PPC Bits For Students
PPC Bits For Students
PPC Bits For Students
a) Material
b) Machine
c) Motion
d) Method
2. The interchangeability can be achieved by
a) Standardization
b) Better process planning
c) Bonus plan
d) Better product planning
3. Progress reporting and corrective action belongs to _______________
phase of PPC.
a) Action phase
b) Prior phase
c) Planning phase
d) Control phase
4. Steel, paper, paints, and chemicals are examples of products that use
a) Mass production
b) Continuous production
c) Repetitive production
d) Batch production
5. Correct sequence of operations in the Production Planning and Control
process is ________.
a) Routing – Scheduling – Follow up – Dispatching
b) Scheduling – Follow up – Dispatching – Routing
c) Routing – Scheduling – Dispatching – Follow up
d) Dispatching – Routing – Scheduling – Follow up
6. Planning and Control function is crucial for ensuring cost savings and
efficiency in
a) Planning
b) Controlling
c) Promotion
d) Production
7. Forecasting which assumes a static environment in the future is
a) Passive forecasting
b) Active forecasting
c) Long term forecasting
d) Short term forecasting
8. Given an actual demand of 60 for a period when forecast of 70 was
anticipated and an alpha of 0.3, what would be forecast for next period be
using simple exponential smoothing?
a) 60 - 65
b) 66
c) 67
d) 69
9. The control activity in Production Planning and Control is performed
________ of the plan.
a) Before execution
b) After execution
c) During execution
d) None of the above