Electricity 02 00033 v2
Electricity 02 00033 v2
Electricity 02 00033 v2
Institute for Electrical Energy Storage Technology, School of Engineering and Design, Technical University of
Munich (TUM), 80333 Munich, Germany; [email protected] (L.S.); [email protected] (N.C.);
[email protected] (A.J.); [email protected] (H.H.)
* Correspondence: [email protected]
Abstract: The growing global electricity demand and the upcoming integration of charging options
for electric vehicles is creating challenges for power grids, such as line over loading. With continu-
ously falling costs for lithium-ion batteries, storage systems represent an alternative to conventional
grid reinforcement. This paper proposes an operation strategy for battery energy storage systems,
targeted at industrial consumers to achieve both an improvement in the distribution grid and electric-
ity bill savings for the industrial consumer. The objective is to reduce the peak power at the point of
common coupling in existing distribution grids by adapting the control of the battery energy storage
system at individual industrial consumer sites. An open-source simulation tool, which enables a
realistic simulation of the effects of storage systems in different operating modes on the distribution
grid, has been adapted as part of this work. Further information on the additional stress on the
Citation: Kucevic, D.;
storage system is derived from a detailed analysis based on six key characteristics. The results show
Semmelmann, L.; Collath, N.;
that, with the combined approach, both the local peak load and the global peak load can be reduced,
Jossen, A.; Hesse, H. Peak Shaving
while the stress on the energy storage is not significantly increased. The peak load at the point of
with Battery Energy Storage Systems
common coupling is reduced by 5.6 kVA to 56.7 kVA and the additional stress for the storage system
in Distribution Grids: A Novel
Approach to Reduce Local and Global
is, on average, for a six month simulation, period only 1.2 full equivalent cycles higher.
Peak Loads. Electricity 2021, 2,
573–589. https://doi.org/10.3390/ Keywords: battery energy storage system; lithium-ion; grid-integrated energy storage; peak shaving;
electricity2040033 distribution grid; peak load reduction
MV grid
LV grid
Figure 1. Graphical overview of the simulated grid and battery energy storage systems (BESSs), as
well as the investigated operation strategies. The BESS, modeled in detail, located at various nodes
in a test grid, is operated in three different operation strategies to reduce the local peak load (Strategy
α) or the peak load at the point of common coupling (β) or both (γ).
Figure 2. Overview of all open-source simulation tools, which have been adapted for use in this
study. The open_BEA tool operates as both a central control unit and as a configuration unit. The
eDisGo tool conducts the power flow analysis and SimSES operates as a validation unit for the battery
energy storage systems’ behavior.
In addition to the specification of the test grid and the operation strategies (α − γ) of
the BESSs, individual load demands are assigned to the various actors in the grid within
open_BEA. Based on these load demands for residential or industrial consumers, the
eDisGo software performs a power flow analysis for a selected period. In this step, the
power flow analysis is conducted without storage systems. This allows determining the
power flows at all specific nodes and lines for the entire simulation period. These power
flow results as well as the power at the PCC are transferred back to open_BEA for the next
simulation step. Based on the power flow results, the dis(-charging) strategy for each BESS
is calculated according to the selected operation strategy (cf. Section 3).
The main task of SimSES is to validate the effects of the target power provided by the
energy management system of the open_BEA tool regarding efficiency, temperature, and
degradation of the BESS when applied to the storage system. Each implemented compo-
nent, such as the power electronics unit or the battery type, is responsible for modeling
its relevant principles [12]. SimSES can be split into a simulation part for modeling the
physical behavior of the BESS and an evaluation part that provides technical results for
this study. The validated BESS time series are now included in the grid and an additional
power flow analysis is conducted with eDisGo and the results are fed back to open_BEA
for further analysis and visualization.
Figure 3. Graphical representation of the test distribution grid. The open circuit breakers are marked
in gray, the MV/LV transformers are marked in light blue, the PCC in red, and all branch tees in
dark blue.
The distribution grid includes 72 industrial consumers with an annual load above
100 MWh. Only these end-users can potentially benefit from applying peak shaving
through a BESS as described in Section 3.1. Equation (1) defines the vector N for all
industrial consumers b within the described distribution grid, with a total number of
nodes B:
N = [1, · · · , b, · · · , B]T (1)
The current time step t within a defined time horizon T is defined by a vector H as shown
in Equation (2):
H = [1, · · · , t, · · · , T] (2)
Finally, the apparent power Sbt at each node b for each time step t is defined by a
matrix S (Equation (3)). The individual load profiles for these industrial consumers as well
as all other consumers in the grid are according to a former publication [14].
Table 1. Parameters and settings of the simulated battery energy storage system (BESS) comprising
battery cells, a power electronics unit, and a battery management system (BMS).
apparent power SPCC at the PCC is used to determine the operation strategy of BESSs of
industrial customers instead of the local load profile vector.
h i
SPCC = SPCC1 , · · · , SPCC
t , · · · , SPCC
T (6)
The optimization goal of grid-centered peak shaving is to minimize the peak power
at the PCC instead of the power peak at a specific node b (Strategy α). Consecutively, the
peak shaving thresholds of the industrial customers storage systems are recalculated in
order to maximally reduce the peak power with a given BESS capacity by the previously
introduced method, while SPCC serves as input for the peak shaving scheduling. The new
threshold Sthresh,PCC is calculated using an iterative approach [20].
In Equation (8), every load of the vector SPCC is multiplied by σb to scale the PCC load
profile down to the dimensions of the load profile at a specific node b. The scaled-down
vector is denoted as SScaled,b .
Scomb,b = max(SScaled,b
t , Sbt ) ∀t (9)
Subsequently, Scomb
t serves as the input for the peak shaving operation strategy. Again,
the peak shaving thresholds of the industrial customers’ storage systems are recalculated
in order to maximally reduce the peak power with given capacities. The new threshold
Sthresh,comb is calculated using an iterative approach [20]. It must be noticed that this
strategy is less reliable for the reduction of the local peak load than strategy α, since the
BESS now also might be used to reduce the peak load at the PCC. However, this will be
discussed in more detail in Section 4.
All three energy management strategies used in this work are depicted in Figure 4.
All solid lines mark the results of the power flow analysis without BESS and the dashed
lines marks the results of the power flow analysis including a BESS at a specific node b.
The black solid line associated to the right y-axis shows the difference in power, covered by
the BESS. In this example, a BESS with an energy content of 100 kWh is used to shave the
peaks. The upper plot (a) shows the results for an exemplary industrial consumer if the
BESS operates in a stand-alone peak shaving mode. While in this study the BESS works
only in a real power operation, the apparent power is shown in the plot.
The solid line at subplot (b) shows the results for the power flow analysis at the PCC if
the BESS at the same node b operates in a grid-centered peak shaving mode. The difference
between with and without storage is very small due to the significantly higher load at
the PCC compared to the load at a specific node b, so the dashed line follows the solid
line almost exactly. The difference is displayed with the black solid line associated to the
right y-axis. The maximum difference is with 100.2 kVA slightly higher than the maximum
Electricity 2021, 2 580
power of the exemplary BESS. This is due to the fact that the BESS is placed at a specific
node b and because of this, less energy has to be transmitted from the PCC to this node.
This allows line losses to be reduced.
50 -75
0 -150
4000 (b) 150
3115 PCC power wo BESS
" power
3075
2000 06:30 0
1000 -75
0 -150
200 (c) 150
Comb. power wo BESS
" power
100 0
50 -75
0 -150
0 2 4 6 8 10 12 14 16 18 20 22 24
Hour of the exemplary day
Figure 4. Graphical representation of all three energy management strategies used in this study.
Subplot (a) shows an exemplary load profile for an industrial consumer at a specific node b. The
related power at the point of common coupling is displayed in subplot (b) and subplot (c) shows the
combined profile. The solid line marks the results of the power flow analysis without the battery
energy storage system (BESS) at a specific node b and the dashed line marks the results of the
power flow analysis including the BESS. The black solid line associated to the right y-axis shows the
difference in power, covered by the BESS.
