0% found this document useful (0 votes)
8K views3 pages

CIP Schedule UP 02-2022 - WIP 03-15-2022

This document is a capital improvement program schedule for Miami International Airport facilities development projects from February 2022. It lists 50 ongoing and planned projects from 2015 through 2036, including the Central Base Apron and Utilities Program, Concourse E Program, South Terminal Program, Passenger Boarding Bridges Program, Terminal Wide Roof project, and various support projects. The schedule outlines the planned start and finish dates for each project through 2036 to coordinate their implementation.

Uploaded by

the next miami
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
0% found this document useful (0 votes)
8K views3 pages

CIP Schedule UP 02-2022 - WIP 03-15-2022

This document is a capital improvement program schedule for Miami International Airport facilities development projects from February 2022. It lists 50 ongoing and planned projects from 2015 through 2036, including the Central Base Apron and Utilities Program, Concourse E Program, South Terminal Program, Passenger Boarding Bridges Program, Terminal Wide Roof project, and various support projects. The schedule outlines the planned start and finish dates for each project through 2036 to coordinate their implementation.

Uploaded by

the next miami
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
You are on page 1/ 3

MDAD FACILITIES DEVELOPMENT DIVISION

Data Date: 28-Feb-22


CIP SCHEDULE
As of February 28, 2022
# Activity ID Activity Name Start Finish 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036
Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q QQ
1 CENTRAL BASE APRON & UTILITIES PROGRAM 01-Dec-15 A 30-Aug-23
2 V037A - MIA Central Base Apron and Utilities Modifications and Expansion Phase 1 01-Dec-15 A 30-Aug-23
3 CONCOURSE E PROGRAM 22-Apr-16 A 22-Sep-26
4 U010C - MIA Satellite E Ramp Level Demolition and Additional Work 26-Jan-18 A 24-Jul-23
5 U010F-7 - MIA New E-Satellite Elevator 27-Nov-18 A 23-Dec-22
6 U010F-7 - MIA Satellite E Elevator Refurbishment 30-Nov-16 A 19-Feb-23
7 AA046A - MIA Lower Cc E and Satellite E Third Floor APM Platform Annunciation System 02-Dec-19 A 02-Aug-23
8 T072E-1 MIA CBP Offices at Concourse E - Third Level 27-Nov-19 A 26-Jul-23
9 T072B-3 - Lower Concourse E 400 Hz Generator Room Upgrade 22-Apr-16 A 24-Mar-24
10 AA005A MIA Lower Cc E, E Sat and DE Connector Stucco, Ext Painting, Lightning Prot. & VDGS 27-Nov-18 A 14-May-25
11 U010A-1 - Satellite E Structural Repairs - Phase II 13-Mar-20 A 12-Nov-23
12 U010F-5 - MIA Satellite E Mech and Electrical Equip Replacement - Group No. 01 (AHU#5, 6) 25-Oct-19 A 06-Aug-23
13 U010F-5 - MIA Satellite E Mech and Electrical Equip Replacement - Group No. 02 (Rooftop & APM Area) 14-May-22 22-Nov-24
14 U010F-5 - MIA Satellite E Mech and Electrical Equip Replacement - Group No. 03 (Ramp and 2nd Floor) 12-Aug-22 01-Feb-25
15 U010D-I MIA Satellite E New Chiller Plant 11-Mar-19 A 26-Jul-25
16 T072F-4 - Lower Concourse E Electrical Equipment Replacement 11-Jun-20 A 28-Jun-25
17 T072F-2 - Lower Concourse E Glazing 31-Jul-20 A 22-Sep-26
18 U010F-2 - MIA Satellite E Glazing 31-Jul-20 A 22-Sep-26
19 SOUTH TERMINAL PROGRAM 15-May-17 A 11-Apr-24
20 T042A - MIA South and Central Terminal BHS Improvements 15-May-17 A 29-Jun-22
21 T012A-1 MIA Cc H Gates & Internationalization - Cc H Stair Demolition 27-Nov-19 A 22-Jan-24
22 T012A-2&3 - MIA Cc H Gates & Internationalization - Cc H VGDS & Security System Upgrade 31-May-18 A 11-Apr-24
23 MISCELLANEOUS PROJECTS 04-Jan-16 A 13-Jul-25
24 P256C - MIA Building 704 Tenants Relocation, Finish Out of Building 701 04-Oct-17 A 04-Mar-22
25 P256B - MIA Partial Demo of Building 704, FPL Vault Relocation & Wash Rack Relocation 05-Jul-17 A 31-Mar-22
26 P256E - MIA West Cargo Fuel Tender Facility Relocation 01-Nov-17 A 30-Aug-22
27 P256A - MIA Rehabilitation of Taxiways R, S, T; Extend Taxiway R, Reconfigure Connector Taxiway M5 28-May-16 A 26-Aug-22
28 V006A -MIA Taxi and Transportation Network Company (TNC) Parking Lot and Facilities (Demo Bldg 3039) 04-Jan-21 A 03-May-23
29 V043A-4 Area A TC 12-17 & Area A K1 Doors 30-Sep-19 A 19-Aug-24
30 V042A - MIA Employee Parking Garage (Park 6 Garage) 30-Nov-16 A 13-Jul-25
31 D105C-I MIA Flamingo & Dolphin Garages Repairs and Upgrades 10-Oct-16 A 25-May-25
32 P250A-1 - MIA Cc D 3rd Floor Demolition 06-Jan-20 A 27-Oct-23
33 P250A - MIA Airport Operations Center (AOC) 04-Jan-16 A 14-Jan-25
34 V043A-5 Area B Soffit Above Checkpoint H - ON-HOLD 20-Dec-19 A 19-Apr-23
35 V043A-6 Area B TC 11 Conveyor-Dog House - ON-HOLD 31-Jan-20 A 24-Mar-24
36 PASSENGER BOARDING BRIDGES PROGRAM 03-Oct-16 A 24-Jul-24
37 W099A - MIA North & Central Terminal Passenger Boarding Bridges - Phase 1 03-Oct-16 A 24-Jul-24
38 TERMINAL WIDE ROOF 04-Dec-19 A 12-Aug-29
39 AA078A - MIA Terminal Wide Re-roofing and Lightning Systems Upgrades 04-Dec-19 A 12-Aug-29
40 SUPPORT PROJECTS 20-May-15 A 15-Nov-26
41 Y003A - MIA Airport Surface Management System (SMS) 01-Sep-18 A 18-Mar-22
42 V056A - MIA Conc. D Mechanical Room Mildew Remediation 07-Jan-20 A 31-Mar-22
43 X149A - MIA Cc G Preconditioned Air Equipment 10-Sep-18 A 28-Jun-22
44 AA142A MIA Perimeter Protection 15-Jan-20 A 14-Jul-23
45 U040A - MIA Parking Access & Revenue Control System Replacement 09-Oct-15 A 08-Dec-22
46 V144A - MIA Credentialing and Identity Management System (COTS) 28-Feb-17 A 10-Jul-23
47 AA044A - MIA Checkpoint Queue Wait Time Analyzer 23-Jun-17 A 27-Sep-25

A/E Procurement Bid, Award & NTP Planning Page 1 of 3 DRAFT (Work in Progress for Discuss Purposes Only)
PRINT DATE 03-15-2022
Contract Documents Construction Closeout
MDAD FACILITIES DEVELOPMENT DIVISION
Data Date: 28-Feb-22
CIP SCHEDULE
As of February 28, 2022
# Activity ID Activity Name Start Finish 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036
Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q QQ
48 W064A - MIA Cc E thru F Life Safety Upgrades 02-Mar-21 A 03-Jan-23
49 AA094A - Biometric Enabled Common Use Passenger Processing System 11-May-20 A 20-Dec-24
50 AA136A - MDAD Security Cameras Project 30-Nov-20 A 20-Sep-24
51 V058A - EFSO IVP 14 (Near Gate D16) 01-Jun-20 A 07-Jan-24
52 U128A - MIA Central Terminal CCTV and Access Control 18-Oct-21 A 29-Jan-24
53 V102A - OPF Customs Building Expansion-Remodeling 20-May-15 A 06-May-24
54 V100A - MIA Cc. J Gates Advanced Visual Docking Guidance System (VDGS) 29-Aug-16 A 06-Oct-25
55 U023A - MIA South Terminal Smoke Evacuation Modifications 02-Jan-19 A 15-Nov-26
56 AIRFIELD / AIRSIDE 25-Mar-21 A 06-Apr-28
57 AA054A - MIA Runway 9-27 Rehabilitation 25-Mar-21 A 07-Nov-27
58 Y118A - MIA RIM Hot Spot 4 (Corral Area) 29-Jul-22 06-Apr-28
59 NORTH TERMINAL PROGRAM 30-Nov-19 A 27-Mar-32
60 AA126A - MIA North Terminal Ramp Level Restrooms Upgrade 30-Nov-19 A 09-Oct-24
61 AA048A - MIA North Terminal Gate Optimization Phase 1 & 2 28-Feb-22 20-Jan-30
62 AA048B - MIA North Terminal Gate Infrastructure Upgrades 28-Feb-22 06-Nov-28
63 AC001A - Central Base AOA Construction Gate 28-Feb-22 11-Apr-26
64 T180B - MIA Concourse D West Extension - D60 Building Expansion 27-Jun-22 27-Mar-32
65 T180D - MIA Concourse D West Extension - D60 Apron and Utilities 27-Jun-22 27-Mar-32
66 BA017A - MIA North Terminal Additional Skytrain Vehicles 15-Jun-22 28-Jul-26
67 AB040A - MIA NTD Baggage Handling System Modifications to the Inline CBIS 18-Sep-20 A 04-Jun-30
68 CENTRAL TERMINAL 27-Dec-19 A 01-Nov-41
69 P248A - MIA Central Terminal Upper Drive Facade & Curbside (Design) 27-Dec-19 A 29-Apr-22
70 V008F - MIA Cc F Refurbishment Phase 1 01-Dec-20 A 28-Mar-22
71 V008F - MIA Cc F Refurbishment Phase 2 28-Jun-21 A 13-Jan-25
72 V008A - MIA Central Terminal Redevelopment - Phase 1 (E-F Connector & Cc F Infill) 04-Aug-22 19-Oct-31
73 V008C - MIA Central Terminal Redevelopment-Phase 2 (Facade, Checkpoint, V.C., E-F TC, Roof Bump) 04-Aug-22 18-Oct-32
74 T072L - MIA Lower Cc E FIS Renovations - Phase 2 21-Jun-23 16-Apr-32
75 V008B - MIA New Concourse F 08-Jan-24 04-Nov-34
76 V013A - MIA Concourse F New Apron Phase 1 12-Oct-28 07-Nov-34
77 V013A - MIA Concourse F New Apron Phase 2 31-Oct-30 05-May-36
78 V013B - MIA Cc F Demo Phase 1 - Headhouse Demo & New Hardstand Area 07-Jul-31 02-Nov-38
79 V013C - MIA Cc F Demo Phase 2 - Cc F Pier Demo & New Cc F Apron Phase 3 02-Jan-34 30-Apr-41
80 P259A - MIA Concourse "E" and "F" Taxilane and Apron Rehabilitation 15-Oct-37 01-Nov-41
81 V008E - MIA Cc F Enabling Gates Striping 13-Jun-25 03-Oct-29
82 X079A MIA Concourse G Demolition 12-Jun-25 11-Oct-32
83 SOUTH TERMINAL EXPANSION 29-Nov-19 A 15-May-30
84 T042B - BHS Cross Over Central to South Terminal 11-Oct-21 A 17-Jun-24
85 W019B - MIA Fueling Maintenance and Administration Consolidation Building - Enabling 22-Apr-24 08-Jul-29
86 X071A - MIA Vehicle Fueling and Car Wash Facility - South Terminal Enabling 28-Feb-22 16-Apr-25
87 AB048B - MIA Demolition Building 3051 (Gas Station) and 3045 (Car Wash) - South Terminal Enabling 10-Apr-23 13-Mar-26
88 AB049A - Temporary South Terminal GSE facility & 20th Street Modifications AOA - Enabling 14-Mar-24 08-Feb-28
89 AB050A - MIA Building 3050 Demolition - South Terminal Enabling 24-Jun-24 07-Feb-27
90 V005A - MIA South Terminal Apron and Utilities Modification 28-Feb-22 15-May-30
91 X078A - MIA South Terminal Expansion East (New Gates) Phase 1 28-Feb-22 15-May-30
92 AA018B - MIA Concourse H Glazing, Curtain Wall Assessment and Corrective Action 29-Nov-19 A 21-Aug-25
93 CARGO AND NON-TERMINAL BUILDINGS 01-Dec-20 A 01-Sep-32
94 X035C - MIA Buildings 703 and 703A Demolition and Environmental Assessment and Remediation 30-Sep-21 A 29-Oct-24

