Guideline On Digital Substation Implementation Process Under Grid Division Rev1.2
Guideline On Digital Substation Implementation Process Under Grid Division Rev1.2
Fail
Pass
CRP Panel Panel List &
Panel Certification
Certification Typical Drawing
Evaluation
Process
Standard SSD
& IEDs ICD
Product
Approve List
FAT - ITP
FAT - Setting
Deliver Panel to
GRID Contract Project Kick-Off by Site Acceptance Live Panel Maint. End Of Warranty
Request Relay site Commissioning
Development Document PMO test & Load test (Note: perform by GM)
Setting and Installation
(Construction)
Note: Live Panel Maint.
only applicable for OHL/
UGC 275 kV and above
GRID
Maintenance Operational
(MTEP) Setting
Tender Floating,
P&SC
Evaluation & Award
1
Guideline on Digital Substation Implementation Process
Protection Automation & Control
Grid Solution Expertise Department
Our Ref : GRID/GSE(PAC)/Digital Substation
Implementation Process
Revision: 1.2 Date: 3/6/2021
Work Process
Scope Remarks
Specifications Secondary Specifications under GSE • GTS-GSE-APCI
• GTS-GSE-PROT
• GTS-GSE-SPACS IEC61850
• GTS-TK-AXQ
• TTS-TK-ESM
• GTS-GSE-SSR
• TTS-TK-SGW
• TTS-TK-SLOI
• GTS-GSE-DPM
Standard Design & Product Secondary Guidelines related to Protection and Telecontrol
Requirements (SPDR) and Requirements under GSE
Guidelines
Secondary Product Approved Product To be Used in Grid Division (Product Acceptance • Product Failure Management Process
List Process) under GSE (inclusive of Root Cause Analysis)
• Product Warranty
• For IED, product must be less than 2 years at
FAT from manufacturing date
Other Deliverables for Deliverables to support Digital Substation design under GSE • Standard Conceptual & Schematic Drawing for
Engineering and Verification typical bays (applied under CRP Panel
Certification Process)
• SSD Template file
• Product Application & Logic
2
Guideline on Digital Substation Implementation Process
Protection Automation & Control
Grid Solution Expertise Department
Our Ref : GRID/GSE(PAC)/Digital Substation
Implementation Process
Revision: 1.2 Date: 3/6/2021
• ICD file
• DV Procedure, ITP & WI
• FAT Setting
CRP Panel Certification Process Panel Certification Process for Digital Substation Standard • Panel Certification Application Form
Design in Grid Division under GSE: • Panel Builder Assessment
• Conceptual and Schematic Drawing Approval (Typical • TNB CRP Panel Approved List with standard
Bay at one voltage level) typical bay Conceptual and Schematic Drawing
• Typical Panel Design Verification (under version tracking)
Allowed to be conducted under tender for limited time as • To be completed in 6 months under tender
specified under ITT*
Drawing Approval Process Engineering Review to be conducted by GD Design (21 days Schedule D
for each review)
CRP Internal Testing To conduct internally with proper test report covering: • Approved Drawing (Schedule D)
• Routine Test • SSD template file
• Functional Test • Product Applications & Logic
• Scheme Test • ICD file
• System Integration Test • FAT Setting
• DV Procedure, ITP & WI
Design Verification (DV) Process To be witnessed by GD Design with assistance from GSE • Approved Drawing (Schedule D)
To allocate one month per system (one voltage level) • SSD template file
Complete Scheme and System Integration Test (all CRP • Product Applications
panels inclusive RTCC and DFR, network and clients) • Product Logic & ICD file
• FAT Setting
• DV Procedure, ITP & WI
3
Guideline on Digital Substation Implementation Process
Protection Automation & Control
Grid Solution Expertise Department
Our Ref : GRID/GSE(PAC)/Digital Substation
Implementation Process
Revision: 1.2 Date: 3/6/2021
DV/FAT IED Setting & • CRP Panel Manufacturer & Integrator to compile all IED Proprietary IED setting and configuration files with
Configuration Compilation Setting & Configuration upon successful of DV and FAT proper naming convention
• To be submitted together with Setting Request to
Protection Setting Unit, MTEP by Project Manager
Setting Request Setting Management Process under Protection Setting Unit, Operational Setting for IEDs for SAT
MTEP
Setting Request through SWIM or official letter by external
party
Site Acceptance Test Refer to updated SAT document and TOR CRP portion by appointed TNB Tester and System
portion by System Integrator
Live Protection Maintenance & New requirement under revised GTS-GSE-PROT Incorporated under CRP Panel Certification Process
Load Test specification on Live Protection Maintenance (Phase 2)
Refer to updated SAT document
End of Warranty Test To be performed by Grid Maintenance (GM) Duration 1 year from commissioning for Grid projects
or as specified under PPA
4
Guideline on Digital Substation Implementation Process
Protection Automation & Control
Grid Solution Expertise Department
Our Ref : GRID/GSE(PAC)/Digital Substation
Implementation Process
Revision: 1.2 Date: 3/6/2021
1.1 17 Nov 2020 Added Main Contractor role in the process flow as per discussion between GSE and GD (Design)
Design Verification process to be conducted in 2 stages:
1.2 3 Jun 2021 Stage 1: CRP Design Verification (Panel + IED)
Stage 2: System Verification