Guidelines for the distribution of

Propylene Oxide

Revision 2 - July 2009


Propylene Oxide/Propylene Glycols Cefic Sector Group
Notice

The information, specification, procedures, methods and recommendations herein are presented in good faith, are
believed to be accurate and reliable, but may well be incomplete and/or not applicable to all conditions or situations that
may exist or occur. No representation, guarantee or warranty is made as to the accuracy, reliability or completeness of
said information, specifications, procedures, methods and recommendations or that the application or use of any of the
same will avoid hazards, accidents, losses, damages or injury of any kind to persons or property or that the same will not
infringe patents of others or give desired results. Readers are cautioned to satisfy themselves as to the suitability of said
information, specifications, procedures, methods and recommendations for the purposes intended prior to use.
If there are national or international legal requirements on any of the recommendations stated in this document, these
shall prevail.

2
Table of contents

1 Introduction 5
2 Product information 6
2.1 General data 6
2.2 Physical properties 6
2.3 Flammability hazards 7
2.4 Reactivity hazards 7
2.5 Toxicology and occupational health hazards 8
2.6 Emissions and degradation 9
2.7 International transportation regulations 10
2.8 EEC labelling/special risks/safety advice 12
3 Transport and storage operations 13
3.1 Loading operations 13
3.2 Transport of Propylene Oxide by road 16
3.3 Transport of Propylene Oxide by rail 17
3.4 Transport of Propylene Oxide by sea 18
3.5 Unloading operations 19
4 Design and construction of transport and storage equipment 21
4.1 Current operation practices 21
4.2 Design and construction of railcars (rail tank cars) 21
4.3 Design and construction of tank trucks (road tankers) 23
4.4 Design and construction of tank containers 23
4.5 Design and construction of vessels and barges 23
4.6 Design and construction of storage tanks 23
4.7 Design and construction of loading and unloading facilities 23
5 Emergency procedures 24
5.1 Emergency planning 24
5.2 Measures in the event of a release of Propylene Oxide 24
5.3 Fire fighting 25
6 Personal protection, first aid and medical treatment 26
6.1 Personal protection 26
6.2 First aid and medical treatment 27

7 Training for road tanker and tank container drivers 28

3
Table of contents

Appendix 1 29
Cefic and Responsible Care
Appendix 2 31
Cefic recommendations on safe management practices in distribution. (SQAS)
Appendix 3 32
Inspection of transport equipment
Appendix 4 37
Instructions in writing
Appendix 5 42
Guide for the marine chartering and handling of Propylene Oxide

Appendix 6 45
A Safety Scheme for the reception and storage facilities at Propylene Oxide customers

Appendix 7 51
Design and construction of rail tank cars
Appendix 8 53
Design and construction of tank trucks and tank containers
Appendix 9 55
Design and construction of vessels and barges
Appendix 10 56
General Guidelines for design and construction of Propylene Oxide storage tanks
Appendix 11 62
Member Companies of the Propylene Oxide/Propylene Glycols Sector Group
Appendix 12 63
Glossary of abbreviations
Appendix 13 65
Recommended general instructions for Propylene Oxide drivers

4
1 Introduction

The Cefic (European Chemical Industry Council) Responsible Care Program requires that Chemical Companies
demonstrate their commitment to continuously improve all aspects of Performance which relate to Protection of Health,
Safety and the Environment.

An overview of the Key Elements of Cefic’s Distribution Responsible Care Program is contained in appendix 1.

These Guidelines have been prepared by a Task Force under the direction of the Cefic Propylene Oxide Sector Group
as their execution program with regard to the application of Responsible Care in the distribution of Propylene Oxide.
They are consistent with the Cefic Recommendations on Safe Management Practices in Distribution and establish
appropriately high standards of safety for the distribution of Propylene Oxide. The key elements of these Management
Practices are contained in appendix 2.

Although Propylene Oxide is a hazardous material in terms of flammability, reactivity and toxicity, it can be distributed
and handled safely provided that appropriate precautions are observed.

The Distribution of Propylene Oxide is already subject to regulations within most countries in Europe. In addition,
the international movement of Propylene Oxide by road, rail, sea or river/canal is subject to international agreements
which lay down specific requirements concerning distribution which must be observed by all parties involved.
National regulations may differ from international regulations.

These Guidelines take into account the distribution of Propylene Oxide in bulk road tankers, rail tank cars, sea tank ships,
barges and tank containers. They cover all aspects of the transport activity from loading to delivery point. Reference to
existing regulatory controls is only made where this is considered necessary for the purpose of clarification.

Since drum shipments are not carried out by the Sector Group Propylene Oxide manufacturers, specific distribution risk
management requirements for drum shipments are not discussed in these guidelines. However, individual companies
can offer advice upon request.

The Cefic Propylene Oxide Sector Group recommends that these Guidelines are adopted by all parties who are involved
in the distribution of Propylene Oxide. This includes Commercial Transactions, Swap, Toll or Trade agreements and
Customer Collection Arrangements.

The Sector Group Members will review these Guidelines on a regular basis.

5
2 Product information

2.1 General Data


EINECS NUMBER INDEX NUMBER CAS NUMBER SYNONYMS FORM

200-879-2 603-055-00-4 75-56-9 1,2-epoxypropane liquid


epoxypropane
methyl ethylene oxide
methyloxirane
1, 2-Propylene Oxide

HAZARDS IDENTIFICATION

Extremely flammable
May cause cancer
May cause heritable genetic damage
Harmful by inhalation, in contact with skin and if swallowed
Irritating to eyes, respiratory system and skin

WARNING PROPERTIES

The odour of this material is inadequate to warn of excessive exposure.

2.2 Physical Properties

Formula O

H 2C CH-CH2

Molar mass 58.08 g/mol

Melting Point (101.3 kPa) -111.9°C

Boiling Point (101.3 kPa) 34.2°C

Flash Point (closed cup) -37°C

Critical Temperature 209.1°C

Critical Pressure 4920 kPa

Critical Density 312 kg/m3

Critical compressibility factor 0.2284

6
Product information Chap 2

Auto ignition temperature in air at 101.3 kPa 449°C

Explosive limits in air (STP):


- Lower 1, 7 vol%
- Upper 37.0 vol%

Heat of combustion (25°C 101.3 kPa) -33035 kJ/kg

Heat of Polymerization -1500 kJ/kg

Heat of fusion 112.6 kJ/kg

Heat of solution in water at 25°C -45 kJ/kg

Heat of formation of the ideal gas (25°C) -1600 kJ/kg

Heat of formation of liquid Propylene Oxide (25°C) -2080 kJ/kg

Standard enthalpy (298.15K) 248 kJ/kg

Standard entropy (298.15K, 1 atm.) 4.94 kJ/kg -1 K-1

Free energy of formation (25°C, 101.3 kPa) 459 kkJ/kg

Cubic expansion coefficient at 20°C 0.00151 1/K

Solubility of Propylene Oxide in water at 20°C 40.5 wt%

Solubility of water in Propylene Oxide at 20°C 12.8 wt%

Density gr/cm3 at 20°C 0.83

Relative vapour density (air=1) 2.0

Vapour pressure (kPa at 20°C) 57.7

Saturation concentration at 20°C 1360 g/m3

Minimum ignition energy 0.13 mJ

Flashpoint of 1% aqueous solution 23°C

2.3 Flammability hazards


Propylene Oxide, a colourless highly volatile liquid with a sweet ethereal odour, is extremely flammable with a flashpoint
of -37°C (closed cup) and a wide explosive range of 1.7-37 Vol % in air.
The vapour is heavier than air and spreads at ground level, with the risk of ignition at great distance and flash back.
Propylene Oxide has ignition energy of 0.13 mJ.

2.4 Reactivity hazards


Bases, acids or metal halides can cause violent polymerization. Propylene Oxide is presumed to be able to form peroxides
and thus to polymerize. Do not use compressed air when filling, emptying or processing. Propylene Oxide reacts violently
with oxidants, organic and inorganic acids, organic and inorganic bases, anhydrides, chlorides of iron, aluminium and tin,
chlorine, amines, ammonia and alkali metals with risk of fire and explosion. Do not use clay based absorbent materials.

7
Product information Chap 2

2.5 Toxicology and occupational health hazards


2.5.1 Inhalation
Propylene Oxide is classified as harmful by inhalation and irritating to the respiratory system.

Inhalation studies in laboratory animals suggest no adverse nasal or respiratory effects will occur with Propylene
Oxide vapour concentrations of 100ppm or lower. Repeated exposure was associated with central nervous system
depression and irritation of the eyes and respiratory system. Mild to moderate damage to the nasal epithelium
was seen in rats after repeated exposure to 200 - 400 ppm.

In humans, exposure to Propylene Oxide at several hundred ppm may result in headache, dizziness, drowsiness,
nausea, chest discomfort and cough. Higher concentration (above 1000 ppm) may cause irritation and oedema
of the respiratory tract and loss of consciousness. The odour threshold in air is 100 - 350 ppm. This is well above
the occupational hygiene level; hence smell should not be used as an indicator of exposure to Propylene Oxide.

2.5.2 Oral toxicity


Propylene Oxide is classified as harmful by ingestion.

Oral LD 50 values in the range of 520 - 1140 mg/kg have been reported from rat studies.

2.5.3 Skin contact


Propylene Oxide is classified as harmful and irritating after contact with skin.

The dermal LD50 from rabbit studies is in the range of 1240 - 7200 mg/kg. Propylene Oxide liquid is moderately
to severely irritating to skin.

In an occupational setting, skin irritation following accidental contact with liquid Propylene Oxide will be
minimised if the material is allowed to evaporate freely, although contact for several minutes may produce
moderate to severe irritation. Aqueous solutions (10 % vol / vol or greater) are more irritating than undiluted
material. Note that such conditions may arise following dissolution of Propylene Oxide in body sweat.

Prolonged or repeated skin contact will result in the development of chemical burns, blistering and swelling.
There are reports that it may also produce allergic dermatitis.

2.5.4 Eye contact


Propylene Oxide is classified as irritating to the eyes.

High vapor concentrations may cause eye irritation, while liquid will produce corneal burns with permanent
impairment of vision possible.

8
Product information Chap 2

2.5.5 Carcinogenicity
Propylene Oxide is classified as a Category 2 carcinogen (i.e. a substance which should be regarded as if it were
carcinogenic to man).

