Rrnmu Manual
Rrnmu Manual
Rrnmu Manual
Government of India
Table 1.1: Nodal Agencies for PMGSY Works in the RCIP States
All rural roads constructed under PMGSY that are older than 5 years and have completed their initial
PBMC built into the construction contract, upkeep and management of such road network for
preserving the assets is the responsibility of Nodal Agency. The Agency would, over time, be
responsible for these activities not only in respect of PMGSY roads but the entire rural roads sector. A
typical set-up for the Nodal Agency in a State is shown in Figure 1.1
Thirty RRNMUs have been set up as an intermediary facilitating organization between SRRDA and PIUs,
initially covering maintenance activities for planning, programming, and budgeting in a network management
concept covering multiple PIUs. Each RRNMU will be a zonal or regional level organization in the hierarchy of
the state. The PIUs continue to undertake the execution of new construction works, whilst maintenance planning,
programming, budgeting after the 5-year post-construction period will be managed by the newly introduced
RRNMU. The PIU will provide all the data needed for the planning purposes, and after the planning and
budgeting have been finalized by RRNMU, PIUs will undertake the execution of the maintenance works. A
satellite model of the RRNMU based on a 3-tier working system of SRRDA would subsequently be developed
as shown in Figure 1.2
a. PIU has to be adequately staffed for new PMGSY roads as well as rural road
maintenance activities. Staffing may be periodically reviewed and appropriately amended
depending on the ongoing construction and maintenance works. The staffing will require to be
balanced as the need for new road works will eventually fall off and the demand for
maintenance works will increase.
b. PIU personnel are to be deputed for regular training in technical, accounting, contract
management, asset management, and quality management of rural road construction and
maintenance. RRNMU Management will arrange for training of its staff in coordination with
the staff of the RCTRCs. Other SRRDA personnel will periodically be included in such
training programs.
c. PIU personnel are to have a tenure of at least 3 years. Frequent transfers, particularly
of trained and experienced staff, adversely affect programming and implementation of
maintenance and construction programs and require additional investments in training and
HRD.
This database needs to be regularly updated with a full inventory and condition database for the
network to be of optimum use in maintenance management. This system has the GIS interface, the
road, culvert, and bridge inventory data with a pre-decided frequency of condition survey that needs
to be incorporated in the online database system.
The basic principles of this On-line Monitoring and Management System (OMMAS) are:
data is entered at the point of origin, (i.e. at PIU and RRNMU levels);
the same data is available in the processed form at SRRDA and NRRDA levels; with a
facility to drill down to basic units i.e. ‘road’ and ‘habitation’;
MIS outputs can be tailor-made to suit PIU, RRNMU, SRRDA, and NRRDA needs and
thus eliminate paper reporting.
The OMMAS has been created as a transparent (to citizen) website-based information
system with access by all stakeholders: PIUs, RRNMU, SRRDA, STA, SQC, NRRDA,
NQM, etc. to enable pooling of data emanating from a variety of sources.
CHAPTER 2
The Road Network
2 THE ROAD NETWORK
Historically, roads were simply recognizable routes without any formal construction or maintenance.
The Organization for Economic Co-operation and Development (OECD) defines a road as "a line of
communication (traveled way) using a stabilized base other than rails or air strips open to public
traffic, primarily for the use of road motor vehicles running on their wheels", which includes "bridges,
tunnels, supporting structures, junctions, crossings, interchanges, and toll roads, but not cycle paths".
‘The Legal Insider’ defines the “Road Network as all types of roads, including international roads,
national highways, district roads, feeder roads, urban roads, mule tracks/ trails, and roads not under the
authority of a Department, such as but are not limited to forest roads, farm roads, power tiller roads,
telecommunications road, power roads, mining and exploration roads, industry roads, health roads,
education roads, public roads, private roads, project roads and all the types of bridges on that road.”
For this document, we will restrict the definition of the road network to all the roads that come under
the purview of RRNMUs, the rural roads constructed under PMGSY or by states, and maintained by
the department.
2.2 PREPARATION
The identification and inventory of rural roads to be maintained by the maintenance agency is the basis
for maintenance management. It is necessary to identify and inventory the roads for the initial
documentation of the network. As the road network will change with time (as new roads are
constructed or roads are transferred to and from the jurisdiction of the rural road maintenance agency ).
it is essential to carry out periodic checks and update the inventory at frequent intervals. There are
three stages in the preparation of the inventory:
Identification
Inventory
Categorization
2.2.1 Identification
A list of all rural roads that need to be maintained (this is usually presented as a zonal/area map of the
geographical coverage of the maintenance agency) should give basic information on:
• Road no;
• Start/endpoints (to/from);
• Class/category of the road (TR – through routes collect traffic from link roads or chain of
habitations and connect to higher category road, such as district, state, national highway; LR –
roads connecting one or more habitations to TR or higher category road.)
