles along the signal path, and adding a suitable percentage for future expansion,
During the design phase, to ensure Line of sight for 5 years ,the contractor should
provide a Break down prices of green field towers with highs of 10m, 18m, 25m, 30m, 40,
45m and 50m from the ground
, an area in substation layout to be dedicated for ground field tower installation, the
dimensions of required area is about 4×4m to 11×11m according to tower foundation
which is based on tower height and soil test result.
The tower shall be of a self-supporting, non-tubular, lattice structure type suitable to
carry the required antenna together with the associated feeders and be able to withstand
the continuous wind pressure and wind gusting encountered onsite.
The tower design shall be such that under maximum site wind speed (which is 45m/sec.)
from any direction the maximum change in azimuth and elevation of any antenna shall
be no more than 0.25 degree, tacking into the account that at least four antennas to be
installed on the top of the tower.
Some system of security shall be provided at the bottom of the tower to prevent
unauthorized climbing. A removable ladder section will not be acceptable. Locking
shall be possible by use of padlocks.
Platforms shall be provided with guard rails at 550 mm and 1100 mm above the
platform. Working platforms shall have adequate working space and shall be at 1.3
meters below the level at which the antennas are to be mounted. Rest platforms shall
be provided at no more than 10 meters intervals. Kicking plates shall be provided on
all platforms.
Radio antennas shall be mounted on the faces of the tower rather than on the
corners. Feeder supports shall be provided at 1 meterintervals.
All connections at site shall be made by nut and bolt with means of locking the nut.
Where possible all bolt threads shall be inside the tower.
All towers shall be capable of having aircraft warning lights fitted. When required an
aircraft warning shall be fitted at the top of the tower and shall comply with the
requirements of the local Aviation Authority. Alarm equipment shall be installed to
detect the failure of aircraft warning lights, and indication shall be by local alarm
lamps and voltage free contacts for connection to the alarm supervisory system.
All metal work and metal fittings shall be hot dip galvanized to the relevant
standards.
Lightning protection devices shall be provided to protect and prevent equipment
from malfunction or damage caused by lightning strikes. Lighting cable shall be
stranded copper cable with cross sectional area not less than 90 mm2 and shall be
insulated form tower structure.
Note: For tower height less than 18m, it can be installed on the roof of substation in
case that there is no enough area to install it on ground.
5.7.1 Erection
The Contractor shall be responsible for excavations, setting of foundation and removal
of all surplus soil and restoration of the site to the satisfaction of the Employer.
- An earthing system shall be provided and shall be electrically bonded to the tower.
A maximum earth resistance of one (1) ohm shall be obtained. The calculation shall
take into consideration the soil resistivity of the places where the substation will be
installed.
- Power cables, and communication cables (including feeder cables, phone
cable,…etc) shall each be routed in separate trays, racks or ducts which shall be
suitable to be used inside substation building and outside building (between site
and tower) according to international standards.
- The material of the cable tray/ladder should be galvanized; tray structure, material
and dimensions should be approved by employer. The tray/ ladder structure with
its supports (and the required foundation) should be rigid and resistant to wind
movement.
Hi-discharge type Ni-Cd battery cells fulfill all requirements according to IEC 62259.
The battery charger are to be provided each being capable of supplying the DC load
requirements under normal operating conditions and at the same time provide the
boast charging requirements of the battery. The two chargers are to be suitable for
operating in parallel with eachother.
5 Spare 4 No.
PART 9: Cables
9.1 General
The Contractor shall provide the 33kV Power cables in station and all LV auxiliary
control and protection cables of a suitable design is used for site operation equipment.
The materials shall be of first class quality and designed for continuous satisfactory
operation as continuity of supply is of prime importance and to operate satisfactorily
under variation of load, voltage and short circuit or other conditions which may occur
on the system provided that these variations are within the assigned rating of the
apparatus.
The materials used shall be suitable for the clause 2.1.1.3 service conditions and the
soilconditions.
All cables provided under this Contract shall be of type approved by Owner and
shall be provided with the cover which resists a termite and avermin.
