Ghana Grid Company Ltd. (Gridco) : APRIL 2022
Ghana Grid Company Ltd. (Gridco) : APRIL 2022
Ghana Grid Company Ltd. (Gridco) : APRIL 2022
(GRIDCo)
TO
APRIL 2022
PUBLIC UTILITIES REGULATORY COMMISSION
PROPOSALS FOR REVIEW OF ELECTRICITY TRANSMISSION AGGREGATE REVENUE REQUIREMENT AND TARIFF
TABLE OF CONTENTS
LIST OF TABLES
Table 1: Key Operational Assumptions ............................................................................................ 3
Table 12: Summary of Capital Expenditure Financing Plan (Million GHS) 2021 - 2027......... 19
Table 13: Summary of Operation and Maintenance Costs (Million GHS) 2021-2027............. 19
Table 14: Summary of Administration and General Costs (Million GHS) 2021-2027.............. 19
Table 15: Summary of Human and Resource Cost (Million GHS) 2021 - 2027 ....................... 20
Table 16: Summary of Financing and Interest Costs (Million GHS) 2021-2027 ...................... 20
1 Introduction
Ghana Grid Company Limited (GRIDCo), is responsible for developing, managing and
operating the National Interconnected Transmission System (NITS) in a reliable,
efficient and sustainable manner. GRIDCo has been operating independently since
2008, facilitating wholesale electricity trading and the provision of ancillary services on
the NITS.
GRIDCo’s mission is to provide reliable grid for the development of Ghana and the Sub-
region at large rests on the sustainability and financial viability of GRIDCo.
A cost-reflective transmission tariff will ensure a reliable and stable NITS which will
restore confidence in Ghana’s power system for sustainable economic development.
The current tariff of 0.060398GHS/kWh does not adequately reflect the cost of
GRIDCo’s operational activities.
The tariff granted by PURC since July 2019 has depreciated in US Dollar terms from
1.0915 US Cents/kWh in 2019 to 0.8492 US Cent/kwh in March 2022 notwithstanding
increases in Regulatory Asset Base over the years (See Figure 1 below).
1
PUBLIC UTILITIES REGULATORY COMMISSION
PROPOSALS FOR REVIEW OF ELECTRICITY TRANSMISSION AGGREGATE REVENUE REQUIREMENT AND TARIFF
on the coastal transmission lines, illegal mining activities (galamsey) and other forms of
encroachments to grapple with. The coastal and western transmission line corridors are
critical to the stability of the power system since it is the main corridor for evacuating
over 1600MW of power generated from the Western Region.
However, GRIDCo’s weakened liquidity position does not allow reasonable coverage of
all these maintenance obligations comprehensively. These factors among others are
detrimental to the optimal performance of the transmission assets. GRIDCo therefore
requires a cost reflective tariff to be able to maintain the various assets in the short to
medium term to enhance efficiency.
2
PUBLIC UTILITIES REGULATORY COMMISSION
PROPOSALS FOR REVIEW OF ELECTRICITY TRANSMISSION AGGREGATE REVENUE REQUIREMENT AND TARIFF
Projected Transmission
Losses % 4.49 4.21 4.23 4.30 3.90 3.80
Average Exchange Rate GHS 8.57 9.20 9.70 9.88 10.06 9.41
Using the assumptions and the proposed methodology outlined by the PURC in the
Tariff Methodology, GRIDCo proposes the following Transmission Service Charges
excluding all levies as shown in table 2 for the 5-year tariff period.
Operating Cost
Staff Costs Gh¢'M 256.33 280.61 320.30 366.16 390.87 450.77
Administrative Costs Gh¢'M 79.48 84.83 92.45 100.53 109.91 117.33
Materials and Spares Gh¢'M 18.48 25.51 28.72 31.67 36.34 38.11
Maintenance Costs Gh¢'M 93.83 115.43 134.53 156.05 190.20 215.62
Operating Cost Gh¢'M 448.12 506.38 576.01 654.40 727.33 821.83
Regulated Fixed Asset Base 1 Gh¢'M 5,169 5,546 5,746 5,884 6,208 6,563
2
Rate of Return on Fixed Asset Base % 20% 21% 25% 25% 25% 25%
Return on regulated fixed asset base Gh¢'M 1,033.74 1,164.58 1,436.42 1,470.92 1,551.97 1,640.75
Annual Revenue Requirement Gh¢'M 2,008.35 2,250.22 2,677.46 2,865.06 3,124.20 3,272.16
The tariff proposal considers operating and maintenance costs, depreciation for the
asset usage, return on regulatory assets base and corporate income tax.
