Arch Bridge Code Updated Upto ACS 9
Arch Bridge Code Updated Upto ACS 9
GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
(Railway Board)
ADOPTED –1941
FIRST REVISION - 1962
ISSUED BY
VI-i
CONTENTS
PAGE No.
1. SCOPE … 1
2. DESIGN LOADS AND THEIR METHODS OF APPLICATION … 1
2.1 Dead Load … 1
2.2 Live Load … 1
2.3 Temperature Stresses … 1
2.4 Rib-shortening Stresses … 1
2.5 Shrinkage Stresses … 1
3. SHAPE OF THE ARCH RING … 1
4. THICKNESS OF ARCH RIB … 2
5. ANALYSIS OF STRESSES IN THE ARCH RING … 2
5.1 Conditions of Loading … 2
5.2 Method of Analysis … 2
5.3 Existing Arches … 2
6. ‘EFFECTIVE LENGTH’ OF ARCH RING … 3
7. ABUTMENTS FOR ARCH BRIDGES … 3
7.1 Thickness at the skew-backs … 3
7.2 Forces Acting on an Abutment … 3
7.3 Conditions of stability … 4
7.4 Foundations for Abutments … 4
8. PIERS OF ARCH BRIDGES … 4
8.1 Thickness at Top … 4
8.2 Forces Acting on the Pier … 4
8.3 Conditions of Stability … 5
8.4 Foundations for Piers … 5
9. DESIGN OF RETURN AND WING WALLS … 5
10. ECONOMY IN ARCH BRIDGE DESIGN … 5
11. TYPE OF MASONRY … 5
12. WORKING STRESSES … 5
12.1 Masonry Arches … 5
12.2 Plain Concrete Arches … 5
13. FOUNDATION PRESSURE … 5
14. SEISMIC EFFECT … 5
15. SKEW ARCHES … 6
16. WEEP HOLES … 6
17. FILLING OVER ARCHES … 6
18. STRIKING OF CENTRES AND APPLICATION OF LOAD … 6
VI-ii
Indian Railway Standard
CODE OF PRACTICE FOR
THE DESIGN AND CONSTRUCTION OF MASONRY AND
PLAIN CONCRETE ARCH BRIDGES
(Arch Bridge Code)
VI-3
in this case may be taken as 0.7 and the safe (c) Dead load plus live load on the entire
shearing stress as given in Clause 12. span.
7.2. Forces Acting on an Abutment: For each of the above conditions of loading,
the line of pressure in the course enumerated
7.2.1 The forces acting on an abutment are
above shall lie within the middle half of every
as follows:
section of the abutment. The stresses at any
(a) Reaction from the arch. section shall not exceed the working stresses
(b) Pressure of earth at back. specified in clause 12. The shearing stresses
at any place shall be assumed to be resisted
(c) Weight of abutment and overlying fill. by the frictional forces and safe shearing
(d) Water pressure and buoyancy – These strength of the masonry.
should be considered when depth of
water may exceed 6m the calculations 7.4. Foundations for Abutments.
being made both with and without the
effect of the water pressure and 7.4.1 Arches shall only be built where
buoyancy acting together. foundation conditions are such that there will
be no risk of unequal settlement or horizontal
7.2.2 In calculating the thrust of the arch ring movement.
for designing the abutment, Dynamic effects 7.4.2 The permissible pressure on the soil
may be neglected. shall not exceed that specified in Clause 13.
7.2.3 The total thrust from the live load may 7.4.3 The line of pressure shall lie within the
be assumed to be distributed over the whole middle third of the foundation and every effort
length of the abutment, or a length bounded by should be made to keep it as near the center of
lines drawn at a slope of 1` horizontal to 2 the base as possible, to ensure a uniform
vertical from the bottom edges of sleepers to distribution of pressure.
the section under investigation whichever 7.4.4 The depth of foundation shall be
length is less. Over this length, the thrust due determined by the Engineer with due regard to
to dead load may be assumed to have a the conditions at the site but should not,
uniform value, corresponding to that produced ordinarily, be less than 1.25 m.
by the maximum height of the filling.
8. PIERS OF ARCH BRIDGES.
7.2.4 The active earth pressure at the back of
an abutment (which adds to its stability) shall 8.1 Thickness at Top The thickness at
not be taken to be more than the pressure of a the top shall be adequate to accommodate the
3
fluid weighing 2353 N/m (240 kg/m ). This
3 skew backs on both sides and to resist the
pressure shall be assumed to act over a height stresses imposed under the most unfavourable
from bed level to springing only, due allowance conditions of loading.
being made for surcharge of the overlying fill.
No allowance shall be made for the surcharge 8.2 Forces Acting on the Pier.
due to the live load.
8.2.1 The forces acting on the pier are as
7.3. Conditions of Stability An arch follows:-
abutment shall be investigated for the following (a) reactions from the adjacent arches,
three conditions of loading:-
(b) weight of masonry and fill and the
(a) Dead load plus live load on 5/8 span weight of pier itself.
adjacent to abutment.
(c) Water pressure and buoyancy with the
(b) Dead load plus live load on the other same provision as for abutments in
5/8 span. Clause 7.2.
VI-4
8.2.2 The provisions regarding dynamic 11. TYPE OF MASONRY:
effects and distribution of thrust shall be the
11.1 Arch rings shall be constructed either
same as laid down for abutments in clause 7.2.
with voussoirs of precast cement concrete or
8.3 Conditions of Stability: sound durable building stone, or brick work in
first class bricks and 1:4 cement mortar. Plain
8.3.1 The stability of piers shall always be cement concrete cast in-situ may also be used
investigated for the following two conditions of in which case reinforcement shall be provided
loading:- as per Clause 2.5.
(a) when only one of the adjacent spans
12. WORKING STRESSES;
carries live load – This condition will
usually give the maximum stresses in 12.1 Masonry Arches
the masonry of the pier. 12.1.1 Clause 5.14.3 of IRS: Bridge Substructure &
(b) When both adjacent spans carry live Foundation Code shall be
load – This condition usually gives the
applicable for the permissible stresses in Masonry
maximum intensity of foundation with Standard Mixes.
pressures.
8.3.2 The provision of Clause 7.3 regarding 12.1.2 Clause 5.14.4 of IRS: Bridge Substructure &
Foundation Code shall be applicable for the
the location of the line of pressure and the permissible stresses in Masonry without Standard
stresses, apply to the piers also. Mixes.
8.4 Foundations for piers – These shall 12.2 Plain Cement Concrete Arches - The
be governed by the same provisions as laid working stresses shall not exceed those laid down in
down for abutments in Clause 7.4. the Indian Railway Standard "Concrete Bridge
Code". It shall be ensured that standard of
construction and supervision are in conformity with
the codes.
9. DESIGN OF RETURN AND WING
WALLS 12.3 For certification of Masonry/Concrete Arches
provisions of clauses 5.16.2.2 & 5.16.2.3 of IRS:
9.1 The return and wing walls should be Bridge Substructure & Foundation Code shall be
designed in accordance with the Indian applicable. (ACS 9 dtd. 19.11.2019)
Railway Standard “Code of Practice for the
design of sub-structure of bridges”. 13. FOUNDATION PRESSURE
10. ECONOMY IN ARCH BRIDGE 13.1 Owing to the wide variation in safe
DESIGN: bearing pressures on foundations in different
parts of India, it is not possible to specify
10.1 In the case of arch bridges in high permissible bearing pressures which will have
banks, the height of the springing, the length of universal application. Designs should be
the arch barrel and, in the case of multiple based on local conditions and permissible
span bridges, the size of the span of the pressures may be established on the basis of
arches should be so fixed that the total cost of tests or on pervious experience. Normally,
the bridge for the required water-way is a foundations, unless resting directly on rock,
minimum. shall not be less than 1.25m in depth. It is,
10.2 In order to avoid excessive lateral generally, safe to increase the permissible
tension in the arch ring or excessive load on bearing pressure at the rate of 17647 N/m2
the ends of the barrel, the height of the parapet (1800 kg per sqm) for each additional metre
wall above the crown of the arch should, of depth below 1.25 m.
generally, not exceed 1000mm when the depth
of fill is considerable.
14. SEISMIC EFFECT:
14.1 Masonry or plain cement concrete
arches shall not be constructed in zone V.
VI-5
Masonry or plain cement concrete arches shall 18. STRIKING OF CENTRES AND
not be constructed with spans exceeding 6 m APPLICATION OF LOAD:
in Zone IV and 10m in Zone III.
18.1 The centers should not be struck before
15. SKEW ARCHES:
one week after the completion of the arch.
15.1 Skew arches shall be so constructed
that the courses are everywhere at right angles 18.2 After completion of any portion of the
to the lines of thrust. masonry of an arch bridge, the following
minimum periods of time as specified in Table-
16. WEEP HOLES: II below should be allowed to elapse before
loads as specified therein may be imposed on
16.1 Weep holes should be provided
that portion of the masonry:-
through abutments, wing or return walls, and
parapets, as may be necessary, adequate TABLE-II
arrangements being made to lead water to the
weep holes. 50% of 75% of Full
design design design
Description
17. FILLING OVER ARCHES: load load load
Ordinary 7 14 28
17.1 It is recommended that the depth of the cement mortar days days days
fill between the underside of the sleeper and and concrete.
the crown of the arch should not be less than
1 m. Rapid- 5 10 28
hardening days days days
17.2 Filling of a porous nature, such as cement mortar
brickbats or ballast, should be used to cover and concrete.
the whole extrados of the arch to a depth of at
least 300 mm over the crown.
17.3 Earth filling should be done in layers,
NOTES:
each being consolidated by ramming and by
sprinkling with water. Black cotton soil should 1. The expression “load” means the total
not be used. calculated load with the appropriate Dynamic
effects allowance specified for the speed at
17.4 In existing arches the filling should be which the load is permitted to run.
disturbed as little as possible as, after a time,
2. The above periods shall be suitably
the arch action in the filling relieves the arch
increased where the mean air temperature is
ring of a considerable portion of the
superimposed load. less than 160 C.
VI-6