0% found this document useful (0 votes)
111 views27 pages

Design Guide For Line Sizing of Power Plant Piping

This document provides guidelines for selecting pipe sizes for power plant piping systems. It outlines procedures for calculating pressure drop due to friction, including defining key terms like mass flow, pipe diameter, velocity, density, viscosity, length, friction factor, Reynolds number, and pressure drop. Design flows should consider all possible plant operating modes and be sufficient to meet system requirements.

Uploaded by

ajiths89
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
111 views27 pages

Design Guide For Line Sizing of Power Plant Piping

This document provides guidelines for selecting pipe sizes for power plant piping systems. It outlines procedures for calculating pressure drop due to friction, including defining key terms like mass flow, pipe diameter, velocity, density, viscosity, length, friction factor, Reynolds number, and pressure drop. Design flows should consider all possible plant operating modes and be sufficient to meet system requirements.

Uploaded by

ajiths89
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 27

TATA CONSULTING ENGINEERS LIMITED SECTION: TITLE

TCE.M6-ME-590-406 DESIGN GUIDE FOR LINE SIZING OF POWER PLANT


SHEET i OF iii
PIPING

DESIGN GUIDE FOR LINE SIZING OF POWER PLANT PIPING

FILE NAME: M6ME406R3.DOC

REV. R0 R1 R2 R3
NO.
ISSUE

INITIALS SIGN. INITIALS SIGN. INITIALS SIGN. INITIALS SIGN.

PPD. BY RS Sd/- VS Sd/- MSR Sd/- AJN

CHD. BY BVR Sd/- DP Sd/- VS Sd/- MSR


R3
APD. BY TKR Sd/- MLN/RL Sd/- DVL/RL Sd/- GSK
/Sd/-

DATE 23.09.1983 28.04.2000 27.05.2003 03-02-2011


FILE NAME: M6ME406R3.DOC TCE FORM NO. 020 R4
SECTION:
TATA CONSULTING ENGINEERS LIMITED CONTENTS
TCE.M6-ME-590-406
DESIGN GUIDE FOR LINE SIZING OF POWER
SHEET ii OF iii
PLANT PIPING

CONTENTS

SL. NO. TITLE SH. NO.

1.0 SCOPE 1

2.0 UNITS & SYMBOLS 1

3.0 CONTINUITY EQUATION 2

4.0 DESIGN FLOW 2

5.0 SYSTEM REQUIREMENTS 3

6.0 RECOMMENDED RANGE OF VELOCITIES 4

7.0 CALCULATION OF PRESSURE DROP 5

8.0 SPECIAL CONSIDERATIONS FOR SELECTION OF 8


LINE SIZES IN POWER PLANTS

APPENDICES

1. VALUES OF RESISTANCE COEFFICIENTS 17

2. EXAMPLE FOR OPTIMISING PIPE SIZE 23

3. EXAMPLE FOR CALCULATING K FACTOR FOR 24


REDUCED PORT VALVES

ISSUE
R3

FILE NAME: M6ME406R3.DOC TCE FORM NO. 120 R3


SECTION: REV.
TATA CONSULTING ENGINEERS LIMITED STATUS
TCE.M6-ME-590-406
DESIGN GUIDE FOR LINE SIZING OF POWER
SHEET iii OF iii
PLANT PIPING

REVISION STATUS

REV. NO. DATE DESCRIPTION

R0 23.09.1983 --

R1 28.04.2000 Document completely revised and document


number changed.

R2 27.05.2003 Sizing of fuel gas lines and velocity range


for vacuum lines included. Appendix-1
updated. Motor efficiency included in
Appendix -2

R3 03-02-2011 Document generally revised

ISSUE
R3

FILE NAME: M6ME406R3.DOC TCE FORM NO. 120 R3


TATA CONSULTING ENGINEERS LIMITED SECTION: WRITE-UP
TCE.M6-ME-590-406 DESIGN GUIDE FOR LINE SIZING OF POWER
SHEET 1 OF 24
PLANT PIPING

1.0 SCOPE

This design guide indicates guidelines for selecting pipe sizes for various
services and procedures for calculating pressure drop due to friction in
piping systems.

1.1 The procedure indicated for calculating pressure drop is valid only for
single-phase flows of Newtonian fluids. Further, incompressible fluids can
also be handled by the same procedure if the density variations are not
significant.

1.2 When density variations are significant, the pipeline can be broken up into
sections short enough to keep the pressure drop per section below 15%
of the initial pressure for the section and the average density may be
considered for each section. Such a treatment of compressible fluid flows
is again valid only when the acceleration effects are insignificant and do
not contribute to the pressure drop.

1.3 This document does not apply to cooling water and such lines where
Hazen-Williams equation is used.

1.4 For condensate recovery line sizing, refer TCE design guide document
no: M1-ME-CL-552-005.

1.5 For compressed air system line sizing, refer TCE design guide document
no: M6-ME-640-011.

The systems discussed in this guide generally pertain to power plants.

2.0 UNITS AND SYMBOLS

Symbol Description Unit

M Mass flow kg/hr

d Internal Diameter of pipe m

ϑ Specific volume of fluid m3/kg

V Velocity of fluid m/sec

ρ Density of fluid kg/m3

µ Absolute viscosity of fluid Centipoise

ISSUE
R3

FILE NAME: M6ME406R3.DOC TCE FORM NO. 120 R3


TATA CONSULTING ENGINEERS LIMITED SECTION: WRITE-UP
TCE.M6-ME-590-406 DESIGN GUIDE FOR LINE SIZING OF POWER
SHEET 2 OF 24
PLANT PIPING

g Acceleration due to gravity m/sec2

L Length of pipe m

f Friction factor (Darcy) -

Re Reynolds Number -

∆P Pressure drop kg/cm2

h Head drop m

K Resistance coefficient of valve or fitting -

3.0 CONTINUITY EQUATION

The size of a pipeline is related to the flow handled by the pipeline through
the continuity equation as under:
1
2
4Mϑ
d = - Eq.3.1
Π 3600V

To determine the pipe size therefore, the volumetric flow M ϑ and the
velocity should be established.

4.0 DESIGN FLOW

4.1 In general, all possible operating modes of the plant, normal and abnormal
should be considered including planned and forced outages of equipment
or systems, thereupon, the design flow or flows should be established as
those which are critical from the point of view of system requirements
discussed subsequently.

It should be borne in mind that it is not the mass flow, which is important,
but the volumetric flow. High volumetric flows might occur inspite of the
mass flows being low when the specific volumes are large, as might be the
case during low loads.

4.2 In particular, the design flows considered should not be less than the
following requirements, as applicable.

4.2.1 System heat and/or mass balance diagrams.

4.2.2 Rated capacities of connected equipment such as pumps, compressors,


blowers, turbines, boilers etc.

4.2.3 Rated capacities of control valves, flow-limiting orifices, etc.


ISSUE
R3

FILE NAME: M6ME406R3.DOC TCE FORM NO. 120 R3


TATA CONSULTING ENGINEERS LIMITED SECTION: WRITE-UP
TCE.M6-ME-590-406 DESIGN GUIDE FOR LINE SIZING OF POWER
SHEET 3 OF 24
PLANT PIPING

5.0 SYSTEM REQUIREMENTS

5.1 As can be seen from the continuity equation, the larger the velocity the
smaller is the pipe size and hence lower is the piping cost. However, the
selection of a suitable velocity is governed by the following system
requirements.

5.1.1 Pressure Drop

(a) The calculated pipe line pressure drop should be within the system
permissible limits

(b) Where the system permissible limits have not been pre-determined
and where the total cost of system is significant, the line sizes may be
determined by optimising the line drop with the system/equipment
parameters so as to result in least capitalised cost, which shall include
installed cost, running cost and maintenance or replacement costs.

5.1.2 NPSH

Where applicable, the pipeline velocities and sizes shall be such as to


ensure that the NPSH requirements are less than available NPSH.

5.1.3 Pipe Line Erosion

High line velocities lead to line erosion, particularly in case of wet steam
and water.

5.1.4 Water Hammer & Surge Pressures

High line velocities result in significant pressure increases due to water


hammer or surge action.

5.1.5 Noise

High line velocities in case of piping carrying compressible fluids lead to


high noise levels.

5.2 Section 6.0 indicates recommended ranges of velocities for various


services and guidelines for selecting a suitable velocity from within the
range for preliminary line sizing. The procedure for line sizing is to first
select a preliminary size based on assumed velocity and then examine the
suitability of the selected size from the point of view of the various system
requirements discussed above. The smallest pipe size, which meets all the
system requirements, is the optimum size for the intended service.

ISSUE
R3

FILE NAME: M6ME406R3.DOC TCE FORM NO. 120 R3


TATA CONSULTING ENGINEERS LIMITED SECTION: WRITE-UP
TCE.M6-ME-590-406 DESIGN GUIDE FOR LINE SIZING OF POWER
SHEET 4 OF 24
PLANT PIPING

6.0 RECOMMENDED RANGE OF VELOCITIES

6.1 The following table gives the recommended ranges of velocities for
commonly encountered fluids:

Sl. No. Fluid Recommended velocity range


(m/s)
1.0 Steam
1.1 Superheated steam 40 to 75
1.2 Saturated 20 to 40
steam/Turbine exhaust
steam
1.3 Wet steam 20 to 30
1.4 HP / LP Bypass 100 to 120
downstream piping
2.0 Water
2.1 Pump suction 0.5 to 1.5
2.2 Pump delivery 1.0 to 3.0
2.3 Boiler feed discharge 3 to 6.0
2.4 City water 0.5 to 1.5
3.0 OIL
3.1 Heavy oil (heated) 1 to 2
3.2 Light oil 1 to 2
4.0 Gases
4.1 Compressed air 5 to 15
4.2 Fuel gas 10 to 30
5.0 Vacuum 100 to 200

6.2 The above table indicates ranges of velocity, which in some cases are
large. The following additional guidelines may be considered while
selecting a suitable value from the range.

6.2.1 For a given velocity, the pressure drop varies inversely with the pipe size.
Select lower values of velocities for smaller pipes.

6.2.2 When line pressures are low, select lower values of velocity to keep

ISSUE
R3

FILE NAME: M6ME406R3.DOC TCE FORM NO. 120 R3


TATA CONSULTING ENGINEERS LIMITED SECTION: WRITE-UP
TCE.M6-ME-590-406 DESIGN GUIDE FOR LINE SIZING OF POWER
SHEET 5 OF 24
PLANT PIPING

pressure drop also low. Conversely, at high line pressures, higher


velocities should be acceptable.

6.2.3 In case of short pipe runs, pressure drops are generally inconsequential.
Hence, high velocities can be selected.

6.2.4 For superheated steam lines, the upper limit is from noise considerations.
In case of pipelines located outdoor, higher values of velocity are
acceptable. In case of indoor piping where background noise is generally
low, use an upper limit of 50 m/s for steam velocity.

6.2.5 In case of high temperature and high-pressure steam piping, pipe


expansion will introduce problem of flexibility. Use of high velocity would
keep pipe sizes down and minimise flexibility problems but may create
flow-induced vibrations.

6.2.6 Steam lines for intermittent service can be designed with relatively higher
velocities since higher noise levels can be tolerated for short durations. In
specific cases where pressure drop considerations are unimportant,
velocities in excess of 75 m/s upto 100 m/s may also be considered. For
example LP Bypass downstream steam lines where higher velocities of
about 100 to 120 m/s are acceptable.

