FMS50 Manual A001 V10
FMS50 Manual A001 V10
FMS50 Manual A001 V10
Manual
This document consists of 4 parts, divided up into:
Order no.:
Designation: FMS50_Manual_A001_V10
Date: 22.12.2004
Layout: Schober
Internet: www.festo.com/didactic
e-mail: [email protected]
This manual, all text and illustrations contained included, is protected by copyright. Any utilization
outside the limits of the copyright law and other than training purposes are not permissible without
our definite approval. This applies in particular to reproductions, operations, translations, micro
filming and the storing and processing into electronic systems. Parts of this manual may be copied by
the authorized user, exclusively for teaching purposes. Distribution of this documentation, as well as
reproduction, use and spread of its contents is prohibited, insofar not permitted explicitly. Offences
are liable to compensation. All rights reserved, especially the right to execute registrations concerning
patents, designs for use and patterns.
1. Contents_______________________________________________________ 3
2. Introduction ____________________________________________________ 7
3.3. Personnel___________________________________________________ 11
4. Start-up ______________________________________________________ 13
5. Operation_____________________________________________________ 31
7. Technology ___________________________________________________ 73
8. Pneumatics ___________________________________________________ 77
10.2. Wiring____________________________________________________ 86
10.2.2. ASi-participant_________________________________________ 89
2.1. General information This manual describes the handling of a FMS 50 system. It contains explanations
FMS 50 and descriptions of all the processes required for operation. Facts are partly
described with the help of graphics or images subserving an easier understanding.
Operation is not dependant on the operating position the material flow is being
started from. Still, the sequential order of the stations requires adherence, as it is
pre-defined in the SPS-program.
The FMS 50 system is designed in such a way, that the amount and kind of attached
MPS-stations attached is not important. A complete processing cycle of the work-
piece is always warranted. Therefore, the transport system is required under any
circumstances.
Testing of the work-pieces for their condition, according to type, is required in the
station. The work-piece carriers are distinguishable by their drillings on the
underside, but they do not carry any work-piece information. Therefor only this
assures correct processing.
2.2. Transport system The transport system is responsible for the transport of the work-pieces within the
system, which consists of various stations. A transport system comes into action to
ensure faultless carriage of work-pieces over long distances between stations.
For identification, the work-piece carriers are equipped with an I/O-ident system.
Each work-piece carrier has its individual number, as realised by a varied amount of
drillings on its underside. Thus it is possible to provide them with a specification on
their way. Up to max. 8 work-piece carriers can be used in one system.
Control of the transport system is realised by a Siemens S7, for which a control
cabinet is available, mounted onto the basic frame of the station. The station’s
internal data transmission ensues by an ASi-bus. Transmission to the other stations
is realised by an exactly defined I/O-interface.
2.3. Short cuts In this technical documentation the following abbreviations are being used:
WT = work-piece carrier
AP = operating position
Hubix = stroke and index unit
IX = stroke and index unit
ST = stopper
VS = virtual stopper!
3.1. Use according to This installation has been developed and produced exclusively for training purposes
regulations in the fields of automation and communication. The training company, as well as the
instructors have to ensure, that the trainees pay strict attention to the safety
precautions, as described in the accompanying manuals.
Festo Didactic accepts no liability charges for possible damages to any trainee of the
training company and/or further third parties, which might occur during
use/operation of the installation, if it is not part of a real training situation; except
Festo Didactic caused such damages deliberately or by negligence.
Due to the product liability law and various EC-directives, the following directions
are required and are to be strictly observed by the operator.
Safety endangering malfunctions can not be tolerated during training and have to be
removed immediately.
Put the installation into operation only, once all of the protection settings are
completely functional.
At least, before starting operation, check the installation for externally visible
damages and for the reliability of the safety devices.
Before circuit construction, circuit disassembly and circuit modification: switch off
air pressure and power supply.
General safety regulations are to be observed: DIN 58126 and VDE 0100.
Only trained experts in electric or electronic engineering are permitted to carry out
work on the electric supply system.
The terminal boxes are to be kept closed at all times. Access must be permitted only
under supervision of a member of the training staff.
Do not activate electric limit switches manually during fault search. Tools are to be
used.