• Surface type;
• Traffic (AADT/EDT);
• Linkage to other roads (best shown on a map and usually undertaken during regular inspection
and condition survey of the rural road network);
• Major structures.
2.2.2 Inventory
This stage is the collection and recording of more detailed information on the locations of each
infrastructure feature and their location along that road.
The inventory should be recorded in as much detail as is possible, subject to constraints of time and
resources, and in line with local requirements and practices. The information in Table 2-1 is
considered as ‘necessary’ and ‘desirable’ for efficient maintenance operations. Standard forms may be
prepared for recording inventory information or, more sophisticated, GIS and/or computer-based
logging systems may be used for this.
Table 2-1: Information Relevant to Maintenance Management
Location of inventory features is important. This may be fixed by vehicle odometer but a
complementary measure that may be considered is the installation of km posts along the road by fixing
km 0 as one end or the other of the road in question. Some roads may tend to have very different
characteristics along the length of that road (e.g higher traffic volumes between the main road junction
and a quarry, thereafter little traffic) and it may be suitable to sub-divide the road into different
sections which might be considered separately for planning, prioritization, design, and justification for
maintenance interventions.
2.3 PRESENTATION
Maps may be used at two levels:
a database that is a computer-based RMMS or GIS system may be used to present data
visually.
strip plan
a. Terrain map
Rural roads may be marked upon a geographical map which also shows locations of physical features
such as watercourses, villages (a scale of 1:250000 can be useful for overall network presentation),
and Survey of India: Topographical Map 1:50000 can show greater colour-coded detail (e.g. road
condition, individual inventory features, contract packaging) and useful for display. These maps are
available in digitized form for some rural areas under IRS-P5 CARTOSAT 1 and IRS – P6
CARTOSAT 2. Such digitized maps can be readily updated and scales adjusted as required.
b. Diagrammatic map
Roads may be shown as straight lines between nodes/junctions giving a clear network layout including
inventory features although not to scale. These maps can also be digitized.
c. Strip plan
This is a detailed variant of the diagrammatic map that shows each road represented as a straight line
on which inventory features are marked on each side of the road centreline. An example showing
typical inventory details is shown below in Figure 2-1. Typical pre-printed blank proformas for site
recoding of inventory features are set out in Annexure B-1.
Another variant of the strip plan is a segmented map in which the road is divided into sections (e.g.
lengths of 5 km) and marked up with inventory features. These maps often show the geometric
alignment of the road and are most easily handled in digital format. These maps can show the
inventory information in greater detail and also has additional (overlay) information such as condition,
maintenance, contract data, accident and traffic figures, etc.
Source: Rural Road Maintenance Management, Bjorn Johannessen, IT Transport Ltd, 1999
2.4 CATEGORISATION
Although the rural road may already be classified following the national/state road classification
system, within this network there will be functional categories of the rural road e.g. village access,
through road, link road as identified under PMGSY. This functionality is often confirmed by
population, traffic and usage characteristics, or political importance. Broadly categorizing the rural
roads can give a useful hierarchy of strategic value or importance of a road within the network which
can be useful for prioritization. An example of such categorization criteria is given below in Table 2-
2.
Table 2-2: Categorization of Roads
For the rural roads devolved to PRIs, simple inventory details (length, width, cross drainage works)
and visual condition surveys may be carried out and a unique ID is given to every rural road. This
should form the basis for the preparation of Annual Maintenance Plans. While data regarding the
length of the core network is regularly updated by the states and the NRRDA. For rural roads with
the PRIs, there is currently no system of road inventory and condition surveys. Traffic counts are
also not practiced on these roads. However, data on the length and width of roads is available at the
district level in many of the states.
Where this Masterplan does not exist, the District Panchayats should lead the process in
collaboration with Gram Panchayats and Block Panchayats:
Prepare a layout of the roads from the existing revenue map of the District Panchayat and
plot the District Rural Roads Plan (DRRP) on it.
The Colour code on the roads of the map as yet to be constructed and yet to be upgraded.
Each rural road in every district should be given a Unique ID number just as Aadhaar
Card for every citizen so that the total stock of rural roads is available at one place in the
Zilla Panchayat Headquarter. The Zilla Panchayat, through the GIS platform, can
monitor and track the progress of road activities including maintenance.
The Zilla Panchayat will coordinate with the State Rural Roads Development Agency
(SRRDA) in the state through the PIU and RRNMUs for monthly progress review and
coordination meetings.
The Zilla Panchayat will strengthen the capacity of Block/Mandal Panchayat by placing
Junior/Asstt. Engineers and Revenue Patwari/officials to prepare the maps as mentioned
above.
