Grid Connectivity
Grid Connectivity
ENE51-COM0CON/10/2020-EECOM
ORDER
P.T.O
File No.ENE51-COM0CON/10/2020-EECOM
To
All Functional heads /APTransco/ VidyutSoudha/
Vijayawada.
The Chief Engineers/Zones/Kadapa/Vijayawada/
Visakhapatnam.
The Chief General Manager/ EC, EA & Solar Energy/APEPDCL/ Visakhapatnam.
The Chief General Manager/ PPA, RA/APEPDCL/ Visakhapatnam.
The Chief General Manager/IPC/APSPDCL/ Tirupathi.
The Chief General Manager/IPC/ APCPDCL/Vijayawada.
All SEs in Kadapa, Vijayawada, Visakhapatnam Zones.
Copy to:
PS to Chairman & Managing Director/APTransco/VS/Vijayawda.
PS to Chairman & Managing Director/APSPDCL/Tirupathi.
PS to Chairman & Managing Director/APEPDCL/Visakhapatnam.
PS to Chairman & Managing Director/APCPDCL/Vijayawada.
PS to Joint Managing Director(Vigilance& Security)/APTransco/V.S/Vijayawda.
PS to Joint Managing Director(Comml, IPC, HRD & IT)/APTransco/V.S/Vijayawda.
PS to Director/Finance/APTransco/V.S/Vijayawda.
PS to Director(Grid Management&Transmission Management)/APTransco/V.S/Vijayawda.
Form C1
APPLICATION FOR CONNECTIVITY
Sl.No
1. DEVELOPER INFORMATION
Name
Address for
Correspondence: D.No Street Mandal/City Ditrict State Pincode
Registered
address: D.No. Street Area Mandal./City District State Pincode
Name: Name:
Designation: Designation:
Email: Email :
2. PROJECT DETAILS
Nature of Generation: Solar Wind Others Capacity: MW Type of Utilization: Captive(In-house) Captive(OA) PPA 3rd Party
Project Location:
Plot.No Village Mandal District State Pincode
3. LAND DETAILS
Project
Land required in Acres Acquired To be acquired In - Possession
Total
Remarks:
4. PROJECT PERMITS
NREDCAP approval given Enclosed Copy Capacity sanction: MW
Date:
Note:
6. CONNECTIVITY SS DETAILS
`
Option 3 400 220 132 33
7. DECLARATION:
9) To comply with CEA (Technical Standards for connectivity to the grid) Regulation 2007, APERC regulation, APSLDC and APTRANSCO instructions from
time to time.
10) To install the WTGs/Solar panels as per the GoI specifications.
11) To submit the BG for Rs.5 Lakh/MW for first 12 months and thereafter Rs.10Lakh/MW till commissioning.
12) To submit BG within 30days from receipt of the connectivity permit, failing which connectivity permit will be cancelled without intimation.
I here by certify that all information furnished is true to the best of my knowledge.
D D / M M / Y E A R
1. DEVELOPER INFORMATION
2. PROJECT DETAILS
Financial Closure done
3. LAND DETAILS
4. PROJECT PERMITS
rd
PPA Captive/3 Party sale
Date
D D / M M / Y E A R
Date
D D / M M / Y E A R
Permit No:
APPROVAL DETAILS
Project Location:
Plot.No Village Mandal District State Pincode
Period From To
PERMIT CONDITIONS
1) Developer shall pay transmission & wheeling charges fixed by APERC from time to time.
2) Developer shall issue letter of credit for payment of transmission/wheeling charges or both as the case may be equivalent to two months charges for the period of
connectivity within 30 days of issue of this permit failing which his connection permit shall stand cancelled.
3) The permit for sale of power to DISCOM shall stand terminated upon termination of PPA with DISCOM.
4) Developer shall pay scheme cost/supervision charges to APTRANSCO.
5) Developer shall bear the construction cost for the following (i) Pooling Station (ii) Lines from Pooling Station to Grid substation.
6) Developer shall buy/bear the cost of land required for bays at APTRANSCO SS and hand over the assets which includes metering bay and equipment at power
plant premises, line from metering point(outgoing feeder of power project) to Grid SS and bay equipment at Grid SS to APTRANSCO as per clause 3-ix(a&b) of
T.O.O(CE-Construction-2)Ms.No:20 dt:23.11.2012 and Clause-14 of APERC regulation 3 of 2017.
7) Developer shall pay Deviation Settlement charges fixed by APERC.
8) Developer shall provide Interfacing Meters as per relevant regulations.
9) Developer shall abide by all SLDC instruction including (i) To provide SCADA (ii) To provide LVRT (iii) To provide QCA (iv) To curtail generation whenever
directed.
10) Developer shall comply with CEA (Technical Standards for connectivity to the grid) Regulation 2007, APERC regulation, APSLDC and APTRANSCO instructions
from time to time.
11) Developer shall install the WTGs/Solar panels as per the GoI specifications.
12) Developer shall submit unconditional BG within 30days from the date of receipt of this connectivity permit for Rs. 5 Lakh/MW for first 12 months and
thereafter Rs. 10 Lakh/MW till date of commissioning failing which this permit shall stand cancelled.
D D / M M / Y E A R
Signature of the Issuing Authority
Date: