1) Most Economic Hauling Distance (M) Calculation
1) Most Economic Hauling Distance (M) Calculation
1) Most Economic Hauling Distance (M) Calculation
𝟒𝟗𝟐 ₺⁄ 𝟑
𝒎
𝐹𝑏 = 1.25 ∗ 0.00034 ∗ 𝐾 ∗ √𝑀𝑏 − 0.00425 ∗ 𝐾
𝑭𝒃 = 𝟑. 𝟒𝟗𝟐 ₺⁄ 𝟑
𝒎
𝑴𝒆𝒉 = 𝟏𝟕𝟔𝟎 𝒎
2) Mass Table
A portion of the mass table for this alternative is provided below
Table 1 Mass Table Alternative 2
Station (m) Cut (m3) Fill (m3) Corrected Cut (30%) Fill + Cut Cum. Volume
0 0 0 0 0 0
100 2492,273 0,028 3239,9549 3239,927 3239,9269
200 2141,728 406,27 2784,2464 2377,976 5617,9033
300 1092,12 647,745 1419,756 772,011 6389,9143
400 6331,879 241,503 8231,4427 7989,94 14379,854
500 34773,021 0 45204,9273 45204,93 59584,7813
600 82459,353 0 107197,1589 107197,2 166781,9402
700 78057,76 0 101475,088 101475,1 268257,0282
800 36242,612 0 47115,3956 47115,4 315372,4238
900 17100,999 121,828 22231,2987 22109,47 337481,8945
1000 5893,008 2407,04 7660,9104 5253,87 342735,7649
1100 336,508 4467,506 437,4604 -4030,05 338705,7193
1200 2,618 96248,394 3,4034 -96245 242460,7287
3) Mass Diagram
Mass diagram is given below in two parts.
For first seven loops, multiple loops method was applied. In the remaining part, two loops
method was applied for 5 times and for 13th loop, axis was assumed as balanced line. For 10th and
14th loops, all methods were trialed, however, appropriate one could not be determined.
Therefore, balanced line of closest double loops was extended and the extended part taken as
balanced line for both 10th and 14th loops.
Loop
Number V (m3) M (m) sqrt(M) sqrt(M)*V
1 191666,7 530 23,02172887 4412498,11
2 11060,6 240,2 15,49838701 171421,459
3 27318,2 168 12,9614814 354084,341
4 628787,9 448,5 21,17781858 13316355,7
5 237295,5 296 17,20465053 4082585,46
6 27280,3 137,3 11,71750827 319657,141
7 1200811 421,7 20,5353354 24659048,6
8 8712,12 105,6 10,27618606 89527,3661
9 8030,3 107,1 10,34891299 83104,876
10 256287,9 205,4 14,33178286 3673062,25
11 16159,1 115 10,72380529 173287,042
12 11030,3 116,4 10,78888317 119004,618
13 347651,5 257 16,03121954 5573277,52
14 1131023 264,4 16,2603813 18390860,4
15 21227,3 132,7 11,5195486 244528,914
16 22757,58 131 11,44552314 260472,409
17 100530,3 294 17,1464282 1723735,57
18 108878,8 283,7 16,84339633 1833888,78
19 786568,2 569,5 23,86419913 18770819,7
20 163219,7 602 24,53568829 4004707,68
ƩV= 5306295 Ʃ(V*sqrt(M))= 102255928
Σ𝑉 ∗ √𝑀 102255928
√𝑀𝑎𝑣𝑔 = = = 19.271 𝑚
Σ𝑉 5306295
Hauling Unit Price:
𝑭𝒉 = 𝟐. 𝟎𝟐𝟔 ₺⁄ 𝟑
𝒎
5) Waste and Borrow Volumes
1 2 3 4 5 ƩV (m3)
Waste Volume (m3) 148765,2 934924,2 708676,8 590083,3 43989,4 2426438,9
3
Borrow Volume (m ) 897446,97 185757,7 1131022,7 - - 2214227,3
Unit Price:
𝐹ℎ = 2.026 ₺⁄𝑚3
𝐹𝑏 = 3.492 ₺⁄𝑚3
𝐹𝑤 = 3.492 ₺⁄𝑚3
Total Cost:
𝐶𝑡 = 𝐶ℎ + 𝐶𝑏 + 𝐶𝑤 = 𝐹ℎ ∗ Σ𝑉ℎ + 𝐹𝑏 ∗ Σ𝑉𝑏 + 𝐹𝑤 ∗ Σ𝑉𝑤
𝐶𝑡 = 2.026 ∗ 5306295 + 3.492 ∗ 2214227,3 + 3.492 ∗ 2426438,9