Design Guide For Line Sizing of Power Plant Piping
Design Guide For Line Sizing of Power Plant Piping
REV. R0 R1 R2 R3
NO.
ISSUE
CONTENTS
1.0 SCOPE 1
APPENDICES
ISSUE
R3
REVISION STATUS
R0 23.09.1983 --
ISSUE
R3
1.0 SCOPE
This design guide indicates guidelines for selecting pipe sizes for various
services and procedures for calculating pressure drop due to friction in
piping systems.
1.1 The procedure indicated for calculating pressure drop is valid only for
single-phase flows of Newtonian fluids. Further, incompressible fluids can
also be handled by the same procedure if the density variations are not
significant.
1.2 When density variations are significant, the pipeline can be broken up into
sections short enough to keep the pressure drop per section below 15%
of the initial pressure for the section and the average density may be
considered for each section. Such a treatment of compressible fluid flows
is again valid only when the acceleration effects are insignificant and do
not contribute to the pressure drop.
1.3 This document does not apply to cooling water and such lines where
Hazen-Williams equation is used.
1.4 For condensate recovery line sizing, refer TCE design guide document
no: M1-ME-CL-552-005.
1.5 For compressed air system line sizing, refer TCE design guide document
no: M6-ME-640-011.
ISSUE
R3
L Length of pipe m
Re Reynolds Number -
h Head drop m
The size of a pipeline is related to the flow handled by the pipeline through
the continuity equation as under:
1
2
4Mϑ
d = - Eq.3.1
Π 3600V
To determine the pipe size therefore, the volumetric flow M ϑ and the
velocity should be established.
4.1 In general, all possible operating modes of the plant, normal and abnormal
should be considered including planned and forced outages of equipment
or systems, thereupon, the design flow or flows should be established as
those which are critical from the point of view of system requirements
discussed subsequently.
It should be borne in mind that it is not the mass flow, which is important,
but the volumetric flow. High volumetric flows might occur inspite of the
mass flows being low when the specific volumes are large, as might be the
case during low loads.
4.2 In particular, the design flows considered should not be less than the
following requirements, as applicable.
5.1 As can be seen from the continuity equation, the larger the velocity the
smaller is the pipe size and hence lower is the piping cost. However, the
selection of a suitable velocity is governed by the following system
requirements.
(a) The calculated pipe line pressure drop should be within the system
permissible limits
(b) Where the system permissible limits have not been pre-determined
and where the total cost of system is significant, the line sizes may be
determined by optimising the line drop with the system/equipment
parameters so as to result in least capitalised cost, which shall include
installed cost, running cost and maintenance or replacement costs.
5.1.2 NPSH
High line velocities lead to line erosion, particularly in case of wet steam
and water.
5.1.5 Noise
ISSUE
R3
6.1 The following table gives the recommended ranges of velocities for
commonly encountered fluids:
6.2 The above table indicates ranges of velocity, which in some cases are
large. The following additional guidelines may be considered while
selecting a suitable value from the range.
6.2.1 For a given velocity, the pressure drop varies inversely with the pipe size.
Select lower values of velocities for smaller pipes.
6.2.2 When line pressures are low, select lower values of velocity to keep
ISSUE
R3
6.2.3 In case of short pipe runs, pressure drops are generally inconsequential.
Hence, high velocities can be selected.
6.2.4 For superheated steam lines, the upper limit is from noise considerations.
In case of pipelines located outdoor, higher values of velocity are
acceptable. In case of indoor piping where background noise is generally
low, use an upper limit of 50 m/s for steam velocity.
6.2.6 Steam lines for intermittent service can be designed with relatively higher
velocities since higher noise levels can be tolerated for short durations. In
specific cases where pressure drop considerations are unimportant,
velocities in excess of 75 m/s upto 100 m/s may also be considered. For
example LP Bypass downstream steam lines where higher velocities of
about 100 to 120 m/s are acceptable.
3
10 ρVd
Re = - Eq. 7.1
µ
3
10 .Vd
Re = - Eq. 7.2
ϑµ
Viscosity of the gas / liquid / steam under consideration shall be taken from
the Handbook or Crane – ‘Flow of Fluids’.
When the Reynolds Number for a flow through a closed conduit is less
than 2000, the flow is said to be LAMINAR. When the Reynold’s number
exceeds 4000, the flow is called TURBULENT. In between the values of
2000 and 4000, the flow could be either laminar or turbulent depending
upon several factors. Such flows are called TRANSIENT flows.
ISSUE
R3
64
f = - Eq.7.3
Re
7.3.3 The friction factor for transient flows is indeterminate and has lower limits
based on laminar flow and upper limits based on turbulent flow conditions.
For purposes of design, transient flows are best treated as turbulent flows.
The pressure drop in a straight pipe due to frictional flow of a fluid is given
by the following generalised formula known as DARCY or FANNING
formula:
−4 2
10 fLV ρ
∆Ρ = - Eq. 7.4
2gd
−4 2
10 fLV
∆Ρ = - Eq. 7.5
2g ϑd
2
fLV
h = - Eq. 7.6
2gd
The above expression is more commonly used in the case of liquid flows.
length of the pipe. Pressure drops across valve and fittings are
experimentally determined and are expressed in terms of velocity heads.
Thus, the pressure drop ‘h’ across a valve or fitting is obtained as
2
KxV
h= - Eq. 7.7
2g
7.6 AGEING
While sizing pipelines for water service, the likely increase in pressure drop
with the ageing of the pipe due to increase in pipe roughness, encrustation
of pipe with scale, dirt, foreign matter etc. should be considered. The
extent of increase in pressure drop is difficult to predict with any accuracy.
However, inadequate allowances would result in shortfall in capacity at a
future date. On the other hand, excessive allowances result in over sizing
of piping, which besides increasing piping costs could lead to pumps
operating at well above design capacities.
Long Radius elbow with radius 1.5D can be considered for any system
unless the pressure drop is critical. If the pressure drop is critical as in
reheat steam line, then bends with radius 3D are preferred.
ISSUE
R3
7.8 FORMATS
Form 070 has been designed to carry out pressure drop calculations.
The total mass flow indicated in the form shall be established based on the
recommendations of Section 4.0 of this guide.
8.1.1 The boiler outlet pressure and temperature are obtained from boiler
manufacturer, the turbine inlet pressure are obtained from heat balance
diagram (HBD). The Steam Generator Maximum Continuous Rating
(SGMCR) flows are obtained from boiler manufacturer and Valve Wide
Open (VWO) flow are obtained from HBD.
8.1.2 Where the boiler and turbine parameters are already fixed, the maximum
allowable pressure drop in the main steam line is also fixed. The main
steam pipe size is so selected to ensure that the actual pressure drop is
about 90% of the maximum allowable pressure drop at maximum
calculated or expected flow between superheater outlet and HP turbine
inlet. Pressure drop calculations shall be carried out for all guaranteed
conditions.
8.1.3 It must be noted that the superheated steam output of the boiler will
normally be somewhat greater than the throttle flow of the turbine
corresponding to (VWO) condition. Where the differential flow is tapped off
the main steam piping for auxiliary steam station, ejectors, etc., maximum
flows as applicable for individual sections must be considered for
computing line losses.
8.1.4 In cases where the calculated value of the pressure drop is only marginally
in excess of the allowed pressure drop, negotiate with the boiler contractor
for a slight increase in the Super Heater (SH) outlet pressure before
considering increasing main steam line size.
8.1.5 In case of captive power plants, boiler output could be much higher than
turbine requirements in order to meet process steam requirements or to
cater to future expansion or both. Design flows of steam piping should be
established after taking into account these aspects.
8.1.6 Where boiler and turbine parameters are not fixed, the SH outlet pressure
ISSUE
R3
is established after taking into account estimated line losses. The pressure
drop in the main steam piping generally varies between 5-7 percent of the
SH outlet pressure.
8.1.7 While computing the available pressure drop between boiler and turbine,
establish whether the boiler outlet pressure is at the outlet header or at the
contractual terminal point for supply. In case of turbines, establish whether
the turbine inlet pressure furnished by the turbine manufacturer includes
pressure drop across strainers, if any.
8.1.8 Besides piping and fittings, the important components to consider in the
calculation of pressure drop are Main Steam Stop Valve (MSV) and steam
flow nozzle. When no specific figures are available for the pressure drop
across the (MSV), a value of 0.3 kg/cm2 may be assumed for small
capacity plant upto 250MW generating capacity & 0.5 kg/cm2 may be
assumed for large capacity plant above 250MW generating capacity.
When no specific figures are available for the irrecoverable pressure drop
across main steam flow nozzle, a value of 0.3 kg/cm2 may be assumed.
Strainer if any on main steam piping, then drop across it will be generally
included in (HBD) by turbine vendor, but this has to be specifically
confirmed with turbine vendor.
8.1.10 For preliminary line sizing, a velocity of 50-60 m/s may be assumed.
8.2.2 Where the boiler and turbine parameters are already fixed the maximum
allowable pressure drops in the hot and cold reheat piping are also fixed.
