005-Method Statement For Fencing
005-Method Statement For Fencing
Job n.
Contractor logo and business name Contractor Document ID
IGCS
Order n.
MOD Water Treatment Project - METHOD STATEMENT FOR FENC- Plant area
2521
Plant unit
N.A.
ING WORKS
A EX-CO 00
REVISION HISTORY
A EX-CO 00
INDEX
INDEX:
1. OBJECTIVE.......................................................................................................................... 4
2. DEFINITIONS....................................................................................................................... 4
3. REFERENCE DOCUMENTS................................................................................................4
4. RESOURCES....................................................................................................................... 5
4.1. PERSONNEL................................................................................................................ 5
4.2. EQUIPMENT................................................................................................................. 5
5. PROCEDURE....................................................................................................................... 5
A EX-CO 00
1 OBJECTIVE
This method statement outlines the procedure and methodology for the work involved in
the erection and installation of boundary fencing within the scope of the contract For
Valve Station in Zubair Oil Field Development Project, Basrah, Iraq.
This procedure applies to the following:
Quality management.
Safety.
2 DEFINITIONS
For purpose of this work method, the following definition shall apply:
PROJECT MOD WATER TREATMENT PLANT
CONTRACTOR IGC
SUBCONTRACTOR IGCS
3 REFERENCE DOCUMENTS
Drawings
4 RESOURCES
2
3
4
4.1 PERSONNEL
A EX-CO 00
Site Engineer.
QA/QC Engineer
Surveyor.
Foreman.
Skilled Labours.
Safety Officer
4.2 EQUIPMENT
Hand Tamper
Service Crane
Trailer
Small tools (Welding and Cutting machine, hammers, nail guns, wire cut-
ters etc.)
5 PROCEDURE
Installation of Fencing
All personnel entering the site shall have received site safety induction and
have attended a job toolbox talk.
The Fencing Site Engineer will issue a Permit to Dig and advise those carrying
out the works of general health and safety issues and the risks associated with
services in the area of excavation. Construction Sequence
Fence lines will be set out by a Setting Out Engineer or Surveyor. Pegs
(marked PFL) will be placed at all changes in direction of the fence line and at ap-
propriate centres for arcs in the fence line. The locations of gates will also be set
out.
Prior to entering lands, the Section Foreman will liaise with relevant
landowners in relation to the system implemented to protect the livestock. A
Permit to Dig (PTD) will to be issued to the foreman of the fencing crew by the
Section Engineer prior to fencing works commencing.
A EX-CO 00
The posts and bracing fence shall be prepared, such cut, drilled, end
closed and hook welding at BK’s Workshop, and will be delivered to site for the
erection by a manual. Temporary posts shall be set up with a line wire at bottom
rail level to achieve horizontal and vertical alignment. Reinforcement shall be
poured after all post installed properly.
The locations of the posts shall be determined by laying out on the ground
along the proposed fence line of an existing fences.
After erection of permanent posts, the bracing will be fixed. Where brace have
to be cut they shall be treated with two coats of preservative. Steel bracing
shall be fixed to posts by nut and bolt.
Mixing of concrete shall be used mixer machine capacity of 1 bag cement, mix-
ing place shall be set up on site and adjacent to the poring place of the footing.
Chainlink mesh will be fixed to the tension lines during fencing operation
or by a separate crew following behind.
Gates will be provided to comply with the details specified in the contract draw-
ings. Theseshall be adequately supported at the closing end until the concrete
placed around the posts has set.