Matecconf Jcmme2018 02022

Download as pdf or txt
Download as pdf or txt
You are on page 1of 7

MATEC Web of Conferences 277, 02022 (2019)

https://doi.org/10.1051/matecconf/201927702022
JCMME 2018

Facility management and building information


modeling during operation and maintenance
Michal FALTEJSEK*, and Blanka CHUDIKOVA
VŠB - Technical University of Ostrava, Faculty of Civil Engineering, Ludvíka Podéště 1875/17,
Ostrava-Poruba, 708 33, Czech Republic

Abstract. BIM is a concept and also a method currently applied


throughout the world in the modern building construction. The impact and
benefits of the BIM method are clear across all stages of the life cycle of
buildings (project, realization, operation, demolition). The longest and
most expensive phase of buildings life is the operation and usage part.
Many common aspects and linkage of processes between the BIM method
and the facility management, i.e. a modern asset management method, can
provide greater efficiency for these activities, help reduce the cost of
required building operations and maintenance and save time for individual
activities. The BIM can be understood as an information management of
buildings. Many common elements can create a synergy of processes
related to the management of buildings. The article discusses these aspects
and emphasizes the listing of the basic data and processes that are
necessary for mutual interconnectedness.

1 Introduction
Operation and maintenance of buildings are the longest and most expensive parts of the life
cycle of buildings. They are parts of many processes that must work efficiently, clearly and
sustainably in the long run. The life of buildings is in the order of decades, and throughout
the period it is necessary to maintain a standard for the users of these buildings. Properly
set up facility management processes using efficient and effective methods can help extend
the useful life of buildings and delay their degradation. One of these methods that can be
applied is BIM method, i.e. Building Information Modeling / building management.
BIM is a concept that brings a new look at the life cycle of buildings. BIM method can
be applied in two ways. The first is the implementation of BIM method already in the
construction project, through implementation and then in operation and maintenance. This
can only be applied to new constructions. For buildings that are already built, we need to
implement BIM afterwards. BIM implementation process for existing buildings may vary,
depending on the available documentation, information, software used, data formats, the
level of detail, or the expected benefit. f[1]
The procedures and methods for implementing BIM in these two cases are different. For
already constructed buildings, the data is available at the very beginning of BIM
implementation process, as well as the construction, equipment and overall construction.

*
Corresponding author: [email protected]

© The Authors, published by EDP Sciences. This is an open access article distributed under the terms of the Creative Commons
Attribution License 4.0 (http://creativecommons.org/licenses/by/4.0/).
MATEC Web of Conferences 277, 02022 (2019) https://doi.org/10.1051/matecconf/201927702022
JCMME 2018

Most of the companies that has launched BIM is still focused on implementing this concept
in designing and constructing new buildings. [2]
To optimize the facility management processes it is necessary to provide a detailed
overview of structures and elements, and the general state of the buildings already built.
This guarantees BIM and, if properly managed, guarantees long-term benefits in many
forms. Individual activities of a facility management can be simplified by BIM to achieve
greater work efficiency, reduce time for individual activities and cut down costs. [3]
BIM is also about cooperation. Co-operation and correctly set procedures and processes
already at the implementation stage of BIM can be crucial for the following work and
maintenance of BIM. Just as designers and developers of buildings should communicate
with the end user and facility manager, i.e. to take into account the following stages of the
building life cycle, the future work with BIM model (including maintenance and updates)
should also be made provision for in the creation of an additional BIM model and its
implementation into the facility management. The implementation of BIM should then be
built on that. [4]

2 Detailed passportization of property


The real asset overview and its technical and economic features are key to the proper
functioning of facility management. This requires high-quality passportization of the
existing building. A passportization itself is a process consisting of several sub-parts. First
of all, it is necessary to gather the available documents, sort them out and check their up-to-
dateness. The next step is to fill in the missing information. Mostly by a personal survey of
the building or by obtaining it from external sources.
It is also useful to take a photo of individual facilities, especially the technical
equipment, and enclose it to an element in the CAFM system as an attachment. This
ensures checking and a better overview of the equipment, its location in the space,
attachment(s), components, etc.
Personal research is time-consuming and requires access to individual spaces. In rooms,
it may be difficult to locate or physically access the searched for elements. They may be
under lock and key or covered. In many cases they might not be in places indicated by
available data. All this information has to be recorded and then re-edited into the correct
structure and assigned to the corresponding areas (if it involves checking a facility).