Accidents might occur due to bouncing off tubes, caused by air pressure. Interrupt
air pressure supply immediately.
Caution! When the air pressure supply is activated, cylinders may move in or out.
Do not uncouple any tubes under air pressure supply. Exception: Fault finding. In
this case, keep on holding the end of the tube.
Secure the compressed air and electricity supplies to prevent unintentional start-up.
During inspections, maintenance and repair work, the machine must be de-
energised, de-pressurised and secured against unexpected restart.
All screw connections released during maintenance, inspection or repair work must
be checked to ensure correct re-tightening.
Trainees are permitted to work with the machine only under strict supervision of an
experienced person or an instructor.
Activities in the areas of maintenance, service and repair are to be carried out by
only persons with appropriate technical qualifications.
In this manual the following danger designations and signs are being used:
DANGER !
Failure to pay attention to this symbol may result in serious health damage, which
may even lead to life-threatening injuries.
IMPORTANT
Failure to pay attention to this symbol may result in damages to the machine or to
its surroundings.
This symbol assists you to make optimal use of all of your machine’s functions.
4.1. Transport Care is to be taken that the transport of the stations is to be executed only by a
suitable transport vehicle. The weight amounts up to 500 kg, depending on the
station.
i The transport boxes are to be opened with care, as additional components, such as
computers may be contained in the delivery, which are to be protected from falling
out.
Once the transport box has been opened and the possibly contained additional
components removed, the station can be taken out to be transported to its
destination by means of two fork-lifts or one fork-lift truck.
Please check the stability of all of the profile connectors by means of an Allen key
size 6. The connectors may have come loose during transport, due to inevitable
vibration.
Pay special attention to all overhanging components. Sensors and similar small
parts are very easily damaged in case of improper transport.
The stations are not to be picked up by or even under the mounted feet – increased
risk of becoming trapped or contused.
Allow sufficient distance between the installation and the wall of the room.
Any dust originating from construction work has to be kept off the installation (by
covering).
The transport system station is the central element in this system. All of the other
stations are in connection with this station. For this reason, it is necessary to
examine the condition of the accomodation in detail before set-up.
Once the set-up position has been decided upon, the system can be installed in this
position. At first, the room has to be measured, if not done so previously. The
measures of all of the stations have to be marked roughly onto the floor space (i.e.
with adhesive tape), to avoid shifting at a later stage.
Now, the conveyor belt can be adjusted to an even level, by means of a spirit-level.
The belt should be adjusted to the height of 896 mm, the height of the transport belt
itself.
All of the other stations are positioned at their set-up position, to be connected with
the transport system by means of assembly aids.
The following picture shows a complete set-up situation adapted to a more basic
area design. The stations are to be adjusted as shown, to warrant faultless work-
piece transferflow.
4.3. Commissioning Commissioning of the system can ensue only, once all of the stations are connected
to their definite position.
To avoid problems during the operational process, individual protection (16A) of the
installation is recommended.
Attention has to be paid to the correct polarity of the power supply plug, as only one
phase of the main switch is to be de-activated in the transport system.
The internal communication lines of the transport system are hard-wired and do not
require connection or plugging in.
Example I/O-connectors
In order that the system “knows” that stations are present and processing can occur
stations, they have to be connected to the system by I/O-connectors. At each case,
the connections are established the control panel – not in case of the robot and the
vision station, as these are directly connected to the respective control devices (see
the following drawings).
For more detailed information, the possible connections are listed below:
For MPS-stations of the Release B the connections deviate from the connections of
Release C. For this, graphics are also available in the chapter “Preparation of MPS-
stations”.
TRANSPORT
AS-i
IN ........
IN 0.7
IN 0.1
IN 0.1
IN 0.7
OUT 0.7
SYSLINK (AS-i)
AS-I Addr:
IN 1 AS-I Addr:
OUT 0 AS-I Addr:
OUT 1 AS-I Addr:
IN 2
4mm Lab cable
IN 3
Signal SYSLINK
OUT 3
0V 0V
PART AV PART AV
Convert sensor to IN/OUTPUT-Position PART ON
dissemble el. Push-out PALLET
No application
for FMS50
TRANSPORT
AS-i
IN 0.1
IN 0.7
IN 0.1
IN 0.7
OUT 0.7
OUT 0.7
IN ........
SYSLINK (AS-i)
IN 2
4mm Lab cable
IN 3
Signal SYSLINK
OUT 3
0V 0V
PARTAV PARTAV
Transport System
AS-i
IN 0.1
IN 0.7
OUT0.7
IN 0.1
IN 0.7
OUT0.7
AS-I Addr:
SYSLINK (AS-i)
OUT0
Sorting Station not ready, if:
IN 0 - it was not started (START-Button activated)
IN 1 - slides are full with workpieces
- no voltage supplied to the station
IN 2 - the station does not exist
IN 3
SYSLINK
OUT 3
0V 4mm Labor cable
Signal
0V
if a palette with workpiece is in Ap6 and the PIC alfa set signal free, the transport control sets share AV* the
signal . This signal must be evaluated in the program of the station PIC alfa instead of the signal share AV .
PIC alfa station get the part and the signal share AV* disappears again, the pallet can drive on .
AV* is a combination from the sensor share ON PALLET and the condition pallet IN position.
PART ON
Pending PALLET
order Bit1 Bit0 Order
0 X X No processing
1 0 TRANSPORT
0 Reserved
AS-i
Control panel new 1 0 1 Storage
1 1 0 Retrieval, oldest part
IN ........
1 1 1 Retrieval, jungest part
SYSLINK (AS-i)
0V 0V
OUT 6 Pending order
IN 4 OUT 0 AS-I Addr:
OUT 7 OUT 1 AS-I Addr:
Order Bit0
OUT 2 AS-I Addr:
OUT 4 IN 6 Order Bit1 OUT 3 AS-I Addr:
OUT 5 IN 7
Stock is full
AS-I Addr:
Stock is empty IN 1 AS-I Addr:
Order aktiv (busy) IN 2 AS-I Addr:
Station ready IN 3 AS-I Addr:
IN 0
IN 1
Cabel
IN 2 SYSLINK - plug
IN 3
OUT 0 SYSLINK
OUT 1
OUT 2
OUT 3
0V
i Plugs with links are to be inserted into the unoccupied operating positions, as
shown in the picture above.
2-pin Phönix
External
XNA11 2 Contacts for EMERGENCY-STOP
EMERGENCY- switch
STOP switch
4-pin Phönix
2 Contacts for
XNA01 EMERGENCY- e.g. Testing station
STOP,
2 Contacts for
feedback
4.4. Start-up process For the FMS50-installation the first start-up has been executed in the factory
already.
Implement the following directions that the system is ready for operation!
1. Mains supply 230 V AC for power supply unit, connect control cabinet of
transport system and commissioning station.
2. Power supply unit 24V DC with connections +24V/0V/earth are connected
correctly to the stations and activated (except for robot: only after adjustment of
the transport system).
3. Each station is supplied with ca. 6 bar compressed air.
4. I/O-communication connectors (laboratory plugs) are connected according to
communication plan.
5. All of the PLC-programs are loaded into the respective controls. The controls are
switched to RUN and the red error indicators of the controls are not on.
6. All of the EMERGENCY-STOP signal generators (push-buttons, door contact, light
barriers, a.s.o.) are not to be switched on, i.e. activated.
7. Activate the main switch of the transport system station.
8. Acknowledge the EMERGENCY-STOP of the control cabinet of the transport
system.
9. Remove all of the work-pieces from the installation, i.e. stations:
- Remove work-pieces from the palettes on the transport system
- Clear the storage shelves of the AS/RS station (HRL20)
- Clear the slides of the sorting/commissioning station
10. The magazines of all of the stations are to be stocked up:
- Magazines (piston, spring and cover) of the robot station with assembly
- Fill magazine of the distribution station with basic bodies
11. Now adjust the stations and the transport system (see chapter – Operation).
The chapter Operation describes the control units required for the operation, as well
as start-up and close-down of the system.
5.1. General notes on The stations demand strict adherence to certain rules of operation. Negligence in
operation observing these rules may cause errors in the stations’ processes. Also, damage to
physical health can not be excluded.
5.2. Transport system The control elements of the control cabinet of the transport system are required for
the start-up of the transport system and, as such, the complete system.