A/E Procurement Bid, Award & NTP Planning Page 2 of 3 DRAFT (Work in Progress for Discuss Purposes Only)
PRINT DATE 03-15-2022
Contract Documents Construction Closeout
MDAD FACILITIES DEVELOPMENT DIVISION
Data Date: 28-Feb-22
CIP SCHEDULE
As of February 28, 2022
# Activity ID Activity Name Start Finish 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036
Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q QQ
95 X035A - MIA Building 702 Apron & Airside Improvements 28-Feb-22 01-Jan-28
96 AA058A - MIA Consolidated Office Complex (Finishes Cc D Landside) 01-Dec-20 A 18-Nov-24
97 AA058C - Finance and Administration Division Offices Relocation 28-Jan-22 A 03-May-25
98 AA058D - MIA Building 5A Tenants Relocation Projects 31-Dec-22 28-Nov-26
99 TBD - MIA Building 5A Tenants Relocation Projects 31-Dec-22 28-Nov-26
100 AB041A - MIA Building 3032 Replacement 28-Feb-22 28-Nov-26
101 AA058B - MIA Demolition Building 5A 20-Nov-22 22-Feb-28
102 V038A - MIA GSE Facility for North Terminal 28-Sep-23 26-Apr-30
103 X035E - MIA Demolition Building 704 05-Aug-27 20-May-31
104 AA039A - MIA West Cargo Truck Parking 05-Oct-26 01-Sep-32
105 LANDSIDE / ROADWAYS 11-Jul-22 02-Apr-33
106 AC053A - MIA Dolphin/Flamingo and New Employee Parking Garage 6 Exterior Cladding 11-Jul-22 26-Sep-27
107 AB016A MIA AOA Perimeter Security Hardening Project - Phase 01 04-Aug-22 18-Jan-28
108 X061A - MIA Perimeter Road Bridge Replacement 05-Jun-24 02-Apr-33
109 FUEL FACILITIES 27-Oct-21 A 31-Mar-33
110 W019A - MIA Fuel Storage Facility Expansion Phase 1 27-Oct-21 A 21-Jun-29
111 W019C - MIA Fuel Storage Facility Expansion Phase 2 09-Apr-27 31-Mar-33
112 GENERAL AVIATION AIRPORTS 31-Aug-18 A 15-Jan-31
113 V009A - TMB RIM HS1 With Taxiway H West Extension to Threshold 24-Oct-18 A 01-Aug-23
114 X010A - OPF Engine Run Up Pad 15-Aug-19 A 31-Dec-24
115 Y145A Homestead General Aviation (X51A) Security Project Phase2 - Lightning, Cameras, Access Control 31-Aug-18 A 01-Feb-24
116 X009A - OPF Runway 9-27 Rehabilitation 17-Aug-20 A 11-Oct-25
117 W125A/B - TMB South Apron Expansion / New Taxilane 28-Feb-22 08-Aug-28
118 AA022A - TMB New ATCT 31-Aug-21 A 15-Jan-31
119 TERMINAL-WIDE 05-Apr-21 A 23-Jun-28
120 AA075A - MIA Tenant Relocation Projects 05-Apr-21 A 14-Apr-27
121 AC007A - MIA Bldg. 3030 1st Floor D-Wing Tenant Relocation 05-Apr-21 A 06-Sep-23
122 AC007B - SITA Demolition & Renovation 01-Sep-21 A 14-Oct-23
123 TBD - Trailer City for Building 3050 Offices Replacement 26-Sep-22 12-Nov-25
124 TBD - CTR PHASE 1 Tenant Relocation Project 01-Jun-23 14-Apr-27
125 AC045A - MIA PASI Hardware System Upgrade (Terminal & Concourses) 15-Oct-21 A 01-Mar-24
126 BA013A - MIA Security Checkpoints Equipment Replacement 01-Aug-22 09-Mar-26
127 BA013A - Checkpoint D2 01-Aug-22 15-Jun-24
128 BA013A - Checkpoint J South 01-Aug-22 15-Jun-24
129 BA013A - Checkpoint J Central 31-Dec-22 12-Nov-24
130 BA013A - Checkpoint H 23-Mar-23 27-May-25
131 BA013A - Checkpoint G 04-Nov-23 09-Mar-26
132 BA013A - Checkpoints - Equipments 01-Aug-22 23-Jun-25
133 W099B - MIA North and Central Terminal Passenger Loading Bridges Phase 2 07-Apr-23 23-Jun-28
134 TERMINAL WIDE PUBLIC RESTROOMS 04-Sep-19 A 17-Jun-30
135 AA017C-2 - MIA South Terminal Public Restrooms Modernization Phase C2, 6 RR 18-Dec-19 A 13-Mar-23
136 AA017C-1 - MIA South Terminal Public Restrooms Modernization Phase C1, 10 RR 24-Oct-19 A 30-Nov-23
137 AA017A-2 - MIA North Terminal Public Restrooms Modernization Phase A2, 12 RR 13-Dec-19 A 04-Nov-23
138 AA017B-1 - MIA Central Terminal Public Restrooms Modernization Phase B1, 6 RR 10-Sep-19 A 29-Jul-23
139 AA017A-1 - MIA North Terminal Public Restrooms Modernization Phase A1, 10 RR 16-Dec-19 A 09-Nov-23
140 AA017B-2 - MIA Central Terminal Public Restrooms Modernization Phase B2, 8 RR 04-Sep-19 A 12-Oct-23
141 AA017D - MIA Terminal Public Restroom Modernization - Phase 1.2-5 21-May-21 A 17-Jun-30

A/E Procurement Bid, Award & NTP Planning Page 3 of 3 DRAFT (Work in Progress for Discuss Purposes Only)