Report No.
:
ALIGNMENT INSPECTION REPORT
(VERTICAL EQUIPMENT) Page : of
Project Name : Job No. :
Area / Unit : Date :
Equipment No. :: Subcon. Name :
0 OD (mm) :
Height (mm) :
270 90
180
+ 0 - + 0 -
Plumbing (Tolerance : 1mm/1M of Height) (Unit : mm)
Orientation Top Bottom Deviation Result Remark
Inspected /
Prepared By Approved By Witnessed By
. Sign / Date Sign / Date Owner Sign / Date
Form No. : PL-6507-EQA-01
Report No. :
ALIGNMENT INSPECTION REPORT
(HORIZONTAL EQUIPMENT) Page : of
Project Name : Job No. :
Area / Unit : Date :
Equipment No. :: Subcon. Name :
A B
C D
A B C D A B
C D
Elevation (Tolerance : 1mm/1M of Length)
Point Design Measurement Deviation Result Remarks
Inspected /
Prepared By Approved By Witnessed By
Sign / Date Sign / Date Owner Sign / Date
Form No. : PL-6507-EQA-02
Report No. :
LEVELING INSPECTION REPORT -
PUMP & COMPRESSOR (A) Page : of
Project Name : Job No. :
Area / Unit : Date :
Equipment No. :: Subcon. Name :
Pump or
270 90
Comp. Driver
180
Base Level : Before Grouting Scale : 1/100 mm
Measuring location Tolerance Actual Result Remarks
Inspected /
Prepared By Approved By Witnessed By
. Sign / Date Sign / Date Owner Sign / Date
Form No. : PL-6507-EQA-03
Report No. :
LEVELING INSPECTION REPORT -
PUMP & COMPRESSOR (B) Page : of
Project Name : Job No. :
Area / Unit : Date :
Equipment No. :: Subcon. Name :
Pump or
Comp.
270 90
Driver
180
Base Level : Before Grouting Scale : 1/100 mm
Measuring location Tolerance Actual Result Remarks
Inspected /
Prepared By Approved By Witnessed By
. Sign / Date Sign / Date Owner Sign / Date
Form No. : PL-6507-EQA-04
COUPLING ALIGNMENT Report No. :
INSPECTION REPORT - PUMP &
Page : of
COMPRESSOR (A)
Project Name : Job No. :
Area / Unit : Date :
Equipment No. :: Subcon. Name :
After Grouting After Piping After Flushing
A 0
Pump or
270 90
Comp. Driver
A
180
A-A
Alignment : Comp' / Pump - Driver Scale : 1/100 mm
Check Location
Measuring classification Tolerance Result Remarks
0 90 180 270
Parallel
Coupling Gap
Inspected /
Prepared By Approved By Witnessed By
Sign / Date P Sign / Date Owner Sign / Date
Form No. : PL-6507-EQA-05
COUPLING ALIGNMENT Report No. :
INSPECTION REPORT - PUMP &
Page : of
COMPRESSOR (B)
Project Name : Job No. :
Area / Unit : Date :
Equipment No. :: Subcon. Name :
After Grouting After Piping After Flushing
Pump or
A
Comp.
270 90
A
Driver
180
A-A
A
Alignment : Comp' / Pump - Gear Box Scale : 1/100 mm
Check Location
Measuring classification Tolerance Result Remarks
0 90 180 270
Parallel
Coupling Gap
Alignment : Gear Box - Driver Scale : 1/100 mm
Check Location
Measuring classification Tolerance Result Remarks
0 90 180 270
Parallel
Coupling Gap
Inspected /
Prepared By Approved By Witnessed By
Sign / Date Sign / Date Owner Sign / Date
Form No. : PL-6507-EQA-06