MPC Feasibility Study
MPC Feasibility Study
MPC Feasibility Study
Professional Services
Solicitation No.: 2022-0450R
April 26, 2022 REQUEST FOR QUALIFICATIONS
Motion made by Representative Salcido, seconded by Representative Rivera, and unanimously carried
to DIRECT the City Manager or designee to hire a consultant such as ARCHITECTS, URBAN DESIGNERS,
ENGINEERS and to include studies such as an ECONOMIC IMPACT ANALYSIS and PROGRAMMING
OPERATIONS; execute all contracts and amendments to develop the following information: PROJECT
CONCEPT; PARTNERSHIP OPPORTUNITY guidelines including PUBLIC-PRIVATE PARTNERSHIP
SPECIFICATIONS; and FINANCIAL MODEL to include estimate of CAPITAL COSTS AND OPERATING
COSTS which is in compliance with all court rulings and legal decisions to INCORPORATE PRESERVATION
OF HISTORIC BUILDINGS and to PRESERVE HISTORIC CHARACTER and to DIRECT staff to return with
recommendations on how to SAFEGUARD DAMAGED BUILDINGS and options for funding sources in
ways to align with the Temporary Restraining Order (TRO).
3
REQUEST FOR QUALIFICATIONS
• Nov. 9 – Council Action directs City
to hire consultant for feasibility
study
• Jan. 14 – RFQ issued
• Feb. 8 – 10 Submittals received
• All offerors with local teaming
partners
4 SELECTED CONSULTANT ARCHITECTS, URBAN DESIGNERS, ENGINEERS
TEAM
Site/Program/Urban Design/Master Plan – Gensler
Market/Economic Assessment – CSL/Legends
Architectural/Structural Assessment – Countryman & Co.
Walter P. Moore/Mijares-Mora/Rider Levett Bucknall Ltd.
5
SCOPE OF WORK:
6
7
ECONOMIC IMPACT ANALYSIS
MARKET/ECONOMIC ASSESSMENT FINANCIAL MODEL
PUBLIC-PRIVATE PARTNERSHIP SPECIFICATIONS
PROJECT SCHEDULE
& COST:
16 PROJECT SCHEDULE
Notice To Proceed 5/9/2022
Weekly Monday Meetings
Predesign Documents and Reports Phase (Pre-Design) PD 30 days 5/9/2022 6/17/2022
Work Session #1 / Kick-off Session
Community Engagement Meeting/Report #1
Work Session #2
Schematic Design Phase (Preliminary) SD 60 days 6/20/2022 8/19/2022
Work Session #3
Community Engagement Meeting/Report #2
Cost Estimate
Schematic Design Report Submission
Design Development Phase (Pre-Final) DD 90 days 8/22/2022 12/2/2022
Work Session #4
Community Engagement Meeting/Report #3
Cost Estimate
Design Development Report Submission
Final Design Phase FD 30 days 12/5/2022 1/13/2023
Work Session #5
Formal Presentation
Cost Estimate
Final Submissions
17 COST OF SERVICES
Market/Economic Assessment/Project Concept: $393,360
Operations/funding models/partnerships: $287,000
Zoning/Bldg. Code/Accessibility: $ 27,211
Structural/Civil/MEP: $ 23,000
Historic Preservation/Adaptive-Re-use: $ 25,090