RDMP PJT - Pressure Test Work Guide - Rev.002

Download as pdf or txt
Download as pdf or txt
You are on page 1of 10

1) PIPING PRESSURE TEST PACKAGE WORK FLOW CHART

CONTRACTOR
SUBCONTRACT CONTRACTOR
STAGE CONST. IPMT REMARK
OR QA/QC
(TEST GROUP)

1) Preparation of *Engineering Document


STAGE 1 : Marked-up P&ID,
PKG list and Marked-up Spool DWG,
PKG Engineering Line list and etc.
Preparation Document*

2) Preparation of
Test Package
Package Assignment

3) Initial review of Test Package

STAGE 2

Walk-down 4) Pre-Walk Down & Punch Issue


&
Punch Clear

5) Pre- Punch Clear

Master Test PKG. Status


6) Submission of (Recording the all work status
7) Review of Test Package from this step)
Test Package

Walkdown Request
(Only RFI)
8) Walkdown & Punch Issue
Punch Issue

Punch Close
10) Site checking and
9) A Punch clear
Punch Close for A Punch

STAGE 3
Pressure Test Request
(RFI + Press.Test Report)
Pressure Test 11) Pressure Test
to
PKG Handover
Drain & Dry Request
(RFI + Drying Report)
12) Drain & Dry

Punch Close
14) Site checking and
13) B Punch Clear
Punch Close for B Punch

Reinstatement Request
(RFI + Reinst. Report)
15) Reinstatement

16) PKG
handover

1
2) PKG Documentation Guide

Document Source
No Document Description Remark
PIC IT System

1 Pressure Test Cover Sheet Subcon PICS

2 Table of Contents Subcon PICS

3 Test Legend and Symbols Subcon PICS

4 Punch List Subcon PICS

5 Pre-Test Check List Subcon PICS

6 Pressure Test Report Subcon PICS

▷ JO Engineering →
7 Line List Subcon N/A JO Const. → Subcon.

▷ JO Const. → Subcon.
8 Marked-up P&ID Subcon N/A (Original P&ID from JO
Engineering)

▷ Original Spool DWG to be


9 Marked-up Spool Drawings Subcon N/A printed out through PICS

10 Test Package Welding Summary Subcon PICS

11 Calibration Report (Pressure Gauge, Relief Valve) Subcon N/A

12 Water Analysis Report Subcon N/A

13 Test Certificate of Manifold Subcon N/A

14 Drying Report Subcon PICS

15 Line Reinstatement Report Subcon PICS

2
Screen Name PKG Assigned Status Screen Category □ Setup □ Input ■ Search ■ Print

Menu Path STATUS > CONSTRUCTION > Pressure Test Status > PKG Assigned Status

3 4

1
2

- Continue in next page -


1
Screen Name PKG Assigned Status Screen Category □ Setup □ Input ■ Search ■ Print

Menu Path STATUS > CONSTRUCTION > Pressure Test Status > PKG Assigned Status > Joint Summary

2
Screen Name PKG Assigned Status Screen Category □ Setup □ Input ■ Search ■ Print

Menu Path STATUS > CONSTRUCTION > Pressure Test Status > PKG Assigned Status > PKG. Report

3
Punch Item Categorization (Check list for piping line Inspection)
20-Jun-21
Punch Category
No. Repectitive Punch Items Remarks
A B C
Notes
Category of Punches
A : To be rectified or completed before Hydro
B : To be rectified or completed before comisioning
C : To be rectified or completed before turn over
Inspection for piping construction work shall be performed in accodance with the following
construction specification
1 Test package document verification
1-1) Check that the Test Package documentation is consistent X
1-2) Check Isometrics are latest revised drawing or not X
1-3) Check P&ID’s X
1-4) Check Line list X
1-5) Check test method pressure etc. X
2 Material verification (piping,pipe support,inline instrument,special items...)
- Material classification
- Flange rating
- Pipe and fitting schedule (wall thickness')
- Item code (tag number)
* sample *
2-1) Use incorrect bolt at 3/4" vent & blind flange X
2-2) Wrong install (specification) gasket at 8" gate valve to be replace X
2-3) Missing valve tag plate X
2-4) Change temporary valve tag wire X
2-5) Temporary valve tag to be repalce (permanent required) X
2-6) No material "I.D" to be clarification X
2-7) Bolt too short at flange X
2-8) Wrong type valve install X
2-9) Wrong use stud bolt&nuts. X
3 Accurately performed in checking horizantal and vertical direction and mutual
distance between parallel lines using level,plumbness,etc.
* sample *
3-1) Out of verticality or,plumbness X
3-2) Out of levelness from joint no #2-3 X
3-3) Out of straight from joint no #2-3 X
3-4) Elbow stanchion not centerized at concrete foundation
3-5) Joint no #5 to correct angular misalignment X
3-6) line slope clarifiy X
3-7) line not square X
4 Flange such as nozzle joints of pump,compressor, tubine, etc. shall be required
pre alignment check prior to hydro test.
* sample *
4-1) Flange misalignment X
Punch Category
No. Repectitive Punch Items Remarks
A B C
Notes
4-2) Attached nozzle flange alignment report (pump,compressor,turbine...) X
4-3) Loosen bolts for check flange alignment X
5 Every valve stem orientation shall be consideration case of case and operation
* sample *
5-1) Orientation valve handle,handwheel wrong X
5-2) Confirm valve operation access X
5-3) Obstrucion valve stem to steel structure X
if gear type, not possible to turn and
5-4) Valve handwheel interference X X re-orientated is punch "A" otherwise
punch "B"
5-5) Check unit for access to valves and equipment. X
5-6) Correct vents and drains on piping to ensure that they are adequate for operation. X
6 Check paint type according to the base on paint design specification
* sample *
6-1) Wrong paint specification to verifiy X
7 Pipe supporting elements shall be fabrication and installed in accordance with the
pipe standard & special support detail drawing
* sample *
if direct welding to pipe is punch "A"
7-1) Additional support required X X
otherwise punh "B"
7-2) Check support location as following according to iso drawing X
7-3) Missing adjustable jack screw bolts X
Sliding supports that must be mounted on sliding plate that are grouted and bolted to the
7-4) X
paving
7-5) Steel members shall be following according to conversion table X
7-6) Support "S7" no weep hole X
7-7) Support base not resting on concrete foundation X
7-8) Support no #s1 to be shimmed (not resting) X
7-9) U-bolt lock nuts missing X
8 Isomertric drawing & support as-built
* sample *
8-1) Reflected additional support as-built on iso drawing X
8-2) To record additional welding joint X
9 Welding inspection
* sample *
9-1) Build up weld crater X
9-2) Dress poor stop start weld X
9-3) Dress sport weld X
In threaded joint between pipe and flange. The length of thread by 1.5 to 3.0mm when screwed
9-4) X
in
9-5) Remove tack welding plate and build up weld X
9-6) Slag inclusion X
Punch Category
No. Repectitive Punch Items Remarks
A B C
Notes Socket weld fitting and valves are used the pipe face shall be spaced approximately 1 to 1.5 mm
9-7) X
clearnce
9-8) Support number "S7" weldment to rectify and dress X
9-9) Surface defects pin hole X
9-10) To dress up all pipe wrench mark found on pipe surface X
9-11) Undercut X
9-12) Very deep arc strike, requird to grind off and build up X
9-13) Welding fill cover not enough, requied additional one mor pass X
9-14) Welding spatter X
10 In line special items and inline instrument items
* sample *
10-1) Control valve wrong flow direction X
10-2) Provide "BOM",weld map, history sheet for orifice tap valve & plug X
10-3) Orifice tapping wrong orientation X
10-4) PSV not yet install (outlet line) X
10-5) PSV not yet install (inlet line) X
10-6) Control valve and flow meter not yet install X
10-7) Sight glass not yet install X
10-8) Expansion joint not yet install X
10-9) level guage, level transmital, level switch not yet install (flange type only) X
10-10) Steam trap not yet install X
10-11) Strainer not yet install ("T"- type ) X
10-12) Strainer not yet install ("Y"- type bellow 8 inch) X not including test
10-13) Flexible hose not yet install X
10-14) Quick coupling not yet install X
10-15) Sample cooler not yet install X
10-16) Sample bomb not yet install X
10-17) Injection nozzle not yet install X install after flushing by pre-comm'
10-18) Emergency shower not yet install X
11 others
* sample *
11-1) On off valve included test X If valve not available change to "C"
11-2) 6" line low point drain to be provided with elbow for easy usage X
11-3) All the sleeves to be sealed at dike wall X
11-4) Check direction of flow for control valves X
Check that sample points are fitted in accordance with drawings, and that access for sample
11-5) X
bomb connection is adequate.
11-6) Check valve , globe valve flow direction to be verify (as per P&ID) X
11-7) Check valve drain to be seal welding before hydro test (with valves) X
11-8) Check valve plug to be seal weld after hydro test (without valves) X
11-9) Drain valve missing plug X
if finished test without installation of
11-10) Earthing lug install X
earthing lugs is required MT
11-11) EFW weld seam overlapping (5 time the nominal wall thickness or 25mm over) X X if perform RT 100% quality factor "1
Punch Category
No. Repectitive Punch Items Remarks
A B C
Notes
install after line flushing by pre-
11-12) Fire water or form spray nozzle install X
comm'
11-13) Flange assemble off square X
11-14) Flange bolt hole tolerance max 1.5mm X
11-15) Guide bolts and nuts of expansion joints to be loosen. X
11-16) High point vent & low point drain not provide X
11-17) Hose rack (Stand) to be provide and install X
11-18) Install additional steel member for pipe support of rested on platform or check plate X
11-19) Install locking device on valves where necessary. X
11-20) Installation of temporary strainers and later removal as required. X
11-21) Iolation kit to be install (if required) X install after line flushing
ASME B31.3-2002 335.1.1 alignment
11-22) Joint misalignment (hi-low) I.D (1.6mm) O.D (3mm) X
off-set maximum 3mm
11-23) Marking of spring supports and hot setting to be done. X
11-24) Modify the platform affecting the maintenability and accessibility of pump. X
11-25) Operation Access to be provided for isolation valve before RO-007 X
11-26) OS System funnel is covered with debris X
Pipe in to the drain funnel gap clearence from top of hub to pipe end to keep 70mm distance
11-27) X
(visual packages)
11-28) Pipe not rest on beam (required shim plate weld) X
11-29) Pipe shoe welding overlapping (partial open ) X
11-30) Reinstate check valve internal (check valve dismantled) X
11-31) Remove scaffold from the pipe X X if line out of level
11-32) Remove spot contaminated rust on pipe surface X
11-33) Remove temporary gasket and replace permanent gasket X
11-34) Remove temporary support X
11-35) Remove temporary wood X
11-36) Remove wire & rope adjecent joint #8 X
install after line flushing by pre-
11-37) Restriction orifice & orifice plate installation (to maintain gap) X
comm'
11-38) Rotate the isolation Valves which is interfering with the monkey ladder X
install after line flushing by pre-
11-39) Rupture disc installation X
comm'
11-40) Seal weld vent cap after tested X
11-41) Spring support setting cold porsition , remove preset paces X by pre-comm' team
install after line flushing by pre-
11-42) Permanent strainer mesh screen installation X
comm'

11-43) Support pad overlapped to pipe or elbow (welding shall not cross over min 6mm gap) X shoe welding part cutting and open
11-44) The pipe supports for the suction line of the compressor is not grouted. X
11-45) The scaffolding pipes fouling in the access platform on north side to be removed. X
Punch Category
No. Repectitive Punch Items Remarks
A B C
Notes The unwanted opening made on the grating on the walkway platform around the compressor
11-46) X
skid unit to be closed properly.
11-47) Toe guard to be provided for all pipelines that pass through grating. X
11-48) Unequal bolts protrusion at flange X
11-49) Wrong orientation or position of spectacle blind tail X X if equipment nozze to be punch "A"

You might also like