Job Package: 25-203-AD01-A-YC-008

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

Job Package document no.

Job Package 25-203-AD01-A-YC-008


Client: Project description:
Schlumberger Technology Corp GT1000
Cost code: Task ID: Equipment: Date prepared:
On Track System
Responsible executor: Revision:
Cameron software technician Hyd/Mech Software Electrical -
Activity: Est. installation hours:
Deployment of release “Presto 1.1 and Sprint 01_21”.
Purpose: 48
This is an upgrade to Presto 1.1 and of the OnTrack rig control system for standardization of hardware,
improved stability and general system upgrades.
Expected results: Est. test hours:
Improved stability
Related test procedure: Equipment required to perform test procedure: 48
See document reference below
Made by:
Goran Peselj
Personnel required:
2 x Service technicians.
Special tools(s) required:
Laptop, memory stick, ethernet patch cable, aomei booth stick.

Parts list:
Item number Quantity Description

Action No. Job Description: Used time Status Sign.


1 Before downloading new PLC software, make sure to have a backup of following:
 System backup from all PLC’s.
 Snapshot of the DB’s
Backup of all online Simocode, WAGO and Drive settings
Upload the backup to SVN and/or store it on a separate medium
2 Download all PLC modules mentioned in 25-203-EA07-A-XF-110 & 25-203-Z-EA01-A-
SN-001. It is basically all PLC software prepared in SVN:
25/25_203_SLB_GT1000/Release/PLC. All of the needs to be downloaded since it’s an
upgrade to TIA15.
3 Replace old hardware (S1,S2,OH, & TT) Ref. 25-203-AD01-A-YC-005.
Note: New hardware have all necessary software installed and tested.
4 Install new images. First, install new images only to computers that are crucial for the
operation:
 X1
 TPL
 TPR
Ref. 25-203-AD01-A-YC-004
Note: Prepared Images have all necessary software installed and tested.
5 Download new Cisco switch configuration. Ref. 25-203-AD01-A-YC-007
New switch config located in SVN: 25/25_203_SLB_GT1000/Release /Network/Switch
6 Complete job package 25-203-AD01-A-YC-001. Step 1-4 are not applicable as they
have already been taken care of in this job-package.
7 Complete software update test procedure. Ref chapter #6 in 25-203-EA07-A-XF-110

Cameron Sense template T-08-01-01, rev. 04 1/2


Schlumberger-Private
Action No. Job Description: Used time Status Sign.
8 Complete the “Commissioning Procedure DrillOps Presto 1.1 Upgrade”
Ref. 25-203-AB01-A-XF-043
9 Perform the final “Site Test”. Ref chapter #5 in 25-203-Z-EA01-A-ST-001
10 When all steps above are completed and the rig is fully back to operation. Start on the
“offline” part of the job. Install new images to:
 OP1 (HPU)
 OP2 (PCR)
 OP4 (Ex)
 OP5
 WS1
 WS2
Ref. 25-203-AD01-A-YC-004
Note: Prepared Images have all necessary software installed and tested.
11 Install the RA Computer. Ref. 25-203-AD01-A-YC-003
12 Upload all installed rig software to SVN:
25/25_203_SLB_GT1000/PLC/Software
Total hours used:

Consumables:

Drawing & document reference:

Document reference:
 25-203-Z-EA01-A-SN-001 - Software Release Note
 25-203-Z-EA01-A-ST-001 - Software Release Test
 25-203-EA07-A-XF-110 - Software update releases - Rig test procedure
 25-203-AB01-A-XF-043 - Commissioning Procedure DrillOps Presto 1.1 Upgrade

 25-203-AD01-A-YC-001 - Integration of DrillPilot and DrillOps


 25-203-AD01-A-YC-003 - Remote access installation
 25-203-AD01-A-YC-004 - New Images
 25-203-AD01-A-YC-005 - HW Replacement
 25-203-AD01-A-YC-007 - Upload Cisco Configuration

Remarks/Update of documents: (responsible executor on site/rig)


Document Control: [email protected]

Software checkout: (if applicable)


Equipment / Computer / PLC Revision after testing is complete: Compared online vs. offline version: SW Stored on remote computer

Start date: Completion date: Date/ Cameron signature: Date/ Client signature:

Cameron Sense template T-08-01-01, rev. 04 2/2


Schlumberger-Private