The SRRDA would support in training of Gram Panchayat and Block/Mandal Panchayat
Engineers and Revenue officials, through RCTRCs
It is expected that this Master Plan and Core Road Network will be updated as necessary and at
least at an interval of five years. The procedures for initial preparation of the Master Plan and
CRN are set out fully in the NRIDA’s PMGSY Operations Manual Chapter 3: Planning. These
procedures may be taken as a template for updating. Once the Core Network is revised to the new
set of village populations, the road length to be catered under each RRNMU will change
encompassing more road lengths of the new core road network in the updated master plan.
CHAPTER 3
Inspection And Condition
Survey
3 INSPECTION AND CONDITION SURVEY
Inspection and condition surveys, undertaken on a regular periodic basis, are useful for RRNMU and
PIUs:
a. to enable a detailed knowledge of the rural road network, problems, and potential weaknesses;
b. to make objective assessments of maintenance needs;
c. to prioritize routine and periodic maintenance works;
d. to draw up a program of future maintenance needs;
e. to monitor and review the effectiveness of post-maintenance and construction works;
f. to respond more rapidly and effectively to emergencies.
Basic steps for inspection and condition surveys are similar for road inventory surveys, but
concentrating on condition rather than identification and location of individual features. Locations are
identified where deterioration is taking place and the nature of the defect is recorded. Quantification of
defect may be by visual assessment or empirically (e.g. FWD, Bump Integrator, Benkelman Beam).
a. A trained team uses standard procedures and equipment to identify and measure defects
including locations where further investigation might be necessary;
b. Follow up involving more experienced engineering personnel, additional investigation, etc.
This approach ensures that a ‘second opinion’ by an experienced person is obtained and good use of
resources is done by ensuring that ‘higher powered’ identification, quantification, and diagnosis is
concentrated on areas of greatest need.
Completed forms should be retained in the original format. It is desirable to record results in tabular
form. Recording may also be directly logged digitally as an input to a customized RMMS or linked to
GIS location registration. GIS and GPS technology should be used to the maximum extent possible for
information mapping and data collection for the provision of spatial location, statistics, and as an input
to OMMAS.
Recording defects is an activity closely akin to procedures for inspection and condition survey. For
scheduled activities (e.g. routine maintenance) records should show the location and extent of
necessary treatment. For other activities in response to road conditions, records should log not only the
location and extent but also the severity of the defect. Recording may also be directly logged digitally.
Given that the time available for the condition survey is often limited, effort should be concentrated on
the highest priority issues as listed in Table 3-1.
Table 3-1: Priority Issues in the Condition Survey
This method requires a rapid survey of the entire network. Each section of road is subdivided into
lengths of, approximately,1 km and the condition of features of that subsection is assessed, (i.e. road
(pavement, surface, shoulders), drainage, structures/culverts, and bridges) each feature is then rated
from 1 (no defects) to 5 (complete failure). For each rating of 2 or more, a diagnosis/remedy is
indicatively given in the table below and unit cost may be estimated for each defect category for each
subsection of road, a sum of these will give an estimated cost per km. The length of each subsection
may be varied, again depending on the homogeneity of road conditions and degree of detail required.
Additional defect categories may be added if considered appropriate, although this will then tend
towards a detailed estimate as required by the Engineer’s estimate method.
This is a more detailed procedure that provides greater accuracy in diagnosing problems, remedies,
and estimating costs. Given the additional resources required for this level of accuracy, it is suggested
that this method should only be used in the preparation of works contracts (i.e. when adequate budget
provision is assured). The procedure has two steps:
b. Estimation of costs
The indicative remedial actions for (surfaced rural roads i.e. PMGSY standard) different condition
ratings are given in Table 3-3 and Table 3-4. Different rates of criteria would apply to other types of
road (e.g. gravel road, engineered earth road, and non-engineered track).