7.0 CALCULATION OF PRESSURE DROP

7.1 REYNOLDS NUMBER (Re)

It is a dimensionless number representing the ratio of inertial and viscous


forces governing a flow. It is calculated as:

3
10 ρVd
Re = - Eq. 7.1
µ

3
10 .Vd
Re = - Eq. 7.2
ϑµ

Viscosity of the gas / liquid / steam under consideration shall be taken from
the Handbook or Crane – ‘Flow of Fluids’.

7.2 TYPE OF FLOW

When the Reynolds Number for a flow through a closed conduit is less
than 2000, the flow is said to be LAMINAR. When the Reynold’s number
exceeds 4000, the flow is called TURBULENT. In between the values of
2000 and 4000, the flow could be either laminar or turbulent depending
upon several factors. Such flows are called TRANSIENT flows.
ISSUE
R3

FILE NAME: M6ME406R3.DOC TCE FORM NO. 120 R3


TATA CONSULTING ENGINEERS LIMITED SECTION: WRITE-UP
TCE.M6-ME-590-406 DESIGN GUIDE FOR LINE SIZING OF POWER
SHEET 6 OF 24
PLANT PIPING

7.3 FRICTION FACTOR (f)

7.3.1 For laminar flows, friction factor is defined by POISEUILLE’s law as

64
f = - Eq.7.3
Re

7.3.2 In case of turbulent flows, the friction factor cannot be expressed as a


mathematical relationship but is experimentally determined. It depends on
the Reynolds number (Re) of the flow, internal diameter of the pipe d, and
the roughness of the inner wall of the pipe. This relationship is expressed
in the form of a chart called MOODY’s chart.

7.3.3 The friction factor for transient flows is indeterminate and has lower limits
based on laminar flow and upper limits based on turbulent flow conditions.
For purposes of design, transient flows are best treated as turbulent flows.

7.4 PRESSURE DROP IN STRAIGHT PIPES

The pressure drop in a straight pipe due to frictional flow of a fluid is given
by the following generalised formula known as DARCY or FANNING
formula:

−4 2
10 fLV ρ
∆Ρ = - Eq. 7.4
2gd

−4 2
10 fLV
∆Ρ = - Eq. 7.5
2g ϑd

In the above equations, the pressure drop is expressed in units of kg/cm 2


and this form is used in case of gas flows. These equations may be
rewritten to express the pressure drop as head of the corresponding liquid
column.

2
fLV
h = - Eq. 7.6
2gd

The above expression is more commonly used in the case of liquid flows.

7.5 PRESSURE DROP IN VALVE AND FITTINGS

In equations 7.4 to 7.6, the pressure drop is expressed as a function of the


ISSUE
R3

FILE NAME: M6ME406R3.DOC TCE FORM NO. 120 R3


TATA CONSULTING ENGINEERS LIMITED SECTION: WRITE-UP
TCE.M6-ME-590-406 DESIGN GUIDE FOR LINE SIZING OF POWER
SHEET 7 OF 24
PLANT PIPING

length of the pipe. Pressure drops across valve and fittings are
experimentally determined and are expressed in terms of velocity heads.
Thus, the pressure drop ‘h’ across a valve or fitting is obtained as
2
KxV
h= - Eq. 7.7
2g

Where ‘K’ is defined as the resistance coefficient of valve or fittings.


Values of ‘K’ for commonly used valves and fittings are furnished in
Appendix-1. Use ‘K’ factor values furnished by supplier of valves/fittings
when available.

7.6 AGEING

While sizing pipelines for water service, the likely increase in pressure drop
with the ageing of the pipe due to increase in pipe roughness, encrustation
of pipe with scale, dirt, foreign matter etc. should be considered. The
extent of increase in pressure drop is difficult to predict with any accuracy.
However, inadequate allowances would result in shortfall in capacity at a
future date. On the other hand, excessive allowances result in over sizing
of piping, which besides increasing piping costs could lead to pumps
operating at well above design capacities.

The allowance to be provided depend on the following factors:

(a) Size of pipe


(b) Quality of water
(c) Proportion of friction drop to total system resistance
(d) Location of pipe – buried or above ground

Obviously, very large pipelines would be affected to a lesser extent than


smaller pipelines, since friction factor depends on relative roughness and
not on absolute roughness. Unfiltered water, corrosive/erosive water
would be far worse than clean, filtered water. It would be prudent to
provide for an increase over the calculated drop by a factor ranging from
1.1 to 1.4; the actual figure to be decided based on a judgement of the
actual conditions. An average figure of 1.25 may be considered for
average pipe sizes as encountered in power and process plants and
reasonably clean water.

7.7 SELECTION OF ELBOWS & BENDS

Long Radius elbow with radius 1.5D can be considered for any system
unless the pressure drop is critical. If the pressure drop is critical as in
reheat steam line, then bends with radius 3D are preferred.

ISSUE
R3

FILE NAME: M6ME406R3.DOC TCE FORM NO. 120 R3


TATA CONSULTING ENGINEERS LIMITED SECTION: WRITE-UP
TCE.M6-ME-590-406 DESIGN GUIDE FOR LINE SIZING OF POWER
SHEET 8 OF 24
PLANT PIPING

7.8 FORMATS

Form 070 has been designed to carry out pressure drop calculations.

The total mass flow indicated in the form shall be established based on the
recommendations of Section 4.0 of this guide.

8.0 SPECIAL CONSIDERATIONS FOR SELECTION OF LINE SIZES IN


POWER PLANTS

The following specific guidelines should be considered in the design of


power plant piping.

8.1 MAIN STEAM PIPING

8.1.1 The boiler outlet pressure and temperature are obtained from boiler
manufacturer, the turbine inlet pressure are obtained from heat balance
diagram (HBD). The Steam Generator Maximum Continuous Rating
(SGMCR) flows are obtained from boiler manufacturer and Valve Wide
Open (VWO) flow are obtained from HBD.

8.1.2 Where the boiler and turbine parameters are already fixed, the maximum
allowable pressure drop in the main steam line is also fixed. The main
steam pipe size is so selected to ensure that the actual pressure drop is
about 90% of the maximum allowable pressure drop at maximum
calculated or expected flow between superheater outlet and HP turbine
inlet. Pressure drop calculations shall be carried out for all guaranteed
conditions.

8.1.3 It must be noted that the superheated steam output of the boiler will
normally be somewhat greater than the throttle flow of the turbine
corresponding to (VWO) condition. Where the differential flow is tapped off
the main steam piping for auxiliary steam station, ejectors, etc., maximum
flows as applicable for individual sections must be considered for
computing line losses.

8.1.4 In cases where the calculated value of the pressure drop is only marginally
in excess of the allowed pressure drop, negotiate with the boiler contractor
for a slight increase in the Super Heater (SH) outlet pressure before
considering increasing main steam line size.

8.1.5 In case of captive power plants, boiler output could be much higher than
turbine requirements in order to meet process steam requirements or to
cater to future expansion or both. Design flows of steam piping should be
established after taking into account these aspects.

8.1.6 Where boiler and turbine parameters are not fixed, the SH outlet pressure

ISSUE
R3

FILE NAME: M6ME406R3.DOC TCE FORM NO. 120 R3


TATA CONSULTING ENGINEERS LIMITED SECTION: WRITE-UP
TCE.M6-ME-590-406 DESIGN GUIDE FOR LINE SIZING OF POWER
SHEET 9 OF 24
PLANT PIPING

is established after taking into account estimated line losses. The pressure
drop in the main steam piping generally varies between 5-7 percent of the
SH outlet pressure.

8.1.7 While computing the available pressure drop between boiler and turbine,
establish whether the boiler outlet pressure is at the outlet header or at the
contractual terminal point for supply. In case of turbines, establish whether
the turbine inlet pressure furnished by the turbine manufacturer includes
pressure drop across strainers, if any.

8.1.8 Besides piping and fittings, the important components to consider in the
calculation of pressure drop are Main Steam Stop Valve (MSV) and steam
flow nozzle. When no specific figures are available for the pressure drop
across the (MSV), a value of 0.3 kg/cm2 may be assumed for small
capacity plant upto 250MW generating capacity & 0.5 kg/cm2 may be
assumed for large capacity plant above 250MW generating capacity.
When no specific figures are available for the irrecoverable pressure drop
across main steam flow nozzle, a value of 0.3 kg/cm2 may be assumed.
Strainer if any on main steam piping, then drop across it will be generally
included in (HBD) by turbine vendor, but this has to be specifically
confirmed with turbine vendor.

8.1.9 Subject to turbine manufacturer’s confirmation, measurement of turbine


first stage pressure could also be used for steam flow indication and drum
level control. In critical cases, essentiality of flow nozzle for flow
measurement may be thoroughly studied.

8.1.10 For preliminary line sizing, a velocity of 50-60 m/s may be assumed.

8.2 REHEAT STEAM PIPING

8.2.1 HP Turbine exhaust pressure, temperature and IP Turbine inlet pressure,


temperatures are obtained from HBD. Drop across reheater are obtained
from boiler manufacturer. VWO flows are obtained from HBD.

8.2.2 Where the boiler and turbine parameters are already fixed the maximum
allowable pressure drops in the hot and cold reheat piping are also fixed.
The sizes of hot and cold reheat piping are so selected as to ensure that
the actual pressure drop is about 90% of the maximum allowable pressure
drop at maximum calculated or expected flows. Pressure drop calculations
shall be carried out for all guaranteed conditions.

8.2.3 Consider maximum flows as applicable to individual sections. Steam may


be tapped from cold reheat line to HP heater, for example. In such a case,
the flow between turbine outlet and tee off to HP heater would be greater.

8.2.4 It should be ensured that the total pressure drop in the reheat circuit is

ISSUE
R3

FILE NAME: M6ME406R3.DOC TCE FORM NO. 120 R3


TATA CONSULTING ENGINEERS LIMITED SECTION: WRITE-UP
TCE.M6-ME-590-406 DESIGN GUIDE FOR LINE SIZING OF POWER
SHEET 10 OF 24
PLANT PIPING

equal to or less than the available drop in other operating modes as well.
For instance, when steam to top HP heater is taken from cold reheat line,
for the operating condition of top heater being out of service, flow in the
reheat circuit may be greater than for the condition all heaters being in
service, the turbine output being equal to rated value in both cases.

8.2.5 Where boiler and turbine parameters are not fixed or are not firm the sizing
of the cold and hot reheat piping should be carried out in parallel. The total
permissible pressure drop in the reheat circuits is available from the
turbine heat balance diagrams. It is generally about 10% of the absolute
pressure of steam leaving the high-pressure turbine. From this figure, the
drop across reheater must be deducted to obtain the maximum available
drop for the reheat piping. If reheater drop is not known or can be
specified, approximately 40-50 percent of the total drop in the reheat circuit
can be assumed to be the drop across the reheater. The balance is
suitably divided between the cold and hot reheat pipes in such a way as to
minimise cost. It is apparent that hot reheat piping is substantially costlier
than cold reheat piping. Further, due to higher temperatures, flexibility
problems are greater with hot reheat piping. Therefore, the size of the hot
reheat line should be kept as small as feasible.

To start with, assume a velocity of 60 m/s in the hot reheat piping.


Determine the line size and pressure drop. Establish the cold reheat line
size from the remaining pressure drop.

Pressure drop in the hot reheat piping could be between 2 to 4 times the
pressure drop in the cold reheat piping.

