Item Description Substructure: Unit QTY Rate
Item Description Substructure: Unit QTY Rate
Item Description Substructure: Unit QTY Rate
ELEMENT NO 1: SUBSTRUCTURE
Item Description UNIT QTY RATE AMOUNT(UGX)
1.1 SUBSTRUCTURE
Clearing site of bushes, scrub, undergrowth and the like and grubbing up their roots,
1.1.01 and burn all arisings or cart away from site as directed (including cutting down trees M2 102.82
n.e 600mm girth)
Excavating top(vegetable) soil to avarage 200mm deep, including storing in
1.1.02 temporary spoil heaps on site away from excavations and later spread and level M2 102.82
where directed on site
1.1.03 Excavating to Reduced Level over 300mm not exceeding average depth of 1500mm M3 60.81
depth starting from Stripped level.
Excavating trenches to receive strip foundations, starting from the RL level but not M3 21.67
1.1.05
.execeeding 1.5m depth
Excavating pits to receive bases of columns, starting from the stripped level but not M3 25.38
1.1.06
exceeding 1.5m deep
1.1.07 Extra over all excavations for excavating in rock (Provisional) ITEM 1
Planking and strutting to uphold the sides of excavation by whatever means are ITEM 2
1.1.08
necessary (other than special shoring or steel sheet piling).
Treat surfaces of hardcores and Bottoms of excavations with anti termite solutions M2 87.44
1.1.09
as termido or any approved anti termite
Reinforced in-situ concrete, Class 25/20 mm aggregates (or minimum mix ratio M3 6.60
1.1.11 1:1.5:3) at 28days in column bases to receive stud column, manually vibrated
(measured separately)
M3 0.39
Reinforced in-situ concrete, Class 25/ 20 mm aggregates (or minimum mix ratio
1.1.12 1:1.5:3) at 28days , in stub columns, and manually vibrated
M3 2.88
Reinforced in-situ concrete, Class 25/ 20 mm aggregates (or minimum mix ratio
1.1.13 1:1.5:3) at 28days, in ground beams, manually vibrated
M2 40.86
1.1.14 200mm thick solid concrete blocks plinth wall bonded in claa II (1:3) Cement sand
mortar strecher bond with 25mm hopp iron reinforcement every after two courses
M3 30.04
Back filling selected material around foun dations compacted to 98% MDD (
1.1.15
Modified AASHTO to Engineers approval)
M2 51.10
1.1.17
150mm thick bed of hardcore, well ramped and compacted to receive blinding layer
Apply 50mm thick quality sand blinding on top of the hardcore and internal plinth M2 51.10
1.1.18
walls
M2 60.58
1.1.19 1000 gauge clear polythene sheet damp proof membrance on 50mm thick sand
blinding to prevent moisture (m.s) to receive concrete bed (m.s)
A142 BRC mesh on 1000 gauge clear polythene damp proof membrance (size M2 60.58
1.1.20 200×200). Allow for the allowance/concrete cover to length and width to prevent
exposure to atmospheric conditions
36.40
1.1.22 Provide sawn formwork to edge of slab 150mm. Not exceeding 500mm high M
Allow for wrought formworks to the vertical sides of ground beam, together with M2 28.8
1.1.23
struts, battens, wedging and striking
Allow for wrought formwork and plain sheet for circular collumns to vertical sides M2 3.86
1.1.24
of stud columns, together with struts, battens, wedging and striking
25mm Thick render to wall and concrete surfaces in 1:3 ratio mix ,wood float finish M2 49.14
1.1.25
externally
Lay an asphalt bituminous felt Dpc material underneath the external and internal
1.1.26
walls M2 40.00