Appendix D - Makai-DWD - Final Report - May29 - RevB
Appendix D - Makai-DWD - Final Report - May29 - RevB
FOR THE
DEEP WATER DESAL PROJECT
Prepared For
Prepared By
MAKAI OCEAN ENGINEERING, INC.
PO Box 1206, Kailua, Hawaii 96734
Intake - Preferred
Figure 2-1. Plan view of the location of the preferred and alternate intake and discharge pipeline alignments for Deep Water Desal in Moss Landing. The dashed black lines are tunneled discharge pipes across the
harbor to the existing pipeline and easement. The solid black line follows the alignment of the existing pipeline within the easement, with two potential discharge locations shown as black dots. The solid
green lines are the intake pipelines from both wet well locations with a red dot showing the intake location. The yellow dashed line demarcates the approximate limit of horizontal directional drilling (HDD)
capabilities (6,000’ or 1.8km) under satisfactory geological conditions, measured from the preferred wet well location. The dark bathymetry contours are in meters (10m intervals) and the lighter numbers
and contours are in fathom from NOAA nautical charts. An existing power and communications cable buried under the seafloor using HDD and belonging to MBARI is shown in pink.
Discharge Pipe Dimensions Single 36‐inch diameter line (maintain velocity <6 fps.)
Figure 2-2 Gravity Concrete Anchors for an HDPE pipe at Keahole Pt., Hawaii.
In shallow water (typically <50m) the required anchoring for wave loads can exceed the maximum
deployable weight. Site conditions for offshore Moss Landing obtained from the U.S. Army Corps
of Engineer’s Wave Information Studies (WIS) reveal design waves of 8.4 meters and 18 second
period. Figure 2-3, below, shows the WIS data used for this study. Makai performed
hydrodynamic calculations and found the forces exceed the frictional holding power of the
concrete gravity anchors. Additional anchoring will be required such as rock bolts or driven piles.
Both hollow bar and rock bolt anchors are installed by drilling an oversized hole into the seabed,
inserting a threaded steel bar anchor of prescribed length and then filling the annular hole with
grout to form a corrosion resistant and structurally strong connection to the seafloor. An illustration
showing the use of hollow bar anchors is shown in Figure 2-4. These anchors obtain the greatest
holding power in hard bottoms made up or rock or limestone.
Manta Ray anchors are one type of sand embedment anchor. They are installed by driving the
anchor into the seabed using a jack hammer, removing the driving rod and then pulling up on the
attached anchor rod to rotate and set the anchor deep in the seafloor. Often Manta Rays are
installed by first pre-drilling a hole to reduce the anchor installation loads. A hydraulic loading unit
is used to pull up on and set the anchor. The anchor is set when it has rotated into a horizontal
orientation. Manta Ray anchors are shown in Figure 2-5.
A last anchoring method considered was the use of driven steel pipe piles to hold the pipeline in
place in the shallow zone. One way of attaching piles to the pipe weights to obtain additional
anchoring is shown in Figure 2-6. Driven piles are installed on either side of the weight and
connected with chain and turnbuckles to pipe. The piles are heavy steel pipes of at least 20’ length
that are driven into the seafloor from a moored or jack-up barge. Once mobilized at the site, pile
anchors can be quickly installed if no adverse sub-bottom condition (rock) is encountered. Pile
anchor installation is limited to diver depths as all connections between the piles and the pipe are
made up by divers.
There are other types of post-deployment anchors available such as large concrete mats that are
placed over the pipe after deployment. However, any system that depends upon gravity and the
weight of concrete for anchoring is usually much less effective in terms of anchoring per unit cost
than the methods described here.
The above anchoring methods can be used on both the exposed pipe on the seafloor after it leaves
the HDD tunnel and securely anchor the intake structure and discharge diffuser pipe section in
place.
Use of HDD technology will require an onshore area of at least 150’ by 100’ and a source of
freshwater for mixing the drill mud. In addition to the drilling rig, this space is used to house a
drilling fluid cleaning and recirculation unit, drill pipe trailer, water truck, hoses, pumps, driller’s
van, excavator and vacuum pump truck. An aerial view of a site performing HDD, illustrating the
space requirements, is shown in Figure 3-2.
Ideally, the tunnel would breakout as deep as is possible – as close to the required intake and
discharge depths as possible. The breakout depth for tunneling will be deeper than for a trenched
pipeline as there is only a small additional cost to extend the tunnel to a deeper depth, and the
added depth will provide the advantages of smaller hydrodynamic loads and thus reduced
anchoring requirements.