8.2.6 Besides piping and fittings, important components to be considered in the


pressure drop calculation are:

(a) Strainer if any on hot reheat piping, then drop across it will be generally
included in (HBD) by turbine vendor, but this has to be specifically
confirmed with turbine vendor.
(b) Non return valve on cold reheat piping
(c) The Pressure drop across emergency attemperator in cold reheat
piping may be taken as 0.1 kg/cm^2 and same has to be confirmed
from boiler manufacturer.
8.3 EQUALISING LINE

8.3.1 Equalising line is the interconnecting line between the two main steam
inlets to HP Turbine and similarly between the two hot reheat inlets to IP
Turbine. This line is generally adopted in double lead system from boiler
to turbine. This line is provided to enable load testing of the Emergency
Stop Valve (ESV) & Interceptor Control Valve (IV) one after the other. This

ISSUE
R3

FILE NAME: M6ME406R3.DOC TCE FORM NO. 120 R3


TATA CONSULTING ENGINEERS LIMITED SECTION: WRITE-UP
TCE.M6-ME-590-406 DESIGN GUIDE FOR LINE SIZING OF POWER
SHEET 11 OF 24
PLANT PIPING

line also enables to balance the pressure in the two individual leads during
transient conditions. It will also minimize the variation of temperature
between the two leads from the boiler.

8.3.2 The Design flow for equalizing line may be considered as half of the flow
generated during 80% load condition i.e during ESV load testing period.
The other parameters like pressure & temperature will be same as in main
line.

8.3.3 As the pressure drop is not the criteria, so the design velocity may be
considered on the upper limit of recommended range of velocities
mentioned in this design guide.

8.4 EXTRACTION STEAM PIPING

8.4.1 The turbine outlet pressure, temperature and heater inlet pressure,
temperature is obtained from HBD. The design flow is obtained from HBD.

8.4.2 Where the turbine cycle parameters are already fixed, the sizes of
extraction piping should be selected so as to ensure that the pressure drop
in the piping is equal to or less than the allowable pressure drop between
turbine nozzle and extraction feed heater inlet nozzle at maximum flows.

8.4.3 It should be ensured that the line sizes selected are suitable for all
operating modes of the plant, viz. VWO, rated output, individual heater out
of service, lowest CW temperature, maximum make up, etc.

8.4.4 As the turbine output falls, the extraction flows decrease, but so also do
the extraction pressures. Check calculations for all modes of operation
including part load conditions to ensure that the line velocities do not rise
to prohibitive levels.

8.4.5 Where turbine cycle parameters are not finalised, a line drop of 3 to 5
percent of extraction steam line outlet pressure at turbine at maximum
extraction flows may be assumed for purpose of line sizing.

8.4.6 Besides piping and fittings, important components to be considered for


pressure drop calculations are, isolating valves and non return valves.
Pressure drop across isolating valves can be taken from Appendix and the
drop across extraction non return valves shall be obtained from the
Vendor.

ISSUE
R3

FILE NAME: M6ME406R3.DOC TCE FORM NO. 120 R3


TATA CONSULTING ENGINEERS LIMITED SECTION: WRITE-UP
TCE.M6-ME-590-406 DESIGN GUIDE FOR LINE SIZING OF POWER
SHEET 12 OF 24
PLANT PIPING

8.5 TURBINE BYPASS PIPING

8.5.1 The design flow for turbine bypass piping depends on the capacity of the
bypass station. Thus, the flow upstream of the HP and LP bypass
pressure reducing valves should equal the capacity of these valves. When
the desuperheating spray is introduced into the pressure reducing valves
for attemperation, the downstream design flow shall be equal to the
upstream design flow, plus the spray water flow. Where external
(independent) desuperheaters are used, the design flow downstream of
the pressure reducing valves upto the desuperheater is the same as the
upstream design flow. Design flow downstream of the desuperheater is
obtained by adding spray water flow to the upstream design flow.

8.5.2 The steam pressures upstream of the HP and LP bypass valves at the
design flows are same as that as main steam and hot reheat system
respectively. The steam pressure downstream of the HP bypass valve is
equal to the set pressure of LP bypass valve plus the losses in the reheat
circuit or CRH pressure, whichever is lower for line sizing. The steam
pressure downstream of the LP bypass valve should be ascertained from
the Vendor (Turbine Vendor). Downstream pressure of the LP bypass
valve is, in general, much greater than the condenser pressure due to the
drop across the steam throw-off device located inside the condenser.

8.5.3 The temperatures of steam upstream of HP & LP bypass valves at design


flows correspond to the superheater outlet and reheater outlet
temperatures of the boiler at an output equal to the bypass station
capacity. Normally, these temperatures also correspond to the superheater
and reheater outlet temperatures at boiler MCR output.
.
The temperature downstream of the HP and LP bypass valves where the
spray is introduced into the valve bodies and downstream of the
desuperheaters in case of external desuperheating is equal to the set point
of the respective temperature controller.

In case of external desuperheating, the temperature of the pipe section


between the bypass valve and the desuperheater can be obtained from the
Mollier diagram by following an isenthalpic path.

8.5.4 Since the bypass valves are only in intermittent service, high velocities
corresponding to the upper limit of the range recommended in Section 6.0
of this guide may be assumed. In case of piping downstream of LP bypass
valves, due to the high mass flows and high specific volumes, the design
velocity can be increased upto 100 m/s if necessary to keep the pipe sizes
reasonable.

8.5.5 It is obvious that pressure drops in the pipeline are not a major
consideration in the sizing of the bypass piping.

ISSUE
R3

FILE NAME: M6ME406R3.DOC TCE FORM NO. 120 R3


TATA CONSULTING ENGINEERS LIMITED SECTION: WRITE-UP
TCE.M6-ME-590-406 DESIGN GUIDE FOR LINE SIZING OF POWER
SHEET 13 OF 24
PLANT PIPING

8.6 AUXILIARY STEAM PIPING

8.6.1 The auxiliary PRDS station has two salient modes of operation based on
which it is sized :

(a) Cold start up of the TG unit. Here, although the mass flows are less
than the capacity of the PRDS station, boiler pressure is also low
resulting in high specific volume.

(b) Operation of the PRDS at rated capacity

The sizing of the steam line to PRDS shall consider both the above modes.