2.1 Quality records and data sources

Quality records of managed assets’ data are a basic prerequisite for the efficiency and cost-
effectiveness of downstream activities. Quality level of records is a very important element
in any property management. The records should be uniform, comprehensive, clear, of
high-quality and standardized. In the service life cycle of buildings, we assume a long-term
records of assets. That's why their accuracy and up-to-dateness is necessary. [5]
The quality level of the records serves as a prevention of error-making by decisions that
ultimately may have negative impacts due to lack of information and associated poor
evaluation. This creates additional cost items associated with removing or correcting errors.
Data sources should be in the first place verified and up-to-date. For example, the
sources can include:
1. Electronic drawing documentation
2. Digitization of paper drawing documentation
3. Physical data collection on site
4. Suppliers of design services
5. Construction contractors

2
MATEC Web of Conferences 277, 02022 (2019) https://doi.org/10.1051/matecconf/201927702022
JCMME 2018

6. Suppliers of technical equipment and technologies


7. Service suppliers
8. General Central Registers (Land Registry, Territorial Identification Registry of
Addresses, Registers of Economic Bodies, Roads Register) [6]

3 Information model of building in facility management


The interconnectedness of facility management and BIM methods is primarily in data. The
BIM model forms a basic graphical and informative basis for managed asset. Facility
management and support software (CAFM systems) provide detailed inventory of assets
and enable planning of processes and operation and maintenance activities. The
interrelation of these activities is therefore indisputable and lies above all in data that allow
better visualization in a BIM model environment, refurbishment or modernization planning,
their status verification, provide accessibility, etc. [3]
Digital background information created in 2D CAD software can be a good basis for
BIM creation. This is evidenced by the claim that the introduction of BIM for existing
buildings (with 2D only documentation) is possible with the use of this background
information and there is no need to create a completely new model and without background
material.
The 3D model itself does not yet form BIM, but only a suitable background. At present,
"Information Building Management" is increasingly mentioned instead of "Information
Modeling of Buildings", which shifts the importance to the information and subsequent
work with it rather than to the 3D model itself. However this does not mean we should do
BIM without a 3D model. Its use is wide and the creation of such a model in accordance
with the BIM concept is therefore desirable for facility management.

3.1 Additional BIM building model creation

Original drawings of a building usually in 2D serve as a basis for creating a 3D model


(figure 1). This drawing will be a ground plan of the future model and will guarantee the
retention of the ground plan dimensions, equipment layout, etc.
In the Revit software it is very easy to create such a background from a DWG drawing.
For individual floors a corresponding drawing is always attached of the modelled floor and
aligned with the preceding floor so that the individual floors link to each other when drawn
in 3D (that is why it was necessary to modify individual 2D drawings).
The model is drawn on the basis of a defined LoD and the available software options.
For example, structures and rough construction can be drawn in a very detailed and realistic
way. For specific types of devices and other equipment, there may be a problem with the
model. Atypical shapes and many kinds of equipment (such as chairs, tables, cabinets, but
also technical equipment) are often not available in libraries. Also, in cases of existing
buildings the equipment is mostly obsolete and not produced anymore, therefore not
available. In such cases, the placeholder model of a universal element can be applied and
distinguished only by the information / description. Another option may be to create your
own model. However, it is very labor-intensive and the efficiency / time ratio shows that it
is usually not worth it. [1]

3
MATEC Web of Conferences 277, 02022 (2019) https://doi.org/10.1051/matecconf/201927702022
JCMME 2018

Fig. 1. 3D graphic model of the MSDK building (author, Autodesk Revit software).

3.2 Adding basic information to individual elements

What constitutes BIM is the information. It is important, therefore, that individual elements
of the model should be enriched by the information or be properly interconnected with such
information (figure 2). Some information may be inserted directly into the model, but if
there is much of information to the individual elements it is more appropriate to feed it into
the CAFM system and link it to the graphical model. [2]
Therefore, only basic but important information is included in the model. It may be
information about material, colour, type of equipment, or price. Naturally there is also
information on the dimensions and location of the equipment.

Fig.2. Information in the 3D model of construction for individual elements (Author, Autodesk Revit
software).

4 CAFM systems and BIM


Computer Aided Facility Management are systems that should make facility management’s
asset management work easier. These systems are mainly used to manage the FM support
processes, their clarity of records and any planning and evaluation. CAFM systems are

4
MATEC Web of Conferences 277, 02022 (2019) https://doi.org/10.1051/matecconf/201927702022
JCMME 2018

continually improving to meet more modern and newly incoming customer requirements. It
could be said that due to the development of systems around the world, we should only
designate true CAFM system only those systems that feature a statistical, dynamic and
output data area. These are, above all, systems that cover all known areas of support
processes.
The CAFM systems’ deployment aims in particular to:
 reduce operating costs,
 improve the quality of services provided and improve the quality of the
environment,
 optimize the relationship between worker, environment and processes,
 extend the life of the monitored constructions and objects,
 introduce standards, rules and working processes in the given field and in the
system of embedded business logic,
 introduce and distribute internal costs and their assignment to departments,
divisions, activities, projects, etc.,
 manage and maintain documentation, moves, benchmarking, inventory and
inspection,
 prepare for unexpected events and accidents, processes required by legislation
(audits, inspections, ...), sustainable development. [6]

4.1 Connecting to a CAFM system

The 3D BIM model itself is not sufficient enough and needs to be linked to the CAFM
system. This allows for the mutual localization of the elements: from the model to the
CAFM system and vice versa, the exchange of information again in both directions, or the
possibility of colouring the search areas. CAFM (Computer Aided Facility Management) is
a facility management system with a wealth of different asset management functions
(reactive and proactive maintenance, planning of activities, inventory of small and
investment assets, migration planning, room reservation, key management, OSH and FS,
waste management etc.).

5 Linking BIM and Facility Management Processes


The first step is to implement existing FM processes to the BIM model and the CAFM
system. Thus, we create typical operations and maintenance activities in relation to the
areas and equipment we know and that are already being routinely used.
The main interaction consists in visualizing the data into the graphical realistic form of
the building. With the help of virtual reality, this effect can be further enhanced. Facility
management can save the facility managers a lot of time in the case of large complexes and
complicated buildings when they need not go through the building personally to see the
individual facilities, the layout of the equipment in the rooms, the accessibility of the
individual facilities, etc., as a clear and realistic visualization in BIM model with a link to
all important data in the CAFM system is for such tasks sufficient. Also, all changes
(reconstruction, upgrading, transfers, moving, etc.) can be planned through the BIM model
thus creating options for subsequent final decisions.
Basic facility management activities that can be applied:
 reactive maintenance - ad hoc troubleshooting and repairs
 proactive maintenance - planned inspections and checks
 management of lease relations
 energy, media and consumption meter management

5
MATEC Web of Conferences 277, 02022 (2019) https://doi.org/10.1051/matecconf/201927702022
JCMME 2018

 key management
 waste management
 OSH and FS
 cleaning of spaces and elements
 management of held events
 room reservations, room occupancy (offices by internal / external staff)
 document management system (document administration) [6]
There are many activities falling under facility management. Generally speaking, their
task is to ensure that the subject and its staff are carefree, so they do not have to worry
about dealing with the above-mentioned activities in any way.
In the CAFM system, you need to define the processes to support the respective FM
activity (listed above, but also others that are not mentioned here but are associated with
asset management, operation, and maintenance). The linking of activities and their records
in the CAFM system will ensure greater clarity, traceability and access to follow-up
information (by whom and when the activity is performed, for what purpose, which
documents are attached to the activity, responsible persons or entities contact particulars,
further information on the managed element, etc.).

