Rajasthan Electricity Regulatory Commission: Petition No. RERC-1905/21 and 1933/21
Rajasthan Electricity Regulatory Commission: Petition No. RERC-1905/21 and 1933/21
Rajasthan Electricity Regulatory Commission: Petition No. RERC-1905/21 and 1933/21
In the matter of Petition filed for adoption of tariff for 1070 MW Solar PV power
under Section 63 of the Electricity Act, 2003 and
In the matter of Petition under 86(1)(b) of the Electricity Act, 2003 seeking
approval and recognition of Article 12.1.3 and 12.2.3 of the Power Purchase
Agreement dated 04.03.2021 executed between AEW India North One Private
Limited and Solar Energy Corporation of India Limited and appropriate
directions thereof.
Coram:
Dr.B.N. Sharma, Chairman
Sh. S. C. Dinkar, Member
Sh. Prithvi Raj, Member
Page 1 of 32
Present : Sh. Sh. M.G. Ramachandran, Sr. Advocate for SECI
Sh. Sanjay Sen, Sr. Advocate for Green Infra
Sh. Vishrov Mukherjee, Advocate for Green Infra
Sh. Shri Venkatesh, Advocate for NTPC
Sh. Sujit Ghosh, Advocate for AEW
Ms. Mannat Waraich, Advocate for AEW
Sh. Shubham Arya, Advocate for SECI
Sh. Bipin Gupta, Advocate for RUVN
ORDER
1. Rajasthan Urja Vikas Nigam Ltd. (RUVN) had filed this petition on
24.03.2021 under Section 63 of the Electricity Act, 2003 for adoption of
tariff for 1070 MW Solar PV power to be purchased by three Discoms for
which bidding was conducted by SECI.
3. The above order was challenged before Hon‟ble APTEL by Green Infra
Wind Energy Ltd. bearing appeal no. 251 OF 2021. Hon‟ble APTEL
on12.10.2021 passed the order in the matter and directed the Commission
to hear the parties further in the light of the observations made by the
tribunal and pass further orders specifically in relation to the three
„change in law‟ event claims presented by the appellant, preferably
within two months.
Page 2 of 32
Accordingly NTPC Renewable Energy Ltd. and AEW India North One
Private Limited submitted their respective written submissions on
11.11.2021, Green Infra Wind Energy Ltd. on 16.11.2021 and Solar Energy
Corporation of India Ltd on 19.11.2021, Rajasthan Urja Vikas Nigam Ltd.
filed its reply on 22.11.2021 on the submissions made by the Respondents.
5. M/s AEW India North One Private Limited also filed a petition bearing no.
1933/21 for approval and recognition of Article 12.1.3 and 12.2.3 of the
Power Purchase Agreement dated 04.03.2021 executed between AEW
India North One Private Limited and Solar Energy Corporation of India
Limited and appropriate directions thereof. As the issues that arise in both
the petitions for consideration and decision of the Commission are similar,
these petitions referred to in cause title are clubbed and are being
disposed of by this common order.
6. Both the matters were heard together finally on 23.11.2021. Sh. Bipin
Gupta, Advocate appeared on behalf of the Petitioner. Sh. Shubham
Arya, Advocate appeared for SECI. Sh. Sanjay Sen, Sr. Advocate
appeared for M/s Green Infra. Sh. Shri Venkatesh, Advocate appeared
for NTPC, Sh. Sujit Ghosh, Advocate appeared for AEW.
7. M/s Green Infra during the hearing and in its written submissions has
submitted as under:
(a) SC GIB Order in terms of which all existing and future overhead low
and high voltage powerlines in the Priority and Potential habitats of
Great-Indian Bustard shall be undergrounded.
Page 3 of 32
(b) Levy of BCD on import of Solar Cells, Modules /Panels pursuant to
MNRE OM dated 09.03.2021.
7.2 The issues for consideration before the Commission are as follows: -
(c) Whether the SC GIB Order qualifies as change in law under the PPA?
7.3 The present proceedings are remand proceedings pursuant to the Order
dated 12.10.2021. It is settled law that the lower court is bound by the
terms of the remand order. Reliance is placed on the order dated
Page 4 of 32
10.08.2010 passed by the Hon‟ble Tribunal is Appeal No. 37 of 2010 titled
Meghalaya State Electricity Board v Meghalaya State Electricity
Regulatory Commission wherein the Hon‟ble Tribunal laid down the
principles to be followed by the lower court/authority while dealing with
the issue of limited remand.
(a) Vide MoF Notification dated 01.02.2021, the BCD on the import of
Solar Invertors has increased from 5% to 20%.
(c) The MoF Notification dated 01.02.2021 was issued after 28.10.2020
which is the cut-off date for consideration of „change in law‟.