The lower plot (c) shows the combined load profile Scomb
t (solid line) for an exemplary
industrial consumer, including the scaled load from the PCC. In the hours six to eight it can
be seen that the scaled load profile from the PCC is responsible for the peak. Consequently
the BESS shaves this peak and therefore ensures a lower peak load at the PCC. As with
strategy α, the BESS also manages to shave the local peak between hours 16 and 22 with the
combined strategy. Again the black solid line shows the difference in power, covered by the
BESS. Compared to the other two strategies, the BESS is stressed twice on this exemplary
day. The effects of this are discussed in the next chapter.
We choose a parameter set as follows: The storage investment costs pinvest BESS are set to
$
350 kWh as motivated by [21]. A project operation/depreciation period of tproj = 10 years
well covered by BESS-assisted peak shaving analysis studies presented by Martins et al. [9]
as well as degradation studies with the LFP:C battery cell is used herein [16,22].
In accordance with publicly available tariff tables provided by various distribution
$ rate has
grids in Germany, a peak demand charge of ppeak = 110 kVA ·a was chosen. The e
been set to 1 h−1 as described in Section 2.2. For the lithium-ion based BESS investigated
herein, we chose a value of unity for the this parameter yielding a well-balanced system
layout and shaving of distinguished power peaks. Battery cycling and energy throughput
$
is penalized using a weighting factor of wtp = 0.001 kWh in order that the BESS is not
dis(-charging) needlessly [23].
The boundary conditions of the BESS are described in the constraints Equations (11)–(15).
The actual energy content for a specific time step t of a BESS, denoted as Etactual,b , must remain
within the physical bounds of a storage system:
The actual energy content Etactual,b of a BESS is calculated by adding the net charged
charge,b
energy Et to the energy content of the previous time step and subtracting the dis-
discharge,b
charged energy Et . This energy conservation equation of a BESS is defined in
Equation (16).
charge,b discharge,b
Etactual,b = Etactual,b
−1 + Et − Et (16)
In order to derive the best-suited BESS system sizing, we have applied this formulation
(minimize (OBJ)) to the entire set of 72 scenarios. The linear optimization results in BESSs
capacities of less than 10 kWh for 40 out of the 72 customers. These small storage sizes
are neglected in this study, because the capacity is more in the range of home energy
storage systems and no longer in the range of industrial storage systems [24]. The cost
assumptions for the initial costs pinvest
BESS are therefore no longer valid. Furthermore, the
peak load reduction and thus the cost savings would be minor in these cases and therefore
are not considered further. Figure 5 visualizes relative peak shaving limits Sthresh,b in %
for all 32 BESS with a capacity above 10 kWh. The lower plot (b) shows the capacity for
just these BESS.
Electricity 2021, 2 582
(a)
100
80
70
60
(b)
100
Storage capacity in kWh
75
50
25
0
0 5 10 15 20 25 30
Battery energy storage system
Figure 5. Results of the component sizing optimization. The upper plot (a) shows the peak shaving
limits Sthresh,b in % of the original peak power for all 32 battery energy storage system (BESS) with a
capacity above 10 kWh. The lower plot (b) shows the capacity for just these BESS.
1.2
Local (α)
0.8
Centralized (β)
Combined (γ)
0.6
Local All
0.4 CentralizedAll
CombinedAll
0.2
-0.4
Figure 6. Relative peak load reduction for each simulation with various operating strategies for
the battery energy storage system (BESS). The reduction of the peak load at the local node b (=
location of the BESS) is plotted on the abscissa and the reduction of the peak load at the point of
common coupling (PCC) can be seen on the ordinate. The red crosses show the reduction if the BESS
is operated with strategy α. The blue crosses show the results for strategy β and the green ones for
the combined approach (Strategy γ). The filled circles show the reduction of the peak load at the
PCC if all 32 BESSs are integrated into the grid simultaneously.
Electricity 2021, 2 583
The red crosses show the reduction if the BESS is operated with strategy α. It can be
seen that the storage system reaches a reduction of the peak load at the associated node b
in all 32 simulations. In most of the cases no peak load reduction at the PCC can be reached.