Table 3-3: Indicative remedial actions for different condition ratings
Carriageway &
Drainage Culverts Bridges
Rating
Shoulder
Descripti
Remedy Description Remedy Description Remedy Description Remedy
on
Routine Routine
No work No work
5 No defects activitie No defects activitie No defects No defects
s only s only required required
Clear Clear
Minor Minor Minor Minor Clear silt/
Minor drain/ silt/
4 surface sedimentatio sedimentati sedimentatio repair
defects repair repair
repair n /erosion on/erosion n /erosion erosion
erosion erosion
Major Clear
Major
sedimentatio drain/repa Major Major
defects, Major Major
Major n/ erosion ir sedimentatio sedimentatio
but clearing or clearing/
surface but no erosion; n/ erosion, n/ erosion,
access is repair
repair danger or construct but access is but access is repair
3 not at required
risk to scour not at risk not at risk required
risk
access checks
Reform
camber
and Repair
Access is Structural Structural
drains, erosion;
lost or at Major repair; repair;
reconstru construct
risk; the damage to Impassable equivalent Impassable equivalent
ct scour
passage drains; / dangerous to half /dangerous to half
2 pavemen checks;
is access at to pass replaceme to pass replaceme
t, and dig new
dangerou risk nt cost nt cost
improve drains
s
surface
Reform
camber
and
drains;
Road not reconstru Replace Replace
Complete Reconstru
accessible ct Collapsed culvert; Collapsed/ bridge:
failure of ct
road pavemen /absent consider absent requires a
1 drainage
pavement t and drainage culvert enlargin bridge detailed
system
failed improv system g survey
e
surface
This is also a type of ‘broader brush’ approach based on the assumption that maintenance costs may
be typically based upon an estimated unit rate for road length, no. of structures (including CDS) with a
‘factoring’ effect based on local conditions (e.g. terrain, traffic, soils, weather). Typical weighting
factors are set out in Table 3-5 below (but these should be subject to local adjustment for local
indicators).
Table 3-5: Typical Weighting Factors for Maintenance Costing
These are usually used only as a preliminary estimate of maintenance needs for budget preparation,
subsequently, one of the other methods may be used.
a. Scheduled activities are predictable activities that can be planned with reasonable
confidence (e.g. grass cutting, ditch cleaning). The severity of the defect does not
visually have to be identified, only the location and quantum (e.g. sq. m of grass
cutting, length of a longitudinal ditch to be cleared between identified chainages).
With experience, other activities can be predicted even if their location cannot be
pinpointed (e.g. it is reasonable to expect that small diameter CDS will require
cleaning after rains) and provision can be made accordingly.
b. Activities in response to road conditions: These activities are not usually predictable
and a measure of necessary remedial works depends upon the identification of the
defect (e.g. broken culvert headwall). Once repaired, the defect, hopefully, will not re-
occur.
c. Emergency Activities are usually required at short notice in response to the threat to
access or danger, emergency works are usually dealt with under a response system
that is complementary to pre-planned maintenance works. Emergency response is
covered in greater detail in Annexure B-2.
3.4 RECORDING DEFECTS
Pre-printed forms may be used as a checklist for the information required. These forms may be
tailored to local needs but should be kept simple and easy to understand. Should a major or
complicated defect be identified then further detailed investigation may be required.
For scheduled activities, the forms will show the location and extent of necessary treatment. For other
activities in response to road conditions, the form should record not only the location and extent but
also the severity, of the defect. The procedural guidelines for conducting the Rural road maintenance
and the filled sample form for the condition survey is in Annexure B-3
Defects may be recorded as considered most appropriate locally (e.g. numerically from 5 (good
condition) to 1 (very poor condition), or descriptively) as long as the recorded information is sufficient
to diagnose, identify treatment, and quantum of that activity.
Alternatively, recording may also be directly logged digitally as input into a customized RMMS
and/or linked to GIS location registration.
Some situations that are common on surfaced rural roads (e.g. PMGSY standard), diagnosis of a
possible cause, and suggested remedial action are given in Table 3-6. The frequency and quantum of
intervention would depend on the severity of the defect and specific local conditions (e.g. traffic,
climate, etc.).
Table 3-6: Common Defects and Causes in Rural Roads
Drainage
Flowing water Drain may overtop and
Drain is Clear drain
deposited sediment in damage the carriageway
sedimented
drain
Vegetation in Drain poorly Drain will block rapidly and
Grub vegetation
base of drain maintained overtop
Repair erosion
Erosion in side Flow in drain too high Erosion will worsen Construct/repair scour
drain or too fast Soil is Carriageway may be checks Line drain
erodible undermined
Dig mitre drains
Scour checks are Flow in drain too Continuing damage and Repair scour checks Dig
damaged high or too fast erosion mitre drains
Drain was dug to an Soft spots may develop and
Water ponding in Reform drain gradient
inconsistent gradient weaken road pavement
drain
Foundation failure
Lack of load transfer
Corner cracking Full-depth repairs
joints
(D cracking is a Increasing Crack sealing with
variant usually Ingress of debris in joint deterioration of road
or dowel bars restrained bituminous compounds
manifesting at pavement
corners) thus preventing movement
Poor quality aggregate
absorbing moisture
Inadequate carriageway
width
Poor shoulder maintenance
Soluble salts in pavement Reducing Repair carriageway
materials (calcrete or similar)
carriageway width and shoulder
Carriageway Poor shoulder material or
Possible threat Check and amend
edge breakaway compaction
to road pavement camber and drainage as
Poor drainage integrity necessary
Safety issues
According to the policies for rural road network management and maintenance, prioritization stages in
a ‘screening’ process are:
Full access – providing safe, reliable, quick, comfortable all year access
Basic access – providing safe, reliable, all-year access
Partial access – a minimum level of access at a low cost.