For Insulation
Extruded XLPE cured with dry curing process
36kV nominal thickness 8mm
For Insulation screen
(a) Non-metallicscreenapplieddirectlyovertheXLPEinsulationandshallconsistofa layer
of extruded semi conducting compound and of 50% overlap semi- conducting
swelling tape.
(b) The metallic screen must be a combination of copper stranded and coppertape.
• For 33kv cable the equivalent cross-section area to be 35mm2
For Filler & bedding
The three cores then laid up with suitable extruded (low thermal resistivity material
easy to remove good flexibility and to be mentioned with the offer such as (EPR) or
(PP)) fillers, a compact circular assembly and bedded with a layer of extruded P.V.C.
2mm thickness.
For Waterproof tape
A layer or suitable tape (swelling tape) for water proofing to be laid over the bedding.
For Metallic Armor
The three cores then armored with double galvanized steel wires according to
IEC60502 clause 12.4.
For PVC Jacket
Over all extruded PVC seamless sheath to prevent moisture from penetrating and
provides good corrosion protection thickness not less than 3 mm and to be anti-termite
treated (non-polluted material).
Marking of 33kV in the English language should be stamped each one meter length
and treated. Also name, year of manufacture, Voltage & cross section in the English
language.
The colors are to be RED for 33kV
Type of Cables
36kV Cables (1 x 400 mm2) with rated voltage VO/V=18000/30000 V (suitable for
highest system voltage of 36000 V).
The power cables in substation are to be thermally independent circuits laid in trenches
and ducts generally as shown in the layout drawing.
36kV cables from 33kV switchgear to 33/0.416kV Aux. transformercircuit
Technical Information for cables
The Contractor shall be required to give following information in Section 2 Technical
Data in the Bidder.
(a) Resistance of copper per km ofcable
(b) Inductance per km ofCable
(c) Capacitance per km ofCable
(d) Insulation resistance in M.ohms between core/screen
(e) Weight of copper per km ofcable
(f) Overall weight of cable per km ofcable
(g) Overall diameter of finished cable inmm
(h) Type of chemical treatment against termite in the outersheath
(i) Cross section drawing and details of cable layers andcatalogues
33 kV cables accessories shall, as a minimum, meet all the requirements of the latest
editions of IEC standard IEC 60502-4 and BS 7888.
Tests
Cables and accessories shall be subjected to inspections and tests by the Owner‟s
inspectors or international inspectors at any time during manufacture. The
manufacturers shall provide inspection facilities for the said inspection shall be made at
place of manufacture or at international testing facilities.
9.3 Low voltage Power Cables
Low voltage Power Cables shall, as a minimum, meet all the requirements of IEC
standard IEC 60502-1, 60228.
For Conductor
Compact electrolytic annealed stranded plain circular copper Conductor of high
conductivity 99.9% purity in accordance with IEC 60228.
For Insulation
Extruded PVC (polyvinyl chloride) according to IEC table.
Core colors
Colored for identifications (Red, Yellow, blue for phase) and black neutral.
For Filler & bedding
The four cores then laid up with suitable fillers to form a compact circular assembly
and bedded with a layer of extrudedP.V.C.
For Metallic Armor (for multi-core cables)
The four cores then armored with double galvanized steel wires according to IEC60502-
1 clause 12.4.
For PVC Jacket (PVC grade: ST2 table 4 in IEC 60502-1)
Over all extruded PVC sheath water proof gray color of thickness according to
IEC6052-1 and across section marking of (400V) in the Arabic language should be
stamped each one meter length and treated. Also name, year of manufacture, Voltage &
cross section in the Arabic language.
Type of Cables
400V Cables (1 x 95 mm2) with rated voltage VO/V=600/1000 V (suitable for highest
system voltage of 1200 V)
Tests
Cables shall be subjected to inspections and tests by the Owner‟s inspectors or
international inspectors at any time during manufacture. The manufacturers shall
provide inspector‟s facilities for any said inspection shall be made at place of
manufacture or at international testing facilities.