The reason for this behavior is that in these cases the peaks in the load profile have a longer
duration and thus the energy content is the limiting factor. As described in Section 3 and
exemplary shown in Figure 4, the load profiles include reactive power, while the BESS in
this study operates with active power only.
The initial motivation for a peak power tariff was to smooth out power peaks in the
entire distribution grid. However, with this state-of-the-art peak shaving strategy only
one case shows a reduction at the PCC. Even with all 32 storage systems integrated in the
grid at the same time, only very small (13.63 kVA) improvements can be achieved with a
conventional peak shaving algorithm.
The reduction for strategy β is marked with blue crosses. Since only one very high
peak occurs at the PCC during the period under consideration, the change is almost
identical with all 32 storage systems and corresponds to the maximum possible discharge
power. Due to the fact that the BESS is located in different locations in the grid, line losses
can be reduced during discharge. This results in relative reductions above one. However,
for industrial customers themselves, the centralized algorithm never achieves a reduction
in the peak load in this simulation setting.
The green crosses show the reduction if the BESS is operated in accordance to the
newly developed combined approach (Strategy γ). In this case, both the local peak load
and the global peak load will be reduced. It can be seen that the reduction at the location of
the storage is nearly as high as with the state-of-the-art peak shaving strategy. However, a
significant peak load reduction in the PCC is now also achieved. The filled circles in the
figure show the reduction of the peak load at the PCC if all 32 BESSs are integrated into
the grid simultaneously. Again, due to the fact that only one very high peak occurs at the
PCC, the reduction with the centralized approach is almost the summed-up maximum
possible discharge power of all BESSs. In contrast, with the combined approach with a
reduction of 706.70 kVA, almost the same reduction is achieved as with the centralized
approach (868.02 kVA).
Figure 7 supports the statements from the relative reduction plot by showing the
absolute reduction for each simulation. The upper plot (a) shows the absolute peak load
reduction for each simulation if the BESS is operated with strategy α. It can be seen that
the peak reduction at the respective node b is minimum 5.05 kVA and maximum 53.3 kVA,
which results with the numbers of Section 3.4 in an annual revenue of approximately $ 555.5
to $ 5,858.6. However, with this state-of-the-art peak shaving strategy only simulation 13
achieves a reduction at the PCC with 13.6 kVA. All others fail to reduce the peak load at
the PCC. With the centralized approach (Strategy β), depicted in plot (b) the peak load at
the PCC is reduced by 10.4 kVA to 83.1 kVA. The industrial consumers peak load is not
reduced in any case, but is increased by up to 16.6 kVA in six cases.
The lower plot (c) shows the absolute peak load reduction for each simulation if the
BESS is operated with strategy γ. The red bars show the difference in peak load at a local
node b (=storage location), the blue bars show the peak load reduction at the PCC. The
industrial consumers peak load reduction differs only in two cases above 1.0 kVA. The
maximum occurs in simulation six with 2.8 kVA, which would result in a decreased annual
revenue of $ 308.0. However, with this combined approach the peak load at the PCC is
also reduced by 5.6 kVA to 56.7 kVA. Compared to the maximums before (53.3 kVA and
83.1 kVA), which both occurs at simulation six, the combined approach achieves a summed
up reduction of 107.2 kVA. Integrating all 32 BESSs to the grid simultaneously, a reduction
at the PCC of 706.7 kVA can be achieved.
Electricity 2021, 2 584
(a)
120
60
40
20
0
-20
(b)
120
" Peak load in kVA
100 Local
80 PCC
60
40
20
0
-20
(c)
120
Local
" Peak load in kVA
100
PCC
80
60
40
20
0
-20
5 10 15 20 25 30
Battery energy storage system
Figure 7. The upper plot (a) shows the absolute peak load reduction for each simulation if the
battery energy storage system (BESS) is operated with strategy α. Plot (b) shows the results for the
centralized approach (Strategy β). The lower plot (c) shows the absolute peak load reduction for
each simulation if the BESS is operated with the newly developed combined approach (Strategy γ).