The occurrence of nasal tumours in rats and mice was increased after lifetime inhalation exposure to 400 ppm,
but not at 200 ppm. Shorter term (30 day) exposure to 900 ppm caused marked nasal irritation, but no increase
in tumours was recorded during a 155 week follow-up period. The findings suggest a weak carcinogenic response
in rodents that is confined to the principle site of contact (i.e. nasal tissue).

There is no evidence of any carcinogenic effect in humans.

2.5.6 Mutagenicity
Propylene Oxide was inactive in a dominant lethal assay in rodents, suggesting that it does not cause heritable
mutations in sperm. Nevertheless Propylene Oxide is classified as a Category 2 mutagen (i.e. a substance which
should be regarded as if it were able to cause heritable mutations in man) because of the findings of micronuclei
in mice (described above) and that it was found in the testes of animals exposed to 500ppm Propylene Oxide for
4 weeks.

2.5.7 Effects on reproductive system


Propylene Oxide is a low concern for reproductive and developmental toxicity.
No effect on fertility, litter size, neonatal growth or survival was seen in male and female rats exposed to 300 ppm
Propylene Oxide by inhalation over two generations. Foetotoxicity and developmental effects in laboratory animals
exposed during pregnancy were minor in nature and only occurred at exposures that were maternally toxic.

2.6 Emissions and degradation


Propylene Oxide is not known to occur naturally.

Occurrence of Propylene Oxide in the environment is expected to be mainly in the atmosphere due to fugitive emissions
from production or further processing.

In the atmosphere, Propylene Oxide is indirectly degraded by reaction with photo chemically produced hydroxyl radicals.
The half-life of Propylene Oxide in the atmosphere is estimated to be 13 - 35 days. Propylene Oxide is not expected to
contribute to ozone depletion.

In water, Propylene Oxide is hydrolyzed to Propylene Glycol with an estimated half-life of 4 - 12 days. Biodegradation
under aerobic static laboratory conditions is moderate to high. According to MITI, Propylene Oxide is readily
biodegradable. The chloride ion in salt water accelerates the chemical degradation with a half-life of 2 - 4 days, as well as
basic and acidic condition. Further more Propylene Oxide is eliminated from water by volatilisation with a half-life of 3
days for rivers and up to 18 days for lakes. Propylene Oxide toxicity to fish or daphnia is low.

Propylene Oxide rapidly evaporates from dry surfaces and is moderately volatile from wet surfaces.

Propylene Oxide is expected to be very mobile in soil. In moist soils, hydrolysis will be the most significant
degradation process.

Accumulation in biological or environmental systems is not to be expected.

9
Product information Chap 2

2.7 International transportation regulations


ADR / RID / ADN

PROPER SHIPPING NAME Propylene Oxide

UN N° 1280

CLASS 3

PACKING GROUP I

LABEL 3

HAZARD ID. N° 33

Fig. 1 Legend table of a Propylene Oxide rail car

10
Product information Chap 2

IMDG

PROPER SHIPPING NAME Propylene Oxide

IMO/IMDG CLASS 3

PACKING GROUP I

LABEL 3

UN N° 1280

TANK TYPE UN-T11, (IMO-1) - Test Pressure (bar): 6.0

MARINE POLLUTANT No

IBC CODE

Proper shipping name Propylene Oxide

IMO/IMDG Class 3

UN N° 1280

TANK TYPE 2G

SHIP TYPE 2

POLLUTION CATEGORY Y

IATA

PROPER SHIPPING NAME Propylene Oxide

ICAO/IATA CLASS 3

UN N° 1280

PACKING GROUP I

Remarks: Sample shipment not allowed by mail

11
Product information Chap 2

2.8 EEC labelling / special risks / safety advice


CLASSIFICATION

Classification according to Annex I of council Directive 67/548/EEC


(Dangerous substances Directive) (“EEC Label”)

F+ Extremely flammable R 12

Carcinogen Category 2 R 45

Mutagen Category 2 R46

Xn Harmful by inhalation, in contact with skin and if swallowed R 20/21/22

Xi Irritating to eyes, respiratory system and skin R 36/37/38

LABELLING

F+, T

RISK PHRASES

R12 Extremely flammable

R45 May cause cancer

R46 May cause heritable genetic damage

R 20/21/22 Harmful by inhalation, in contact with skin and if swallowed

R36/37/38 Irritating to eyes, respiratory system and skin

SAFETY PHRASES

S 53 Avoid exposure - obtain special instructions before use

S 45 In case of accident or if you feel unwell, seek medical advice immediately


(show the label where possible)

12
3 Transport and storage operations

3.1 Loading operations


3.1.1
The operation of filling of any road tanker, tank container, railtankcar or barge / vessel with a dangerous substance
is a potential hazard. It is therefore important that loading facilities and transport equipment are correctly
designed and constructed, and properly used and maintained.
Loading facilities should be situated at a safe distance from storage tanks. Loading facilities at terminals should
have a remote controlled shut-off valve between the storage tanks and the loading vehicles.
For loading and unloading operations (PO selectively coded) dry disconnect couplings (NATO standard 3756) are
the European standard (liquid: 3 inch selectivity code 3-5; gas: 2 inch selectivity code W; Gasket: Chemraz 505)
ADR & RID dictates the present of three closing devices. Pressure retaining caps are strongly recommended.

3.1.2
The recommended design and construction of transport equipment is described in appendices 6 to 8 of these
Guidelines. Equipment that meets the requirements of the ADR, ADNR, RID and IMO Regulations is subjected to
periodic inspection and testing requirements as laid down in these Regulations. These inspections and tests are
carried out by certified bodies.

3.1.3
Written operating instructions should be available for all filling points covering the loading of Propylene Oxide
into bulk road tankers, tank containers, rail tank cars, barges or vessels, and personnel involved should be fully
trained in their use. The instructions should recognise the specific hazards of Propylene Oxide, and ensure the
correct operation of filling equipment in both normal and emergency situations.

3.1.4
All necessary protective clothing and emergency equipment should be available for loading operations. Personnel
should be trained in the correct use of this clothing and equipment.

13
Transport and storage operations Chap 3

Fig. 2 Dry Disconnect Coupling connection

Fig. 3 Dry Disconnect Coupling equipment

14
Transport and storage operations Chap 3

Fig. 4/5 Worker in protective clothing, connecting DDC liquid connection

15
Transport and storage operations Chap 3

3.1.5
It is not the intention in this Section of these Guidelines to attempt to set detailed operating instructions for
loading Propylene Oxide, since these, of necessity, will depend upon local situations. However, as part of the
operating instructions, an inspection of the transport equipment should be carried out by the loading terminal
staff before, during and after loading. This inspection does not replace nor diminish the responsibility of the
owner of the road tanker, tank container, rail tank car, barge or vessel to ensure that the equipment is properly
tested, maintained and fit for purpose. It is meant to ensure that the transport of Propylene Oxide is conducted as
safely as possible. The inspection list detailed in appendix 3 is recommended for use by the supplier to check the
condition of the Propylene Oxide transport equipment, and this should apply to the loading operations of rail and
road mode.
Barges and vessels have specific checklists according to ADN/IMO regulations.

3.1.6
The inspection list assumes that Propylene Oxide is to be conveyed by international transport. In circumstances
where Propylene Oxide is to be conveyed nationally, in accordance with regulations, which may differ from
the requirements laid down in international transport agreements, the inspection list should be modified as
appropriate.

3.2 Transport of Propylene Oxide by road


3.2.1
The carrier is responsible for the safe transport of Propylene Oxide by road from the loading point to the
discharge point. Road carriers must meet all relevant national and international regulations relating to Propylene
Oxide. Road carriers should preferably have a Quality system (like ISO 9000) and participate in an SQAS scheme.
Cefic guidelines provide a framework for the implementation of the principles of Behaviour Based Safety (BBS)
(http://www.cefic.org/en/transport-and-logistics-best-practices-guidelines.html) to safe driving of road freight
vehicles. BBS is a programme aimed at increasing safety during transport by positively influencing the behaviour
of drivers through observation, coaching and communication.
For reasons of unwanted reactions, contamination must be avoided. Therefore, only dedicated road tankers
and tank containers must be used for Propylene Oxide. Transport equipment has to be held under (positive)
nitrogen/PO vapor pressure at all times (to avoid air ingress). All connections should be sealed (see appendix 3).

3.2.2 Routing
The transport of Propylene Oxide has to follow the ADR regulations. Propylene Oxide should only be transported
on defined routes. The route to be followed must be selected carefully and should be known to both the carrier
and the consignor.

As far as possible, the route should:


a) Utilise motorways,
b) Avoid areas of high population density.

3.2.3 Severe Weather conditions


When severe weather conditions occur during transport, for example icy roads, snow or poor visibility, the delivery
has to be stopped at the next suitable parking place.

16
Transport and storage operations Chap 3

3.2.4 Delays or accidents


All delays during transport, whether due to severe weather conditions, breakdown or other reasons must be
reported to the consignor as soon as possible.
Transport accidents must also be reported to the consignor as soon as possible.

3.2.5 Emergency procedure


If emergency action needs to be taken by drivers when leaks, spills or fire occur during transport, then the
instructions given in the “Instructions in writing” must be followed. See appendix 4.

3.2.6 Ferry selection


The consignor will ensure that he knows which ferry operators are being used by the road carrier and will satisfy
him of their suitability.

3.2.7 Customer collection


Customer collection should be avoided, except for co-producers.
However, if such collections take place, appendix 3 should be used.

3.2.8 Multimodal transport


Tank containers are often transported in a multimodal system. This is generally organised by the carrier.
Management systems shall be in place to ensure quality and safety of operations by the carrier for the complete
supply chain. This system should preferably be checked by means of an SQAS.

3.2.9 Subcontracting
Contractual arrangements between consignor and carrier should explicitly state that transport must not be
subcontracted without prior approval of the consignor.
The subcontractor must fulfil the same requirements as the principal contracting carrier.

3.3 Transport of Propylene Oxide by rail


3.3.1
The appropriate railway companies, freight forwarders and authorities are responsible for the safe transport of
Propylene Oxide by rail from dispatch location to final reception facilities. For reasons of unwanted reactions,
contamination must be avoided. Therefore, only dedicated rail tank cars must be used for Propylene Oxide.
Transport equipment has to be held under (positive) nitrogen / PO vapor pressure at all times (to avoid air
ingress). All connections should be sealed (see appendix 3).

The selection of route, intermediate stopping locations and delay of traffic due to severe weather conditions are
matters to be decided by the railway companies and authorities.

As SQAS Rail is now available, it should progressively be used.

3.3.2
The consignor will ensure that they are informed which rail-ferry operators the national railways are using.

17
Transport and storage operations Chap 3

Fig. 6 Derailleur at a filling station to prevent other railcars from entering the loading station

3.4 Transport of Propylene Oxide by sea


3.4.1
Transport of Propylene Oxide by sea may be either:
a) By roll on/roll off ferries, or
b) Lift on/lift off shipment in tank containers
c) Bulk by seagoing vessels.

3.4.2
Because of the nature of the transport, a number of different parties may be involved in the transport of
Propylene Oxide from consignor to customer. These may include the shipping company, port or harbour
authorities and carriers.

3.4.3
Prior to the commencement of each traffic flow; the consignor should make sure that all parties involved have
adequate Safety, Health and Environment standards.

Particular areas of interest are:


a) The shipping company
b) Loading/unloading facilities at container terminals
c) Emergency handling within hazardous cargo yards at container terminals
d) Emergency handling on board.

The Safety, Health and Environment system should preferably be checked by means of a CDI-Marine inspection.

18
Transport and storage operations Chap 3

3.4.4
The consignor should issue specific instructions for the control of the operation to all parties involved and the
actions to be taken in the event of an emergency.

3.4.5
Transport by sea and inland waterways in bulk requires a suitable ship or barge that is certified to carry Propylene
Oxide. Refer to appendix 5 for details.

3.5 Unloading operations


3.5.1
The unloading of any road tanker, tank container, rail tank car, ship or barge of Propylene Oxide is a potential
hazard. It is therefore important that unloading facilities are correctly designed and constructed, and properly
used and maintained. Unloading facilities should be situated at a safe distance from storage tanks. Unloading
facilities at terminals should have a remote controlled shut-off valve between the storage tanks and the loading/
unloading vehicles (see chapter 4).

For loading and unloading operations PO selectively coded dry disconnect couplings (NATO standard 3756) are
the European standard (liquid: 3 inch selectivity code 3-5; gas: 2 inch selectivity code W; Gasket: Chemraz 505)
Pressure retaining caps are strongly recommended.

Fig. 7 Dust caps

19
Transport and storage operations Chap 3

3.5.2
Unloading facilities should be designed and located having due regard to the potential hazards associated with
Propylene Oxide.
The equipment should be subject to regular and documented checks to ensure reliability.
Maintenance should be done by trained personnel.

3.5.3
Written operating instructions should be available for unloading Propylene Oxide from road tankers; tank
containers, rail tank cars and ships as appropriate, and personnel involved should be fully trained in their use.
The instructions should recognise the specific hazards of Propylene Oxide, and ensure the correct operation of
unloading equipment in both normal and emergency situations.

3.5.4
All necessary protective clothing and emergency equipment should be available for unloading operations.
Personnel should be trained in the correct use of this clothing and equipment.

3.5.5 Maintenance of transport equipment


Customers are requested to report any difficulties, which are experienced with the operation of valves,
immediately to the consignor. The use of an information tag on the returning transport equipment identifying
the problem can be of assistance.

3.5.6
The conditions for discharge of Propylene Oxide at a customer’s premises are the customer’s responsibility.
If the customer requires such, the consignor may provide him with technical advisory and safety service, which in
principle may include an EH&S visit.
If an EH&S visit is made, the scheme included in appendix 5 may be used as a checklist. Normally the customer
himself should evaluate whether his premises, especially his reception and storage facilities, correspond with the
requirements of the scheme included in appendix 6.

20
4 Design and construction of transport
and storage equipment

4.1 Current operating practices


The Propylene Oxide manufacturers use either equipment for the bulk transport of liquefied or pressurized gases (LG) or
equipment for bulk liquid transportation of Propylene Oxide according to the applicable regulations.

4.2 Design and construction of railcars (rail tank cars)


Railcars for the carriage of Propylene Oxide must meet the design and construction requirements of:
a) National Regulations or Local Railway Administration Regulations, when used for national transport.
b) International Regulations, such as the International Regulations concerning the Carriage of Dangerous Goods
by Rail (RID), when used for international transport.

In addition it is recommended that railcars are designed and constructed in accordance with the recommendations
contained in appendix 7.

Fig. 8 Blockade to fix a rail car together with a spiral spring handle, which closes the valves automatically
when the rail car rolls away

21
Chap 4
Design and construction of transport and storage equipment

Fig. 9 Rail hook combined with a remote control, which closes the bottom valve if activated. This example shows
only the set up for liquefied gas railcars.

22
Chap 4
Design and construction of transport and storage equipment

4.3 Design and construction of tanktrucks (road tankers)


Tank trucks used for the carriage of Propylene Oxide by road must meet the design and construction requirements of:
a) National Regulations, when used for national transport.
b) International Regulations depending on the mode of transportation (e.g. shortsea voyage), such as the
European Agreement concerning the International Carriage of Dangerous Goods by Road (ADR), when used
for international transport.

In addition to the above requirements, it is recommended that tank trucks are designed and constructed in accordance
with the recommendations contained in appendix 8.

4.4 Design and construction of tank containers


Tank containers may be used for the carriage of Propylene Oxide by road, rail, and sea. They must meet the design
and construction requirements of the appropriate National or International Regulations depending upon the specific
transport modes which are to be utilized.

In addition to the above requirements, it is recommended that tank containers are designed and constructed in
accordance with the recommendations in appendix 8.

4.5 Design and construction of vessels and barges


Vessels used for the carriage of Propylene Oxide by sea must meet the design and construction requirements of:
International Regulations such as the international Code for the construction and equipment of ships carrying dangerous
chemicals in bulk as produced by the International Maritime Organization (IMO).

Barges used for the carriage of Propylene Oxide by inland waterways must meet the design and construction
requirements of National and International Regulations for the design and construction of barges such as the regulations
concerning the Transport of Dangerous Substances in Barges on the River Rhine (ADN).

In addition to the above requirements, it is recommended that the vessels and barges are designed and constructed in
accordance with the recommendations contained in appendix 9.

4.6 Design and construction of storage tanks


The storage and handling of Propylene Oxide is subject to legislative controls in many countries. The design and
construction of storage tanks for Propylene Oxide must therefore comply with national legislative controls.
The general guidelines contained in appendix 10 exemplifies the best general practice which is followed within the
Propylene Oxide manufacturing industry and should be used provided it does not conflict with any specific legal obligation.

4.7 Design and construction of loading and unloading facilities


As transport and storage equipment have their own specific design and construction requirements it is essential to
ensure the correct design of equipment for loading and unloading facilities. Loading and unloading facilities should be
designed and located to meet appropriate engineering standards having due regard to the hazards associated with the
handling of Propylene Oxide and the transfer rates which are to be achieved. Particular attention should be given to the
ergonomics of connecting transportation equipment and to the health and safety protection of operators.

23
5 Emergency procedures

5.1 Emergency planning


5.1.1
All Propylene Oxide producers involved in transporting Propylene Oxide in Europe should have an established
Emergency Plan for receiving transport incident reports and for providing expert advice by telephone and, as
necessary, at the incident scene to the Emergency Services on how to minimize any danger arising from an
incident on road, rail or waterway. The Cefic document “Distribution Emergency Response - Guidelines for Use by
the Chemical Industry” provides advice on setting up a Company Emergency Plan.

5.2 Measures in the event of a release of Propylene Oxide


5.2.1
• Shut off all potential ignition sources and leaks, if without risk
• No open flames
• Keep upwind
• Isolate area and deny entry
• Do not get into eyes
• Avoid contact with skin
• Avoid breathing vapour.

5.2.2
• Dilute liquid spills with large amounts of water
• Use water spray to reduce the extent of vapour
• Avoid the use of clay-based absorbents
• Dike larger spills and recover
• Prevent entry into sewers and/or natural waters
• If substance has entered a water course or sewer, inform/advise Authorities.

5.2.3
By covering a liquid spill as quickly as possible with foam, evaporation and hence the formation of a flammable
gas cloud can be prevented. The released liquid must then be recovered and transferred to sealable tanks or
drums. Any remaining quantities of Propylene Oxide should be absorbed into suitable materials such as sand

24
Emergency procedures Chap 5

and transported in closed drums to a suitable processing installation. The recommended method of disposal is
by incineration.

5.3 Fire fighting


5.3.1
Do not put out any fire until leak is shut off. The reason is to prevent re-flash.

5.3.2
Cool containers exposed to heat / fire with water, to prevent overpressure / bursting.

5.3.3 Small fires


Use dry chemical or carbon dioxide (CO2).

5.3.4 Large fires


Use water spray, fog or alcohol foam.

5.3.5 Massive fires


• Use unmanned hose holders or monitor nozzle
• Consider letting the fire burn out
• Dike liquid run-off
• Prevent entry into sewers and/or natural waters.

25
6 Personal protection, first aid and medical treatment

6.1 Personal protection


6.1.1
Eye protection: Use chemical resistance safety goggles.

6.1.2
Normal working clothes should be worn during routine handling.

6.1.3
Clothing for spill and fire:
• wear full protective clothing PO resistant gloves under gauntlet type Nitriles rubber gloves, rubber
safety boots and approved positive pressure breathing apparatus
• remove contaminated clothing immediately, preferably under safety shower / fire hose spray, and wash
before re-use
• destroy contaminated shoes and leather items

Review supplier safety data sheet for more information.

Fig. 10 Fully protected operator

26
Personal protection, first aid and medical treatment Chap 6

6.2 First aid and medical treatment


Never give fluids or induce vomiting if patient is unconscious or is having convulsions.

Inhalation
Remove to fresh air. If not breathing, give artificial respiration. If breathing is difficult, oxygen should be
administered by qualified personnel. Call a physician or transport to medical facilities for immediate
medical advice.

Skin contact
In case of contact, immediately flush skin with plenty of water for at least 15 minutes while removing
contaminated clothing and shoes. Call a physician if irritation persists. Wash clothing before reuse.
Destroy contaminated shoes. Seek medical attention immediately.

Eye contact
Immediate and continuous irrigation with running water for at least 15 minutes is imperative.
Prompt medical consultation is essential. Seek medical attention immediately.

Ingestion
If swallowed, rinse mouth and go immediately to hospital.
Inducement of vomiting to be indicated by a doctor only.

Note to physician
Causes central nervous system depression. If burn is present, treat as any thermal burn, after decontamination.
Treat symptomatically. No specific antidote. Supportive care. Treatment based on judgement of the physician in
response to reactions of the patient.

27
7 Training for road tanker and tank container drivers

The ADR agreement requires a valid dangerous goods driving license for all drivers of road tankers or transport units
carrying tank containers with a total capacity of more than 3000 liters.

Before transporting Propylene Oxide, it is recommended that the driver is trained on the specific hazards of Propylene
Oxide. This training should include security aspects according to 1.10 ADR and may contain the topics mentioned in
appendix 13.

28
Appendix 1 Cefic and Responsible Care

1 Responsible Care - a public commitment


"Chemical companies shall demonstrate their commitment to continuously improve all aspects of performance which
relate to protection of health, safety and the environment."

2 Prevention of accidents
Within Responsible Care, prevention is a prerequisite to Emergency Response. The Cefic-ICE (International Chemical
Environment) prevention program provides a valuable tool in reducing the number of incidents during the distribution of
chemicals, from the time they leave the factory gate until their arrival at the customer's premises.

3
The objective is to minimize the possibility for incidents to happen. Since most distribution activities are subcontracted
and since compliance with regulations is a necessary but not a sufficient condition to prevent accidents, there is a need
for uniform safety & quality criteria against which distribution companies are regularly assessed. Unlike ISO 9002,
which concentrates on quality, at a level set by the individual distribution company, SQAS - Safety & Quality Assessment
Systems - provide objective performance indicators, which allow the monitoring of continuous improvements.

4
Based on detailed questionnaires, distribution contractors can be assessed by a qualified third party. Questions relate to
management, equipment and operations, split by: statutory requirements, additional chemical industry requirements and
desirable items. Scoring results can be presented in different ways but it is up to each individual chemical company to
evaluate the results according to its own standards.

The distribution contractors will include:


• Marine transport: Vessels and barges. (Ferries)
• Road transport: Road carriers
• Storage operations: Terminals/Warehouses
• Ferry operators

29
Appendix 1
Cefic and Responsible Care

5 Emergency response
Although the chemical industry has a fine record in preventing chemical transport incidents, it is committed to
continuous improvement. The ICE Emergency Response scheme, a cooperative program coordinated by Cefic, will
provide emergency response across national boundaries. It aims to build upon the best existing prevention practices,
preserve proven emergency response schemes and extend the best emergency schemes to countries where none exist.

The chemical industry makes its expertise available to authorities - who are normally in charge of the emergency - at three
levels of assistance.

• Level 1: Remote information and general advice by telephone or fax


• Level 2: Presence of an expert who will provide advice at the scene of an incident
• Level 3: Actual help with equipment and personnel at the scene of an incident

For detailed information on this subject consult: the Cefic ICE - European Emergency Response Network: Operational
National ICE schemes (www.Cefic.org).

30
Appendix 2 Cefic recommendations on safe management practices
in distribution (SQAS)

These recommendations conform to the principles of Responsible Care and include the following topics:
1. Safety, health and environmental policies
2. Auditing
3. Risk reduction
4. Specification of packages, tanks and other equipment
5. Incidents evaluation
6. Codes and regulations
7. Control operations
8. Training
9. Selection and monitoring of Contractors
10. Data and information
11. Emergency Response
12. Information to the public

Although these Guidelines for the distribution of Propylene Oxide are product specific, it is essential that policies,
systems and procedures as described in the Cefic recommendations on Safe Management Practices in Distribution are in
place and well maintained.

31
Appendix 3 Inspection of transport equipment

1 Routine inspection of road tankers and tank containers


at loading terminals
If any of the following conditions are not met, the loading operation must be stopped and the situation rectified before
commencing loading.

A) BEFORE LOADING

1. Does the truck have any visual defects (e.g. lights and tyres in good condition)?

2. Is there a valid ADR equipment-certificate for carriage of Propylene Oxide?

3. Has the driver a valid ADR license for the bulk transport of dangerous substances of Class 3?

4. For tank containers, is the CSC (Convention of Safe Container) tank plate valid?

5. Are all ‘dangerous goods’ labels fitted (see Chapter 2.7), are the identification numbers
33
1280
attached, or the national identification plate in accordance with national regulations, and is the Tremcard
in all required languages on board?

6. For combined ADR/IMO transport: are the IMO ‘dangerous goods’ labels fitted? Is the UN number
attached as per these regulations?

7. Does the driver have all the necessary items of protective clothing and safety equipment as specified
by the Tremcard?

8. Is the equipment dedicated for transporting PO?

9. Determine the maximum payload based on:


• Tare weight
• Route
• Country of destination
• Transport mode
• Minimum and maximum filling degree
• Volume of tank

10. Are all the valves closed upon arrival?

11. Can all valves be operated correctly?

12. Are the loading/unloading valves leak proof?

13. Is the tank placed at the correct loading position?

14. Are the wheels of the truck blocked by wheel blocks or other tools?

15. Is the road tanker or tank container equipped with Propylene Oxide selective dry disconnected couplings?

16. Is the vehicle earthed? The earthling cable should be fitted and a satisfactory earth established before loading
connections are made.

32
Appendix 3
Inspection of transport equipment

B) WHILST LOADING

1. Is the maximum degree of filling not exceeded?

2. Is the minimum degree of filling in line with ADR 4.2.1.9.6 a?

3. When filling transport tanks, an appropriate allowance should be made to the pressures indicated to allow for
equilibration between the gas and liquid phases after the tank is sealed. This allowance will vary depending
upon loading conditions, but may be of the order of 0.5- 1.0 bar. Even after unloading Propylene Oxide tanks
should be maintained at a minimum overpressure of 0.2-0.3 bars by using nitrogen.

C) AFTER LOADING

1. Is the maximum gross weight not exceeded?

2. Are all valves closed and blinded, with all bolts in place and are all dry disconnected couplings/metal
caps in place?

3. Are all openings sealed?

4. Before disconnection, the loading arms/flexible hoses must be purged with nitrogen.

5. Is the vehicle earthling removed? At the end of the transfer operation, the loading connections must be
disconnected before the earthing cable is removed.

2 Routine inspection of rail tank cars (RTCs) at loading terminals


If any of the following conditions are not met, the loading operation must be stopped and the situation rectified before
loading is allowed to continue.

A) BEFORE LOADING

1. Is the rail track secured to prevent collision?

2. Is the RTC suitable for Propylene Oxide transport, e.g. in respect of maximum working pressure of tank?
Is the inspection date not exceeded?

3. Are all ‘dangerous goods’ labels fitted and are the identification numbers?
33
1280
attached?
For RTCs in combined RID/IMO transport: are the IMO labels fitted?

4. Determine the maximum payload based on:


• Tare weight
• Country of destination
• Route
• Transport mode
• Minimum and maximum filling degree
• Volume of tank

5. Are all the valves on either side of the RTC properly closed and blinded upon arrival?

33
Appendix 3
Inspection of transport equipment

6. In case of hydraulically or mechanically operated valves:


Is the emergency bolt unused and stored in a safe position on the RTC chassis?
(This emergency bolt may only be used to open the bottom valves in the case of an emergency. It is strictly
forbidden to start loading with the internal valve blocked by the emergency bolt.)

7. Can all valves be operated?

8. Are the loading / unloading valves leak proof?

9. Is the RTC placed at the correct loading position?

10. Are the wheels of the RTC blocked by wheel blocks or other tools?

11. Is the RTC equipped with Propylene Oxide selective dry disconnect couplings?

12. Is the vehicle earthed? The earthling cable should be fitted and a satisfactory earthing established before
loading connections are made.

13. After connection, the loading arm / flexible hoses must be pressurized with nitrogen and the connections
checked for leaks before transfer is allowed.

B) WHILST LOADING

1. Is the maximum degree of filling not exceeded? See Chapter 2.7.

2. When filling transport tanks, an appropriate allowance should be made to the pressures indicated to allow for
equilibration between the gas and liquid phases after the tank is sealed. This allowance will vary depending
upon loading conditions, but may be of the order of 0.5- 1.0 bar. Even after unloading Propylene Oxide tanks
should be maintained at a minimum overpressure of 0.2-0.3 bars by using nitrogen.

C) AFTER LOADING

1. Is the maximum gross weight not exceeded, concerning A, B, C or D grid?

2. Are all valves closed and blinded, with all bolts in place and are all dry disconnect couplings / metal caps in
place on either side of the RTC?

3. Are all openings sealed?

4. Before disconnecting, the flexible hoses must be purged with nitrogen.

5. Is the RTC earthing removed? At the end of the transfer operation, the loading arm / hose must be
disconnected before the earthing cable is removed.

34
Appendix 3
Inspection of transport equipment

3 Unloading
The same guidelines as in appendix 3 paragraph 1 and 2 (relevant items) should be used for preparing a checklist for the
inspections of the transport equipment before and during unloading.

The conditions of discharge at customer’s premises are the customer’s responsibility.

1. Are written operating procedures at the premises?

2. Have personnel engaged in this operation been adequately trained?

3. Has the product been positively identified as Propylene Oxide?

4. In case of multiple possibilities at the discharge point has the correct discharge point been identified?

5. Can the receiving tank(s) take the complete load?

6. Is the driver available (road tanker) and within sight of his vehicle for emergency reasons?

7. Has the content of the truck, RTC, barge or vessel been included in the emergency plan?

8. Does the operating procedure contain actions if a problem develops i.e. stopping and closing the external
discharge valves?

9. Does the operator use an unloading checklist?

10. Is the unloading site equipped with Propylene Oxide selective dry disconnect couplings? Have these been
regularly been inspected and maintained?

4 Initial inspection of road tankers, tank containers


and rail tank cars (RTCs)
Before road tankers, tank containers or RTCs are first introduced to Propylene Oxide service, or reintroduced to service
following maintenance or repair, a responsible person from the loading company should seek confirmation of the
following items:
a) Is the transport equipment identical in all respects with the general arrangement engineering drawing?
b) Have the correct packing’s and gaskets been fitted?
c) Has the tank been properly cleaned? (Grit blasting and vacuum cleaning for carbon steel tanks, with no rust
remaining; degreasing for stainless steel tanks).
d) Do all valves function correctly? It is recommended before starting with the first loading of a new or repaired
vehicle a “take into service procedure” will be conducted.
e) Do all dry disconnect couplings function correctly?

35
Appendix 3
Inspection of transport equipment

Fig. 11 Example of checklist

5 Maintenance of transport equipment


During operations, unscheduled maintenance of the transport equipment may be necessary if quick closing valves or
bottom valves and dry disconnect couplings on road tankers/tank containers or RTC’s cease to function correctly.
Similar difficulties may be experienced with excess flow valves on tank containers and road tank cars.

Valves may become blocked with small amounts of polymer. Customers should be instructed to immediately report to the
consignor any difficulties which are experienced with the operation of valves. The provision of an information tag on the
returning transport equipment identifying the difficulty can be of assistance.
Consignors of RTC’s should maintain close liaison with local railway authorities on all matters concerning the running
gear of RTC’s.

The O-rings of the PO selective dry disconnect couplings shall be replaced regularly according to the recommendations of
the couplings manufacturer.

36
Appendix 4 Instructions in writing

Actions in the event of an accident or emergency


In the event of an accident or emergency that may occur or arise during carriage, the members of the vehicle crew shall
take the following actions where safe and practicable to do so:
• Apply the braking system, stop the engine and isolate the battery by activating the master switch
where available;
• Avoid sources of ignition, in particular, do not smoke or switch on any electrical equipment;
• Inform the appropriate emergency services, giving as much information about the incident or accident
and substances involved as possible;
• Put on the warning vest and place the self-standing warning signs as appropriate;
• Keep the transport documents readily available for responders on arrival;
• Do not walk into or touch spilled substances and avoid inhalation of fumes, smoke, dusts and vapours
by staying up wind;
• Where appropriate and safe to do so, use the fire extinguishers to put out small/initial fires in tyres,
brakes and engine compartments;
• Fires in load compartments shall not be tackled by members of the vehicle crew;
• Where appropriate and safe to do so, use on-board equipment to prevent leakages into the aquatic
environment or the sewage system and to contain spillages;
• Move away from the vicinity of the accident or emergency, advise other persons to move away and follow
the advice of the emergency services;
• Remove any contaminated clothing and used contaminated protective equipment and dispose of it safely.

37
Appendix 4
Instructions in writing

Additional guidance to members of the vehicle crew on the hazard characteristics of dangerous goods by class and on
actions subject to prevailing circumstances

DANGER LABELS AND PLACARDS (1) HAZARD CHARACTERISTICS (2) ADDITIONAL GUIDANCE (3)

Explosive substances and articles May have a range of properties and effects Take cover but stay away from
such as mass detonation; projection of windows.
fragments; intense fire/heat flux; formation
of bright light, loud noise or smoke.
Sensitive to shocks and/or impacts
1 1.5 1.6 and/or heat.

Explosive substances and articles Slight risk of explosion and fire. Take cover.

1.4

Flammable gases Risk of fire. Take cover.


Risk of explosion. Keep out of low areas.
May be under pressure.
Risk of asphyxiation.
May cause burns and/or frostbite.
2.1 Containments may explode when heated.

Non-flammable, non-toxic gases Risk of asphyxiation. Take cover.


May be under pressure. Keep out of low areas.
May cause frostbite.
Containments may explode when heated.

2.2

Toxic gases Risk of intoxication. Use emergency escape mask.


May be under pressure. Take cover.
May cause burns and/or frostbite. Keep out of low areas.
Containments may explode when heated.

2.3

Flammable liquids Risk of fire. Take cover.


Risk of explosion. Keep out of low areas.
Containments may explode when heated. Prevent leaking substances
from running into the aquatic
environment or the sewage
3 system.

38
Appendix 4
Instructions in writing

DANGER LABELS AND PLACARDS (1) HAZARD CHARACTERISTICS (2) ADDITIONAL GUIDANCE (3)

Flammable solids, self-reactive Risk of fire. Flammable or combustible, Prevent leaking substances
substances and desensitized may be ignited by heat, sparks or flames. from running into the aquatic
explosives May contain self-reactive substances that environment or the sewage
are liable to exothermic decomposition in system.
the case of heat supply, contact with other
substances (such as acids, heavy-metal
compounds or amines), friction or shock.
4.1 This may result in the evolution of harmful
and flammable gases or vapours.
Containments may explode when heated

Substances liable to spontaneous Risk of spontaneous combustion


combustion if packages are damaged or contents
are spilled.
May react vigorously with water.

4.2

Substances which, in contact with Risk of fire and explosion in contact Spilled substances should
water, emit flammable gases with water. be kept dry by covering
the spillages.

4.3

Oxidizing substances Risk of ignition and explosion. Avoid mixing with flammable
Risk of vigorous reaction in contact with or combustible substances
flammable substances. (e.g. sawdust).

5.1

Organic peroxides Risk of exothermic decomposition Avoid mixing with flammable


at elevated temperatures, contact with or combustible
other substances (such as acids, heavy- substances (e.g. sawdust).
metal compounds or amines), friction or
shock. This may result in the evolution of
5.2 harmful and flammable gases or vapours.

Toxic substances Risk of intoxication. Use emergency escape mask.


Risk to the aquatic environment and
the sewerage system.

6.1

39
Appendix 4
Instructions in writing

DANGER LABELS AND PLACARDS (1) HAZARD CHARACTERISTICS (2) ADDITIONAL GUIDANCE (3)

Infectious substances Risk of infection.


Risk to the aquatic environment and
the sewerage system.

6.2

Radioactive material Risk of intake and external radiation. Limit time of exposure.

7A 7B

7C 7D

Fissile material Risk of nuclear chain reaction.

7E

Corrosive substances Risk of burns. Prevent leaking substances


May react vigorously with each other, with from running into the aquatic
water and with other substances. environment or the sewage
Risk to the aquatic environment and the system.
sewerage system.
8

Miscellaneous dangerous Risk of burns. Prevent leaking substances


substances and articles Risk of fire. from running into the aquatic
Risk of explosion. environment or the sewage
Risk to the aquatic environment and system.
the sewerage system.

NOTE 1: For dangerous goods with multiple risks and for mixed loads, each applicable entry shall be observed.

NOTE 2: Additional guidance shown above may be adapted to reflect the classes of dangerous goods to be carried
and their means of transport.

40
Appendix 4
Instructions in writing

Equipment for personal and general protection to carry out general


actions and hazard specific emergency actions to be carried on
board the vehicle in accordance with section 8.1.5 of ADR
The following equipment shall be carried on board the transport unit for all danger label numbers:
• for each vehicle, a wheel chock of a size suited to the maximum mass of thevehicle and to the diameter
of the wheel;
• two self-standing warning signs;
• eye rinsing liquida; and

for each member of the vehicle crew


• a warning vest (e.g. as described in the EN 471 standard);
• portable lighting apparatus;
• a pair of protective gloves; and
• eye protection (e.g. protective goggles).

Additional equipment required for certain classes:


• an emergency escape maskb for each member of the vehicle crew shall be carried on board the vehicle
for danger label numbers 2.3 or 6.1;
• a shovelc;
• a drain sealc;
• a collecting container made of plasticsc.

a Not required for danger label numbers 1, 1.4, 1.5, 1.6, 2.1, 2.2 and 2.3.
b For example an emergency escape mask with a combined gas/dust filter of the A1B1E1K1-P1 or A2B2E2K2-P2 type which is similar to that described
in the EN 141 standard.
c Only required for danger label numbers 3, 4.1, 4.3, 8 and 9.

41
Appendix 5 Guide for the marine chartering and handling
of Propylene Oxide (PO)

Ships complying with bulk chemical codes


Inspection of all marine vessels for compliance with the Guidelines shall be made by a responsible and competent person
prior to each loading to confirm a satisfactory condition of the vessels cargo system.

Ships that have never been in the company’s service will be inspected by a Marine Surveyor, under the CDI scheme (see
note) or a Company initiated scheme, to verify compliance with these guidelines and all applicable regulations prior to
charter acceptance.

1 Certification
Propylene Oxide will only be loaded/carried on vessels meeting all currently applicable requirements and regulations of
all applicable IMO codes and conventions, such as Bulk Gas Codes, Bulk Chemical Codes, SOLAS and MARPOL 73/78,
and standards such as the U.S. Coast Guard Standard for the carriage of OXIDES.

The carriage of Propylene Oxide should be permitted by the vessel’s International Certificate of Fitness for the Carriage of
Dangerous Chemicals in Bulk, which should be valid for the expected duration of the voyage, state the carriage conditions
for Propylene Oxide and be suitably endorsed. Alternatively a letter of compliance of the US Coast Guard or any other
competent Flag State Authority can permit the carriage.

2 Prior cargoes
Documentation of the previous three (3) cargoes must be provided prior to the ships arrival at the loading berth.
Propylene Oxide will not be transported in cargo systems which have contained as one of the three (3) previous cargoes
any material known to catalyse the reaction of Propylene Oxide, unless adequate cleaning and inspection is possible and
procedures to affect this have been issued.

Table 1 Products known to catalyse polymerisation of Propylene Oxide

ACIDS ALKALIES AMINES AMMONIA

Hydrochloric Caustic Ethylamines

Phosphoric Sodium Hydroxide Propylamines

Nitric Potassium Hydroxide Ethyleneamines

Acetic and other metal Methyleneamines

Sulphuric hydroxides and and other Amines

and other acids solutions and solutions

See Table 1 for cargoes known to catalyse polymerisation of Propylene Oxide in the US Coast Guard Chemical Compatibility Chart

42
Appendix 5
Guide for the marine chartering and handling of Propylene Oxide

3 Inspection, segregation and loading


Proper procedures for inspection, segregation of cargo and loading should be developed and used by the loader.

Prior to PO loading the cargo tanks ought to be purged with Nitrogen to <2% oxygen.

4 Carriage
Propylene Oxide must be maintained under Nitrogen blanketing within the ship’s tank design pressure limits and the
system relief valve.

A copy of the carriage log recording cargo tank(s) temperature, pressure and exceptions must be available at the
discharge port.

The ship nitrogen supply used to pad the Propylene Oxide tanks shall contain less than 2000 ppm oxygen.

5 General information
Prior cargoes of butadiene, isoprene and styrene
containing the polymerisation inhibitor tertiary butyl catechol are known to have resulted in contamination of
Propylene Oxide cargoes.

A thorough methanol wash followed by a water wash has been shown to be effective in removing polymerisation
inhibitor residues from some vessel tanks and cargo systems. Cargo tanks with extensive internal structural
members or heavy rust accumulations will be extremely difficult to clean. A water wash will not effectively remove
TBC residues.

Completion (balance) cargoes


Completion cargoes are cargoes shipped concurrent with Propylene Oxide. Compounds which are reactive with or
that catalyse the self-reaction of Propylene Oxide are not desirable completion cargoes. Compatible cargoes are
acceptable. (See US Coast Guard Compatibility Chart).

Adjacent cargo tanks that share a common bulkhead should not be heated above 30 °C.
(Note: the vapour pressure of Propylene Oxide is 760 mm Hg at 34.2 °C.)

Properties
Physical properties and other useful safety and health information relating to Propylene Oxide are contained in the
Safety Data Sheets.

Propylene Oxide vapour is highly soluble in water. This property is useful for control of a vapour leak and for
cleaning systems of Propylene Oxide. However, the introduction of water in a tank containing oxide vapour,
through a spray system or cleaning machines could result in a collapse of the tank. The owner or master of the
ship should be cautioned to exercise care in cleaning and washing tank to avoid creating a vacuum within the
cargo tank. Use of an inert gas system is an acceptable method of purging tanks for cleaning.

43
Appendix 5
Guide for the marine chartering and handling of Propylene Oxide

Chemical distribution institute (CDI)


This is a system that provides objective information on the quality of shipping.

CDI is an independent system to select and monitor contractors involved in shipping. The system emphasises
safety performance, environmental protection, regulatory compliance, maintenance and training.
A regular review of the above mentioned performance and necessary improvements are part of the system.

CDI accreditates inspectors and facilitates the distribution of assessment results.


Chemical companies or consignors can initiate an assessment and/or request the assessment results from the
ships owner.

44
Appendix 6 A Safety Scheme for the reception and storage facilities
at Propylene Oxide customers

1 ESAD / SQAS Guidelines


The European Single Assessment Document (ESAD) and the Safety & Quality Assessment Scheme (SQAS) have been
developed jointly by chemical suppliers and distributors for use in one single assessment of distributors, offering
simultaneously a measurement of the commitment of distributors to their Responsible Care Programme a common
tool for suppliers to evaluate, against their individual requirements, the safety, health and environmental performance
of their distributors.

2 Purpose
The Cefic Propylene Oxide Sector Group has developed a specific checklist for Propylene Oxide, which should be used for
self-auditing by the customer. It can also be used as a guideline for the safety service of the supplying company.

3 Scope
3.1
This scheme shall apply to the reception of Propylene Oxide by road and rail at all customers.

3.2
The principal objective is to ensure that the transfer of Propylene Oxide from the delivering vehicle to the storage
tank can be carried out safely. However, because the storage system and procedures may affect the safety of the
unloading operation, these also need to be considered.

3.3
The scheme should also be used to:
a) Assess and record any changes in policy, attitude or equipment since the previous check.
b) Obtain customer’s comments on the transport operation and equipment being used.

45
Appendix 6
A Safety Scheme for the reception and storage facilities

Propylene Oxide unloading/storage checklist

1. THE UNLOADING AREA

1.1 Ease of access

1.2 Housekeeping

1.3 Separation from other activities

1.4 Ability to mobilise and remove road tanker/RTC in case of emergency

1.5 Facilities to isolate area and restrict access

1.6 Fire water / foam systems

1.7 Electrical classification

1.8 Minimum safety distances according to national regulations between the offloading point and:
• Storage
• Ignition source
• Boundary fence/or other facilities

1.9 Adjacent offloading points

1.10 Hoses / loading arms / dry disconnect coupling

1.11 Earthing Point

1.12 Pipe damage protection

1.13 Other vehicles/fork lift truck movements

1.14 Communication systems

1.15 Shutdown systems

2. UNLOADING

2.1 Personnel and equipment

2.2 The presence of customer’s operator

2.3 Operator’s competence

2.4 Deputy availability

2.5 Hose testing and renewal policy

2.6 Selectivity code of dry disconnect coupling

2.7 Fixed loading arm testing and maintenance

2.8 Availability of suitable safety equipment

2.9 Unloading lines should be properly labelled as Propylene Oxide

OPERATIONS

2.10 Written procedures

2.11 Hose purging and leak testing

2.12 Sampling procedure

46
Appendix 6
A Safety Scheme for the reception and storage facilities

2.13 Atmospheric/personal Propylene Oxide exposure monitoring

2.14 METHOD OF UNLOADING:


• Nitrogen Pressure
• Pump

2.15 Use of rail hook (for LG equipment)

2.16 Safeguards for pump

2.17 Emergency response

3. NITROGEN SUPPLY

3.1 Source of nitrogen

3.2 Protection of nitrogen purity

4. STORAGE TANK

4.1 LOCATION
• Bundled area
• Shared
• If shared, with what? Are they compatible?
• Separation distances
• Emergency disposal facilities

4.2 CONSTRUCTION
• Insulated
• Un-insulated
• Refrigerated
• Fire water / foam availability
• Earthed
• Maximum pressure rating
• Maximum allowed working pressure
• Date and type of last test/inspection
• Dip inlet pipe

4.3 RELIEF VALVES


• Separate
• Combined with interlock
• Size
• Venting to:
- Stack
- Scrubber
- Other
• Flame traps
• Nitrogen purged vents

47
Appendix 6
A Safety Scheme for the reception and storage facilities

4.4 INSTRUMENTATION
• Nitrogen padding pressure
• Control points:
-Temperature
-Pressure
-Level
• Alarm settings:
-Temperature
-Pressure
-Level
• Are control systems, and alarm systems independent?

4.5 MONITORING OF STORAGE


• Temperature
• Pressure
• Available ullage (available space) in the tank

5. STORAGE TANK TO PROCESS

Precaution to prevent backflow from plant streams contaminating storage vessels

Measures to prevent contamination via the vent gas system

6. PROCEDURES

There should be written procedures available for the following:

• Unloading Propylene Oxide

• Testing, inspection and maintenance of equipment

• Emergency

7. COMMENTS

...............................................................................................................................................

...............................................................................................................................................

...............................................................................................................................................

48
Appendix 6
A Safety Scheme for the reception and storage facilities

Guidance notes for Propylene Oxide unloading/storage checklist

1. THE UNLOADING AREA

1.1 There should be sufficient space for easy vehicular access.

1.2 Unless it is connected to the unloading facilities, it should be possible for the vehicle to be removed
from the unloading area in the case of an emergency. If it is connected to the unloading facilities, then
the emergency arrangements should take account of the contents of the vehicle.

1.3 Barriers, warning notices (e.g. no access; no smoking) are required. Special consideration may need to
be given to prevent shunting close to the unloading area.

1.4 There should be a fire fighting system. Preferably this should be a permanent installation over/around
the unloading area. Strategically placed fire hoses/monitors ready for use are acceptable.

1.5 The electrical classification shall be EX D2 G4; Division 1/Class C or equivalent.

1.6 All unloading points must be clearly labelled. If compatible substances are unloaded in the Propylene
Oxide area procedures and/or engineering controls should be in place to avoid unloading of Propylene
Oxide into wrong tanks.

1.7 Hoses or unloading arms should preferably be of stainless steel or so called “Cryoflex”. They should
be dedicated to Propylene Oxide, have suitable gaskets (spirally wound PTFE or equivalent), have
Propylene Oxide selective dry disconnect couplings and stored in such a way that contamination and
damage will be prevented.

1.8 The earthing point should be checked on a regular basis.

2. THE UNLOADING

2.1 The driver should be available during offloading and within sight of his vehicle for emergency reasons.
He should not be in the cabin of his truck. Drivers must report back to the principal / consignor if
noticed that unloading conditions do not meet the necessary safety requirements.

2.2 The customer’s operator must be present during off-loading or equivalent control measures executed
e.g. such as camera supervision from a remote location and remote process control.

2.3 & 2.4 There should be at least two trained deputies to provide cover for illness and holidays.

2.5 The test pressure of the hoses should not be less than 1.3 times the maximum design working
pressure. The frequency of testing is recommended as at least every 12 months.

2.6 Dry disconnect couplings with PO selectivity keys must be used.

2.7 Hoses must be purged with nitrogen and leak tested before commencing the discharge.

2.8 Air breathing sets with eye coverage, protective suits, boots and gloves of suitable material should
be readily available (butyl rubber has been found to give the best degree of protection. Neoprene or
natural rubber may also be considered for protective clothing, but may not remain as vapour-tight as
butyl rubber, particularly after continued use. PVC offers only very limited resistance).

A safety shower and eye fountain should be sited adjacent to the unloading area.

2.9 - 2.12 No additional comments.

2.13 If unloading is by pump, a dedicated vapour return system (balance line) should be used.

2.14 Rail hook only in connection with LG equipment (see chapter 4.1).

49
Appendix 6
A Safety Scheme for the reception and storage facilities

3. NITROGEN

3.1 The purity of the nitrogen must be maintained.

3.2 The nitrogen should preferably be supplied by a separate and independent dedicated supply system.
The Propylene Oxide nitrogen supply system must not be shared with supplies to amines, acids or
other catalysts for Propylene Oxide polymerisation.

3.3 Ideally the supplies for storage and the plant should be taken from two completely independent
sources. If this is not possible or the system is shared the integrity of the nitrogen supply system must
be protected.

3.4 All nitrogen lines to storage and to process must be fitted with back flow protection for instance such
as double block and bleed systems activated by a low positive pressure difference across the valves.

4. THE STORAGE TANK

Some of this section falls outside the unloading safety checking procedure. However, the information is useful both
from safety and quality viewpoints. It also provides information on the customer’s competence and attitudes to
safety.

4.1 No additional comment.

4.2 Storage tanks are either pressure tanks or temperature controlled.


Insulation is normally not required. However in case it has been installed, procedures shall be in place
to detect and control under-insulation corrosion (e.g., wall thickness test or visual inspection).
Especially in hot climates, refrigeration and / or closed cell structure insulation should be considered.

