Problem Set 01 Work Study

The document contains two examples of calculating standard times for industrial operations based on observed times and performance ratings of elements. The first example has 5 elements and the second has 4 elements. Standard time is calculated by accounting for rest/personal allowance of 15% and contingency allowance of 2% of basic time.

Uploaded by

Amit
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
21 views

Problem Set 01 Work Study

The document contains two examples of calculating standard times for industrial operations based on observed times and performance ratings of elements. The first example has 5 elements and the second has 4 elements. Standard time is calculated by accounting for rest/personal allowance of 15% and contingency allowance of 2% of basic time.

Uploaded by

Amit
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

1.

An industrial operation consists of five elements with following observed time and the
performance ratings.
Element Observed time (min.) Performance Ratings (%)
A 0.20 85
B 0.08 80
C 0.50 90
D 0.12 85
E 0.10 80
Assuming that rest and personal allowance as 15% and contingency allowance as 2% of the
basic time. Calculate standard time per piece.

2. A time study was conducted on a job contains four elements. The observed times and
performance ratings are shown in the following table for six cycles.
Performance Observed time (mins)
Elements Rating (%) 1 2 3 4 5 6
1 90 0.44 0.50 0.43 0.45 0.48 0.46
2 85 1.50 1.54 1.47 1.51 1.49 1.52
3 110 0.84 0.89 0.77 0.83 0.85 0.80
4 110 1.10 1.14 1.08 1.20 1.16 1.26
Assuming that rest and personal allowance as 15% and contingency allowance as 2% of the basic
time. Complete the standard time.

WORK STUDY Page 1