5.1 Optimization of Facility Management Processes

The optimization involves primarily analysis and evaluation of results / comparison with
the original state. For this purpose it is advisable to pre-determine the quantities that we
will track over time and compare. On this basis, it is possible to define the differences and
clearly define the gaps in the individual processes. You can then optimize these based on
your experience, options and data.
Optimization is a long-term and repetitive process. It is necessary to have the process
set for some time and to monitor and record it in detail. After performing optimization
(change), it is necessary to again analyze and track newly established procedures, which are
then compared with the original ones and their contribution evaluated.
In the long run the overview makes it much easier to evaluate and analyze facility
management processes, track back their workflows, and then optimize them accordingly. [6]

6 Conclusion
On the whole, facility management and use of the BIM model offers clarity: if we have a
large complex and are looking for a specific facility, room or equipment, we can easily
visualize this element or person through the CAFM system and display it in a 3D model.
Realistic graphical depiction will help to avoid lengthy search and visualization during
team work will help without having to physically visit a particular part or equipment.
Other uses may be in the colouring of areas: e.g. planning for cleaning or moving,
reconstruction and upgrading (e.g. colouring of all areas where the floor covering is tiled or
where a non-load-bearing partition of 100 mm thickness is used, etc.).
Using a BIM model interconnected with CAFM system during modernization and
reconstructions we can plan the work activities, the applicable bill of quantities and find out
where the technical building installation systems are concealed in walls, what the properties
of the current structure are, what materials have been used, and much more.
An important element for the operation and collaboration of facility management and
BIM method is the aspect of the data update. BIM itself, if it remains inactive, lacks sense
in the long term. This problem is very common in new constructions, when a BIM model
was created and the data passed to the implementation stage. Based on the BIM concept,

6
MATEC Web of Conferences 277, 02022 (2019) https://doi.org/10.1051/matecconf/201927702022
JCMME 2018

the construction is subsequently implemented, but most of the time the BIM process ends
there and does not continue into the operation and maintenance phase. Which is a problem
that is still very much underestimated. Yet, the operating phase of the construction is the
longest and most costly part of the life cycle during which the wide scope of the BIM
model and data use could be utmost beneficial.

Acknowledgement
This work was supported from the funds of the Students Grant Competition of the VSB –
Technical University of Ostrava. Project registration number is SP SP2018/113.

References
1. BRUMANA R, DELLA TORRE S, PREVITALI M, BARAZZETTI L, CANTINI L,
ORENI D and BANFI F. Generative HBIM modelling to embody complexity (LOD,
LOG, LOA, LOI): surveying, preservation, site intervention—the Basilica di
Collemaggio (L’Aquila). Applied Geomatics. 2018, 10(4), 545-567, DOI:
10.1007/s12518-018-0233-3. ISSN 1866-9298. Available from:
http://link.springer.com/10.1007/s12518-018-0233-3
2. SMITH, DANA K and TARDIF M. Building information modeling: a strategic
implementation guide for architects, engineers, constructors, and real estate asset
managers. Hoboken, NJ: Wiley, 2009, ISBN 978-0-470-25003-7.
3. Černý M a kol. BIM příručka, 1. vydání, Praha, 2013, ISBN 978-80-260-5297-5, s. 80.
4. SANCHEZ A X, HAMPSON K D and VAUX S. Delivering Value with BIM, A
whole-oflife approach. London a New York: Routledge, 2016. ISBN: 978-1-138-
11899-7.
5. EASTMAN Ch, TEICHOLZ P, SACKS R and LISTON K. BIM Handbook, A Guide
to Building Information Modeling for Owners, Managers, Designers, Engineers, and
Contractors. New Jersey: John Wiley & Sons, Inc, 2008. ISBN: 978-0-470-18528-5.
6. Kuda F, Beránková E and Soukup P.. Facility management v kostce pro profesionály i
laiky, nakladatelství FORM Solution, 2012, první vydání, ISBN 978-80905257-0-2.