(d) The MoF Notification dated 01.02.2021has been issued by the Ministry
of Finance which qualifies as an Indian Governmental Instrumentality
under the PPA.
(e) Increase of BCD from 5% to 20% will have an impact on the Project
cost.
7.5 Article 12.1.2 of the PPA states that if a change in law event occurs up to
inter alia SCD of the Project, GIRPL will be entitled for compensation
subject to the condition that such „change in law‟ is recognized by the
Appropriate Commission.
7.6 Further, Article 12.1.3 specifically provides that in case of change in rates
of safeguard duty, GST and basic customs duty after 28.10.2020,resulting
in change in Project cost, then such change will be treated as 'change in
Page 5 of 32
law'. Further, the quantum of payment of compensation on account of
change in rates of such duties shall be provided to the affected party by
the other party as per Article 12.2.3, subject to the provision that
Appropriate Commission recognizes such provisions at the time of
adoption of tariff.
7.8 As on the cut-off date i.e., 28.10.2020, BCD on Solar Cells & Modules /
Panels was nil. BCD of 25% and 40% on Solar Cells and Modules
respectively has been introduced vide MNRE OM dated 09.03.2021.
Further, MNRE‟s proposal to impose BCD on Solar Cells and Modules /
Panels at 25% and 40% respectively has been accepted by the Ministry of
Finance.
(a) The MNRE OM dated 09.03.2021is a notification and falls within the
definition of „Law‟ under the PPA.
7.10 Increase in the rate of GST from 5% to 12% on renewable energy devices
and parts for their manufacture pursuant to MoF Notification No. 8/2021-
Page 6 of 32
Integrated Tax (Rate) dated 30.09.2021 constitutes a „change in law‟ in
terms of the PPA.
7.11 As on the cut-off date i.e., 28.10.2020, GST on renewable energy devices
and parts for their manufacture was 5%. However, on 30.09.2021, MoF
issued the MoF GST Notification increasing the rate of GST from 5% to 12%.
(b) MoF GST Notification issued by the Ministry of Finance and falls within
the definition of „Law‟ under the PPA.
(c) The MoF GST Notification was issued after 28.10.2020 which is the cut-
off date for consideration of „change in law‟.
(d) The MoF GST Notification has been issued by the Ministry of Finance
which qualifies as an Indian Governmental Instrumentality under the
PPA.
(e) Increase of GST from 5% to 12% will have an impact on the Project
cost.
Page 7 of 32
the State Commission to inquire into such claim at the first opportune
time and bring in suitable corrections; and
(b) If the event actually constitutes „change in law‟ within the four
corners of its definition under the PPA, there is no reason why it
cannot be duly recognized as a change in law at the stage of tariff
adoption
7.14 The Order passed by the Hon‟ble Supreme Court in W.P(C) No. 838 of
2019 titled M.K. Ranjitsinh & Ors. v. Union of India & Ors. constitutes as a
change in law in terms of the PPA.
7.15 The Hon‟ble Supreme Court vide the SC GIB Order directed that all
existing and future overhead low and high voltage power lines in the
Priority and Potential habitats of Great-Indian Bustard (“GIB”) shall be
undergrounded.
7.16 Due to the SC GIB Order, there is complete uncertainty regarding the
Project with respect to feasibility of undergrounding. Further, the Project is
now subject to technical feasibility, availability of land for
undergrounding, grant of necessary approvals as may be applicable
from the regulatory bodies, etc.
7.17 In view of the above, it is submitted that the SC GIB Order qualifies as
change in law as:-
(b) The SC GIB Order dated 19.04.2021 was issued after 28.10.2020 which is
Page 8 of 32
the cut-off date for consideration of „change in law‟.
(c) The SC GIB Order has been issued by the Hon‟ble Supreme Court of
India which qualifies as an Indian Governmental Instrumentality under
the PPA.
(d) The SC GIB Order will have an impact on the Project Cost and will
require time extensions in respect of the SCD along with
corresponding extension of other timelines under the PPA.
7.18 It is pertinent to note that the Hon‟ble Tribunal has held the cancellation
of coal blocks by the Hon‟ble Supreme Court of India in the case of
Manohar Lal Sharma vs. UOI to be a change in law event in Judgment
dated 21.12.2018 in Appeal No. 193 of 2017 - GMR Kamalanga Energy
Limited & Anr. vs. CERC & Ors.
7.20 GIRPL is entitled to the following reliefs due to the SC GIB Order: -
(a) In terms of Article 2.1.3 of the PPA, the tariff is to be adopted within
120 days from the Effective Date i.e., 27.01.2021. However, in the
intervening period, the SC GIB Order was passed on
19.04.2021. Further, the Hon‟ble Tribunal has held the tariff adoption
order to be inchoate and proceedings incomplete. Therefore, in
terms of Article 2.1.4 of the PPA, the SCOD of the Project and all
other timelines ought to be extended appropriately till the date on
which the Commission passes the final order in the present
proceedings, deciding GIRPL‟s change in law claims thereby
completing the tariff adoption process.