4.3 Relief valves should be large enough to meet local regulatory requirements e.g., the requirements for
fire engulfment.

4.4 Level alarms are required.

Procedures must be present which prevent tanks overfilling.

4.5 The temperature and pressure of the storage tank should be monitored regularly.

5. STORAGE TANK TO PROCESS

Back flow and contamination prevention is essential.

Similar equipment to that used for maintaining the nitrogen integrity should be used.

50
Appendix 7 Design and construction of rail tank cars

It is recommended that the company’s technical railtankcar experts will use the following list of key railtankcar
specifications in the contractual agreement with the different railtankcar lessons.

General recommendations
1
Tanks are generally constructed of carbon steel. No baffle plates are to be fitted.

2
Top or bottom loading/unloading facilities are used, depending on customer requirements.
(General practise in Europe is bottom unloading)

3
Sloped bottom to outlet to provide complete unloading.

4
In case of top loading/unloading facilities:
• Maintenance platform around top nozzles and manhole with galvanised anti-slip-grating and a kick
plate. The holes in the grating must be sufficient to allow access for flange bolting.
• The top valves shall be designed in the longitudinal direction to allow operation of fixed liquid and
vapour arms.
• One ladder with access to the platform shall be provided.
• Internal ladders are not recommended, as they will hinder the use of professional cleaning equipment.

5
Earthing connections shall be provided to prevent dangerous differences in electrical potential arising between the
carrying tank, the body of the vehicle, the piping and the ground during the filling or discharging of the vehicle.
Connections should be provided at each end of the tank and also adjacent to the discharge connections.

6
All valves shall be of a leak-tight design and have a dry-disconnect coupling + pressure cap or cover plate.
Valves packing must be resistant to Propylene Oxide and all valves must be of a fire-safe design.

7
Insulation is not required, however if installed, verify protection/inspection of carbon steel corrosion under
the insulation.

51
Appendix 7
Design and construction of rail tank cars

8
The right front side of the railtankcar shall be provided with a ladder and handgrips for the shunter.

9
Gaskets: PTFE, PTFE spiral wound or other PO compatible material.

10
Tank design according to ADR/ RID is L4BN (L= Liquid; 4= minimum calculation pressure 4 bar; B= bottom
unloading and 3 independent closures; N = tank without a venting system according to 6.8.2.2.6 and not
hermetically closed). This requirement is met by both LG and BL railcar types.

11 Equipment
11.1 PRESSURE RELIEF DEVICES
No pressure relief devices shall be fitted.

11.2 FILLING/DISCHARGE AND VAPOUR RETURN FITTINGS


11.2.1 The tank must be fitted with a DN80 filling / discharge pipe with a shut off valve. The vapour
return connections shall be a DN50 pipe, fitted with a shut off valve. Valves shall be of an approved
make & type, e.g. bellow valve.
11.2.2 In addition, a quick closing internal safety device shall be fitted in the tank shell for the liquid
filling/discharge connection. The device shall be capable of being operated remotely. The device shall
also close automatically in the event of a hose rupture or the inadvertent movement of the rail tank car.
The valve actuator shall consist of a hydraulic system.
11.2.3 Both the filling/discharge and vapour return connections are equipped with PO selective dry
disconnect coupling (NATO standard 3756) and a pressure retaining cap. Materials of connections must
be similar to that of the tank shell. It is recommended to maintain the shut off valve in addition to the
dry disconnect coupling.
11.2.4 Connections should be adequately protected against possible impact that may occur during
transport. This protection could be provided by means of a strong steel guard or by utilising the chassis
of the vehicle. Both the liquid and vapour connections shall be clearly marked by their name (liquid/
vapour). To ensure that the foot valves/internal safety devices remain closed should either of the
connection pipes be damaged, the design should be such that if the pipes are subjected to excessive
strain, the tank shell remains undamaged. Connection pipes, flanges and valves shall be suitable for the
same test pressure as the tank shell.

11.3 INTERNAL VAPOUR RETURN PIPE


11.3.1 The tank pipe shall be fitted with a DN50 internal vapour return pipe which shall extend from the
foot valve/internal safety device to the vapour space. The pipe shall be designed to restrict liquid entry
and shall be supported so as to withstand any vibration during movement of the rail tank car.

12
For inspection purposes, the tank shall be fitted with one manhole not less than 500 mm diameter (gas type
RTC’s only), the manhole shall be fully bolted and may have a hinged design (right hand side).

52
Appendix 8 Design and construction of tank trucks
and tank containers

It is recommended that the company’s technical tank truck / tank container experts will use the following list in the
contractual agreement with the different road carriers.

General recommendations
1
Stainless steel tank material is preferred, in order to facilitate cleaning operations.

2
Baffles may need to be fitted to meet the requirements of transport regulations. However, the number of baffle
plates should be kept to a minimum, as they may hinder professional cleaning operations.

3
Bottom loaders / unloaders are preferred; they prevent working on top of the truck / container.

4
Top loading/unloading facilities are acceptable: At least one walkway of anti-slip grating shall be provided on top
of the tank to give access to the top nozzles and man way. The walkway on tank trucks should be fitted with a
collapsible handrail, and be reached by an open rung access ladder.

5
All valves shall be leak tight, resistant to Propylene Oxide and made of fire-safe design.

6
Earthing connections shall be provided. These connections shall not be painted.

7
Gaskets: PTFE, PTFE spiral wound or other PO compatible material.

8
UN tank instructions: T 11

53
Appendix 8
Design and construction of tank trucks and tank containers

9 Equipment
9.1 PRESSURE RELIEF DEVICES
Any pressure relief design must be in line with the requirements of the ADR / RID and the IMDG-Code.

9.2 FILLING / DISCHARGE AND VAPOUR RETURN FITTINGS


9.2.1 The tank must be fitted with a DN80 filling / discharge pipe with a shut off valve. The vapor return
connections shall be a DN50 mm pipe, fitted with a shut off valve. Valves shall be of an approved make
and type.
9.2.2 In addition, a quick closing internal safety device would be recommended in the tank shell for the
liquid filling/discharge connection. The device shall be capable of being operated remotely. The device
shall close automatically in the event of a hose rupture and it is recommended that it closes automatically
in case of inadvertent movement of the road tankers/tank containers. The valve actuator shall consist
preferably of a hydraulic system.
9.2.3 Both the filling/discharge and vapor return connections are equipped with Propylene Oxide selective
dry disconnect coupling (NATO standard 3756) and a pressure retaining cap. Materials of connections
must be similar to that of the tank shell. It is recommended to maintain the shut off valve in addition to
the dry disconnect coupling
9.2.4 Connections should be adequately protected during transport. For tank containers, all connections
should be contained within the ISO framework. Both the liquid and vapor connections shall be clearly
marked by their name (liquid/vapor). These connections should be provided with means to prevent
unauthorized access.

9.3 INTERNAL VAPOR RETURN LINE


The tank pipe shall be fitted with a DN50 internal vapor return line which shall extend from the foot valve/
internal safety device to the vapour space. The pipe shall be designed to restrict liquid entry and shall be
supported to withstand any vibration during movement of the road tankers / tank container.

54
Appendix 9 Design and construction of vessels and barges

1 Vessels
Detailed Requirements for Marine movements of Propylene Oxide in gravity Vessels are contained in the International
Code for the Construction and Equipment of Ships Carrying Dangerous Chemicals in Bulk, under Chapter 15: Special
Requirements. The 30 Topics list include requirements on design, inspection on cleaning quality prior to initial loading,
cargo segregation, loading/unloading operations, refrigeration and nitrogen padding. The key requirements for
Chartering and Handling are described in appendix 4.

2 Barges
The product specific requirements mentioned for vessels are also recommended for barge movements. In general these
detailed requirements can best be met by using LPG Type Barges. It is recommended to consider using this barge type.

3 Vessels and Barges


Special attention shall be given to:
• Ship-Shore safeguarding systems
• Leak tight flanges of dome covers
• In line-sample systems

55
Appendix 10 General Guidelines for design and construction
of Propylene Oxide storage tanks

1 Location of storage tanks


1.1
The arrangement and lay out of storage tanks should take into account:
a) Normal operation
b) Emergency operation
c) Fire fighting activities

1.2
The design of the tank farm should take account of the likely consequences of any accidental spillage or fire.
Products that react chemically with Propylene Oxide, such as oxidants, acids, anhydrides, chlorine, and ammonia,
should be kept in total segregated storage.

1.3
Storage tanks shall be located away from potential sources of ignition, and in a position so as to minimise the
effect of radiation from any fire which could possibly occur in an adjacent area.

1.4
Storage tanks shall be discharged by pump. Tanks should not be elevated to allow gravity discharge, because of
the difficulties of stopping gravity flow in the event of a fire.

1.5
Every tank shall be sited on an impervious base and should be surrounded by a bund wall capable of containing
110 % of its contents in the event of spill or leak. The walls and floor of the bund should be impervious to liquid
and designed to withstand a full hydrostatic head. Bund walls should be designed to ensure adequate natural
ventilation of the bunded areas, ready access for fire fighting, and good means of escape in any emergency
situation.

1.6
Intermediate lower bund walls are recommended to divide tanks into groups to contain any accidental leakage
and to minimise the surface area of any spillage. If tanks share a common diked area, products within the area
should be chemically compatible.

1.7
The floor of the bund shall be sloped to prevent minor spillage’s remaining below any tank. Provisions should be
made for the removal or drainage of surface water from the area within the bund. Preferably, surface water should
be pumped out of the bund with an appropriate pump. If bund drains are used, they shall be provided with valves
outside the bund wall, with procedures in force to ensure these valves remain closed, except when draining is
being removed.

56
Appendix 10
Design and construction of Propylene Oxide storage tanks

1.8
No combustible materials, equipment, etc. shall be stored in the bund or against the bund wall.

2 Tank construction
2.1
The tank shall be of adequate strength and capacity for the proposed duty. The tank and its supports shall
be designed and constructed in accordance with an appropriate nationally recognised standard of good
engineering practice.

2.2
Copper and copper containing alloys shall not be used in Propylene Oxide service.

2.3
Storage tanks should be compatible with shipping and/or receiving requirements.

2.4
Vapour control systems shall meet local and/or governmental regulations. The vent system discharge should be
preferably into a closed system or an atmospheric discharge at a safe distance from possible ignition sources.

2.5
Carbon steel storage tanks are generally the most economical for Propylene Oxide. Vertical storage tanks are often
used for large volume storage. Horizontal tanks are also satisfactory for bulk storage, but these are generally used
for small installations.

2.6
Tank filling shall be either from the bottom or with a vertical pipe extended to a designed distance from the tank
bottom. It will ensure that Propylene Oxide can not fall freely through the vapour space with the hazard of
electric discharges.

2.7
Insulation is normally not required, however in case it has been installed, inspection procedures shall be in place
to detect and control corrosion. Closed cell structure insulation is recommended, as it does not lower the self-
ignition temperature of Propylene Oxide in case of leakage.

2.8
In hot climate, large tanks with low throughput shall be protected against direct sun heating by using reflecting
paint, a sun protection roof, or equivalent. In case of extreme high temperatures, insulation and a separate
cooling-unit is recommended.

2.9
An accessible manhole of minimum 500 mm diameter shall be provided on all tanks to allow for internal
inspection and cleaning.

57
Appendix 10
Design and construction of Propylene Oxide storage tanks

2.10
Design of new storage tanks shall be based on full draining concept, sloped to outlet with no trapped areas.
Eliminate "dead spots" of liquid and vapour phase in the system.

2.11
It is normal practice to fit tanks, which are storing highly flammable liquids, with a pressure relief valve (PRV) to
protect the tank against overpressure. The design shall be according good engineering practice. For new tanks a
rupture disc under the safety valve may be considered. This design eliminates the need for vent purging.

2.12
Each tank shall have a designed earthing system. Resistance to earth to be checked at least annually.

3 Storage tank engineering controls


Level, pressure and temperature measurement, nitrogen padding system

3.1
Storage tanks shall be provided with a suitable means of determining the liquid level, the pressure and the
temperature in the tank.

3.2
Audible high level alarms, which automatically shut down the unloading process in the event of overfill, are
strongly recommended. High/low pressure and high temperature alarms shall be fitted.

3.3
All storage tanks should contain local temperature and pressure indicators and temperature sensors for remote
readings. It is recommended that level, pressure, and temperature recording equipment is provided in the
control room.

3.4
A separate and preferably independent, dedicated nitrogen padding system shall be installed. The system design
must prevent backflow.
If the prevention of a vacuum cannot be guaranteed, the tank should also be protected against vacuum with a
vacuum-breaking valve.

3.5
It is desired to install either a low pressure snuffing steam system or nitrogen purge to all safety valve discharges.
It will allow for dilution of potential Propylene Oxide vapours, especially during lightning. Design snuffing steam
systems on freezing weather conditions.

58
Appendix 10
Design and construction of Propylene Oxide storage tanks

4 Pipelines
4.1
All pipelines shall be adequately grounded, to discharge static electricity safely.

4.2
The tank discharge line shall be designed with an emergency block valve (EBV) which will shut off the tank
contents in case of an emergency.

4.3
It is recommended that all gaskets used in the handling of Propylene Oxide are made of PTFE, stainless steel
spiral wound with external guide-ring, or equivalent.

4.4
Wherever possible, continuous welded pipelines should be used. However where pipelines have to be
disconnected for maintenance or inspection, flange joints should be fitted. Screwed fittings should not be used
except for stainless steel instrumentation lines.

4.5
Pipelines should be routed to ensure that flanges are not located over doorways, windows or close to possible
sources of ignition and to minimise the possibility of accidental damage.

4.6
Fixed dedicated loading / unloading arms are recommended. If hoses are used for loading/unloading operations,
they should be stainless steel or equivalent. Hoses shall be inspected and pressure tested on a regular basis.
Records of inspection data and results shall be retained.

4.7
All tanks and pipeline connections must be clearly product identified.

4.8
It is recommended to install a closed sample system for Propylene Oxide samples, to minimise emissions.

4.9
Valves should be fitted as close as feasible to the tank. Unused outlets should be blanked off.

59
Appendix 10
Design and construction of Propylene Oxide storage tanks

5 Pumps
5.1
Pumps should be located outside tank bunds, on an impervious base, in an open space, and not in walled or
confined spaces.

5.2
Centrifugal pumps with enclosed impellers and mechanical seals or canned motor pumps are most widely used in
Propylene Oxide service.

5.3
Pumps should be constructed of ductile steel, or stainless steel.

5.4
Electrical pump motors shall be of ex proof design.

5.5
If pumps are remotely controlled then stop buttons shall be provided at the pump and at the remote
control centre.

5.6
Pumps should be process controlled, e.g., by flow metering.

5.7
It should be noted that if centrifugal pumps are used, flow under gravity might occur when the pump is stopped.

6 Electrical considerations
6.1
The selection, installation and maintenance of electrical equipment for use in hazardous areas should be
according to national regulations.

6.2
Pumps, tanks, electrical motors, pipelines, and all parts of the system must be effectively earthed to prevent the
accumulation of static electrical charges. A compliance program shall be in place.

6.3
Working areas, i.e. tank stairs, platforms, loading/unloading facilities should be adequately illuminated for
emergency response and security reasons.

60
Appendix 10
Design and construction of Propylene Oxide storage tanks

7 Fire fighting considerations


7.1
A contingency plan shall be in place and tested in practice on a regular basis, at least once per year.

7.2
It is recommended to install sprinkler water at tanks and pumps, preferably triggered by an automatic gas
detection system.

8 Systems for gas detection and monitoring


8.1
Depending on the storage volume, the storage area, the transfer pump area, gas detection and/or gas monitoring
systems should be considered with audible, visible and remote alarms.

9 Measures to prevent contamination of storage tanks


A particularly high safety standard is necessary to provide protection against products that react with Propylene Oxide or
products that are able to catalyse reactions.

9.1
Two redundant and quick shut-off valves to prevent backflow from the production plant should be installed.
This equipment must be very reliable.

9.2
Measures to prevent contamination via the nitrogen system (see Customer checklist).

9.3
Measures to prevent contamination via the vent gas.

61
Appendix 11 Member Companies of the Propylene Oxide /
Propylene Glycols Sector Group

MEMBER COMPANIES

BASF SE Germany
DOW Deutschland Anlagengesellschaft GmbH Germany
INEOS Germany
LYONDELLBASELL INDUSTRIES the Netherlands
REPSOL QUIMICA Spain
SHELL CHEMICALS EUROPE the Netherlands
BAYER MATERIALSCIENCE Germany

62
Appendix 12 Glossary of abbreviations

ADR Accord européen relatif au transport des marchandises dangereuses par route.
European agreement concerning the international carriage of dangerous goods by road.

ADN Accord européen relatif au transport des marchandises dangereuses par voie de
navigation intérieure.
Regulations concerning the transport of dangerous substances in barges on inland
waterways.

ADNR See ADN: R for Rhine

ASME American Society of Mechanical Engineers

BL Bulk liquid

CAS Chemical Abstract System

CDI Chemical Distribution Institute

Cefic Conseil Européen de L’Industrie Chimique

DIN German Industry Standard (Deutsche Industrie Norm)

DOT Department of Transportation

EEC European Economic Community

EINECS European Inventory of Existing Commercial Chemical Substances

Ems Emergency procedures of ships carrying dangerous goods

ERG Code Emergency Response Drill Code

IARC International Agency for Research on Cancer

IATA International Air transport Association

IBC Intermediate Bulk Container

IBC Code International code for the Construction and equipment of ships carrying dangerous
chemicals in bulk

ICAO International Civil Aviation Organization

ICE International Chemical Environment (Cefic)

IMDG Code International Maritime Dangerous Goods Code

IMO International Maritime Organization

ISO International Standard Organization.

JSA Job Safety Analysis

LC50 Lethal Concentration (50%)

63
Appendix 12
Glossary of abbreviations

LD50 Lethal Dose (50%)

LG Liquefied Gas

MAC Maximum Acceptable Concentration

MARPOL Marine Pollution Act

MFAG Medical First Aid Guide for use in accidents involving dangerous goods at sea

MITI Ministry of International Trade and Industry (Japan)

N.A. Not Applicable

OSHA Occupational Safety and Health Administration (USA)

PTFE Polytetrafluorethylene

RID Règlement International concernant le transport de marchandises dangereuses


par chemin de fer.
Regulations concerning the international carriage of dangerous goods by rail.

RTC Rail Tank Car

RTECS Registry of Toxic Effects of Chemical Substances

SOLAS Safety of Life at Sea

SQAS Safety and Quality Assessment System (Cefic)

STEL Short Term Exposure Limit

Tremcard Transport Emergency Card (ADR)

TLV Threshold Limit Value

TWA Time Weight Average

UN United Nations

64
Appendix 13 Recommended general instructions
for Propylene Oxide drivers

Propylene Oxide (PO) is flammable and chemically reactive, having harmful properties as to health and to the
environment. Nevertheless, it can be handled, transported and stored in a safe way, provided that appropriate
precautions are observed.

The Propylene Oxide driver has an important job to do. He is accompanying the shipment and is, during the entire
transport, in charge of the technical care of his vehicle and the product. It is essential that the driver is totally familiar with
the nature of the potential hazards which may be presented by Propylene Oxide during transport, and the action to be
taken in the event of an emergency.

These recommended general instructions for Propylene Oxide drivers have been prepared by the Propylene Oxide
Distribution Working Group of Cefic.

The objective in preparing a uniform set of instructions for drivers is to ensure that Propylene Oxide is handled and
transported in a safe manner.

It should be noted that individual Propylene Oxide producers may stipulate additional requirements where they see fit
for safe transport.

Before drivers are permitted to convey Propylene Oxide they must be in possession of a valid ADR driver’s certificate,
dangerous goods, class 3 for international transport, or an equivalent document.

Drivers who have successfully completed Propylene Oxide training and associated test will receive a company issued
Propylene Oxide training certificate.
The Training Certificate is mutually accepted by all Propylene Oxide producing companies affiliated to Cefic.

Topics that will be covered as part of the driver training are:


1. Product Information (as per Chapter 2)
2. Health hazards (as per Chapter 2)
3. Personal Safety Equipment (as per Chapter 5)
4. Loading/unloading (as per Chapter 3.1 and 3.5 and relevant sections of appendix 3 and 5)
5. Transportation (as per Chapter 3.2)
6. Emergency Procedure (as per Chapter 6)