MOS For T&C For CO2 System-1
MOS For T&C For CO2 System-1
MOS For T&C For CO2 System-1
Method of statements (MOS) for Testing & Commissioning for CO2 System
pg. 1
COMEP
Method of statements (MOS) for Testing & Commissioning for CO2 System
TABLE OF CONTENTS
1. SCOPE OF WORK
2. REFERENCE DOCUMENTS
3. RESPONSIBILITIES:
4. SAFETY PLAN
pg. 2
COMEP
Method of statements (MOS) for Testing & Commissioning for CO2 System
1. SCOPE OF WORK
The methodology covers the procedure to be followed the sequence of work. The main works involve in the
Testing & Commissioning for C O 2 S ys t e m and specialties in line with specifications. This includes but is not
limited to the support systems, inspection, testing and acceptance of such Testing & Commissioning for CO2
System as indicated on the approved project shop drawings.
2. REFERENCE DOCUMENT
Project Specification
Approved Shop Drawing
Approved Safety Plan
Manufacturer Recommendations
3. RESPONSIBILITIES:
It is the Site Construction Manager's duty to ensure that all necessary safety and protective equipment are provided
along with properly trained and the qualified personnel. Moreover, to ensure that all works are carried out in
accordance with this method statement.
It is the Site Engineer/Supervisor's duty to organize the work force in a safe manner and to ensure that safety and
protective equipment are being properly utilized. He must also ensure that the method statement procedure is followed
and notify Consultant for inspection.
Use appropriate equipment to complete assigned task. Abide by all Site Safety and quality requirements.
The Safety Engineer is responsible for devising and implementing programs and plans to safeguard, health and safety
of all employees, and to prevent loss or damage to the existing assets and projects, he is responsible for the
implementing of the safety programs. He is also responsible to:
Provide support to site safety officers advising them on safe working methods and assisting with training of personnel.
Carryout regular site safety audits and reports and correct unsafe work practices and potential hazards.
Investigate and report all accidents near misses and recommended preventive measures. Ensure Maintenances of good
hygienic standards and availability of safety equipment and first aid treatment.
pg. 3
COMEP
Method of statements (MOS) for Testing & Commissioning for CO2 System
Cooperate with safety engineer to create and maintain safe working conditions. Assist the Site Engineers and foremen
to organize the work area so that the men can perform their duties with maximum efficiency and minimize risk to
them or to equipment. Inspect equipment and tools before use to ensure correct storage and properly utilization.
Maintain record of all injuries and damages on site, submit reports as required.
It is the QA/QC Project Quality Manager's responsibility to ensure that all inspections and tests are carried out as per
Project requirement and that all are recorded.
Safety plan requires that proper regard is given to occupational and environmental safety during all activities.
pg. 4
COMEP
Method of statements (MOS) for Testing & Commissioning for CO2 System
The purpose of this method statement is to outline the method for handling, storage, installation, testing and
commissioning for the FM200 in accordance with the requirements specified in the relevant NFPA Codes,
Standards and Project specifications in all applicable areas for the project.
A PRE-COMMISSIONING
Ensure that the installation activity of the FM200 fire extinguishing system is completed.
Ensure that the Co2 system has been checked against the approved installation drawings.
Ensure that the pipes are cleaned by blowing air.
Ensure that the leak test of the piping has been carried out and witnessed.
Ensure that the discharge nozzles and orifice units have been installed in accordance with the approved gas
flow calculations.
Ensure that the actuation hose and discharge hose are rigidly fitted.
Ensure that the Co2 cylinder pressure gauges showing the acceptable pressure range.
Ensure that the installation of control panel and associated cabling / installation of devices are completed and
tested.
Ensure that the termination to all devices (like smoke detectors, bells, flasher beacons, solenoids & pressure
switches) are completed and loops are checked.
Ensure that all the identification and warning signs, flow directions are marked as appropriate / required.
Ensure that the solenoid actuator is disconnected from the master cylinder.
pg. 5
COMEP
Method of statements (MOS) for Testing & Commissioning for CO2 System
COMMISSIONING
Before commencing the commissioning activities, please ensure that solenoid actuator is disconnected from
the master cylinder and all loops have been checked for continuity and are witnessed by client/ contractors.
Switch ON the power for the control panel and check for the following functions of the control panel
Using Auto / manual / disabled key switch, check the operation of system status indication
Operate 1 NO. Of smoke detector in the protected area using a smoke gun and confirm the FOLLOWING Sequence
of operations:
Common fire alarm bell & common fire beacon in the building activate.
Fire indication on the Extinguishing Control Panel operates.
Fire signal on the F&G Panel and the shutdown of equipment.
Operate one more detector in the protected area and confirm the FOLLOWING SEQUENCE OF OPERATIONS:
Pre-discharge sounder inside & outside the protected room is active. (Intermittent Tone)
On expiry of time delay period, confirm that the FM200 solenoid actuator is activated.
Discharged sounder/beacon outside
Protected area is activated. (Tone continuous)
Operate the gas discharge pressure switch and confirm the following:
On completion of the tests as per above, reset the panel and install the solenoid on the master cylinder to
place the system in service
Install the manual release leaver to the master cylinder.
pg. 6