An industrial operation consists of five elements with following observed time and the
performance ratings.
Element Observed time (min.) Performance Ratings (%)
A 0.20 85
B 0.08 80
C 0.50 90
D 0.12 85
E 0.10 80
Assuming that rest and personal allowance as 15% and contingency allowance as 2% of the
basic time. Calculate standard time per piece.
2. A time study was conducted on a job contains four elements. The observed times and
performance ratings are shown in the following table for six cycles.
Performance Observed time (mins)
Elements Rating (%) 1 2 3 4 5 6
1 90 0.44 0.50 0.43 0.45 0.48 0.46
2 85 1.50 1.54 1.47 1.51 1.49 1.52
3 110 0.84 0.89 0.77 0.83 0.85 0.80
4 110 1.10 1.14 1.08 1.20 1.16 1.26
Assuming that rest and personal allowance as 15% and contingency allowance as 2% of the basic
time. Complete the standard time.