The red bars show the difference in peak load at a local node b, the blue bars show the peak load
reduction at the point of common coupling (PCC).
To evaluate the reduction in detail, the additional stress on the energy storage must
also be considered. Figure 8 shows the results for all simulations using various key
characteristics, which have been defined in a previous publication [14]. Subplot (a) shows
the number of full equivalent cycles and the mean round-trip efficiency is displayed in
subplot (b). The remaining characteristics describe the stress on the BESSs in greater detail.
Subplot (c) shows the average cycle depth in discharge direction and the average resting
time between two actions is illustrated in subplot (d). The number of alternations between
charging and discharging (sign changes) per day is indicated in subplot (e), while subplot
(f) shows the energy in relation to the BESS capacity that is charged or discharged between
sign changes, respectively.
The highest peak at the PCC is 40.9 MVA and thus 1.4 MVA higher than the second
highest peak. Consequently, all BESSs at the centralized approach (Strategy β) are only able
to reduce this one maximum 15-minute peak and therefore only one sign change occurs.
This also results in high resting times for the six month simulation period. Due to the losses
in the storage system the total number of full equivalent cycles is 0.28 and consequently
the cycle depth in discharge direction is 28% with a storage systems erate of one.
Comparing the results for strategy α and strategy γ, it can be seen that the BESSs
have on average 1.2 full equivalent cycles more than the storage systems operating with a
conventional peak shaving strategy. In the case of the LIB used, this results in a deviation
in the remaining capacity of 0.01% (95.31 to 95.32) for the six month simulation period due
to the high cycle stability. Resulting from very low additional stress on the storage system,
there are hardly any differences for almost all other key characteristics. Only the duration
Electricity 2021, 2 585
of the resting times between two actions falls significantly from 237.8 h to 131.3 h. However,
this average resting time is still quite long and the storage systems remain underutilized
with both strategies and it should be considered to use these to achieve additional revenues
by using a multi-use approach [25]—a topic beyond the scope of this study.
(a) (b)
20 90
Full equivalent cycles
System efficieny in %
15
10 85
0 80
Local (α) Centralized (β)Combined (γ) Local (α) Centralized (β)Combined (γ)
25
10
DOCdis in %
trest in min
20
15 5
10
0
Local (α) Centralized (β)Combined (γ) Local (α) Centralized (β)Combined (γ)
(e) (f)
30
E swapsign(pos.) in %
2
nswapsign per day
25
1.5
20
1
15
0.5
10
0
Local (α) Centralized (β)Combined (γ) Local (α) Centralized (β)Combined (γ)
Figure 8. Detailed results about the additional stress on the battery energy storage systems (BESSs)
for a six month simulation period. Subplot (a) shows the number of full equivalent cycles and the
mean round-trip efficiency in % is displayed in subplot (b). Subplot (c) shows the average cycle depth
in discharge direction in % and the average resting time in minutes between two actions is illustrated
in subplot (d). The number of alternations between charging and discharging (sign changes) per day
is indicated in subplot (e). Finally, subplot (f) shows the energy in relation to the BESS capacity that
is charged between these sign changes.
Results show that with strategy γ both the local peak load and the global peak load
can be reduced. The reduction at the location of the storage is nearly as high as with
strategy α. With strategy γ the peak load at the PCC is reduced by 5.6 kVA to 56.7 kVA and
the total reduction is always higher than with strategy α or strategy β. Although in this
scenario the BESSs reduce both peaks, the additional stress for the six month simulation
period is on average only 1.2 full equivalent cycles higher. This additional stress results in
slightly higher aging (0.01%) with the used LIB.
Accelerated aging as well as adaptions in the energy management systems would
have to be compensated financially by the grid operator to the storage owner or indus-
trial consumer. However, it must be taken into account that the grid operator benefits
economically by being able to avoid a possible grid reinforcement or transformer upgrade.
The framework shown in this study requires communication (e.g., via the 5G communi-
cation standard [26,27] or the IEC 60870 standard [28]) between the grid operator and its
current load at the PCC and the industrial consumer including the storage system. In
addition, the algorithms introduced in this study require the creation of an economic and
legal framework.