The sizes of hot and cold reheat piping are so selected as to ensure that
the actual pressure drop is about 90% of the maximum allowable pressure
drop at maximum calculated or expected flows. Pressure drop calculations
shall be carried out for all guaranteed conditions.
8.2.4 It should be ensured that the total pressure drop in the reheat circuit is
ISSUE
R3
equal to or less than the available drop in other operating modes as well.
For instance, when steam to top HP heater is taken from cold reheat line,
for the operating condition of top heater being out of service, flow in the
reheat circuit may be greater than for the condition all heaters being in
service, the turbine output being equal to rated value in both cases.
8.2.5 Where boiler and turbine parameters are not fixed or are not firm the sizing
of the cold and hot reheat piping should be carried out in parallel. The total
permissible pressure drop in the reheat circuits is available from the
turbine heat balance diagrams. It is generally about 10% of the absolute
pressure of steam leaving the high-pressure turbine. From this figure, the
drop across reheater must be deducted to obtain the maximum available
drop for the reheat piping. If reheater drop is not known or can be
specified, approximately 40-50 percent of the total drop in the reheat circuit
can be assumed to be the drop across the reheater. The balance is
suitably divided between the cold and hot reheat pipes in such a way as to
minimise cost. It is apparent that hot reheat piping is substantially costlier
than cold reheat piping. Further, due to higher temperatures, flexibility
problems are greater with hot reheat piping. Therefore, the size of the hot
reheat line should be kept as small as feasible.
Pressure drop in the hot reheat piping could be between 2 to 4 times the
pressure drop in the cold reheat piping.
(a) Strainer if any on hot reheat piping, then drop across it will be generally
included in (HBD) by turbine vendor, but this has to be specifically
confirmed with turbine vendor.
(b) Non return valve on cold reheat piping
(c) The Pressure drop across emergency attemperator in cold reheat
piping may be taken as 0.1 kg/cm^2 and same has to be confirmed
from boiler manufacturer.
8.3 EQUALISING LINE
8.3.1 Equalising line is the interconnecting line between the two main steam
inlets to HP Turbine and similarly between the two hot reheat inlets to IP
Turbine. This line is generally adopted in double lead system from boiler
to turbine. This line is provided to enable load testing of the Emergency
Stop Valve (ESV) & Interceptor Control Valve (IV) one after the other. This
ISSUE
R3
line also enables to balance the pressure in the two individual leads during
transient conditions. It will also minimize the variation of temperature
between the two leads from the boiler.
8.3.2 The Design flow for equalizing line may be considered as half of the flow
generated during 80% load condition i.e during ESV load testing period.
The other parameters like pressure & temperature will be same as in main
line.
8.3.3 As the pressure drop is not the criteria, so the design velocity may be
considered on the upper limit of recommended range of velocities
mentioned in this design guide.
8.4.1 The turbine outlet pressure, temperature and heater inlet pressure,
temperature is obtained from HBD. The design flow is obtained from HBD.
8.4.2 Where the turbine cycle parameters are already fixed, the sizes of
extraction piping should be selected so as to ensure that the pressure drop
in the piping is equal to or less than the allowable pressure drop between
turbine nozzle and extraction feed heater inlet nozzle at maximum flows.
8.4.3 It should be ensured that the line sizes selected are suitable for all
operating modes of the plant, viz. VWO, rated output, individual heater out
of service, lowest CW temperature, maximum make up, etc.
8.4.4 As the turbine output falls, the extraction flows decrease, but so also do
the extraction pressures. Check calculations for all modes of operation
including part load conditions to ensure that the line velocities do not rise
to prohibitive levels.
8.4.5 Where turbine cycle parameters are not finalised, a line drop of 3 to 5
percent of extraction steam line outlet pressure at turbine at maximum
extraction flows may be assumed for purpose of line sizing.
ISSUE
R3
8.5.1 The design flow for turbine bypass piping depends on the capacity of the
bypass station. Thus, the flow upstream of the HP and LP bypass
pressure reducing valves should equal the capacity of these valves. When
the desuperheating spray is introduced into the pressure reducing valves
for attemperation, the downstream design flow shall be equal to the
upstream design flow, plus the spray water flow. Where external
(independent) desuperheaters are used, the design flow downstream of
the pressure reducing valves upto the desuperheater is the same as the
upstream design flow. Design flow downstream of the desuperheater is
obtained by adding spray water flow to the upstream design flow.
8.5.2 The steam pressures upstream of the HP and LP bypass valves at the
design flows are same as that as main steam and hot reheat system
respectively. The steam pressure downstream of the HP bypass valve is
equal to the set pressure of LP bypass valve plus the losses in the reheat
circuit or CRH pressure, whichever is lower for line sizing. The steam
pressure downstream of the LP bypass valve should be ascertained from
the Vendor (Turbine Vendor). Downstream pressure of the LP bypass
valve is, in general, much greater than the condenser pressure due to the
drop across the steam throw-off device located inside the condenser.