Page 9 of 32
with the SC GIB Order including time required for obtaining
consents and approvals, land acquisition and completion of the
transmission system;
7.21 It is submitted that the time and cost overrun being claimed by GIRPL
herein is provisional and GIRPL reserves all rights to claim any additional
time / cost on account of Change in Law / Force Majeure events
including the change in law events for which provisional relief has been
claimed herein.
(a) Hold and declare that the levy of BCD on the import of Solar Cells and
Modules/Panels pursuant to the MNRE OM dated 09.03.2021 with
effect from 01.04.2022 is a change in law event under the PPA and
that GIRPL is entitled to compensation for actual impact of BCD;
(b) Hold and declare that the increase in rates of BCD on the import of
Solar Inverters pursuant to the MoF Notification dated 01.02.2021
whereby the Exemption Notification dated 06.01.2011 has been
rescinded is a change in law event under the PPA and that GIRPL is
entitled to compensation;
(c) Hold and declare that the MoF GST Notification is a change in law
event under the PPA and that GIRPL is entitled to compensation;
(d) Hold and declare that the SC GIB Order qualifies as a change in law
event under the PPA and consequently, GIRPL is entitled to
compensation and extension of time accordingly;
(e) Since the Project has already been delayed due to SC GIB Order as
well as delay in tariff adoption proceedings, the SCD and other time
Page 10 of 32
lines under the PPA be extended to account for the time spent in the
legal proceedings before the Hon‟ble Tribunal and this Hon‟ble
Commission;
(f) RUVNL be directed to place on record the impact of the SC GIB Order
on the downstream transmission line / system.
(g) Pass any such other and further reliefs as the Commission deems just
and proper in the nature and circumstances of the present case.
8. AEW India North One Private Ltd. during the hearing, in its written
submissions and in petition no. 1933/21 has submitted as under:
8.1 M/s Green Infra preferred an appeal before the Hon‟ble Appellate
Tribunal for Electricity (Tribunal) being Appeal No. 251 of 2021 challenging
the Order dated 23.07.2021 passed by the Commission in Petition No. 1905
of 2021.
8.2 After hearing the parties in detail, the Hon‟ble Tribunal disposed off
Appeal No. 251 of 2021 vide its detailed Order dated 12.10.2021. In light of
the Order dated 12.10.2021 passed by the Hon‟ble Tribunal in Appeal No.
251 of 2021, the present matter has been remanded to the Commission
for the consideration of the change in law events raised by the Solar
Developers in their Reply filed in the present Petition and also raised in
present written submissions being filed hereto.
8.3 On the basis of the aforementioned, the following reliefs are being sought
by AEW India from the Commission in the present matter:
(a) Approval and Recognition of Article 12.1.3 and Article 12.2.3 of the Power
Purchase Agreement dated 04.03.2021 executed between AEW India
and SECI which specifically provides that change in rate of safeguard
duty, GST and basic customs duty after 28.10.2020 will be treated as
Page 11 of 32
„change in law‟ and every net increase/decrease of 1 lakh per MW in
Project cost will be liable for corresponding increase or decrease of an
amount equal to Rs. 0.005/kWh;
(b) Declaration of the Order dated 19.04.2021 by the Hon‟ble Supreme Court
of India in Writ Petition (Civil) No. 838 of 2019 as „change in law‟ in terms of
Article 12.1.1 of the Power Purchase Agreement dated 04.03.2021
executed between AEW India and SECI read with Article 12.1.2 and
Article 12.2.4 of the PPA.
8.4 M/s AEW in the petition no. 1933/21 prayed for approval and recognition
of Article 12.1.3 and 12.2.3 of the Power Purchase Agreement dated
04.03.2021 executed between AEW India North One Private Limited and
Solar Energy Corporation of India Limited and appropriate directions
thereof.
9. NTPC Renewable Energy Ltd. during hearing and in its written submissions
has submitted as under:
Page 12 of 32
9.1 On 12.10.2021, the Hon‟ble Tribunal by way of its Order disposed of the
Appeal filed by M/s Green Infra against the order dated 23.07.2021 of the
Commission and remanded the matter back to the Commission.
9.2 From a bare perusal of the Article 1.1 and Article 12 of the PPA, the
following emerges for consideration of the Commission:
(a) The definition of law under the PPA is an exhaustive definition which
considers all laws issued by an Indian Government Instrumentality.
However, for an event to be considered a „change in law‟ event, the
same ought to be caused by the operation of law or by an Indian
Governmental Instrumentality.
(d) The object of the „change in law‟ provision is to compensate the Party
affected by such an event which was beyond its control so as to
restore it, to the same financial position as if such change in law event
had not occurred.
(e) The event being claimed as change in law should have occurred
after the last date of bid submission, i.e., 28.10.2020.
(f) Article 12.1.3 of the PPA categorically envisages that any change in
rates qua Safeguard Duty, GST and BCD after the last date of bid
Page 13 of 32
submission, i.e., 28.10.2020 which results in a change in overall cost of
the project, then in that case such change will be treated as change
in law and shall be decided at the time of adoption of Tariff under
Section 63 of the i.e., the current proceedings.
(g) Further, the compensation shall be payable for such change in law
event as per Article 12.2.3 of the PPA only when the Appropriate
Commission, i.e., the Commission in the instant case approves the
same at the time of adoption of Tariff.
9.3 It is a settled position of law that change in taxes and duties which result in
additional expenses must be allowed as change in law events. In this
regard, reliance is being placed upon the following Judgments:
Page 14 of 32
to MNRE‟s Notification dated 09.03.2021 qualifies as a change in law
event.
9.5 The Notification referred above as issued by MoF and MNRE which are
Indian Government Instrumentality as defined under the PPA executed
between the parties qualifies as a change in law events.
9.6 The Judgment passed by the Hon‟ble Supreme Court of India qualifies as
an event of change in law considering the position that it casts upon a
new obligation upon NTPC REL to obtain requisite consent in order to
install underground power lines in compliance of the direction passed by
the Hon‟ble Supreme Court of India.
9.7 In this regard, reliance is placed upon the Judgment dated 21.12.2018
passed by the Hon‟ble Tribunal in Appeal No. 193 of 2017 titled as GMR
Kamalanga Energy Ltd vs Central Electricity Regulatory Commission
wherein it was held that shortage of coal on account of cancellation of
coal block by the Hon‟ble Supreme Court of India in M.L. Sharma vs the
Principle Secretary &Ors constitutes a change in law event.
9.8 In view of the law settled above and on a reading of provisions envisaged
under the PPA, it is evident that the event under question would qualify as
a change in law event, therefore, NTPC REL is entitled to be compensated
for the same.
9.10 NTPC REL in terms of Article 12.2 of the PPA is bound to be placed in the
same financial position as it would have been had the Amended GST
Page 15 of 32
Notifications not been notified by MoF. In this regard, reliance is being
placed upon the Judgment passed by the Hon‟ble Supreme Court of
India inUttar Haryana Bijli Vitran Nigam Limited v. Adani Power Limited
&ors.(2019) 5 SCC 325.
9.11 In view of the law settled by the respective Court of Law and submissions
made above, it is evident that:
(a) The relief sought by NTPC REL squarely qualifies as a change in law
event in terms of Article 12 of the PPA.
(b) The GST Amended Notifications have a direct bearing on the
financial cost of the Project under question, therefore, NTPC REL is
entitled to be placed in the same financial position as on the bid
submission date.
10. SECI in its written submissions has submissions and in its reply in petition no.
1933/21 has submitted as under:
10.1 The judgment dated 12.10.2021 passed by the Hon‟ble Appellate Tribunal
for Electricity in Appeal No.251 of 2021in the matter of Green Infra
Renewable Energy Limited Vs Rajasthan Electricity Regulatory
Commission and Others, inter alia, decides as under:
“16…………it is the duty of the State Commission to inquire into such claim at
the first opportune time and bring in suitable corrections, may be first by
declaration and followed up by detailed tariff orders. If the event referred to
actually constitutes change in law within the four corners of its definition under
the PPA, there is no reason why it cannot be duly recognized as a change in
law at the stage of tariff adoption, the actual impact and extent of the relief
admissible to be determined at the appropriate stage.
17. For the forgoing reasons, we allow the appeal finding the impugned order
to be an adjudication that is incomplete and proceedings wherein the
appellant had sought the above-mentioned declarations having remained
inchoate. The State Commission is directed to hear the parties further in the
light of the above observations and pass further orders specifically in relation to
the three change in law event claims presented by the appellant, rendering its
decision as expeditiously as possible, preferably within two months from today.”
Page 16 of 32
10.2 In terms of the above, the Commission may be pleased to recognise the
following three events as constituting the change in law events under
Article 12 of the respective Power Purchase Agreements (hereinafter
„PPAs‟):
“(i) Increase in rates of Basic Customs Duty on import of Solar Inverters pursuant
to Ministry of Finance Notification No. 07 /2021-Customs dated 01.02.2021
whereby custom duty exemption notification no. 1/2011 dated 06.01.2011 has
been rescinded;”
(iii) The direction issued by Hon'ble Supreme Court of India by its Order dated
19.04.2021 in Writ Petition (Civil) No. 838 of 2019 titled M.K. Ranjitsinh& Ors. v.