8.6.2 Normal flow through the PRDS is much less than the rated capacity.
Velocity in the steam line to PRDS at design flow can be taken as high as
the upper limit of the recommended range.

8.6.3 Steam line downstream of the desuperheater upto the auxiliary steam
header should be considered as handling wet steam for purposes of
selection of design velocities.

8.6.4 Steam lines from the header to individual consumers other than
deaerator/feed water tank should be designed so as to drop not more than
60 percent of the maximum allowed pressure drop at their design flows.

8.6.5 Steam line to deaerator should be designed for the following modes of
operation as applicable :

(a) Cold start of unit


(b) Warm start of unit
(c) HP/LP bypass operation
(d) Normal operation of unit at full load
(e) Operation of unit at part loads

In each case, the pressure downstream of the pressure control valve on


the line should be equal to the corresponding pegging pressure of the
deaerator.

8.7 BOILER FEED DISCHARGE PIPING

8.7.1 On individual pump discharge lines, the design flow should be equal to the
rated capacity of the feed pump. On common discharge line to heaters
and economiser, the design flow should be the rated capacity of the feed
control valve.

ISSUE
R3

FILE NAME: M6ME406R3.DOC TCE FORM NO. 120 R3


TATA CONSULTING ENGINEERS LIMITED SECTION: WRITE-UP
TCE.M6-ME-590-406 DESIGN GUIDE FOR LINE SIZING OF POWER
SHEET 14 OF 24
PLANT PIPING

8.7.2 In plant where no feed control valve is envisaged, the design flow of the
common line may be taken as 1.3 times the boiler MCR output.

8.7.3 The velocity in the feed water piping should be limited to 6 m/s at the
design flow.

8.8 BOILER FEED PUMP SUCTION PIPING

8.8.1 For preliminary line sizing, use a line velocity of 1 to 1.5 m/s

8.8.2 The pressure drop in the suction piping shall be such as to meet the NPSH
requirements of the boiler feed pumps under all operating conditions,
steady state and transient.

Transient conditions are said to occur when the steam supply to deaerator
is not commensurate with the demand set by the inflows into the deaerator
and the pressure in the deaerator/feed water tank starts decaying as a
result. Such conditions can arise when the steam supply to the deaerator is
cut off or preheating of condensate in the low pressure heaters of the feed
cycle is stopped as might happen on a turbine trip out and turbine bypass
station coming on line.

8.8.3 From the point of view of steady conditions, larger suction line sizes lead to
lower line velocities and hence lower friction drops, thus lower improving
NPSH availability. On the other hand, lower line velocities lead to
increased residence time of the fluid in the suction piping and worsen the
NPSH availability under transient conditions. Since the suction strainer
accounts for a higher percentage of the total pressure drop, it is
recommended to install large suction strainers with high straining area/pipe
flow area ratios in order to minimise friction drop. The line sizes may then
be finalised to suit the transient operating conditions.

8.8.4 For optimum designs, the feed water tank elevation and the NPSH
requirements under steady state and transient operating conditions should
be studied in combination with the feed water tank storage capacity and
the suction line size.

8.8.5 When more than one feed pump is designed to be in operation at any time
(parallel operation of pumps), NPSH calculations shall be carried out for
the condition of one of the operating pumps having tripped and the standby
pump having failed to come into service.

8.9 CONDENSATE PUMP AND HEATER DRAIN PUMP SUCTION PIPING

8.9.1 Line size selection is based on NPSH requirements of the pumps

8.9.2 For NPSH calculations, consider the maximum flow corresponding to the

ISSUE
R3

FILE NAME: M6ME406R3.DOC TCE FORM NO. 120 R3


TATA CONSULTING ENGINEERS LIMITED SECTION: WRITE-UP
TCE.M6-ME-590-406 DESIGN GUIDE FOR LINE SIZING OF POWER
SHEET 15 OF 24
PLANT PIPING

capacity of a full open control valve in the pump delivery line.

8.9.3 In the case of more than one pump operating in parallel, NPSH
calculations shall be carried out for the condition of one of the operating
pumps having tripped and the standby having failed to come into service.

8.10 FUEL OIL DECANTATION PUMP SUCTION PIPING

8.10.1 The most important consideration is to reduce the pressure drop in the
decantation header to negligible value so as to enable unloading of oil from
all wagons as nearly at an equal rate as possible.

8.10.2 Consider several header sizes and compute the total loss in the header for
each size. Select the size beyond which any increase in header size does
not result in any significant reduction in the pressure drop in the header.

8.10.3 Check the header size selected from the point of view of layout of piping
between wagon outlet and pump inlet. The layout shall be such as to result
in no high points in the system and header to slope towards pump suction.

8.10.4 Although the flow in the header varies from section to section depending
on the number of wagons contributing to the header flow, adopt a uniform
size for the entire length of the header.

8.11 FUEL OIL DECANTATION PUMP DELIVERY PIPING

8.11.1 The line size for the delivery piping shall be selected after optimising the
installed cost of piping, valves, pumps and motors and the pumping cost.
Example for optimising pipe size on pump delivery is given in Appendix-2.

8.11.2 While computing the pumping cost, it should be noted that the pumps are
in intermittent service.

8.12 FUEL GAS PIPING

8.12.1 The pressure drop in gas lines is generally large relative to the inlet or
source pressure and for these cases the Darcy equation will not give
accurate results. Weymouth formula, which is derived from isothermal
equations, gives more accurate results since the flow of gases in long
pipelines closely approximates isothermal conditions. The line size of fuel
gas piping is done generally using Weymouth formula.