9.4 Control & AuxiliaryCables
All control, alarm and indication cables shall be of single-core or multi-core, PVC
insulation and overall over sheath, stranded copper conductors with galvanized steel
wire armor as a minimum, meet all the requirements of IEC standard IEC 60502-1 and
BS6346.
The conductors shall be plain annealed copper wire complying with IEC 60228 as
applicable or equivalent and all cores shall be clearly identified by printed numbers at
regular intervals.
Many instances of rats eating away the outer PVC insulation cover are reported,
therefore, a suitable non-corrosive wire armor to make the cable vermin-proof shall be
provided for all low voltage auxiliary and control and protection cables.
The minimum conductor size shall be not less than seven strands of 0.67 mm diameter
wire, or in the case of single wire conductors the minimum cross-sectional area shall be
not less than 1.5 mm2 for control and auxiliary circuits and 4 mm2 for current
transformer circuits. When the Contractor uses a less than 1.5mm conductor for an
electronic circuit, the approval of Owner shall beneeded.
The Contractor is responsible for checking all cable routes for burden on CT's and VTs
for voltage drop on DC control and trip circuits and for satisfactory service with the
supplied equipment. It is also the Contractor's responsibility to take precautions to
prevent damage to cable sheaths from system earth fault current.
The Contractor shall provide fully detailed wiring diagrams covering all parts of the
substation.
The cable cores shall be long enough to be terminated to any terminal in an enclosure
without extension.
All cables shall enter cubicles and boxes from bottom side. PVC sheathed cables shall
be terminated by compression glands complying with BS 6121 orequivalent.
Where cable cores are liable to be in contact with oil or oil vapor the insulation shall be
unaffected by oil. The Contractor must terminate all power and control cables inside
the appropriatecubicle.
The spare cores of all multicore cables shall be numbered and terminate at a terminal
block in the cubicle. AC terminals shall be clearly color coded and shrouded.
Colors shall be marked on cable box, cable tail ends and single core cables at all
connecting points and/or any positions. Cable boxes shall be marked with stamped
stainless steel labels indicating the purpose of the supply where such supply is not
obvious.
9.6 Cable installationrequirement
The following requirements shall apply
LV power cables, multicore cables and communication cables (if necessary) shall each
be routed in separate trays, racks, ducts, troughs or compartments separated by steel
sheetbarriers.
Fiber optic cable (if necessary) shall be routed and installed such that they are protected
from deformation or damage by auxiliary power or control cables throughout their
installed length when available.
Sufficient space shall be allowed to run in each duct or compartment the necessary
draw wires, being of non-corrosive metal and having devices for securing the
conductors. A spare capacity of 20% shall be provided on cable trays, ladder racks,
ducts, compartments, or openings in walls and floors.
Openings in floors and foundation pads shall be large enough to permit free movement
of cables during installation. Openings in walls and floors shall be sealed after the cable
installation with a fireproof barrier.
Cabling and wiring installations shall be arranged to minimize the risk of fire and
damage which might be caused in the event of fire.
Only one layer of power cables shall be laid on one tray or in one cable channel.
All cables leaving buildings for outside plant shall be laid in cable ducts or trenches
when available.
Where cables emerge from grade they shall be protected by a section of steel pipe
extending 150mm above grade.
Cables above ground shall be run on galvanized cable racks, tray or supports, suitably
clipped to prevent movement. Care shall be taken to provide for differential movement
between structures.
Protection from direct sunlight shall be provided by means of suitable continuously
covering the cable and of the same materials as the rack/tray. Cable strap shall be
made of stainless steel.
Conduits shall be provided wherever possible, at least 300mm away from heating
devices, or similar equipment, when it is evident that such proximity might impair
theservice life of cables.
9.9 Painting
The painting at site of electrical apparatus and equipment shall be limited to touching
up any surfaces scratched or marred during shipment or inland transportation or
installation.
11.1 General
The Contractor shall carry out Factory tests, Type test and Site test in accordance with
the latest IEC standard. The Contractor shall submit all test procedures to the Owner
forapproval.
All tests shall be carried out in accordance with the approval test procedures.
All tests results shall be approved by Owner. The approval of the tests, acceptance of
the test certificates or waiving of tests shall not relieve the contractor from his
contractualobligations.