3
PUBLIC UTILITIES REGULATORY COMMISSION
PROPOSALS FOR REVIEW OF ELECTRICITY TRANSMISSION AGGREGATE REVENUE REQUIREMENT AND TARIFF
Total 327.72
The addition of these assets has significantly increased GRIDCo’s Regulatory Asset
Base as depicted in Figure 1 below:
4
PUBLIC UTILITIES REGULATORY COMMISSION
PROPOSALS FOR REVIEW OF ELECTRICITY TRANSMISSION AGGREGATE REVENUE REQUIREMENT AND TARIFF
Figure 1
The upgrade of the 161 kV Achimota-Mallam Transmission Line which serves the
highest load centre in Ghana will significantly improve supply reliability to the national
capital.
Medium-Term Projects
The medium-term projects to be completed within the 5-year tariff period as listed below
in Table 4 are expected to build a robust transmission system that enable to deliver
5
PUBLIC UTILITIES REGULATORY COMMISSION
PROPOSALS FOR REVIEW OF ELECTRICITY TRANSMISSION AGGREGATE REVENUE REQUIREMENT AND TARIFF
power reliably, minimise system interruptions, lower transmission losses and be able to
meet increasing demand.
• Aboadze - Takoradi
• Takoradi -Tarkwa
• Tarkwa - New Tarkwa 2025 224.00
• New Tarkwa - Prestea
• Bogoso - Dunkwa
• Dunkwa - New Obuasi
• Dunkwa - Ayanfuri
• Ayanfuri-Asawinso
6
PUBLIC UTILITIES REGULATORY COMMISSION
PROPOSALS FOR REVIEW OF ELECTRICITY TRANSMISSION AGGREGATE REVENUE REQUIREMENT AND TARIFF
TOTAL 990.53
7
PUBLIC UTILITIES REGULATORY COMMISSION
PROPOSALS FOR REVIEW OF ELECTRICITY TRANSMISSION AGGREGATE REVENUE REQUIREMENT AND TARIFF
A key strength of this new Performance Management System enables planning at all
levels (corporate, departmental and employee) to be results-oriented. The results are
clear, measurable and motivational. This has enhanced operational efficiency.
The ERP system integrates data and processes across multiple departments and
locations making information available for decision making at all levels.
The system streamlines business operations by integrating the data and refining the
processes required to operate as an organization. It also enhances data sharing
among departments and related organisations to enable quick decision making.
8
PUBLIC UTILITIES REGULATORY COMMISSION
PROPOSALS FOR REVIEW OF ELECTRICITY TRANSMISSION AGGREGATE REVENUE REQUIREMENT AND TARIFF
cost of these assets should be excluded from GRIDCo’s assets based. We recommend
that Stakeholders are engaged to implement a policy for efficient recovery for such third
parties.
9
PUBLIC UTILITIES REGULATORY COMMISSION
PROPOSALS FOR REVIEW OF ELECTRICITY TRANSMISSION AGGREGATE REVENUE REQUIREMENT AND TARIFF
Transmission Losses
Actual
6.00% Forecasted
5.00%
4.00%
3.00%
2.00%
1.00%
0.00%
2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027
7.0 TSAIDI
6.0 TSAIDI PURC Benchmark
4.0
Hours
3.0
2.0
1.0
0.0
Jul-19
Jul-20
Jul-21
Jul-22
Jul-23
Jul-24
Jul-25
Jul-26
Jul-27
Nov-19
Nov-20
Nov-21
Nov-22
Nov-23
Nov-24
Nov-25
Nov-26
Mar-20
Mar-21
Mar-22
Mar-23
Mar-24
Mar-25
Mar-26
Mar-27
Figure 3: Transmission System Interruption Duration Index (TSAIDI) Jul 2019 -Jul
2027
10
PUBLIC UTILITIES REGULATORY COMMISSION
PROPOSALS FOR REVIEW OF ELECTRICITY TRANSMISSION AGGREGATE REVENUE REQUIREMENT AND TARIFF
GRIDCo has not been able to satisfy key financial covenants on loans contracted for its
projects. Within this tariff proposal, GRIDCo has projected the levels of tariff that will
progressively help attain an appreciable level of financial performance that will bring
comfort to both current and prospective financiers.
In determining the expected tariff for the regulatory period 2022 – 2027, GRIDCo took
into consideration, the ongoing interventions in the sector which are aimed at
addressing the levels of inter-utility debts and invariably low liquidity. Hence the working
capital assumptions for 2022 onwards, excludes the debts prior to the implementation
of the Cash Waterfall Mechanism.
11
PUBLIC UTILITIES REGULATORY COMMISSION
PROPOSALS FOR REVIEW OF ELECTRICITY TRANSMISSION AGGREGATE REVENUE REQUIREMENT AND TARIFF
• Low voltages on the eastern corridor due to low network capacity (Ho, Kpeve
and Sogakope)
GRIDCo has installed 796MVAr Capacitor Banks. We note that capacitor banks are
more effective when installed within the Distribution Network as well as the networks of
Bulk Customers which are the sources of reactive power demand.
Currently a 40MVAr SVC is in service at Tamale. A new 50MVAr SVC has been installed
and commissioned as part of the Kasoa BSP project. As indicated above, GRIDCo is
also working at installing a 50MVAr SVC in Kumasi.
12
PUBLIC UTILITIES REGULATORY COMMISSION
PROPOSALS FOR REVIEW OF ELECTRICITY TRANSMISSION AGGREGATE REVENUE REQUIREMENT AND TARIFF
Currently GRIDCo is facing several court cases which could involve in the payment of
about GHS106,810,500.00. These claims have at times led to delays in the execution
of projects across the country thereby affecting the ability of GRIDCo to meet its
statutory objectives.
The GWEM Design has been completed and approved by the Energy Commission.
Market Participants and Regulators were engaged in 2020 on the Market Design and
Draft Market Rules to educate and inform participants and solicit their comments. These
comments have been incorporated to finalize the draft Rules. The Draft Final Rules
have been submitted to the Energy Commission for approval. Subsequently, GRIDCo
together with the Market Consultant will carry out Gap Analysis to identify gaps in
Ghana’s current electricity market relative to the Final Market Rules. GRIDCo will
engage Stakeholders to address the gaps for the implementation of the GWEM.
13
PUBLIC UTILITIES REGULATORY COMMISSION
PROPOSALS FOR REVIEW OF ELECTRICITY TRANSMISSION AGGREGATE REVENUE REQUIREMENT AND TARIFF
14
PUBLIC UTILITIES REGULATORY COMMISSION
PROPOSALS FOR REVIEW OF ELECTRICITY TRANSMISSION AGGREGATE REVENUE REQUIREMENT AND TARIFF
7 Projected Generation
Hydro:
Akosombo Generating
1023.15 900 22,075
Station
Kpong Generating
183.6 140 4,425
Station
Thermal:
TT2PP 86.2 70
MRP
15
PUBLIC UTILITIES REGULATORY COMMISSION
PROPOSALS FOR REVIEW OF ELECTRICITY TRANSMISSION AGGREGATE REVENUE REQUIREMENT AND TARIFF
Target Availability of
Power Plant
Target Availability of
Power Plant
16
PUBLIC UTILITIES REGULATORY COMMISSION
PROPOSALS FOR REVIEW OF ELECTRICITY TRANSMISSION AGGREGATE REVENUE REQUIREMENT AND TARIFF
Gross Generation
364 364 364 364 364
Capacity
Net Effective /
Dependable 300 150 150 300 300
Generation Capacity
Projected Energy
1,577 788 788 1,971 1,971
Generated
Target Availability of
0.6 0.6 0.6 0.6 0.6
Power Plant
Gross Generation
364 364 364 364 364
Capacity
Net Effective /
Dependable 320 320.00 320.00 320.00 320.00
Generation Capacity
Projected Energy
2,102 2,102 2,102 2,102 2,102
Generated
Target Availability of
0.75 0.75 0.75 0.75 0.75
Power Plant
Gross Generation
113.4 113.4 113.4 113.4 113.4
Capacity
Net Effective /
Dependable 100.00 100.00 100.00 100.00
Generation Capacity 100
17