The main switch is located on the side of the control cabinet of the transport system
station, supplying the control cabinet with voltage. The conveyor belts and the
system can only be started, if the control cabinet receives voltage supply.
S5 Start up system
Indicator Request
H3 Light on
Controller on Acknowledge EMERGENCY-STOP
S3 Acknowledge EMERGENCY-STOP
EMERGENCY-
S2 De-activate control / EMERGENCY-STOP function
STOP
The table assists in operating the transport system station. All of the push-buttons
and lamps are described within.
5.5. Error and In case an error occurs in the transfer system, it is shown by a slowly flashing of the
error 'AUTOMATIC ON'-lamp and a lighten 'ERROR' lamp. As soon as the error has been
acknowledgement eliminated, it can be confirmed with the 'AUTOMATIC ON'-push-button.
Possible errors: e.g. a palette with work-piece arrives at the stopping station for
distribution/testing.
Assembly Spring magazine empty Cover magazine empty Piston magazine empty
As a rule, the production process starts with the distribution station, where a
cylinder basic body is seperated and transfered into the system by means of the
testing station. In case no distribution station is included in the system, it is possible
to place the cylinder manually onto a work-piece carrier at any place of the transport
system. Processing of the work-piece takes place from the “place of equipment”
onwards.
5.6. Process description The following process description is limited to the transport system. The processes
of the other stations are described in the respective manuals.
5.7. Material flow The FMS50 installation reacts flexible to the changes during the production process
and controls the material flow according to circumstances. For this, various starting
conditions are described.
Warenausgabe
Product output Lager
Stock Montage
Assembly
Pre-sorting
Wareneingang
Product input Processing
Bearbeitung Quality assurance
Qualitätssicherung
The following icons are used for the representation of the material flow.
Legend
The material input – the distribution station can distribute work-pieces (magazines
are filled) and the work-piece transfer of the test station functions faultless, ready to
start operational processing.
The AS/RS station is ready for operation and parts-storage (stock is empty).
The product output is ready, i.e. the PIC-alfa and sorting stations are ready for
operation and parts can be accepted.
Warenausgabe
Product output Lager
Stock Montage
Assembly
Wareneingang
Product input
The product input – the distribution station can seperate work-pieces (magazines
are filled) and the work-piece transfer of the test station functions faultless, ready to
start operational processing.
The AS/RS station is ready for operation and parts-storage (stock is empty).
Warenausgabe
Product output Lager
Stock Montage
Assembly
Wareneingang
Product input
In case parts are still remaining between stock and product output, they are placed
onto a buffer slide by PIC-alfa.
The system is in operation. The magazine of the distribution station is empty. For
this reason it is impossible for the test station to place any work-pieces onto the
palettes. The empty palettes are allowed to pass the operating position.
The robot assembly station cannot be supplied with basic bodies, therefore
production of cylinders cannot ensue.
The AS/RS station is ready for operation and parts can be stored or removed, as the
stock contains parts and is not full up. Parts arriving on palettes are allowed to pass
through to the product output. Empty palettes are filled with parts from the stock.
The product output is ready, e.g. the PIC-alfa and sorting stations are ready for
operation and able to sort parts.
Warenausgabe
Product output Lager
Stock Montage
Assembly
Wareneingang
Product input
The product output is ready, e.g. the PIC-alfa and sorting stations are ready for
operation, cylinder sorting.
The AS/RS station is ready for operation and is able to store or remove parts, as the
stock contains parts and is not full up. Parts arriving on palettes are allowed to pass
through to the product output. Empty palettes are filled with parts from the stock
(retrieval).
Warenausgabe
Product output Lager
Stock Montage
Assembly
Wareneingang
Product input
6.1. System information The FMS50 system is extended with a communication layer for using a SCADA
for FMS50 Level 2 system (Supervision, Control And Data Acquisition) like WinCC, for FMS50 it is called
"Level 2". For data exchange between SCADA system WinCC and the PLCs the
Profibus-DP field bus is used. All PLC stations are configured as Master, therefore
there is no data exchange programmed between PLC stations. WinCC is sending and
receiving data from/to the PLCs. PLC inputs, outputs or memory bits are used for
visualization. Reading and writing information (change value) is only possible with
memory bits or data block contents (bit, byte, word, …).