8.5.4 Since the bypass valves are only in intermittent service, high velocities
corresponding to the upper limit of the range recommended in Section 6.0
of this guide may be assumed. In case of piping downstream of LP bypass
valves, due to the high mass flows and high specific volumes, the design
velocity can be increased upto 100 m/s if necessary to keep the pipe sizes
reasonable.
8.5.5 It is obvious that pressure drops in the pipeline are not a major
consideration in the sizing of the bypass piping.
ISSUE
R3
8.6.1 The auxiliary PRDS station has two salient modes of operation based on
which it is sized :
(a) Cold start up of the TG unit. Here, although the mass flows are less
than the capacity of the PRDS station, boiler pressure is also low
resulting in high specific volume.
The sizing of the steam line to PRDS shall consider both the above modes.
8.6.2 Normal flow through the PRDS is much less than the rated capacity.
Velocity in the steam line to PRDS at design flow can be taken as high as
the upper limit of the recommended range.
8.6.3 Steam line downstream of the desuperheater upto the auxiliary steam
header should be considered as handling wet steam for purposes of
selection of design velocities.
8.6.4 Steam lines from the header to individual consumers other than
deaerator/feed water tank should be designed so as to drop not more than
60 percent of the maximum allowed pressure drop at their design flows.
8.6.5 Steam line to deaerator should be designed for the following modes of
operation as applicable :
8.7.1 On individual pump discharge lines, the design flow should be equal to the
rated capacity of the feed pump. On common discharge line to heaters
and economiser, the design flow should be the rated capacity of the feed
control valve.
ISSUE
R3
8.7.2 In plant where no feed control valve is envisaged, the design flow of the
common line may be taken as 1.3 times the boiler MCR output.
8.7.3 The velocity in the feed water piping should be limited to 6 m/s at the
design flow.
8.8.1 For preliminary line sizing, use a line velocity of 1 to 1.5 m/s
8.8.2 The pressure drop in the suction piping shall be such as to meet the NPSH
requirements of the boiler feed pumps under all operating conditions,
steady state and transient.
Transient conditions are said to occur when the steam supply to deaerator
is not commensurate with the demand set by the inflows into the deaerator
and the pressure in the deaerator/feed water tank starts decaying as a
result. Such conditions can arise when the steam supply to the deaerator is
cut off or preheating of condensate in the low pressure heaters of the feed
cycle is stopped as might happen on a turbine trip out and turbine bypass
station coming on line.
8.8.3 From the point of view of steady conditions, larger suction line sizes lead to
lower line velocities and hence lower friction drops, thus lower improving
NPSH availability. On the other hand, lower line velocities lead to
increased residence time of the fluid in the suction piping and worsen the
NPSH availability under transient conditions. Since the suction strainer
accounts for a higher percentage of the total pressure drop, it is
recommended to install large suction strainers with high straining area/pipe
flow area ratios in order to minimise friction drop. The line sizes may then
be finalised to suit the transient operating conditions.
8.8.4 For optimum designs, the feed water tank elevation and the NPSH
requirements under steady state and transient operating conditions should
be studied in combination with the feed water tank storage capacity and
the suction line size.
8.8.5 When more than one feed pump is designed to be in operation at any time
(parallel operation of pumps), NPSH calculations shall be carried out for
the condition of one of the operating pumps having tripped and the standby
pump having failed to come into service.
8.9.2 For NPSH calculations, consider the maximum flow corresponding to the
ISSUE
R3
8.9.3 In the case of more than one pump operating in parallel, NPSH
calculations shall be carried out for the condition of one of the operating
pumps having tripped and the standby having failed to come into service.
8.10.1 The most important consideration is to reduce the pressure drop in the
decantation header to negligible value so as to enable unloading of oil from
all wagons as nearly at an equal rate as possible.
8.10.2 Consider several header sizes and compute the total loss in the header for
each size. Select the size beyond which any increase in header size does
not result in any significant reduction in the pressure drop in the header.
8.10.3 Check the header size selected from the point of view of layout of piping
between wagon outlet and pump inlet. The layout shall be such as to result
in no high points in the system and header to slope towards pump suction.
8.10.4 Although the flow in the header varies from section to section depending
on the number of wagons contributing to the header flow, adopt a uniform
size for the entire length of the header.
8.11.1 The line size for the delivery piping shall be selected after optimising the
installed cost of piping, valves, pumps and motors and the pumping cost.