PUBLIC UTILITIES REGULATORY COMMISSION
PROPOSALS FOR REVIEW OF ELECTRICITY TRANSMISSION AGGREGATE REVENUE REQUIREMENT AND TARIFF
Projected Energy
613 613 613 613 613
Generated
Target Availability of
Power Plant
Gross Generation
86.2 86.2 86.2 86.2 86.2
Capacity
Net Effective /
Dependable
70.00 70.00 70.00 70.00
Generation Capacity 70
Projected Energy
Generated 429 429 429 429 429
Target Availability of
Power Plant
18
PUBLIC UTILITIES REGULATORY COMMISSION
PROPOSALS FOR REVIEW OF ELECTRICITY TRANSMISSION AGGREGATE REVENUE REQUIREMENT AND TARIFF
8 Capital Expenditure
Table 12: Summary of Capital Expenditure Financing Plan (Million GHS) 2021 -
2027
Item 2021/2022 2022/2023 2023/2024 2024/2025 2025/2026 2026/27
Accumulated
155.95 193.49 199.32 204.88 217.15 222.11
Depreciation
Retained
654.89 636.16 844.46 1,198.37 1,692.54 2190.00
Earnings
Commercial
Borrowings:
Domestic 0 0 0 0 0
Foreign 688.43 157.65 157.33 - 207.20
Additional
Equity
0 0 0 0 0
Contribution by
Shareholder(s)
Grants:
Domestic 0 0 0 0 0
Foreign 0 0 0 0 0
Tariff Revenue
(Revenue from
Projected 1,094.06 1,108.96 1,249.88 1,443.39 1,547.66 1764.24
Capacity
Charge)
Table 13: Summary of Operation and Maintenance Costs (Million GHS) 2021-2027
Item 2021/2022 2022/2023 2023/2024 2024/2025 2025/2026 2026/27
Fixed O & M
93.83 115.43 134.53 156.05 190.20 215.62
Costs (GHS ‘M)
Variable O & M
Cost
Table 14: Summary of Administration and General Costs (Million GHS) 2021-2027
Item 2021/2022 2022/2023 2023/2024 2024/2025 2025/2026 2026/27
Fixed O & M
79.48 84.83 92.45 100.53 109.91 109.91
Costs
Variable O & M
Cost
19
PUBLIC UTILITIES REGULATORY COMMISSION
PROPOSALS FOR REVIEW OF ELECTRICITY TRANSMISSION AGGREGATE REVENUE REQUIREMENT AND TARIFF
Table 15: Summary of Human and Resource Cost (Million GHS) 2021 - 2027
Item 2021/2022 2022/2023 2023/2024 2024/2025 2025/2026 2026/27
Fixed O & 234.67 256.33 280.61 320.30 366.16 366.16
M Costs
(GHS ‘M)
Variable O
& M Cost
Table 16: Summary of Financing and Interest Costs (Million GHS) 2021-2027
Item 2021/2022 2022/2023 2023/2024 2024/2025 2025/2026 2026/27
Interest on 49.88 53.04 57.67 65.32 83.91
Foreign Loans
Interest on 37.61 28.49 19.37 13.86
Domestic
Loans
Interest on 384.30 330.08 324.62 330.71 342.47 384.30
Working
Capital Loan
13 Conclusion
GRIDCo is committed to deliver on its mandate to provide to fair and non-discriminatory
access to power transmission to support economic development. This request therefore
seeks a cost reflective tariff to sustain GRIDCo’s operation of the NITS.
20
PUBLIC UTILITIES REGULATORY COMMISSION
PROPOSALS FOR REVIEW OF ELECTRICITY TRANSMISSION AGGREGATE REVENUE REQUIREMENT AND TARIFF
14 Appendices
F-1T - Transmission Lines Data
F-2T - Transmission Substations Data
F-3T - Transmission Fixed Assets Schedule
F-4T - Transmission Fixed Assets Depreciation Schedule
F-5T - Transmission System Project Cost Data
F-6T - Transmission Project Cost Data (Foreign Costs)
F-7T - Transmission Project Cost Data (Local Costs)
F-8T - Capital Expenditure Funding/Financing Plan
F-9T - Transmission Operation and Maintenance Cost Data
F-10T - Transmission Administration and General Cost Data
F-11T - Transmission Human Resource Cost Data
F-12T - Working Capital Requirement Data
F-13T - Summary of Transmission Costs
F-14T -Relevant Documentation in Respect of Transmission Tariff Proposal
F-15T -Summary of Qualitative and Quantitative Data Contained in Forms F-1T-F14T
in Respect of Tariff Application
21