Abbreviations
AC alternating current
Electricity 2021, 2 588
References
1. Bollen, M.; Rönnberg, S. Hosting Capacity of the Power Grid for Renewable Electricity Production and New Large Consumption
Equipment. Energies 2017, 10, 1325. [CrossRef]
2. Benetti, G.; Caprino, D.; Della Vedova, M.L.; Facchinetti, T. Electric load management approaches for peak load reduction: A
systematic literature review and state of the art. Sustain. Cities Soc. 2016, 20, 124–141. [CrossRef]
3. Brinkel, N.; Schram, W.L.; AlSkaif, T.A.; Lampropoulos, I.; van Sark, W. Should we reinforce the grid? Cost and emission
optimization of electric vehicle charging under different transformer limits. Appl. Energy 2020, 276, 115285. [CrossRef]
4. Nykvist, B.; Nilsson, M. Rapidly falling costs of battery packs for electric vehicles. Nat. Clim. Chang. 2015, 5, 329–332. [CrossRef]
5. Mehr, T.H.; Masoum, M.A.; Jabalameli, N. Grid-connected Lithium-ion battery energy storage system for load leveling and peak
shaving. In Proceedings of the 2013 Australasian Universities Power Engineering Conference (AUPEC), Hobart, TAS, Australia,
29 September–October 2013; pp. 1–6. [CrossRef]
6. Oudalov, A.; Cherkaoui, R.; Beguin, A. Sizing and Optimal Operation of Battery Energy Storage System for Peak Shaving
Application: 2007 IEEE Lausanne Power Tech. In Proceedings of the IEEE PowerTech, 2007 IEEE Lausanne, Lausanne, Switzerland,
1–5 July 2007; pp. 1–5. [CrossRef]
7. Mamun, A.; Narayanan, I.; Wang, D.; Sivasubramaniam, A.; Fathy, H.K. Multi-objective optimization of demand response in a
datacenter with lithium-ion battery storage. J. Energy Storage 2016, 7, 258–269. [CrossRef]
8. Tiemann, P.H.; Bensmann, A.; Stuke, V.; Hanke-Rauschenbach, R. Electrical energy storage for industrial grid fee reduction—A
large scale analysis. Energy Convers. Manag. 2020, 208, 112539. [CrossRef]
9. Martins, R.; Hesse, H.; Jungbauer, J.; Vorbuchner, T.; Musilek, P. Optimal Component Sizing for Peak Shaving in Battery Energy
Storage System for Industrial Applications. Energies 2018, 11, 2048. [CrossRef]
10. Danish, S.M.S.; Ahmadi, M.; Danish, M.S.S.; Mandal, P.; Yona, A.; Senjyu, T. A coherent strategy for peak load shaving using
energy storage systems. J. Energy Storage 2020, 32, 101823. [CrossRef]
11. Kucevic, D.; Englberger, S.; Sharma, A.; Trivedi, A.; Tepe, B.; Schachler, B.; Hesse, H.; Srinivasan, D.; Jossen, A. Reducing grid peak
load through the coordinated control of battery energy storage systems located at electric vehicle charging parks. Appl. Energy
2021, 295, 116936. [CrossRef]
12. Naumann, M.; Truong, C.N.; Schimpe, M.; Kucevic, D.; Jossen, A.; Hesse, H.C. SimSES: Software for techno-economic Simulation
of Stationary Energy Storage Systems. In International ETG Congress 2017; ETG-Fachbericht; VDE: Berlin/Offenbach, Germany,
2017; pp. 442–447.
13. Müller, U.P.; Schachler, B.; Scharf, M.; Bunke, W.D.; Günther, S.; Bartels, J.; Pleßmann, G. Integrated Techno-Economic Power
System Planning of Transmission and Distribution Grids. Energies 2019, 12, 2091. [CrossRef]
Electricity 2021, 2 589
14. Kucevic, D.; Tepe, B.; Englberger, S.; Parlikar, A.; Mühlbauer, M.; Bohlen, O.; Jossen, A.; Hesse, H. Standard battery energy storage
system profiles: Analysis of various applications for stationary energy storage systems using a holistic simulation framework.