Union of India & Ors. in terms of which all existing and future overhead low and
high voltage power lines in the Priority and Potential habitats of Great-Indian
Bustard are necessarily required to be laid under-ground;”
……”
10.4 The nature and extent to which the above events will have an impact is
to be considered based on the factual details and circumstances having
implications of the above laws on the implementation of project by the
Solar Power Developers („SPDs‟). It is the obligation of the SPDs to establish
the same as being covered by the change in law at the appropriate
stage to the satisfaction of the Commission.
Page 17 of 32
10.5 At this stage, what is required to be done, in terms of the decision of the
Hon‟ble Tribunal, is only the recognition of the change in law events
[recognition of Basic Custom Duty on Solar Modules, Cells shall be subject
to issuance of appropriate notification by the Ministry of Finance
(competent authority)].
10.6 Article 12.2.3 of the PPAs provides for a formula for determination of the
relief with reference to every net increase/decrease of Rs.1 lakh per MW
in the project cost (i.e. the cost incurred by the Project Developer towards
supply and services of the project concerned, upto the actual
commissioning date of the last part capacity or Scheduled
Commissioning Date/Extended Scheduled Commissioning Date,
whichever is earlier) as a result of change in law events set out in Article
12.1.3 i.e. in the present case the Basic Custom Duty:
10.7 As regards the other changes in law, namely, the implication of the Order
dated 19.04.2021 passed by the Hon‟ble Supreme Court relating to Great
Indian Bustard, the same has to be considered as per Article 12.1.1, 12.1.2,
12.2.1, 12.2.2, 12.2.3, 12.3 etc. of the PPA.
10.8 Therefore, Article 12.2.3 of the PPAs [providing formula for determination
of relief for change in law applies to all change in law events i.e. those
events covered under Article 12.1.3 as well as events covered under
Article 12.1.1 of the PPAs.
10.9 The implications of the decision dated 19.04.2021 of the Hon‟ble Supreme
Court in Writ Petition (Civil) No. 838 of 2019 in the matter M.K. Ranjitsinh
and Others -v- Union of India & Ors dealing with Great Indian Bustard case
has to be considered at the appropriate stage, namely in terms of the
recommendation of the Committee appointed by the Hon‟ble Supreme
Court. Further, it would have to be examined whether it would have any
Page 18 of 32
implication in the present case, and if so to what extent and in what
manner.
10.10 It is further submitted that in terms of Article 12.2.3 of the PPAs, the actual
expenditure incurred by the SPD upto the actual commissioning date of
the last part capacity or Scheduled Commissioning Date/Extended
Scheduled Commissioning Date (whichever is earlier)is required to be
considered and determined for the application of the formula provided in
the said provision.
10.11 At this stage, for the application of the formula provided in Article 12.2.3
of the PPAs for relief of change in law, the amount constituting the project
cost cannot be considered on an estimate basis. The project cost will be
available only upon the capital expenditure being incurred as on the
actual commissioning date of the last part capacity or Scheduled
Commissioning Date/Extended Scheduled Commissioning Date.
10.12 In the present case, the order of the commission is to be restricted to the
above aspect of the recognition of the three events as change in law.
However, the recognition of Basic Customs Duty on Solar Modules and
Cells as a change in law event shall be subject to issuance of appropriate
notification by the Ministry of Finance, Government of India (Competent
Authority).The SPDs are not entitled to claim consideration of any other
aspects. The remand direction of the Hon‟ble Appellate Tribunal is
restricted to recognition of the above three change in law events at the
stage of tariff adoption. The Hon‟ble Tribunal in the Judgement dated
12.10.2021 has itself clarified that the actual impact and the extent of
relief admissible for the above-mentioned change in law events is to be
determined at the appropriate stage. It is therefore submitted that at
present there is no requirement to hold a detailed hearing except for the
Page 19 of 32
recognition of three events to be admissible as Change in law within the
scope of Article 12 of the PPAs.
10.13 SECI in its reply in petition no. 1933/21 submitted that the scheme under
Article 12.1.3 of the PPA is that the Commission while adopting the tariff
discovered under Section 63 competitive bid process, recognize the
events specified therein namely change in rates of Safeguard Duty, GST
and Basic Customs Duty after 28.10.2020 and resulting in change in
Project Cost. On such recognition, upon the commissioning and
commercial operation, the adjustment by way of tariff increase is to be
implemented as per the mechanism provided in Article 12.2.3. The
recognition made by the Commission in this regard shall govern the
Petitioner, the Solar Power Developer (SPD), RUVNL as the Buying Entity
and SECI as the intermediary.