ISSUE
R3

FILE NAME: M6ME406R3.DOC TCE FORM NO. 120 R3


TATA CONSULTING ENGINEERS LIMITED SECTION: WRITE-UP
TCE.M6-ME-590-406 DESIGN GUIDE FOR LINE SIZING OF POWER
SHEET 16 OF 24
PLANT PIPING

8.12.2 Weymouth formula

q’h = 2.61 x 10-8 * d 2.667 (P’1)2 – (P’2)2 * 288 -- Eq.8.1


S
g * Lm T
Where,
q’h - rate of flow in cubic metres per hour at metric standard
conditions
d - internal diameter of pipe, in mm
P’1 - source or inlet pressure in Newtons per square
metre (pascals) absolute
P’2 - terminal pressure in Newton per square metre (pascals)
absolute
S
g - specific gravity of gas relative to air = ratio of molecular
weight of gas to that of air
Lm - length of pipe, in kilometres
T - absolute temperature in kelvins

8.12.3 Gas line velocity to be maintained is indicated in table 6.1. Where the
pressure drop criteria determine the gas line sizing, velocity range closer to
lower limit of 10m/s to be adopted. For other cases, closer to 30m/s can be
maintained to economise the pipe line size.

8.12.4 Density of gases are more sensitive to pressure variations as compared to


temperature variation. Hence, while calculating the gas line velocity
average density of gas to be taken considering the inlet and outlet
pressure.

8.12.5 Density of gas (ρ) at any given pressure (P’) is calculated as below:

ρ = P’ ----- Eq.8.2
RT
Where,
P’ – Pressure in Newtons per square metre (pascals) absolute
R – Individual gas constant = Ro / M in J/kg K
T --Temperature in Kelvins
Ro = 8314 J/kg-mol K
M -- Molecular weight of gas

ISSUE
R3

FILE NAME: M6ME406R3.DOC TCE FORM NO. 120 R3


SECTION:
TATA CONSULTING ENGINEERS LIMITED APPENDIX
TCE.M6-ME-590-406
DESIGN GUIDE FOR LINE SIZING OF POWER
SHEET 17 OF 24
PIPING

APPENDIX-1

VALUES OF RESISTANCE CO-EFFICIENTS

1. PIPE FRICTION DATA FOR CLEAN COMMERICAL STEEL PIPE WITH FLOW IN ZONE
OF COMPLETE TURBULENCE

Nominal size ½" ¾" 1" 1…" 1½" 2"


Friction Factor (fT) 0.027 0.025 0.023 0.022 0.021 0.019

Nominal size 2½",3" 4" 5" 6" 8-10" 12"-16" 18"-24"


Friction Factor (fT) 0.018 0.017 0.016 0.015 0.014 0.013 0.012

Above factor is based on the following schedule numbers:

Class 300 & below Schedule 40

Class 400 & 600 Schedule 80

Class 900 Schedule 120

Class 1500 Schedule 160

Class 2500 (Size ½ to 6”) XXS

Class 2500 (Size 8” & above ) Schedule 160

For connecting pipe sizes different from those listed above `K’ factor for valve
& fittings would be as follows:
4

( )
da
Ka = Kb
db

Where subscript a defines `K’ and `d’ with reference to internal


diameter of the connecting pipe

b defines `K’ and `d’ with reference to internal


diameter of the pipe for which values of `k’ were
established.

ISSUE
R3

FILE NAME: M6ME406R3.DOC TCE FORM NO. 120 R3


SECTION:
TATA CONSULTING ENGINEERS LIMITED APPENDIX
TCE.M6-ME-590-406
DESIGN GUIDE FOR LINE SIZING OF POWER
SHEET 18 OF 24
PIPING
2. GATE VALVES - Wedge Disc, Double Disc or Plug Type
d1

d2

d2

d1

d2
0
If: = 1, € = O ……………………………… K1 = 8fT

(
d1
< 1 and € < 45O ……………………… K2 = Formula 5 =
d2 )
< 1 and 45O < € < 180 O ……… K2 = Formula 6

3. SWING CHECK VALVES

d2
d1
2

d1

K = 100 fT K = 50 fT

Minimum pipe velocity (fps) Minimum pipe velocity (fps)


for full disc lift = 35 υ for full disc lift = 60 υ
υ = Specific volume)

4. LIFT CHECK VALVES

If β= 1 k1= 600 fT Minimum pipe velocity


2
β< 1 k2= Formula 7 β υ
(fps) for full disc lift = 40β

K factors for other type of valves refer Appendix-A of ‘Flow of Fluids’ of Crane

ISSUE
R3

FILE NAME: M6ME406R3.DOC TCE FORM NO. 120 R3


SECTION:
TATA CONSULTING ENGINEERS LIMITED APPENDIX
TCE.M6-ME-590-406
DESIGN GUIDE FOR LINE SIZING OF POWER
SHEET 19 OF 24
PIPING

5. FORMULAE FOR CALCULATING “K” FACTORS FOR VALVES AND


FITTINGS WITH REDUCED PORT

• Formula 1

θ (1 -
0.8(sin ) K1
K2 = 2 ) =

• Formula 2
θ
0.5(1 - ) (sin ) K1
2
K2 = =

• Formula 3

θ (1 - )
2.6 (sin ) K1
2
K2 = =

• Formula 4

(1 - ) K1
K2 = =

• Formula 5

K1
K2 = + Formula 1 + Formula 3

θ
K1 + sin [0.8(1 - ) + 2.6(1 - )
2
K2 =

ISSUE
R3

FILE NAME: M6ME406R3.DOC TCE FORM NO. 120 R3


SECTION:
TATA CONSULTING ENGINEERS LIMITED APPENDIX
TCE.M6-ME-590-406
DESIGN GUIDE FOR LINE SIZING OF POWER
SHEET 20 OF 24
PIPING

• Formula 6

K1
K2 = + Formula 2 + Formula 4

K2 θ (I - ) + (1 - )
K1 + 0.5 sin
2
=

• Formula 7

K1
0
K2 = + Formula 2 + Formula 4) When θ = 180

K1 + [0.5 (1 - ) + 2.6(1 - ) ]
K2 =

d1
=
d2

( )
2
d1 a1
2
= =
d2 a2

Subscript 1 defines dimensions and coefficient with reference to the smaller


diameter.

