Haramaya University
Haramaya University
Haramaya University
HARAMAYA INSTITUTE
OF TECHNOLOGY
(HIT)
INTERNSHIP REPORT
School of Electrical and Computer Engineering
Power stream
Hosting Company: - Ethiopia Electric Utility Harari Region
NAME ID NO
1. Obasi Tadese……………………………………………… 4379/10
2. Samuel Bekele…………………………………………….4449/10
4. Yoseph Edosa……………………………………………….4693/10
HARAMAYA, ETHIOPIA
2022 G.C
DECLARATION
We have been taking internship experience in Ethiopian electric utility at Harari region from
November 17, 2021 up to February 21, 2022 under the supervision of the Harari region EEU
supervisor and Haramaya University advisor.
We declare that this report has took many efforts to finalize till the end and written according to
internship report writing format given by university industry linkage office of the institute and all
sources of materials used for the report has been fully encountered.
ADVISOR APPROVAL
The report has been submitted for examination with approval of university advisor.
Advisor Name signature date
Ms. Medhanit Mulatu ______________ _____________
i
ACKNOWLEDGMENT
First of all, we would like to thank almighty God for his provision of strength that helped us to
accomplish our duration during the internship work. Within his help we have achieved our
practical experience harmoniously and safely.
Next, we would like to express our deepest appreciation and gratitude to our advisor
Ms.Medhanit Mulatu, for her kind advice and guidance on preparing Internship report, and also
we would like to give our deepest appreciation and gratitude to Haramaya University, for
creating an opportunity to pursue a practical experience through two-month internship program.
Finally, we want to thank Ethiopian Electric Utility for hosting us as intern and giving us such an
opportunity to improve our technical as well as professional skills.
ii
ACRONYMS
AC Alternating current
DC Direct Current
LV Low Voltage
MV Medium Voltage
CT Current Transformer
VT Voltage Transformer
LIST OF FIGURES
iii
FIGURE 1 OVERALL ORGINIZATION STRUCTURE...........................................................................................3
FIGURE 2 SINGLE LINE DIAGRAM FOR HARARI III SUBSTATION................................................................9
FIGURE 2.1 HARARI SUBSTATION.......................................................................................................................9
FIGURE 2.2 POWER TRANSFORMERS AT SUBSTATION................................................................................11
FIGURE 2.3 GROUNDING TRANSFORMER........................................................................................................12
FIGURE 2.4 VOLTAGE TRANSFORMERS (VT)..................................................................................................13
FIGURE 2.5 CURRENT TRANSFORMERS (CT)...................................................................................................14
FIGURE 2.6 RADIATOR OF TRANSFORMER......................................................................................................14
FIGURE 2.7 CONSERVATOR OF TRANSFORMER.............................................................................................15
FIGURE 2.8 BUSHING OF TRANSFORMER........................................................................................................16
FIGURE 2.9 SILICA GEL.........................................................................................................................................17
FIGURE 2.10 ARCING HORN OF TRANSFORMER.............................................................................................18
TABLE OF CONTENTS
Declaration...................................................................................................................................................i
iv
Advisor Approval.........................................................................................................................................i
Acknowledgment.........................................................................................................................................ii
Acronyms...................................................................................................................................................iii
List of figures..............................................................................................................................................iv
Summary....................................................................................................................................................vii
CHAPTER ONE..........................................................................................................................................1
Introduction.................................................................................................................................................1
1.1BACKGROUND HISTORY OF ETHIOPIAN ELECTRIC UTILITY..........................................1
1.2 Ethiopian Electric Utility (EEU)......................................................................................................1
1.2.1 Vision.........................................................................................................................................1
1.2.2 Mission.......................................................................................................................................2
1.2.3 Objectives...................................................................................................................................2
1.3 Main services of EEU........................................................................................................................2
1.4 overall organization structure............................................................................................................3
CHAPTER TWO.........................................................................................................................................4
Overall industrial internship Experience......................................................................................................4
2.1 Objectives..........................................................................................................................................4
2.1.1 General Objectives......................................................................................................................4
2.1.2 Specific Objectives.....................................................................................................................4
2.1 The section of EEU we have involved.........................................................................................4
2.2 State of Distribution Network......................................................................................................5
2.3 Distribution network Design and Inspection Department Office.................................................6
2.5 Substation..........................................................................................................................................7
2.6 Observation of substation components.............................................................................................9
2.6.1 Substation equipment’s...............................................................................................................9
2.7 Transformers...................................................................................................................................10
2.7.1 Types of transformer available in the substation.......................................................................10
2.7.2 External Components of Transformer.......................................................................................14
2.8 Failures and causes of distribution transformers.............................................................................18
2.9 Practical maintenance of transformers and materials.....................................................................19
2.10 Methods of performing our task.....................................................................................................19
2.11 How good is in performing our task..............................................................................................19
2.12 Challenges we encountered........................................................................................................20
2.13 Measures we took to solve problems.........................................................................................20
v
CHAPTER THREE...................................................................................................................................21
overall Benefits OF internship Program....................................................................................................21
CHAPTER FOUR Conclusion and Recommendation...............................................................................22
4.1Conclusion........................................................................................................................................22
4.2 Recommendation for university.......................................................................................................22
Reference...................................................................................................................................................23
SUMMARY
The major objective of internship course is to reinforce and enhance the theoretical knowledge
gained in the class room with practical job experience. The first part describes the background of
vi
the internship hosting company. And it includes, its brief history, main products or services,
customers or the end users of its products or services and the company’s overall organization and
work flow. In the second part, the topic that is discussed in detail is the overall internship
experience. It includes details starting from the entry to the company to the challenges that we
faced and the measures that we have taken to overcome the challenges.
The last part of the internship is mainly about the overall benefits that we have gained from the
internship experience and focuses on the problem we have identified in the substation
Generally, it gives an overall description of the company such as its background, organizational
structure, services which is done in EEU. It briefly describes various electrical devices used by
the company and there uses and maintenance mechanism. It also describes the company and the
overall experience we had gained during our stay in the company.
vii
CHAPTER ONE
INTRODUCTION
In December, 2013 the corporation name and structure changed to Ethiopian Electric Utility by
council of minister’s regulation No.303/2013.The purposes for which the enterprise is
established are:
To construct and maintain electric distribution networks, to carry out the distribution
networks construction to contractors as required.
To administer electric distribution networks, to purchase bulk electric power and sell
electric energy to customers.
To initiate electric tariff amendments and upon approval to implement same procedures.
In the line with directives and policy guidelines issued by the ministry of finance and
economic development, to sell and pledge bonds and to negotiate and sign loan
agreements with local and international sources.
To undertake any other related activities necessary for the attainment of its purpose.
1.2.1 Vision
Energizing Ethiopia’s sustainable growth and enabling it to be power hub of
Africa.
1
1.2.2 Mission
To be a world class utility in contributing towards nation building by ensuring
delivery of cost effective safe, reliable and high-quality power and to enable
interconnections across the African continent for exporting surplus power.
EEU shall strive towards achieving international standard of customer care
through sustained capacity building operational and financial excellence, state of
the art technologies while ensuring highest standards of corporate governance and
ethics.
Bulk power purchase and sale, construct and operate off-grid generation, sub-
transmission and distribution networks.
1.2.3 Objectives
The main objectives of Ethiopian Electric utility are generating, transmitting and
distributing electrical energy to the community, industries and organizations to serve its
customers and to satisfy their energy demands.
Therefore, the corporation is giving services to every society of the country waiting for
electricity to life ranging from very small socket outlets and lamps to very enormous industries
is one bulk branch activity. The other activity is making electric power export goods to the
neighboring countries. Ethiopian Electric utility engaged on developing of its services to satisfy
the customers demand through continuous improvement of utility management practices are
responsive to support socio-economic development and environmental protection.
2
1.4 overall organization structure
3
CHAPTER TWO
4
Inspection It means a visual check of distribution network lines, Transformer or
equipment’s without physical disassembly.
Preventive Maintenance is the planned maintenance of plant infrastructure and
equipment with the goal of improving equipment life by preventing excess
depreciation and impairment.
3. Network design and planning section
This section operates on the designing of new transmission network based on the
GPS collected data in the field and forecasting the future energy demand
depending on population growth.
And planning of the next power requirement based on the previous data tabulated.
In the company we joined the distribution system to practice. Distribution systems executed
their work on the two categorizes. These are distribution maintenance and emergency
maintenance for most of time we have been with distribution maintenance groups. Maintenance
of transformer faults for the following cases:
o Loses of the bushes
o Distribution box damages
o High Rupture capturing fuses (HRC) bellowed
o Damage of Drop out of fuses
o Lightening arrestor’s breakdown etc.
Maintenance of medium and low voltage lines and poles if the pole is:
o Decayed
o Tilted
o Damaged
And lines that may be broken down due to various reasons such as falling of trees on the lines,
sagging of lines and short due to overloading.
5
speaking, customer expectations on supply reliability are steadily increasing. The owners of
distribution network are being required to improve the reliability of power delivery through
making the whole operating condition more efficient. Power distribution network is effected
at a primary voltage of 33kv and 15kv consisting entirely of 3-phase, 3-wire feeders and
stepped down to a utilization voltage of 380/220V (3-phase,4-wire) and 500V for some
industries using three phase transformers to customer level. Even though there are many
efforts and launched projects to modernize underground electric cable installation the
medium voltage (MV) and low voltage (LV) networks are still dominated by overhead
lines.
Distribution Transformer
Poles
Insulators and fittings
Conductors and cable connectors
Designing of LV networks
Rehabilitation of overhead LV lines
Rehabilitation of Overhead MV lines
Commissioning of rehabilitation of LV networks
Commissioning of rehabilitation of MV networks
2.5 Substation
6
Harari III substation comes from Dire Dawa and which are R, S, T and communication lines, this
line taps in Harari substation with respective way. Line1, line2 and line3 taps with surge arrester
and each has it is own reading. If over current occur, it comes with arresters to grounding. Three
lines connect with voltage transformer, wave trap (communication line to all grid), isolated
switch (half part maintaining), breaker and current transformer, surge arrester and power
transformer those all tap by bus bar.
Switching substation
Distribution substation
Switching substation
An important function performed any substation including in the substation were switching,
which is the connecting and disconnecting of distribution or transmission lines and other
components to and from the system.
o Circuit Breaker
o Isolator (Dis-connecter)
o Earth Switches
7
Distribution substation
Harari III substation comes from Dire Dawa and which are R, S, T and communication lines.it
provides electric power supply to Harari city and the rural areas in the surrounding. As it can be
seen in the figure below there are two 132/66/33 KV, 25/25/12 MVA power transformers which
operate in parallel from this transformers there are three outgoing 66KV lines, the first is the
incoming line for Harari II substation, the second 66KV is the incoming line for Haramaya
substation which supply electric power for Chelenko substation and also for almost all parts of
East Hararghe and the third 66KV is the incoming for the 12MVA in Harari III substation, this
transformer supplies most of the medium voltage loads in the city and rural areas and it operates
independently. Which is based up on two 132/66/33 KV, 25/25 MVA and 12 MVA power
transformers which are connected in parallel. With an outgoing 66KV lines to 66/15KV Harari II
substation, 66/15KV Haramaya substation. And this transformers feeding four 33kv lines to
HWSA ERER, Industry Line, Fedis, Medhega Tola and Bedassa lines. And the 66/15KV
[12MVA] transformer with 15 KV line feeder supplying the Harari city with two 15KV feeder
and others with 15KV for kombolcha also 15KV for Harari beer factory.
8
FIGURE 2 SINGLE LINE DIAGRAM FOR HARARI III SUBSTATION
9
Wave trap
Power transformer
Control room and control panels
Relay
2.7 Transformers
The transformer is a static device that transfers electrical energy from one electrical circuitto
another electrical circuit through the medium of magnetic field and without a change in the
frequency. Actually, the transformer is an electric energy conversion device, since the Energy
received by the primary is converted to useful electrical energy in the secondary winding
circuit. AC electrical power can be generated at one central location, its voltage stepped up for
transmission over long distances at very low losses and its voltage stepped down again for final
use.
It is used in electronic circuits and come in many different type and applications. Electronic or
power transformers are sometimes considered to be those with ratings of 300 Volt
transformers - amperes and below. These transformers normally provide power to the power
supply of an electronic device, such as in power amplifiers in audio receivers.
A power transformer is used in a sub-station to step-up or step-down the voltage. Except at the
power station, all the subsequent sub-stations use step-down to gradually reduce the voltage of
electric supply and finally deliver it at utilization voltage. The modern practice is to use 3-phase
transformers in sub-stations; although 3 single phase banks of transformer can also be used. The
use of 3-phase transformer (instead of 3 single phase bank of transformers) permits two
advantages;
10
FIGURE 2.2 POWER TRANSFORMERS AT SUBSTATION
The power transformer is generally installed upon lengths of rails fixed on concrete slabs
having foundation 1 to1·5m deep.
For ratings up to 10 MVA, naturally cooled, oil immersed transformers are used.
B) Grounding (Earthling) transformer:
The Earthling transformer is one of the musts to have equipment’s for those distribution
stations, which deals with delta connected transmission lines. Delta connected transmission
lines, have no neutral point. Here we use the earthling transformer or grounding transformer to
create an artificial neutral point for the three-phase system. We all know that, the resistance of
the earthling path should be kept as small as possible, because fault current will always follow
the lowest resistance path. When any single phase to ground fault is occurred, zero sequence
component of earth fault current starts flowing through the neutral wire. In earth fault, the
current flowing in the faulty phase goes to the grounding terminal. And, this fault current is
divided equally in each phases of the earthling transformer.
11
FIGURE 2.3 GROUNDING TRANSFORMER
C) Instrumentation Transformers:
12
Connected across the line. The secondary winding consists of a few turns and provides for
measuring.
Instruments and relays a voltage which is a known fraction of the line voltage. Suppose a
potential transformer rated at 66kV/110V is connected to a power line.
13
FIGURE 2.5 CURRENT TRANSFORMERS (CT)
Radiators: - Radiators are fitted to the tank so that a larger surface is reached by the liquid
flowing into the top, down the tubes of the radiators and back into the bottom of the transformer
mainly used for cooling purpose of the transformer.
14
Conservator: - Conservator conserves the transformer oil. It is an airtight metallic cylindrical
drum which is fitted above the transformer. The conservator tank is vented to the atmosphere at
the top and the normal oil level is approximately in the middle of the conservator to allow
expansion and contraction of oil during the temperature variations. It is connected to the main
tank inside the transformer which is completely filled with transformer oil through a pipeline.
Bushings: - The electrical power circuits must be insulated where they enter the tank. A
bushing provides an insulated oil-tight and weather-tight entrance for the conductor into the
transformer. It is usually composed of an outer porcelain body, and at higher voltages,
additional insulation in the form of oil and wound paper is used within the porcelain column. It
is placed to withstand the electrical field strength produced in the insulation. Bushing has a
conductor (Horn) surrounded by insulation. Used to insulate the incoming or outgoing
conductor into or out of the transformer tank. A bushing is the arrangement of insulating
material that allows the terminals of winding to bring out the transformer tank. The bushing is
made of the highest quality of porcelain clad.