10.14 The Commission vide order dated 23.07.2021 in Petition No.1905/2021 has
adopted the tariff discovered in the Competitive Bidding Process of 1070
MW Rajasthan (Tranche-lll) Scheme. In the said order, the Commission
granted liberty to the Solar Power Developers including the Petitioner
herein to file fresh Petition regarding the claims in respect of change in
law events.
10.15 The present Petition has been filed by the Petitioner in pursuance to the
above order dated 23.07.2021 passed by this Commission, restricting the
claim to for recognition of the Basic Custom Duty and stating that other
claims will be raised by the Petitioner at the appropriate stage. SECI
respectfully submits that the Commission may proceed to consider the
Petition filed by the Petitioner subject to the following submissions of SECI:
Page 20 of 32
10.16 In the present case, the bid deadline i.e. submission of bid was on
28.10.2020. The cut-off date for consideration of change in law is after
28.10.2020.
10.17 The extent to which the relief (increase in tariff) is admissible for change in
law events covered under Article 12.1.3 of the PPA would have to be
determined in terms of Article 12.2.3 as and when the capital expenditure
is incurred by the Petitioner. As per Article 12.2.3 of the PPA, it is further to
the extent of the project cost incurred up to Actual Commissioning date
of the last part capacity or Scheduled Commissioning Date/ Extended
Scheduled Commissioning Date, whichever is earlier.
11. RUVNL in its reply on the written submissions of RE generators and SECI
and in its reply in petition no. 1933/21 has submitted as under:
Page 21 of 32
v. Union of India &Ors. in terms of which all existing and future overhead
low and high voltage power lines in the Priority and Potential habitats of
Great-Indian Bustard are necessarily required to be laid under-ground;”
11.2 The basic custom duty on import of solar invertors was existing since
06.01.2011 and was also applicable on the last day of submission of the
bid. As per the provisions of the RFS, a generator was supposed to quote
its prices based on the existing taxes and levies. That vide notification
dated 01.02.2021 there is a withdrawal of the exemption which cannot
amount to change in law as per the terms and conditions of the change
in law event and therefore, it is submitted that the withdrawal of
exemption of a custom duty on invertors vide notification dated
01.02.2021 cannot amount to change in law as per the provision of RFS as
well as the Power Purchase Agreement and therefore, the generators are
not entitled to seek the notification dated 01.02.2021 as a change in law
event and therefore their claim deserves to be rejected.
11.4 The Hon‟ble Supreme Court orders are always a law of land and an order
dated 19.04.2021 will certainly amount to change in law. However, it is
submitted that before declaring an event as change in law, the
generators are required to place on record the documents to show how
the generators in present case would be affected by the order dated
19.04.2021 and in absence of such documents about the effects of the
Page 22 of 32
same, the claim is not required to be considered and deserves to be
rejected and set aside.
11.5 Some of the generators have also claimed other change of law events
including GST. It is submitted that the generators cannot claim any other
change of law except as directed by the Hon‟ble Aptel and such other
contentions deserves to be rejected.
11.6 RUVNL in its reply in petition no. 1933/21 has submitted that under
Electricity Act, 2003, there is no provision to declare/approve any article
or clause of a PPA. PPA is binding between the parties and is a settled
principle of law that if PPA is contrary to the Regulations then Regulation
will prevail. Therefore prayers prayed for are misconceived and the
petition is liable to be rejected on this count.
Commission’s view
13. The Solar Power Developers (SPDs) Respondents herein have mainly raised
the following issues:
(a) Hold and declare that the increase in rates of Basic Custom Duty (BCD)
on the import of Solar Inverters pursuant to the MoF Notification dated
01.02.2021 whereby the Exemption Notification dated 06.01.2011 has
been rescinded is a change in law event under the PPA;
(b) Hold and declare that the levy of BCD on the import of Solar Cells and
Modules/Panels pursuant to the MNRE OM dated 09.03.2021 with effect
from 01.04.2022 is a change in law event under the PPA;
Page 23 of 32
(c) Hold and declare that the MoF GST Notification is a change in law
event under the PPA;
(d) Hold and declare that the SC GIB Order qualifies as a change in law
event under the PPA and consequently, SPDs are entitled to
compensation and extension of time accordingly;
(e) Since the Project has already been delayed due to SC GIB Order as
well as delay in tariff adoption proceedings, the SCD and other
timelines under the PPA be extended to account for the time spent in
the legal proceedings before the Hon‟ble Tribunal and the Commission;
(f) RUVNL be directed to place on record the impact of the SC GIB Order
on the downstream transmission line / system.