Stage 2 – Maintain roads in relatively good maintainable condition before rehabilitating roads in the
poor (un-maintainable) condition, i.e. preference needs to be given to the maintenance of the roods
before they reach the level of rehabilitation
Stage 3 – Prioritise – this procedure can be used to differentiate between competing maintenance (RM
& PM) and rehabilitation needs. A range of possible procedures, based on the availability of data, is
available and the most appropriate procedure for local needs should be selected. These alternatives are
summarised in Table 4-1.
Table 4-1: Prioritization Procedures
Sl. No Procedure Key Features
The Road Economic Decision (RED) model is a simplified version of the
1. HDM/RED complex Highway Development and Management (HDM IV) computer
software package
Based upon identifying and maintaining a set of core roads within the rural
2. Core Network
road network.
Suited to a Basic Access standard on low volume roads combining technical
3. Socio-economic
analysis with community consultation.
benefit/cost analysis
Places high priority on community participation and the needs of rural
Integrated Rural
households. Most suitable for very low volume roads and village tracks and is
4. Accessibility Planning
often used in association with other infrastructure and mobility projects.
(IRAP)
Rapid and requires little data collection using population in a specific area of
5. Cost-Effectiveness
influence of a road as an indicator of the social impact of road improvements.
Indicator
These procedures use social, economic, strategic, and technical factors. Chapter 7 deals with
Environmental issues.
RED (Road Economic Decision) model is similar to HDM IV but takes into account accessibility and
other costs and is more appropriate for rural roads with AADT 50<x<200.
Consult communities within the catchment area of the rural road(s), explain the consultation process,
establish criteria for selection, screening, technical analysis, and ranking, identify the candidate roads.
4.3.2. Screening
Usually involving strategic considerations of the wider road network, checks are made to ensure that
the candidate roads identified by community consultation
This analysis calculates an Accessibility Index (AI) based upon estimated accessibility and
construction/maintenance costs. Candidate roads are ranked by AI, where AI is equal, the candidate
road with the lowest long-term maintenance cost is marked highest. The calculation of the
Accessibility Index is shown in Annexure B-4.
Current road condition 50>x>10 (Poor condition has more points than good
condition)
25 points for accessing an area of acknowledged
Local social factors, (e.g. poverty)
poverty
Linking primary/secondary tertiary/other access
Connections with other roads
Traffic levels (motorized and nonmotorized) 50>x>25>x>10 High, medium, low traffic
(AADT/EDT to be defined)41
25>x>15>x5 25 points for accessing an area of
Economic potential
acknowledged potential (to be defined)
Existing transport services 25 points for bus service
Health, market, educational, agricultural
processing, tourist, religious, or administrative 5-25 points per facility
facilities
Road Categories
Road category Av. Daily traffic Surface type
1 Strategic roads Paved
2 >1000 Paved
3 500-1000 Paved
4 200-500 Paved
5 <200 Paved
Activity Prioritisation
Priority Road Category
Type of maintenance activity
1 2 3 4 5
Urgent 1 7 8 9 10
Routine drainage 2 11 12 13 14
Routine pavement 3 15 18 21 24
Periodic 4 16 19 22 25
Other routine 5 17 20 23 26
Special- major activities such as 6 27 28 29 30
capital works or reconstruction
A flow chart of the process from condition survey to prioritization and packaging for tendering on a
basis of need is shown in Figure 4-1.
This proposed procedure is partially used in some States for PMGSY maintenance/routine
maintenance activities. Prioritization is based upon the assessment of road condition (road pavement,
shoulders, drainage, CDS, and road furniture) with consideration to additional factors such as rainfall,
terrain, age, and usage.
Good quality condition surveys demand a certain minimum input of resources – time of suitably
experienced personnel, travel costs, etc. The survey information is also a deteriorating asset, as the
roads’ conditions are continually deteriorating (albeit at different rates as they are subject to different
designs, conditions, and usage) condition survey information will become less accurate with time.
The RRNMU/PIU may not have the resources (including time) to carry out a full survey of all rural
roads in the network nor may this be necessary. Some roads are likely to be in good condition such
that only routine maintenance is required. The first step is to make a rapid inspection of all roads such
that the network is broadly grouped into two categories:
Roads in good condition requiring only routine maintenance [condition ratings 3, 4, 5]
Roads requiring additional works (and additional investigation) [condition ratings 1, 2]
A more detailed condition survey should target the second category. Where the survey work may be
carried out using fewer resources than expected, or when more funds are available, the roads in the
first category may also be surveyed as appropriate. The ‘first pass’ inspection could combine a visual
inspection with a ‘drive through’ whereby an approximate. condition rating for a road as a whole
could be derived either from a safe vehicle driving speed or comfort level at 50 kph – see Table 4-5.