Before activating WinCC you have to make sure all FMS50 programs for Level 2 have
been downloaded to each PLC and all system cable connections are made:
Windows 2000 with SP2, English or German Version with Internet Explorer V5.5
Step7 V5.1 SP3
Profibus-card installed to the computer, e.g. Siemens CP5611, CP5613 or CP5511
WinCC V5.1 with WinCC-Application "FMS50_WinCC_Application_V3" or higher
Notice: Please make sure that all software and hardware has been installed in this order !
Profibus-DP
Distribution 2
Testing 4
Processing 6
Handling (Processing) 8
Robot-interface 12
ASRS20 14
Handling (Sorting) 16
Sorting 18
Conveyor System 20
→ File → Open →
for example:
C:\siemens\wincc\WinCCProjects\FMS50_WinCC_Application_V3\FMS50_WinCC_Ap
plication_V3.MCP
If you start WinCC the next time, always the previous project will open automatically.
→ Open
In a WinCC project for Single-User System the computer is the operating server for
the SCADA system. Therefore you have to change the server name to your computer
name. But first you have to start the project and than change the name.
The computer name in the project should be changed to your computer name.
Otherwise the project cannot open the runtime.
If you don´t know the computer name please see Step 3 (example for operating
system Windows 2000)!
→ OK
→ OK
File → Exit
→ OK
next: Step 4
For communication between WinCC and PLCs via Profibus-DP network it is necessary
to choose system parameters for WinCC.
Please choose your Profibus driver card. Possible Profibus cards available:
CP5511, CP5611 (e.g.), CP5613 and old CP5412
→ OK
6.3. Use FMS50 Level2 A process visualization is developed as a hierarchical structure of windows with
Runtime Application different priority. The hierarchy of the FMS50 Level 2 visualization is shown below.
01_Start.pdl
02_System_overview_Anlagen_Uebersicht.PDL
10_Distributing_Verteilen.PDL
03_Commissioning_Inbetriebnahme.PDL
12_Handling_Proc_Bearb.pdl
04_Profibus_Network_Netzwerk.pdl
13_Processing_Bearbeiten.pdl
05_Message_Alarm.pdl
15_RobotAssembly_RoboterMontage.pdl
16_ASRS20_Hochregallager20.pdl
17_Handling_Sorting_Sortieren.pdl
18_Sorting_Sortieren.pdl
Only below the second hierarchical level it is possible to control the FMS50 process.
Window: 01_Start.pdl
3 1
2
Window: 02_System_overview_Anlagen_Uebersicht.PDL
8 9
10
5 6 1 2 3
Buttons
Functions
ASRS20 "Storage full!" Storage is full. Please take out parts and
reset ASRS20. Please see description for
ASRS20 at next pages!
Window: 03_Commissioning_Inbetriebnahme.PDL
4
5
1 Driver Preset Enter the number of the driver you want to connect.
Value
Standard drivers are:
0 = not connected
1 = Distributing and Testing
2 = Handling and Processing
3 = Vision (depends on used vision system)
4 = Robot and Assembly
5 = ASRS20
6 = Handling and Sorting
The function of the driver may vary if specified
differently in the project !
Please check your Step7 program for driver
functions!
Window: 04_Profibus_Network_Netzwerk.pdl
Functions:
Window: 05_Message_Alarm.pdl
Functions:
Window: 10_Distributing_Verteilen.PDL
4 5
1
6
7 8
Window: 11_Testing_Pruefen.pdl
3 4
Window: 15_RobotAssembly_RoboterMontage.pdl
3 4
6
7 8
Window: 16_ASRS20_Hochregallager20.pdl
3 4
The technical drawings and technical data below are very helpful to facilitate set-up
of the station. The technical data of the accomodation is to be checked before set-up
of the station.
The load capacity of the ground, the sizes of doors and access are to suit to the
system’s dimensions.
1 Width 500 mm
3 Length 3000 mm
8 Belt width 40 mm
12 Current consumption 24 W
The transport system contains 6 operating positions. Any of the MPS-stations can be
placed in any of the 6 operating positions. The following description relates to the
standard system.
7.1. Operating position 1 The distribution and testing MPS-stations are situated in operating position 1. The
work-pieces are seperated in the distribution station and transferred to the testing
station. The distribution station is not connected directly to the transport system. It
is located beside the testing station. The testing station is connected to the
transport system, and additionally to work-piece testing it performs the work-piece
transfer to the transport system.