(h) Approval and Recognition of Article 12.1.3 and Article 12.2.3 of the
Power Purchase Agreement which specifically provides that change in
rate of safeguard duty, GST and basic customs duty after 28.10.2020 will
be treated as change in law and every net increase/decrease of 1
lakh per MW in Project cost will be liable for corresponding increase or
decrease of an amount equal to Rs. 0.005/kWh;
Page 24 of 32
14. SECI in its written submissions has prayed to recognise the following three
events as constituting the change in law events under Article 12 of the
respective PPA (a) Increase in rates of Basic Customs Duty on import of
Solar Inverters pursuant to Ministry of Finance Notification No. 07 /2021-
Customs dated 01.02.2021 (b) Levy of Basic Customs Duty on import of
Solar Celts, Modules/Panels pursuant to Ministry of New and Renewable
Energy Office Memorandum dated 09.03.2021 subject to issuance of
appropriate notification by the Ministry of Finance, Government of India
(Competent Authority) (c) The direction issued by Hon'ble Supreme Court
of India by its Order dated 19.04.2021 in Writ Petition (Civil) No. 838 of 2019
titled M K. Ranjitsinh & Ors. v. Union of India & Ors.
15. SECI in its submissions has also submitted that in the present case, the
order of the commission should be restricted to the recognition of the
three events as change in law. The Solar Power Developers are not
entitled to claim consideration of any other aspects in the present matter.
16. RUVN has submitted that the basic custom duty on import of solar
invertors already existed since 06.01.2011 and was also applicable on the
last day of submission of the bid therefore does not qualify as change in
law. Further, the notification dated 09.03.2021 is a notification issued by
Ministry of New and Renewable Energy not by Ministry of Finance
therefore notification dated 09.03.2021 also does not qualify as change in
law.
17. On the Hon‟ble Supreme Court order dated 19.04.2021 RUVN submitted
that it will certainly amount to change in law however the generators are
required to place on record the documents to show the impact of the
said order and in absence of such documents, the claim is not required to
be considered and deserves to be rejected. RUVN further submitted that
Page 25 of 32
the generators cannot claim any other change of law except as directed
by the Hon‟ble Aptel.
18. It is noted that as the issues that arise in both the petitions for
consideration and decision of the Commission are similar, these petitions
referred to in cause title are clubbed and are being disposed of by this
common order.
19. Before going into the merits of the case it is worthwhile to mention the
brief facts of the case.
20. M/s Green Infra filed an Appeal No. 251 of 2021 before the Hon‟ble
Appellate Tribunal for Electricity, challenging the Order dated 23.07.2021
passed by the Commission.
21. The Hon‟ble APTEL vide its order dated 12.10.2021 remanded the matter
to the Commission for passing further orders on these change in law
events. The present proceedings are remand proceedings in pursuance
to order passed by Hon‟ble APTEL. Hon‟ble APTEL vide order dated
12.10.2021 has observed as under:
“16…………it is the duty of the State Commission to inquire into such claim at
the first opportune time and bring in suitable corrections, may be first by
declaration and followed up by detailed tariff orders. If the event referred
to actually constitutes change in law within the four corners of its definition
under the PPA, there is no reason why it cannot be duly recognized as a
change in law at the stage of tariff adoption, the actual impact and extent
of the relief admissible to be determined at the appropriate stage.
17. For the forgoing reasons, we allow the appeal finding the impugned order
to be an adjudication that is incomplete and proceedings wherein the
appellant had sought the above-mentioned declarations having remained
inchoate. The State Commission is directed to hear the parties further in the
Page 26 of 32
light of the above observations and pass further orders specifically in
relation to the three change in law event claims presented by the
appellant, rendering its decision as expeditiously as possible, preferably
within two months from today.”
22. The present proceedings are in pursuance to Hon‟ble APTEL order dated
12.10.2021 therefore should be restricted to the following change in law
events:
23. It is noted that some of the generators have also claimed relief on other
change of law events. In Commission‟s considered view and as rightly
pointed out by RUVNL and SECI in their reply that at this stage, what is
required to be done, in terms of the decision of the Hon‟ble Tribunal, is
only the recognition of the change in law events in respect of aforesaid
three events, therefore Commission has looked into the prayers of the
Generators strictly in terms of Hon‟ble APTEL Order. The generators are not
entitled to claim consideration of any other aspects.
24. Further, the nature and extent to which the above events will have an
impact is required to be considered based on the factual details at the
Page 27 of 32
appropriate stage to the satisfaction of the Commission. The Hon‟ble
Tribunal in the Judgement dated 12.10.2021 has clarified that the actual
impact and the extent of relief admissible for the above-mentioned
change in law events is to be determined at the appropriate stage.
25. We have looked into all the three change in law events in terms of the
relevant provisions of the PPAs.