Table 4-5: Estimation of condition rating by vehicle speed
Condition Rating
Defect
1 2 3 4 5
Riding comfort at 50 kph Very rough Rough Not Comfortable Comfortable Smooth
Safe driving speed kph <10 10 - 20 20 - 30 30 - 40 >40
The above methods are very subjective and could lead to different assessments. ‘Bump Integrators’
may be used for getting a more rigorous assessment of condition rating based only on road pavement.
This parameter can then be used for rating the road pavement conditions at identified points along the
road length as given in Table 4-6. The use of Bump Integrators is limited as they are not always
available and require expertise that may not be available at the PIU level, also they require frequent
calibration for which local facilities may not be available.
Table 4-6: Estimation of condition rating by Bump Integrator
Condition Rating
1 2 3 4 5
Defect
Very Not
Rough Comfortable Smooth
rough Comfortable
Surface dressing >4500 4000 - 4500 3500 - 4000 3000 - 3500 <3000
Open graded premix
>4000 3500 - 4000 3000 - 3500 2500 - 3000 <2500
Seal coated
Semi-dense bitmac >3500 3000 - 3500 2500 - 3000 2000 - 2500 <2000
Bituminous concrete >3000 2700 - 3000 2400 - 2700 2000 - 2400 <2000
Cement concrete >3000 2750 - 3000 2500 - 2750 2250 - 2500 <2250
Although at present the PMGSY roads have surfacings of Premix carpet (PMC) seal-coated wherever
the road passes through open areas, and cement concrete within the built-up areas, other forms of
surfacings have been included keeping in view future requirements.
The methods mentioned in the previous paragraphs take into account only the condition of the
carriageway whereas the rural roads are also seen to be very deficient in the condition of shoulders,
embankments, drainage, cross-drainage, signs, and safety measures, etc. Therefore, a system that is
responsive to these requirements and gives an accurate assessment of road conditions in terms of
various parameters of interest, along with the estimation of quantities of remedial works and costs that
can be achieved with available resources is the need of the hour. For this, a detailed condition survey
system, Road Condition Rating (RCR), has been proposed. The survey should be carried out at a
suitable time, therefore, the period immediately after the rainy season when the conditions are at their
worst is proposed to be adopted for data collection.
The condition survey should collect accurate information on rural road conditions. A format for
recording this information onsite is presented in Annexure B-1 The road may be divided into sections
of 200 m length and the information inserted in the form during the survey at the road site. This may
initially be in paper format for subsequent uploading onto a computerized version or directly onto a
laptop or tablet. Additionally, equipment e.g. GARMIN which records photographs of the road at say,
200m intervals, with GPS reference may be used. The rate of progress will depend upon road
condition and the travel times to and from the road to be surveyed. It is likely to be in the range of 10-
12 km per day. The information recorded onsite on the suitably designed Condition Assessment Form
for flexible pavement is in Annexure B-7 may be completed directly onsite or at the office. Table 4-7
and Table 4-8 indicate the rating of the various designated parameters from 1 to 5 for the degree of
distress indicated. Since there are 13 parameters and 5 levels of distress for each parameter, any
subjectivity that may creep in is assumed to be self-adjusted. The technique is manual and based on
visual assessment, without the use of any equipment and therefore it can be undertaken by the junior
PIU staff after minimal training.
