California Bearing Ratio Test (CBR Test) (IS: 2720 PART-16) : Test Load Standar D Load
California Bearing Ratio Test (CBR Test) (IS: 2720 PART-16) : Test Load Standar D Load
1. Cylindrical mould with inside dia 150 mm and height 175 mm, provided with a
detachable extension collar 50 mm height and a detachable perforated base plate 10 mm
thick.
2. Spacer disc 148 mm in dia and 47.7 mm in height along with handle.
3. Metal rammers:- Weight 2.6 kg with a drop of 310 mm (or) weight 4.89 kg a drop 450
mm.
4. Weights:- One annular metal weight and several slotted weights weighing 2.5 kg each,
147 mm in dia, with a central hole 53 mm in diameter.
5. Loading machine:- With a capacity of at least 5000 kg and equipped with a movable
head or base that travels at an uniform rate of 1.25 mm/min. Complete with load
indicating device.
6. Metal penetration piston 50 mm dia and minimum of 100 mm in length.
7. Two dial gauges reading to 0.01 mm.
8. Sieves. 4.75 mm and 20 mm I.S. Sieves.
9. Miscellaneous apparatus, such as a mixing bowl, straight edge, scales soaking tank or
pan, drying oven, filter paper and containers.
DEFINITION OF CBR:
It is the ratio of force per unit area required to penetrate a soil mass with standard
circular piston at the rate of 1.25 mm/min. to that required for the corresponding
penetration of a standard material.
Test
C.B.R. = x 100
load
Standar
d load
The following table gives the standard loads adopted for different penetrations for the
standard material with a C.B.R. value of 100%
Penetration of plunger
Standard load (kg)
(mm)
2.5 1370
5.0 2055
7.5 2630
10.0 3180
12.5 3600
The test may be performed on undisturbed specimens and on remoulded specimens
which may be compacted either statically or dynamically.
Fix the extension collar and the base plate to the mould. Insert the spacer disc over the
base (See Fig.38). Place the filter paper on the top of the spacer disc.
Compact the mix soil in the mould using either light compaction or heavy
compaction. For light compaction, compact the soil in 3 equal layers, each layer
being given 55 blows by the 2.6 kg rammer. For heavy compaction compact the
soil in 5 layers, 56 blows to each layer by the 4.89 kg rammer.
Remove the collar and trim off soil.
Turn the mould upside down and remove the base plate and the displacer disc.
Weigh the mould with compacted soil and determine the bulk density and dry
density.
Put filter paper on the top of the compacted soil (collar side) and clamp the
perforated base plate on to it.
V = volume of the specimen in the mould = 2250 cm3 (as per the mould available
in laboratory)
Take the weight W (calculated as above) of the mix soil and place it in the mould.
Place a filter paper and the displacer disc on the top of soil.
Keep the mould assembly in static loading frame and compact by pressing the
displacer disc till the level of disc reaches the top of the mould.
Keep the load for some time and then release the load. Remove the displacer disc.
The test may be conducted for both soaked as well as unsoaked conditions.
If the sample is to be soaked, in both cases of compaction, put a filter paper on the top
of the soil and place the adjustable stem and perforated plate on the top of filter paper.
Put annular weights to produce a surcharge equal to weight of base material and
pavement expected in actual construction. Each 2.5 kg weight is equivalent to 7 cm
construction. A minimum of two weights should be put.
Immerse the mould assembly and weights in a tank of water and soak it for 96 hours.
Remove the mould from tank. Note the consolidation of the specimen.
Seat the penetration piston at the center of the specimen with the smallest possible
load, but in no case in excess of 4 kg so that full contact of the piston on the
sample is established.
Set the stress and strain dial gauge to read zero. Apply the load on the piston so
that the penetration rate is about 1.25 mm/min.
Record the load readings at penetrations of 0.5, 1.0, 1.5, 2.0, 2.5, 3.0, 4.0, 5.0, 7.5,
10 and 12.5 mm. Note the maximum load and corresponding penetration if it
occurs for a penetration less than 12.5 mm.
Detach the mould from the loading equipment. Take about 20 to 50 g of soil from
the top 3 cm layer and determine the moisture content.
Fig 1 CBR test setup
If the initial portion of the curve is concave upwards, apply correction by drawing a
tangent to the curve at the point of greatest slope and shift the origin (Fig. 2). Find and
record the correct load reading corresponding to each penetration.
Observation Table:
Readings on
Penetration in-
proving ring* Load in KN Load (Kg) Corrected load
mm
( Ring division)
0
0.5
1.0
1.5
2.0
2.5
3.0
4.0
5.0
7.5
10.0
12.5
Calculation:
Conclusion:
(Faculty Advisor)
Date: