Alignment Inspection Report (Vertical Equipment) : - Sign / Date Sign / Date Owner Sign / Date

The document reports on alignment inspections for vertical and horizontal equipment, pumps, compressors, and couplings. It includes inspection reports on the plumbing, elevation, leveling before and after grouting, and coupling alignment after grouting, piping, and flushing. Measurement points and tolerances are defined, with actual measurement values, deviations, and inspection results and remarks provided.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (4 votes)
4K views6 pages

Alignment Inspection Report (Vertical Equipment) : - Sign / Date Sign / Date Owner Sign / Date

The document reports on alignment inspections for vertical and horizontal equipment, pumps, compressors, and couplings. It includes inspection reports on the plumbing, elevation, leveling before and after grouting, and coupling alignment after grouting, piping, and flushing. Measurement points and tolerances are defined, with actual measurement values, deviations, and inspection results and remarks provided.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 6

Report No.

:
ALIGNMENT INSPECTION REPORT
(VERTICAL EQUIPMENT) Page : of

Project Name : Job No. :

Area / Unit : Date :

Equipment No. :: Subcon. Name :

0 OD (mm) :
Height (mm) :

270 90

180

+ 0 - + 0 -

Plumbing (Tolerance : 1mm/1M of Height) (Unit : mm)

Orientation Top Bottom Deviation Result Remark

Inspected /
Prepared By Approved By Witnessed By
. Sign / Date Sign / Date Owner Sign / Date

Form No. : PL-6507-EQA-01


Report No. :
ALIGNMENT INSPECTION REPORT
(HORIZONTAL EQUIPMENT) Page : of

Project Name : Job No. :

Area / Unit : Date :

Equipment No. :: Subcon. Name :

A B

C D

A B C D A B
C D

Elevation (Tolerance : 1mm/1M of Length)

Point Design Measurement Deviation Result Remarks

Inspected /
Prepared By Approved By Witnessed By
Sign / Date Sign / Date Owner Sign / Date

Form No. : PL-6507-EQA-02


Report No. :
LEVELING INSPECTION REPORT -
PUMP & COMPRESSOR (A) Page : of

Project Name : Job No. :

Area / Unit : Date :

Equipment No. :: Subcon. Name :

Pump or
270 90
Comp. Driver

180

Base Level : Before Grouting Scale : 1/100 mm


Measuring location Tolerance Actual Result Remarks

Inspected /
Prepared By Approved By Witnessed By
. Sign / Date Sign / Date Owner Sign / Date

Form No. : PL-6507-EQA-03


Report No. :
LEVELING INSPECTION REPORT -
PUMP & COMPRESSOR (B) Page : of

Project Name : Job No. :

Area / Unit : Date :

Equipment No. :: Subcon. Name :

Pump or
Comp.

270 90

Driver

180

Base Level : Before Grouting Scale : 1/100 mm


Measuring location Tolerance Actual Result Remarks

Inspected /
Prepared By Approved By Witnessed By
. Sign / Date Sign / Date Owner Sign / Date

Form No. : PL-6507-EQA-04


COUPLING ALIGNMENT Report No. :
INSPECTION REPORT - PUMP &
Page : of
COMPRESSOR (A)
Project Name : Job No. :

Area / Unit : Date :

Equipment No. :: Subcon. Name :

After Grouting After Piping After Flushing

A 0

Pump or
270 90
Comp. Driver

A
180
A-A

Alignment : Comp' / Pump - Driver Scale : 1/100 mm


Check Location
Measuring classification Tolerance Result Remarks
0 90 180 270
Parallel

Coupling Gap

Inspected /
Prepared By Approved By Witnessed By
Sign / Date P Sign / Date Owner Sign / Date

Form No. : PL-6507-EQA-05


COUPLING ALIGNMENT Report No. :
INSPECTION REPORT - PUMP &
Page : of
COMPRESSOR (B)
Project Name : Job No. :

Area / Unit : Date :

Equipment No. :: Subcon. Name :

After Grouting After Piping After Flushing

Pump or
A
Comp.

270 90

A
Driver

180
A-A
A

Alignment : Comp' / Pump - Gear Box Scale : 1/100 mm


Check Location
Measuring classification Tolerance Result Remarks
0 90 180 270
Parallel

Coupling Gap

Alignment : Gear Box - Driver Scale : 1/100 mm


Check Location
Measuring classification Tolerance Result Remarks
0 90 180 270
Parallel

Coupling Gap

Inspected /
Prepared By Approved By Witnessed By
Sign / Date Sign / Date Owner Sign / Date

Form No. : PL-6507-EQA-06