Table 4-7: Estimation of condition rating by detailed site inspection (Bituminous roads)
Condition
Defect Quantum Rating
1 2 3 4 5
Potholes & depressions % area >1% 0.5% - 1% 0.1%-0.5% <0.1% -
Camber Condition Very Poor Poor Fair Good Very Good
Pavement cracking % area >30% 20% - 30% 10% - 20% 5% - 10% <5%
Ravelling % area >30% 10% - 30% 5% - 10% 1% - 5% <1%
Shoving % area >1% 0.5% - 1% 0.1% - 0.5% <0.1% -
Settlement & depressions % area >5% 3% - 5% 1% - 3% <1% -
Rutting mm >50 20 - 50 10 – 20 5 - 10 <5
Pavement edge break % length >50% 30% - 50% 20% - 30% 10% - 20% <10%
Shoulder (grading,
Condition Very Poor Poor Fair Good Very Good
vegetation, trees, shrubs)
Rain cuts alongside
Condition Very Poor Poor Fair Good Very Good
slopes
Side drains % silted 100% 75 - 100% 50 - 75% 25 - 50% <25%
CDS – blocked, %
>75% 50 - 75% 25 - 50% <25% All open
sedimented (erosion) blocked
Road furniture, signs Condition Very Poor Poor Fair Good Very Good
Table 4-8: Estimation of condition rating by detailed site inspection (Concrete roads)
Condition
Defect Quantum Rating
1 2 3 4 5
Rectangular
-
(block) cracking
Corner cracking Extension & Extensive Many Moderate 5 Isolated -
Diagonal cracking width of >10mm >10mm crack – 10mm <5mm -
crack crack width width crack width crack
Longitudinal cracking -
width
Shrinkage cracks -
Transverse cracking -
Joint stepping >5cm 3 - 5cm <3com Slight -
Rocking Incidence Severe Moderate Slight - -
Joints open Major loss of Partial loss
Joint sealant defects Length Failure -
sealant of sealant
Surface spalling >50% 25 - 50% <25% Slight -
% surface
Box-out spalling Severe Extensive Moderate Slight -
area
Ravelling Severe Extensive Moderate Slight -
Pavement edge break % length >50% 30% - 50% 20% - 30% 10% - 20% <10%
Shoulder (grading,
vegetation, trees, Condition Very Poor Poor Fair Good Very
shrubs) Good
Rain cuts
Condition Very Poor Poor Fair Good Very
alongside slopes
Good
Side drains % silted 100% 75% 50% 25% <25%
CDS – blocked,
% blocked >75% 50 - 75% 25 - 50% <25% All
sedimented (erosion)
open
Road furniture, signs Condition Very Poor Poor Fair Good Very
Good
An aggregate road condition rating may be calculated based upon these parametric scores, based on a
matrix of 65 (13x5) cells. Table 4-9 shows the range of RCR values for different road conditions.
The weighted average value of RCR of a network is a true indicator of the Net Asset Value of the
network.
Table 4-9: Indicative range of RCR for different road conditions
This rating allows roads to be rated for prioritization for maintenance and also for assessing the
expenditure needed for making good the distresses e.g. filling rain cuts, dressing shoulders, desilting
drains or CD works, filling potholes or profile correction works, for providing the missing items such
as signs, safety provisions, a non-existent side drain, etc. Projected expenditure on these items of
works will be taken as initial rehabilitation (IR) or special repairs (SR) while assessing the budgetary
requirements.
These RCR scores can be used for rating the pavements. The RCR score is a number that is a true
indication of only the present condition of the road but gives no indication of its potential rate of
deterioration with time under traffic and environmental aspects. Potential deterioration is an important
consideration in deciding priority especially, in the situations of likely budgetary insufficiency. Road
Condition Index (RCI) is used in accounting for the influence of the factors such as Rainfall, Terrain,
Age since the last major renewal or strengthening, and Traffic volume as indicated in Table 4-10.
Table 4-10: Factors for Calculation of RCI
Factor Criteria Multiplier
Low: <500mm/year 1.25
Medium: 500- 1.15
Rainfall
1000mm/year
High: 1000mm/year 1
Mountainous & hill
Terrain 1
areas
1.25
Plain & rolling terrain
Weighted Road Condition Score WRCS = RCS x Rainfall multiplier x Terrain multiplier
NB: if the calculated WRCS > 50, use a maximum value of 50
>5 years 0
Age of road pavement since last 4 - 5 years 5
major renewal or strengthening 3 - 4 years 15
2 - 3 years 25
1 - 2 years 30
Through road Major link Link
0 - 50 5 10 20
Traffic volume (commercial 51 - 150
vehicles per day) 4 8 15
151 - 300 2 6 10
>300 0 2 5
RCI (overall condition/serviceability of rural road) = (W)RCR + Age factor score + Traffic volume
score
RCR Age factor score Traffic volume score Total (Overall RCI)
Min. Max. Min. Max. Min. Max. Min. Max.
10 50 0 30 0 20 10 100
The Weighted Road Condition Rating (WRCR) value, obtained by multiplying the normal RCR value
by Rainfall and Terrain multiplier factors. Since the maximum of add-on factors for the age of road
pavement since the last major renewal or strengthening is 30, and traffic volume is 20, this adds up to
50, to limit the RCI value to 100, it has been mandated that the WRCR will not exceed 50. If the
calculated value of WRCR comes to more than 50, the value will be adjusted to 50.
The RCR value of a Road or a road section will vary from 10 to 50, showing complete correspondence
with the traditional PCI value of 1 to 5 for comparison and comprehension. The RCI value of a road
will vary from 10 to 100. Photographic examples of various types of road pavement distress are
presented in Annexure B-8.