7.2. Operating position 2 The PIC-alfa station is located in operating position 2. It realises the material
transport to the processing station, which is situated directly beside the PIC-alfa
station executing the drilling of a hole and testing afterwards.
7.3. Operating position 3 A vision system is mounted on operating position 3. The camera is mounted directly
at the transport system and is located above the operating position. Therefore
changing position of the work-piece is not necessary . The evaluation system of the
camera is situated on a MPS-carriage or operating table.
7.4. Operating position 4 The robot assembly station is located at operating position 4, consisting of 2 MPS-
carriers, whereby the robot RV-2AJ is mounted onto the carrier, which itself is
directly situated beside the transport system. The robot executes the handling of the
work-pieces and of the assembly components. At this operating position, a model
cylinder is assembled by the robot.
7.5. Operating position 5 At operating position 5, the AS/RS station is available for material storage, where
the work-pieces can be stored and removed.
7.6. Operating position 6 The sorting or commissioning station is situated in operating position 6. By means of
a PIC-alfa station, which is directly connected to the transport system, it receives its
work-pieces to sort them according the colour ot the cylinders.
The work-piece carriers are stopped of a pneumatic cylinders. The valve required for
the control consist of one CPE10 single valve.
Pos. Designation
The valve is controlled via ASI, to connected the valve with the ASI-bus the valve
interface is necessary.
The valve is wired with the valve interface. Optional it is possible to connect to
inputs to the interface.
Pos. Designation
3 Outputs 1
4 Inputs 2
LED display
on 1- Signal at In/Output
* Black = pressed
** The outputs/valves are provided with power via the additional supply
*** The outputs/valves are provided with power via the Asi-Interface bus
8.3. Pneumatic The pressure in the supply line must not exceed 10 bar.
connection
A fine filter has to be installed, to prevent contamination by rust or similar
contamination.
The pressure regulators installed in the system should be set in between 6 and 5
bar. The filter and water separators require maintenance according to the
instructions of this documentation.
Maintenance unit
To this chapter belongs the connection of all of the supply cables and
communication cables required for the operation of the system.
To give you a better overview of the contact lines used in the installation, these are
explained in the following.
9.1. Supply voltage The transport system is delivered with the appropriate power supply plug covered
by protective contact, which is to be plugged into a socket, fixed according to
standard. The voltage amounts to 230 V.
The customer is required to ensure, that the supply net is duly earthed and does not
possess fault current monitoring.
The power supply (24VDC) of the transport system outside the control cabinet is
made by a 2-pin cable. The voltage supply is the 24V power supply unit in the
station. The 24V can be tapped by the clamps.
9.2. Control cabinet The control cabinet is set up as shown in the picture below. The individual
components are designated.
The frequency converter generates the voltage required for the motors.
The ASi-power supply unit supplies not only the ASi-voltage of 30,5 V, but also the
supply voltage of 24V for the control cabinet and the transport system.
9.3. EMERGENCY-STOP The EMERGENCY-STOP system is controlled centrally by the transport system
system station. In the control cabinet of the station an EMERGENCY-STOP switch device is
located, which is connected to all of the operating positions and all external
EMERGENCY-STOP devices.
The external EMERGENCY-STOP devices are controlled by a 2-pin cable. The devices
are connected to the 2-pin Phönix plug-in contact. In case no device is plugged in,
the contact is to be established with a strapped plug.
The PLC-boards are connected to the 4-pin plug-in contacts. In this case 2 lines are
for the feedback (station available) and 2 lines for the EMERGENCY-STOP of the PLC-
board.
External Emergency-Stop
Emergency-Stop push button Emergency-Stop push button
CPU 314
CP 342-2 SM323
SIEMENS SF
BAF
Asi Master DI8/DO8 xDC24V
DC 5V SF
FRCE RUN 0
RUN APF 1
STOP CER 2
AUP 3
CM 4
-XNA1
5
RUN-P
-XN1
Phönix plug-in
30+ 6
RUN
20+ 7
10+
STOP
MRES SET
4 pin
Simatic 0 0
S7-300
1
1
1 1
2 2
5
3 3
4
2
2 4 4
3
5 5
2
6 6
1
3
3
7 7
X 2 X 2
X1MPI 3 4 3 4
4
4
Operatingposition 1
Emergency-stop switch device
A1 B1 13 23 33 43 53 63 73 81 91 A1 Y1 Y2
Power Pilz 13 23 33 43 53 63 73 81 91
If no station exists in an operating position,
-XNA2
Phönix plug-in
CH. 1
CH. 2 IN for the feedback.