J. Energy Storage 2020, 28, 101077. [CrossRef]
15. Murata. Data Sheet of Sony Fortelion US26650FTC1 Battery Cell; Murata: Kyoto, Japan, 2017.
16. Naumann, M.; Spingler, F.B.; Jossen, A. Analysis and modeling of cycle aging of a commercial LiFePO4 /graphite cell.
J. Power Sources 2020, 451, 227666. [CrossRef]
17. Notton, G.; Lazarov, V.; Stoyanov, L. Optimal sizing of a grid-connected PV system for various PV module technologies and
inclinations, inverter efficiency characteristics and locations. Renew. Energy 2010, 35, 541–554. [CrossRef]
18. German Federal Office of Justice. Stromnetzentgeltverordnung. (In German). Avaiable online: https://www.gesetze-im-internet.
de/stromnev/BJNR222500005.html (accessed on 2 November 2021)
19. Tuunanen, J.; Honkapuro, S.; Partanen, J. Power-based distribution tariff structure: DSO’s perspective. In Proceedings of the 2016
13th International Conference on the European Energy Market (EEM), Porto, Portuga, 6–9 June 2016; pp. 1–5. [CrossRef]
20. Collath, N.; Englberger, S.; Jossen, A.; Hesse, H. Reduction of Battery Energy Storage Degradation in Peak Shaving Operation through
Load Forecast Dependent Energy Management; NEIS 2020, Ed.; VDE/ETG: Hamburg, Germany, 2020; pp. 1–6.
21. Mongird, K.; Viswanathan, V.; Balducci, P.; Alam, J.; Fotedar, V.; Koritarov, V.; Hadjerioua, B. An Evaluation of Energy Storage
Cost and Performance Characteristics. Energies 2020, 13, 3307. [CrossRef]
22. Naumann, M.; Schimpe, M.; Keil, P.; Hesse, H.C.; Jossen, A. Analysis and modeling of calendar aging of a commercial
LiFePO4/graphite cell. J. Energy Storage 2018, 17, 153–169. [CrossRef]
23. Vetter, J.; Novák, P.; Wagner, M.R.; Veit, C.; Möller, K.C.; Besenhard, J.O.; Winter, M.; Wohlfahrt-Mehrens, M.; Vogler, C.;
Hammouche, A. Ageing mechanisms in lithium-ion batteries. J. Power Sources 2005, 147, 269–281. [CrossRef]
24. Figgener, J.; Stenzel, P.; Kairies, K.P.; Linßen, J.; Haberschusz, D.; Wessels, O.; Angenendt, G.; Robinius, M.; Stolten, D.; Sauer, D.U.
The development of stationary battery storage systems in Germany—A market review. J. Energy Storage 2020, 29, 101153.
[CrossRef]
25. Englberger, S.; Jossen, A.; Hesse, H. Unlocking the Potential of Battery Storage with the Dynamic Stacking of Multiple Applications.
Cell Rep. Phys. Sci. 2020, 1. [CrossRef]
26. Gheisarnejad, M.; Khooban, M.H.; Dragicevic, T. The Future 5G Network-Based Secondary Load Frequency Control in Shipboard
Microgrids. IEEE J. Emerg. Sel. Top. Power Electron. 2020, 8, 836–844. [CrossRef]
27. Garau, M.; Anedda, M.; Desogus, C.; Ghiani, E.; Murroni, M.; Celli, G. A 5G cellular technology for distributed monitoring
and control in smart grid. In Proceedings of the 2017 IEEE International Symposium on Broadband Multimedia Systems and
Broadcasting (BMSB), Cagliari, Italy, 7–9 June 2017; pp. 1–6. [CrossRef]
28. Hänsch, K.; Naumann, A.; Wenge, C.; Wolf, M. Communication for battery energy storage systems compliant with IEC 61850.
Int. J. Electr. Power Energy Syst. 2018, 103, 577–586. [CrossRef]