Example for optimising pipe size on pump delivery is given in Appendix-2.
8.11.2 While computing the pumping cost, it should be noted that the pumps are
in intermittent service.
8.12.1 The pressure drop in gas lines is generally large relative to the inlet or
source pressure and for these cases the Darcy equation will not give
accurate results. Weymouth formula, which is derived from isothermal
equations, gives more accurate results since the flow of gases in long
pipelines closely approximates isothermal conditions. The line size of fuel
gas piping is done generally using Weymouth formula.
ISSUE
R3
8.12.3 Gas line velocity to be maintained is indicated in table 6.1. Where the
pressure drop criteria determine the gas line sizing, velocity range closer to
lower limit of 10m/s to be adopted. For other cases, closer to 30m/s can be
maintained to economise the pipe line size.
8.12.5 Density of gas (ρ) at any given pressure (P’) is calculated as below:
ρ = P’ ----- Eq.8.2
RT
Where,
P’ – Pressure in Newtons per square metre (pascals) absolute
R – Individual gas constant = Ro / M in J/kg K
T --Temperature in Kelvins
Ro = 8314 J/kg-mol K
M -- Molecular weight of gas
ISSUE
R3
APPENDIX-1
1. PIPE FRICTION DATA FOR CLEAN COMMERICAL STEEL PIPE WITH FLOW IN ZONE
OF COMPLETE TURBULENCE
For connecting pipe sizes different from those listed above `K’ factor for valve
& fittings would be as follows:
4
( )
da
Ka = Kb
db
ISSUE
R3
d2
d2
d1
d2
0
If: = 1, € = O ……………………………… K1 = 8fT
(
d1
< 1 and € < 45O ……………………… K2 = Formula 5 =
d2 )
< 1 and 45O < € < 180 O ……… K2 = Formula 6
d2
d1
2
d1
K = 100 fT K = 50 fT
K factors for other type of valves refer Appendix-A of ‘Flow of Fluids’ of Crane
ISSUE
R3
• Formula 1
θ (1 -
0.8(sin ) K1
K2 = 2 ) =
• Formula 2
θ
0.5(1 - ) (sin ) K1
2
K2 = =
• Formula 3
θ (1 - )
2.6 (sin ) K1
2
K2 = =
• Formula 4
(1 - ) K1
K2 = =
• Formula 5
K1
K2 = + Formula 1 + Formula 3
θ
K1 + sin [0.8(1 - ) + 2.6(1 - )
2
K2 =
ISSUE
R3
• Formula 6
K1
K2 = + Formula 2 + Formula 4
K2 θ (I - ) + (1 - )
K1 + 0.5 sin
2
=
• Formula 7
K1
0
K2 = + Formula 2 + Formula 4) When θ = 180
K1 + [0.5 (1 - ) + 2.6(1 - ) ]
K2 =
d1
=
d2
( )
2
d1 a1
2
= =
d2 a2
Above formulae and data are taken from “Flow of Fluids” – Crane
(Technical paper No. 410)
Example for calculation of `K’ factor for valves with reduced port is enclosed in
Appendix - 3
ISSUE
R3
a2 a1
d2
d1
If: € < 45O ……………………. K2 = Formula 1
45
O
< € < 180O …….. K2 = Formula 2
a1 a2
d2
d1
€ < 45 …………………….
O
If: K2 = Formula 3
45
O
< € < 180O ……. K2 = Formula 4
K = 30 fT K = 16 fT
ISSUE
R3
KB = (n-1)(0.25*3.14*fT*r/d + 0.5K) + K
where n = Deg of the bend for which resistance coefficient has to be found.
_____________________________________________________
90°
o
K= resistance co-efficient of one 90 bend.
0.10 0.09
0.15 & up 0.04
ISSUE
R3
APPENDIX-2
l
(1+z) - 1
2.0 Capitalised Factor (c) = l
z (1+z)
(1+0.12)25 - 1
= = 7.843
0.12 (1+0.12) 25
From the above it can be observed that the total evaluated cost for NB 400 is the lowest.
ISSUE
R3
APPENDIX-3
CONNECTING PIPE
102
(6” NB x SH 80)
0° ID 146 mm
559
d1 102
= = = 0.69 = 0.48, = 0.23
d2 146
(146-102)
θ 2 44 θ
tan = = = 6.17
2 (559-152) 407 2
2
θ
sin = 0.11
2
K2 = Formula 5
θ
K1+sin
2
[0.8(1- (1-
=
8x0.015+0.11 [(0.8x0.52)+2.6(0.52)
=
= 1.06
ISSUE
R3