Quantity Estimate Kanari Park
Quantity Estimate Kanari Park
Quantity Estimate Kanari Park
Name of Project : Kanari Park Khanepani Tanki Nirman Tatha Bitaran Pranali
Name of Work: Drilling and Installation 250/200 mm diameter Deep tubewell by Rig Machine
(Using appropriate drilling method)
S.No. Description of Work Unit Quantity Remarks
Name of Project : Kanari Park Khanepani Tanki Nirman Tatha Bitaran Pranali
Name of Work: Suppy and Installation of Pump and Pumping Main (for One Tube Well )
S.No. Description of Works Unit Quantity Remarks
Name of Project : Kanari Park Khanepani Tanki Nirman Tatha Bitaran Pranali
Name of Work: Suppy and Installation of Electrical Accessories
Name of Project : Kanari Park Khanepani Tanki Nirman Tatha Bitaran Pranali
Name of Work: Borehole Platform
Height or
S.No. Description of Works No. Length Breadth Quantity Unit Remarks
Breadth
8 Reinforcement bar for RCC work @ 135 kg per cum of concrete 225.45 kg
9 Formwork for PCC/RCC work:
PCC in foundation 2 9.20 - 0.075 1.38
Tie beam outer face 2 5.10 - 0.30 3.06
Thrust block for pipe 2 1.70 - 1.00 3.4
Support block for flanged Tee 1 1.60 - 0.50 0.8
8.64 sqm
10 12.5mm thick plaster in 1:4 cement mortar:
Platform 1 2.50 1.60 - 4
Tie beam outer face 2 5.10 - 0.30 3.06
Thrust block for pipe 2 1.70 - 1.00 3.4
Support block for flanged Tee 1 1.60 - 0.50 0.8
11.26 sqm
11 Supply and fixing gantry for chain pulley:
a) Supply of accessories -
100 mm Ø Heavy Class GI Pipe 1 9.60 - - 9.6 m
100 mm Ø GI Socket 4 - - - 4 nos.
100 mm Ø GI Elbow 2 - - - 2 nos.
250x250x12 mm MS Base Plate 4 - - - 4 nos.
12 mm Ø 150 mm long Nut Bolt 8 - - - 8 nos.
B Civil works
1 Site cleareance 1 11 11 121 m2
0
2 Earthwork excavation in Hard soil 0
Earthwork excavation upto 1.5 m for raft footing foundation
including 0.5 +0.5 = 1.0 m extra wide for working space width of 0
raft footing = 2.0 m
Excavation in Hard soil 1 21.99 3 2.5 164.93 m3
Stone soling (Hard core) without sand (Water Tank area below
4
PCC)
Water Tank area below PCC 1 21.99 2 0.15 6.6 m3
0
5 Sand filling work including watering compaction with Hand 1 21.99 2 0.055 2.42 m3
0
6 Lean concrete PCC (M15) in foundation
Water Tank area below footing 1 21.99 2 0.1 4.4
Sub-total of PCC (M15) 4.4 m3
0
7 PCC for RCC M20 (1:1.5:3)
7.1 PCC up to 4 m height
- Raft slab for foundation 1 21.99 2 0.25 11
0
- Raft beam /Circular girder for foundation 1 21.99 0.5 0.5 5.5
0
- Foundation of staircase 0
0
(0.17+.