26. The Article 12 of the PPA pertaining to „change in law‟ reads as under:
12.1.1. The term "Change in Law" shall refer to the occurrence of the following
pertaining to this Project only after 28.10.2020, including
(i) The enactment of any new law; or
(ii) an amendment, modification or repeal of an existing law; or
(iii) the requirement to obtain a new consent, permit or license; or
(iv)Any modification to the prevailing conditions prescribed for obtaining a
consent, permit or license, not owing to any default of the solar power
developer; or
(v) Any change in the rates of any taxes including any duties and cess or
introduction of any new tax made applicable for setting up the solar
power project and supply of power from solar power project by the SPD
which have a direct effect on the project.
However, change in Law shall not include (i) any change in taxes on
corporate income or any withholding tax on income or dividends
distributed to the shareholders of the SPD.
12.1.3 However, in case of change in rates of safeguard duty, GST and basic
customs duty after 28.10.2020 and resulting in change in Project Cost, then
such change will be treated as 'Change in Law' and the quantum of
Page 28 of 32
compensation payment on account of change in rates of such duties
and shall be provided to the affected party by the other party as per
Article 12.2.3, subject to the provision that Appropriate Commission
recognizes such provisions at the time of adoption of tariff by the
Appropriate Commission and any decision in this regard shall be
governing on SPD and Buying Entity.
27. From the perusal of the aforesaid Article of the PPA, it is clear that as per
Article 12.1.3 of the PPA any change in rates qua Safeguard Duty, GST
and BCD after the last date of bid submission, i.e., 28.10.2020 which
resulted in change in overall cost of the project, then in that case such
change will be treated as change in law. In light of these provisions of PPA
we may now discuss each event claimed to be change in law event.
Page 29 of 32
28. SPDs have prayed to hold and declare that the increase in rates of BCD
on the import of Solar Inverters pursuant to the MoF Notification dated
01.02.2021 whereby the Exemption Notification dated 06.01.2011 has
been rescinded is a change in law event under the PPA.
29. SPDs have further prayed to declare that the levy of BCD on the import of
Solar Cells and Modules/Panels pursuant to the MNRE OM dated
09.03.2021 with effect from 01.04.2022 is a change in law event under the
PPA.
30. The Article 12.1.3 of the PPA pertaining to „change in law‟ reads as under:
12.1.3 However, in case of change in rates of safeguard duty, GST and basic
customs duty after 28.10.2020 and resulting in change in Project Cost, then
such change will be treated as 'Change in Law' and the quantum of
compensation payment on account of change in rates of such duties
and shall be provided to the affected party by the other party as per
Article 12.2.3, subject to the provision that Appropriate Commission
recognizes such provisions at the time of adoption of tariff by the
Appropriate Commission and any decision in this regard shall be
governing on SPD and Buying Entity.
Page 30 of 32
31. It is noted that there is clear provision in the PPA that if there are changes
in the rates of Basic Custom Duty (BCD) after 28.10.2020 and resulting in
change in Project Cost, then such change will be treated as 'change in
law' subject to the provision that Appropriate Commission recognizes such
provisions.
Re: Directions issued by Hon'ble Supreme Court of India by its Order dated
19.04.2021 in Writ Petition (Civil) No. 838 of 2019 titled M.K. Ranjitsinha Ors.
v. Union of India &Ors.
33. SPDs have prayed that certain directions issued vide order dated
19.04.2021 passed by the Hon'ble Supreme Court be declared as a
change in law event.
34. We observe that Hon'ble Supreme Court of India by its Order dated
19.04.2021 0in Writ Petition (Civil) No. 838 of 2019 titled M.K. Ranjitsinh &
Ors. v. Union of India & Ors. has issued certain directions in terms of which
all existing and future overhead low and high voltage power lines in the
Priority and Potential habitats of Great-Indian Bustard are necessarily
required to be laid under-ground.
Page 31 of 32
not location specific, therefore, SPDs can set up project anywhere in the
State therefore they cannot claim the benefit of change in law relating to
any specific location.
36. It is also noted that there might be some other unsuccessful bidders who
have quoted higher tariff for some other locations which are out of the
Priority and Potential habitats of Great-Indian Bustard as stated in the
Hon‟ble Supreme Court Order. If this unconditional and location agnostic
interpretation about „change in law‟ event (relating to GIB) is considered
to be approved it will be great injustice to those bidders who lost out by
the aforesaid bid by SECI.
38. It is further clarified that the nature and extent to which the events of levy
of basic custom duty and increase in basic custom duty will have an
impact will be considered separately by the procurer based on the
factual details and circumstances.
39. In view of above, the Petitions bearing no. 1905/21 and 1933/21 are
disposed of, accordingly.
Page 32 of 32