15
FIGURE 2.8 BUSHING OF TRANSFORMER
Silica gel Breather: - The insulating oil of transformer is provided for cooling and insulating
purpose. Expansion and contraction of oil during the temperature variations cause pressure
change inside the conservator. This change in pressure is balanced by the flow of atmospheric air
into and out of the conservator. Transformer breather is a cylindrical container which is filled
with silica gel. Insulating oil reacts with moisture can affect the paper insulation or may even
lead to some internal faults. So it is necessary that the air entering the tank is moisture free. It
consists of silica gel contained in a chamber. For this purpose, breather is used. When the
atmospheric air passes through the silica gel breather the moisture contents are absorbed by the
silica crystals. Silica gel breather is acts like an air filter for the transformer and controls the
moisture level inside a transformer.
Oil Gauge: -Located on the side of the Conservator tank, it indicates the level of oil in the
tank and will provide annunciation when level drops below the gauge limit.
17
Fan: - The fan is mounted under the power transformer, which is used to fan (cooling) the
transformer during the temperature becomes high.
Breather: - A conservator tank has a breather to the outside. In order to take care of the
expansion and contraction of the cooling liquid with varying temperatures smaller units have an
air space above the oil, which connected to atmosphere by a breather. This breather is arranged
to prevent the entry of moisture, snow, etc. into the transformer.
Temperature Gage: -Temperature gage is fitted at the side of the conservator for knowing
the level of the filled oil to the conservator.
Tank failures
Bushing Failure
Protection system failure
18
West crane: -used to carry the upper part of transformer.
Electrical knife: - used cutting purpose.
Cave English: -used punt purpose.
Belt: - used to safety purpose.
Tester: - to know if there is any current flow or voltage.
Cutting pliers: - used to cut electrical wires.
19
The engineers were too busy as a result we were faced a problem of accessing them as
we need.
The engineers were most of the time busy with office work we didn’t get many chances
to field work.
There was shortage of transportation services in order to get to the substation area.
We haven’t got detail documents about the work flow of the EEU Harari region.
We haven’t got access of internet to search some information necessary for us.
CHAPTER THREE
The Internship Program at Haramaya University presents an opportunity for obtaining short
term employment in a position that relates to the student’s chosen field of study. Throughout the
internship these work experiences complement and reinforce the student’s theoretical
knowledge acquired from university. The internship is designed to provide not only practical
20
experience. But also, a detailed evaluation of the intern’s performance. The relationship
between the Intern, Employer, and University are tailored to achieve specific benefits which are
described below to:
upgrade practical skills
improve interpersonal communication skills
improve leadership skills
learn about work ethics and entrepreneurship skills
Be familiar with work tasks keeping as for future career.
Develop new interests in the profession.
Treat the internship experience as a professional job, striving to perform all
duties and responsibilities to the best of one's abilities.
Therefore, the two-month internship practice was very interesting in terms of developing
strength of real time engineering problem solving and gaining work experience.
CHAPTER FOUR
CONCLUSION AND RECOMMENDATION
4.1Conclusion
In this internship period we could understand the relation between theoretical and practical
knowledge and we gained different skills as well as personal and team work skills. And also we
obtained good understanding about the work experience in relation with theoretical knowledge.
This internship program contains the background of the company real situation. Future vision of
the company, working principle of company and goodness and weakness sides of the company.
21
Further, we have added suggested solutions for the identified problems and recommendations
for the limitations of the company. Also did a project concerning another problem of the
company that is earthling transformer so as to improve the shortage of transformers design.
Throughout this internship period we have gained a number of benefits in terms of improving
our practical skills, theoretical knowledge, interpersonal communication skills, leadership skills,
and understanding about work ethics and entrepreneurship skills.
REFERENCE
[1] Turan Gonen,” Electric Power Distribution Engineering”, third edition, CRC Press Taylor
and Francis Group, January 2014.
[2] “Electrical engineering design manual” by Mr. Parker Smith, Mr. M. G. Say.
[3] Martin J. Heathcote, CEng, FIEE “The J&P Transformer Book”, Twelfth edition,
Newness, Reed Educational and Professional Publishing Ltd 1998.
22