AWARNESS PROGRAM ON
.
BOILER SUPPORTING STUCTURES
COLUMN
1.MAIN COLUMN
2.SECONDARY COLUMN
4.ESP COLUMN
COLUMN
CHANNEL-BOX TYPE
Section
Web width depth
+3mm
Flange T
Web width
Web T of I section Section
depth
Web cutting CL
after I formation
COLUMN
I & T fit up
CL
COLUMN
STAGE 1
QUALITY CHECK
1. SECTION DEPTH
2. SQUARENESS OF FLANGE AND WEB
3. CENTER LINE AND WEB ALIGNMENT
COLUMN
Center line marking after welding: mark center of web
thickness and transfer on flange
CL
Web
shift
COLUMN
WELDING OF I &T SECTION(SAW)
STAGE 2
QUALITY CHECK
1 FLANGE WARPAGE : 1/100 OF THE FLANGE WIDTH
or 6MM WHICHEVER IS GREATER
2.TWIST 0.05H/FOR EVERY 5M LENGTH MAX10MM
3. SWEEP AND CHAMBER
4.WELD VISUAL
5. MPI ON WELD
COLUMN
Plus fit up:Check section depth with box type gauge on
both sides (ensure +3mm in section depth for shrinkage
allowance,)
COLUMN
STAGE 3
QUALITY CHECK
1. SECTION DEPTH
2.WEB SHIFT OR ALIGNMENT
COLUMN
WELDING OF PLUS
STAGE 3
QUALITY CHECKS
1. SWEEP AND CHAMBER:10MM MAX
2. SECTION DEPTH : +/- 3MM UP TO 1M
3. TOTAL LENGTH : +/- 3MM
4. WELD VISUAL
5. END EP FOR REST PLATE
6. MPI ON WELDMENT &EP AREA
COLUMN
ASSEMBLY SEQUENCE
1.TOP TO BOTTOM
2.BOTTOM TO TOP
COLUMN
QUALITY CHECKS
1 CENTER LINE ALIGNMENT
WATER LEVELING OF ADJACENT PIECES: WITHIN 2MM
OUT OF STRAIGHTNESS : 18MM MAX.(FULL TA)
:10MM MAX (PARTIAL TA 3PIECES)
2. OUT OF VERTICALITY
AT BASE : 4MM MAX.
A1
A1
A4
A2
A4 A4
A4
Bottom side
A3
COLUMN
MAIN COLUMN
5.ORIENTATION OF CAP(TOP) PLATE
6. FLATENESS OF CAP :0.2MM, LOCALLY 0.5MM
A 1/A4
A 2/A3
BRACING PLATE
SHEAR
LUG
COLUMN
11. ZERO LEVEL 5M
AND OLV PUNCH
12.Every 5M level mark
Punch
0’ M LEVEL at 3 Axis
OLV PUNCH