4 pin
START CH. 2
1
1
CH. 1 OUT
2
2
13 23 33 43
14 24 34 44 54 64 74 82 92
3
3
CH. 2 OUT
4
4
14 24 34 44
14 24 34 44 54 64 74 82 /B2 A2 43 55 A2
CPU 314
CP 342-2 SM323
SIEMENS SF
BAF
Asi Master DI8/DO8 xDC24V
DC 5V SF
FRCE RUN 0
RUN APF 1
STOP CER 2
AUP 3
CM 4
-XNA3
5
RUN-P
-XN3
30+ 6
RUN
Phönix plug-in
20+ 7
10+
STOP
MRES SET
4 pin
Simatic 0 0
S7-300 1 1
1
1
2 2
5
3 3
9
4 4
8
2
2
5 5
7
6 6
6
7 7
3
3
X 2 X 2
X1MPI 3 4 3 4
4
4
Operatingposition 3
For this, the control for the transport system, of the Siemens S7-300 group, consists
of several modules.
3 Virtually occupied
10.2. Wiring The station’s internal wiring and the wiring to the other stations is explained as
following.
10.2.1. I/O-components
The control elements are directly connected to the control of the Transport system.
Data I/O-terminal
Technical data
Allocation I/O-terminal
04 Brown-
3 Output yellow 16 3 Input
green
05 White-
4 Output grey 17 4 Input
yellow
06 Yellow-
5 Output pink 18 5 Input
brown
09 24
Voltage supply black 21 24V Voltage supply White-pink
V
10 22
10.2.2. ASi-participant
Example ASi-wiring
As the internal I/O-mapping of the control only starts showing singularity from ASi-
address 02 onwards, allocation of ASi-address 01 is omitted.
10.3. Programming In this chapter, it is not possible to refer in detail to the programming of a PLC-
control. However, the interface is shown below. The allocation list provides easy and
clear programming . The ASi-tables in this chapter are also very helpful in speeding
up allocation processes.
This error list has been drawn up to restore operation of the system as soon as
possible, after the appearance of an error.
Palette with work-piece arrives in the Remove work-piece from palette and acknowledge
stopping station of distribution/testing error in transfer system.
station. Only empty palettes should reach
this point.
The commissioning station is not ready and Retrieve work-piece from palette. Clear the
the AS/RS station is full. Now, a palette with commissioning slides of the commissioning station. Re-
work-pieces arrives in the AS/RS stopping start station by activating the STARTpush-button (new).
station. Acknowledge error in the transfer system.
A work-piece is placed incorrectly on the Place work-piece manually into palette’s work-piece
empty palette in the stopping station by reception
the (air) slide of the testing station. Work- (in processing direction - right rear-end).
piece is not in fixture or is not placed in
range of the light barrier.
Palette with work-piece waits at the Palettes have to be removed from the stopping station
stopping station of PIC-alfa/sorting or only, once the work-piece has been removed from PIC-
commissioning and no action ensues. PIC- alfa.
alfa is not ready or not started up.
For product output, max. 18 parts can be All 3 of the slides are to be cleared.
commissioned onto 3 slides by the Activate START push-button.
commissioning station. Commissioning station is ready for operation again.
The START-lamp begins to flash, once a
commissioning process has been
concluded (slides full).
Palette with work-piece waits at stopping Work-piece is to be removed from palette by PIC-alfa.
station PIC-alfa/commissioning. Poss. start-up of PIC-alfa.
Palette with work-piece waits at stopping PIC-alfa and sorting station are not ready, e.g. not
station PIC-alfa/sorting. activated, not adjusted or one of the sorting slides is
occupied.
→ poss. retrieve work-pieces from slides
→ adjust stations and start up
→ poss. activate voltage supply or pressure