11.3.2 RoutineTests
The following routine test items, but not limited to, shall be carried out at
manufacturer's factory in accordance to the latest issue of IEC specifications:
The test of the Substation control system shall be executed referring to item 3.5.12 (SCS
Testing).
1) 33kV Metal enclosed GISSwitchgear
- 33kV Circuit Breaker cubicle
(a) Design and Visualcheck
(b) Functional operation test ( Interlocking test D.S andC.B)
(c) Insulation resistancetest
(d) Power-frequency voltage withstandtest
(e) Mechanical operating tests ofC.B
(f) Timing test of closing and open operation ofC.B
(g) Primary injection tests on current transformer including measurement of current
ratio and check of relativepolarity
(h) Residual voltage test ofarrester
(i) Partial discharge test ofarrester
(j) Operation test of surge counter and surgerecorder
(k) Protection relaystest
(l) Indicating meterstest
Note: Magnetization curves and DC resistance values shall be submitted
for each current transformer.
2) Communication equipment(a)
Design and Visual check (b)
Functional operation test (c)
Insulation resistancetest
6) Inverter
(a) Design and Visualcheck
(b) Function test for control circuit, indicating circuit and alarmcircuit
7) UPS ACpanel
(a) Design and Visualcheck
(b) Insulation resistancetest
(c) Function test for control circuit, indicating circuit and alarmcircuit
8) AC LVpanel
(a) Design and Visualcheck
(b) Insulation resistancetest
(c) Function test for control circuit, indicating circuit and alarmcircuit
9) 33kV powercables
(a) Design and visualcheck
(b) Measurement of electrical resistance ofconductors
(c) Partial dischargetest
(d) Voltagetest
(e) Check ofdimensions
2) Communicationequipment
(a) Physical SiteInspection
(b) Operationalchecks
4) 33kV powercables
(a) General inspection of the cable routes, verification of proper installation, fixing
to the racks, bending radius,etc.
(b) Verification of proper earthing of the screen.
(c) Measurement of ConductorResistance;
(d) The Contractor shall measure and record the following as-installed circuitdata;
• As-installed circuit length inm
• DC conductorresistance
• AC conductor resistance(Measured and/orderived)
(e) Verification of proper condition of externalsurfaces.
(f) Measurement of cables insulationresistance.
(g) Circuit phasing check andmarking.
(h) Capacitance of circuit
5) LV cables and multi-core controlcable
(a) General inspection of the cable routes, verification of properinstallation,
(b) fixing to the racks, bending radius,etc.
(c) Verification of proper earthing of the screen andarmoring.
(d) Measurement of cables insulationresistance.
(e) Verification of proper condition of externalsurfaces.
6) DCSystems
- Batterycharger
(a) Physical SiteInspection
(b) Testing of breaker tripsettings
(c) Measurement the continuity of each current carrying connections by
MEGGER
(d) Testing the changing output voltage function by disconnectedbattery
(e) Testing the quick charge and trickle chargemode;
(f) Testingthechargingcurrentlimiting(maximumcurrent)byshort-circuited
DCoutput;
(g) Testing earth-faultmonitoring
(h) Testing the Battery Charger inputs/digital outputs and control (LED‟s) and
protection functions at/from the Battery Charger Board , from the station
level via the RTU/HMI System (in control room) and from the RegionalDCC.
Testing the Battery Charger inputs/digital outputs, alarm indications (LED‟s) and
fault monitoring at the Battery Charger Board and at the sequence event recorder (in
control room) and at the Regional DCC.
- Batteries
(a) GeneralInspection
(b) Checking of the battery assembly to verifyclearances
(c) Checking of properly installed cell terminalcoverings
(d) Battery cells are properly installed andnumbered;
(e) Check Battery electrolyte i.e., level, color and specificgravity
(f) Charging the battery with constant-current in manual mode and recording
the charging current, voltage of each cell and electrolyte temperature of pilot
cell(s) everyhour.
(g) Discharging the battery to a final voltage of min. 1.0 V and recording the
battery voltage, cell voltage and electrolyte temperature of pilot cell(s) every
hour.
(h) Measurement of insulation resistance against the ground. For new batteries
the value shall not be > 1MΩ.
- Distribution panel
(a) General inspection (Physical and visualchecks)
(b) Operationalchecks
(c) Voltage test 2000 V, 50 Hz, 1min
(d) Insulation resistance 500 VDC, R > 50 Mohm
7) GroundingSystem-Inspection
Measuring of earthing impedance, touch and step voltage will check the
effectiveness of the installed earthing system. Measurements will be carried out
with the current injection using „Current and voltage measurement‟method.
(a) Evidence of damage to cables. Repair or replace damagedcables.
(b) Bolted connections made uptight.
(c) Welded or brazed connections aretight.
(d) Exposed cable runs adequately supported andclamped.
(e) Test the resistance of the grounding system by use of Ground Megger Method.
(Resistance to earth shall not exceed 1ohm.)
(f) Test shall be made at the followinglocations:
(g) All groundingwells
(h) Substation transformer
8) Cable TraySystems
- Physical Site Inspection
Checking of the cable tray attachments to brackets and supports, if according to
instructions and this specification and whether appropriate number and quality of
anchor bolts or expansion bolts have been used;
9) StationAuxiliary
- LV AC Distributionpanel
Checking of interior to verify clearances between live electrical parts, insulation of
phase and neutral bus from panel, and tightness of all mechanical connections;
(a) GeneralInspection
(b) Checking of wiring termination and conductor sizes including cable
densifications
(c) Electrical & Mechanical Operationaltests
(d) Voltage test 2000 V, 50 Hz, 1min
(e) Measurement of insulation resistance 500 VDC, R > 50Mohm
Part 12 : Civil Specification
1. General
nd remotely from the dispatch center.
Appendices
Appendix-A: Intermediate Station (GIS)Switchgear 33 KV
VCB,
1. Circuit breaker (CB) 33 kV, 630A, 25 kA/3 sec 1 set
3 phase gas insulated busbars
2. chamber 33 kV, 630 A, 25 kA/ 3sec 1 set
Local-Remote Control
8. switch with lamps Local/remote (White) 1 set
a)Type Nickel-Cadmium
b)Number of battery cell 40 cells
c)Nominal Voltage 1.2 V/cell
d)Nominal capacity According to calculation
e)Necessary provision
Double tier for containing cell
-Multi-tier mounting rack
groups
Fixing the cell group in the
-Fixing plates with rubber
rack for anti-vibration
-DC main conductors Connecting strip
-Signal wire For electrolyte decrease
20. DC distribution circuit 1 set
Type Self
DC outgoing feeders 12 feeders
21. Standard of accessories 1 lot
- Funnel
- Syringe
- Suction type hydrometer Specific Gravity 1.10-1.30
- Rod type thermometer -20℃ to +100℃
- Jug For 1 litter
0-3 Vforbattery cell voltage
- Digital tester
measurement
- Fillingpump
- Spanner
- Container case
(* 1) The following items shall be provided for alarm indication as a minimum:
a) DCUndervoltage
b) DC Earth fault(positive)
c) DC Earth fault(negative)
d) Chargerfailure
e) Electrolytedecrease
d) AC system (33/0.416kV 100kVA TR and One LVAC Distribution Board ) shall
comprise thefollowing:
1 set
1.1 Bushing insulators of each type
(3 phase)
1.2 Lightning arrester 36kV 10kA 1 pc
1 set
1.3 Tripping coil of C.B
(3 phase)
1.4 Auxiliary contact of C.B 1 lot
1.5 Closing coil of C.B 1 lot
1 set
1.6 Complete mechanism of C.B
(3 phase)
1.7 Complete Earth switch 1 set
Complete Voltage transformer with
33 kV/√3, 110 V /√3/ 1 set
1.8 suitable fuses ( if exist )on the HT 110 V/3 class 1.0/3 P (3 phase)
and LTsides (Single phase)
600/5/5 A,
Current transformer for metering 1pc each (1 phase)
1.9 Class 0.2/ 5P10
& protection ( for Incomer )