Subscript 2 refers to the larger diameter.

Above formulae and data are taken from “Flow of Fluids” – Crane
(Technical paper No. 410)

Example for calculation of `K’ factor for valves with reduced port is enclosed in
Appendix - 3

ISSUE
R3

FILE NAME: M6ME406R3.DOC TCE FORM NO. 120 R3


SECTION:
TATA CONSULTING ENGINEERS LIMITED APPENDIX
TCE.M6-ME-590-406
DESIGN GUIDE FOR LINE SIZING OF POWER
SHEET 21 OF 24
PIPING

6. SUDDEN AND GRADUAL CONTRACTION

a2 a1

d2

d1
If: € < 45O ……………………. K2 = Formula 1

45
O
< € < 180O …….. K2 = Formula 2

SUDDEN AND GRADUAL ENLARGEMENT

a1 a2
d2
d1

€ < 45 …………………….
O
If: K2 = Formula 3
45
O
< € < 180O ……. K2 = Formula 4

7. MITRE BEND 8. THREADED ELBOWS


O O
90 45
∝ K
Oo 2 fT
d 15o 4 fT
30o 8 fT
α 45o 15 fT
60o 25 fT
d
75o 40 fT
90o 60 fT

K = 30 fT K = 16 fT
ISSUE
R3

FILE NAME: M6ME406R3.DOC TCE FORM NO. 120 R3


SECTION:
TATA CONSULTING ENGINEERS LIMITED APPENDIX
TCE.M6-ME-590-406
DESIGN GUIDE FOR LINE SIZING OF POWER
SHEET 22 OF 24
PIPING

9. 90o PIPE BENDS AND FLANGED


OR BUTT-WELDING 90o ELBOWS 10. STANDARD
TEES
r/d K r/d K
1 20 fT 8 24 fT
1.5 14 fT 10 30 fT
2 12 fT 12 34 fT
3 12 fT 14 38 fT
r
4 14 fT 18 42 fT
6 17 fT 20 50 fT

Flow thru run……..K = 20 fT


The resistance co-efficient, KB for pipe bends Flow thru branch…K = 60 fT
other than 90 may be determined as follows:
o

KB = (n-1)(0.25*3.14*fT*r/d + 0.5K) + K

where n = Deg of the bend for which resistance coefficient has to be found.
_____________________________________________________
90°
o
K= resistance co-efficient of one 90 bend.

11. PIPE ENTRANCE r/d K


Inward Projecting Flush 0.00 0.5
r 0.02 0.28
0.04 0.24
0.06 0.15
d
d

0.10 0.09
0.15 & up 0.04

. K=0.78 * Sharp edged

12. PIPE EXIT


Projecting Sharp-Edged Rounded

ISSUE
R3

FILE NAME: M6ME406R3.DOC TCE FORM NO. 120 R3


SECTION:
TATA CONSULTING ENGINEERS LIMITED APPENDIX
TCE.M6-ME-590-406
DESIGN GUIDE FOR LINE SIZING OF POWER
SHEET 23 OF 24
PIPING

APPENDIX-2

EXAMPLE FOR OPTIMISING PIPE SIZE


1.0 DATA

System : CONDENSATE PUMP DISCHARGE

Sizes Considered : NB 300, 350, 400, 450 & 500

Flow (Q) : 1170 Tonnes / Hr = 325 Kg/Sec.

Energy Cost (x) : 65 Paise / KWHR

Plant load factor (f) : 0.75

Plant life (l) : 25 Years

Interest rate considered per annum (z) : 12 %

Pump Efficiency ( p) : 0.8

Motor Efficiency ( m) : 0.85

Period ( y ) : 8760 hours ( 1 year )

l
(1+z) - 1
2.0 Capitalised Factor (c) = l
z (1+z)
(1+0.12)25 - 1
= = 7.843
0.12 (1+0.12) 25

3.0 Capitalised Pumping Q H 0.746 x f y c


=
energy cost (E) 75 x p x m
325 x H x 0.746 x 0.65 x 0.75 x 8760 x 7.843
=
75 x 0.8 x 0.85
= [159226 x H]

H CAPTILAISED PIPE INSTALLED TOTAL


PIPE
4.0 CALCULATED ENERGY COST COST EVALUATED
SIZE
MLC E Rs (Lakhs) Rs (Lakhs) COST Rs (Lakhs)
NB 300 10.7 17.03 9.64 26.67
NB 350 6.75 10.75 11.81 22.56
NB 400 3.67 5.84 16.51 22.35
NB 450 2.14 3.4 20.73 24.13
NB 500 1.30 2.07 25.38 27.45

From the above it can be observed that the total evaluated cost for NB 400 is the lowest.

ISSUE
R3

FILE NAME: M6ME406R3.DOC TCE FORM NO. 120 R3


SECTION:
TATA CONSULTING ENGINEERS LIMITED APPENDIX
TCE.M6-ME-590-406
DESIGN GUIDE FOR LINE SIZING OF POWER
SHEET 24 OF 24
PIPING

APPENDIX-3

EXAMPLE FOR CALCULATING `K’ FACTOR WITH


REDUCED PORT VALVES
152

CONNECTING PIPE
102

(6” NB x SH 80)
0° ID 146 mm

559

d1 102
= = = 0.69 = 0.48, = 0.23
d2 146

(146-102)
θ 2 44 θ
tan = = = 6.17
2 (559-152) 407 2
2

θ
sin = 0.11
2

K1 = 8fT ; fT = 0.015 For NB 6" (150) PIPE

K2 = Formula 5

θ
K1+sin
2
[0.8(1- (1-
=

8x0.015+0.11 [(0.8x0.52)+2.6(0.52)
=

= 1.06

ISSUE
R3

FILE NAME: M6ME406R3.DOC TCE FORM NO. 120 R3

You might also like