- Landing beam for staircase 2 0.9 0.35 0.08
07)/2
0
(1.34+0
- Platform / landing slab for staircase 2 0.9 0.18 0.31
.60)/2
- Steps ( T = 200 mm, R = 200 mm) of staircase 24 0.9 0.27 0.15 0.88
0
- Waist slab 2 3.55 0.9 0.18 1.15
Length Breadth Height
S.No Description of Work NO Quantity Unit Remarks
(m) (m) (m)
- Columns 6 5.45 0.45 0.45 6.63
0
- Bracing beam 1 21.99 0.35 0.5 3.85
Sub-total 29.4 m3
RCC post (100 x 100 mm) for railing at the edge of Staircase 29 0.13 0.1 0.9 0.34
9.3 Column
- Columns at Foundation to Ground 6 1.445 1.8 15.61 m2
Columns Upto 4m 6 4 1.8 43.2 m2
Columns from 4m to 8m 6 4 1.8 43.2 m2
Columns from 8m to 12m 6 4 1.8 43.2 m2
Columns from 12m to 16m 6 4 1.8 43.2 m2
Columns from 16m to 20m 6 4 1.8 43.2 m2
- RCC post for railing at cantilever slab(Above20m) 16 0.46 0.9 6.62
RCC post for railing at Top Dome slab(Above 20m) 6 0.46 0.9 2.48
RCC post for railing at Staircase 29 0.46 0.9 12.01
Sub-total of formwork 252.72
Total formwork 252.72 m2
9.4 Beam
9.4.1 Formwork to 4 m height
- Bracing beam 1 21.9911 1.35 29.69 m2
9.4.2 Formwork from 4 m to 8 m height 0
- Bracing beam 1 21.9911 1.35 29.69 m2
9.4.2 Formwork from 8 m to 12 m height 0
- Bracing beam 1 21.9911 1.35 29.69 m2
9.4.2 Formwork from 12 m to 16 m height 0
- Bracing beam 1 21.9911 1.35 29.69 m2
9.4.3 Formwork from 16 m to 20 m height 0
- Bottom circular ring beam 1 21.9911 1.6 35.19 m2
spherica
l
- Top dome 1 48.45
surface
area =
Sub-total 104.14
Sub-total 104.14
surface
- Top dome (top & bottom surfaces) 2 48.45 96.9
area =
16 32 mm dia GI railing
- Railing on cantilever balcony 2 24.7 49.4
Railing on Top of Dome 2 5.5 11
Railing on staircase (longitudinal both sides) from base up to
- 0
top , Nos. = 2*2
2 53.6 107.2
Sub-total of 32 mm dia. GI railing 167.6 Rm
b Washout Fittings
i) DN 150 DI Tail Piece 1 1 No
ii) DN 150 DI Pipe(Class k-9) 20 20 No
iii) DN 150 DI Bell mouth 1 1 Rm
iv) DN 150 DI Duck Foot bend 90 degree Double Flanged 1 1 No
v) DN 150 DI Sluice Valve 1 1 No
vi) DN 150 DI Mechanical coupling with Rubber ring 1 1 No
vii) DN 150 DI bend with Double Flanged 1 1 No
c Overflow Fittings
Length Breadth Height
S.No Description of Work NO Quantity Unit Remarks
(m) (m) (m)
i) DN 150 DI Tail Piece 1 1 No
ii) DN 150 DI Pipe(Class k-9) 24 24 No
iii) DN 150 DI Bell mouth 1 1 No
iv) DN 150 DI Duck Foot bend 90 degree Double Flanged 1 1 Rm
v) DN 150 DI Mechanical coupling with Rubber ring 1 1 No
vi) DN 150 DI bend with Double Flanged 1 1 No
d Outlet Fittings
i) DN 200 DI Tail Piece 1 1 No
ii) DN 150 DI Pipe(Class k-9) 20 20 No
iii) DN 150 DI Bell mouth 1 1 No
iv) DN 150 DI Duck Foot bend 90 degree Double Flanged 1 1 No
v) DN 150 DI Sluice Valve 1 1 Rm
vi) DN 150 DI Mechanical coupling with Rubber ring 1 1 No
vii) DN 150 DI Bulk Water Meter 1 1 No
viii) DN 150 DI bend with Double Flanged 1 1 No
Name of Project : Kanari Park Khanepani Tanki Nirman Tatha Bitaran Pranali
Name of Work: Valve Box
Height or
S.No. Description of Works No. Length Breadth Quantity Unit
Breadth
1 EARTH WORK
TOTAL 1.76625 m2
TOTAL 1.604438 m3
2 CONCRETE WORK
Name of Project : Kanari Park Khanepani Tanki Nirman Tatha Bitaran Pranali
Name of Work: Valve Chamber(0.9*0.9*1)
Height or
S.No. Description of Works No. Length Breadth Quantity Unit
Breadth
1 EARTH WORK
2 CONCRETE WORK
4 Stone Work
4.1 Boulder Soling 1 0.07068583470577 0.15 0.010603
1 0.44178646691107 0.15 0.066268
Total 0.076871 m3
Deductions
1 0.2355 0.075 0.15 0.002649
Total 0.074221 m3