The outcome of the condition survey is an objective RCI value, the compilation of a list of all
surveyed roads will result in a priority list i.e. the higher the RCI the better the road condition. RCIs
can theoretically range from 10 (notionally a through road over 5 years old in mountainous/hill terrain
in very poor condition, subject to heavy traffic and high rainfall) to 100 (notionally a link road less
than 2 years old in very good condition, subject to low traffic and low rainfall). In practice, neither
extreme is likely to be encountered. Indicative values of RCI for different condition ratings are given
in Table 4-11.
Table 4-11: Indicative range of RCI for different road condition rating
The survey can also be used to record potential repairs/remedial measures and an estimate of
quantities (e.g. condition rating 2 for cracking [Table 17: column 4] implies a potential heavy
patching/reconstruction of 20-30% of road pavement area).
Specimen Condition Assessment forms and calculations of RCI for bituminous and concrete
pavements of RCI are given in Annexure B-9; also a case study of prioritization for a rural road
network.
Measurement of RCI pre and post remedial treatment/maintenance enables a ‘before’ and ‘after’
assessment of network condition which may also be used not only to demonstrate the efficacy of
maintenance regimes and compare different treatments but also to contribute to the monitoring of asset
value of a network and compare factors impacting the service levels of rural roads (e.g. climate,
traffic). A case study of RCI as a monitoring tool is given in Annexure B-10.
Monitoring of trends in the condition of a rural road network may permit a predictive function to
permit longer-term network management including projections of maintenance and assignment of
budgetary needs. PMGSY roads are designed for an economic design life of 10 –12 years (NRRDA
Ops. Manual 5.6), i.e. an initial RCI of 100 immediately after construction may be expected to reduce
to the minimum value of 10 over 10 years, if no intervening routine and/or periodic maintenance is
carried out, as depicted in Figure 4-2.
10
Figure 4-2: Schematic deterioration of a road with time
The decay rate will vary (steeper or flatter) depending on different standards of construction and usage
factors (e.g. climate, traffic loading), as depicted in Figure 4-3.
10
Changing road use is often facilitated by the road itself. Confidence in continuing good condition and
predictable all-weather accessibility usually leads to:
d. Urbanization – growth of villages in the catchment areas of the well-maintained rural roads.
There are four responses to such changes, three of which are not mutually exclusive upgrading
including road widening; safety management; general condition improvement. The fourth option of
‘do nothing’ is not a sustainable option as the changed conditions and increased usage of the road will
not be fully realized as this option will lead to accelerating deterioration of the road condition.
a. Upgrading including strengthening and widening the carriageway will better accommodate
higher and heavier traffic volumes. Upgrading may also reduce maintenance and whole life
costs
Studies, over and above those required for annual network management planning, may contribute to
longer-term response and revenue and budgetary planning and such studies may be undertaken by
RRNMUs including the following issues:
Traffic – estimation of traffic growth, including the growth of heavy traffic arising from
industrial and urban development and optimal measures to accommodate such traffic (budgets,
standards, planning policies, road classification, technical standards, etc).
Budgetary, revenues, and expenditure reviews – costs and benefits of strategic planning
(economic and social), revenue forecasts, sources of funding, etc.
Based on the RCR Survey by the PIUs and Prioritization based on RCI at RRNMU, the ideal budget
request will be prepared annually in November-December by the RRNMU with the help of PIUs and
submitted to the Government through SRRDA. A list of roads for inclusion in the proposed annual
maintenance plan is to be prepared by the RRNMUs for the respective regions. The maintenance
planning shall be strictly based on need using the network level maintenance philosophy and not on
road by road maintenance policy. The annual proposal shall be prepared based on the following :
a. Where existing rural roads are in reasonably good condition (i.e. RCR is above 30) the
prioritization for maintenance will be taken up under the RCR/RCI procedure. Based on the
likely value of proposals required to be submitted, the RRNMU will mark eligible road works
in the Order of Priority to the required total value of the Zonal allocations by applying the per
km cost based on previous years cost for a similar type of work.
b. Where the existing rural roads are in poor condition (RCR is 30 or less) up-gradation/renewal
of through routes may be taken up as a prerequisite for maintenance (i.e. the road must be
restored to a maintainable condition – periodic maintenance), and the procedure will be as
follows:
Step 1: Make a preliminary selection of rural roads based on the road inspections and visual
condition assessment.
Step 2: Assess the Road Condition of the Identified rural roads from the RCR register or by
updated RCR assessment.
Step 3: Decide the type of intervention required based on the RCR. This refers to a decision
whether the roads require Upgradation or Surface Renewal or routine Maintenance (Rural
roads having PCI 3 or less and age 6 years or more can be taken up for up-gradation/renewal
and the roads with PCI above 3, or whose age is less than 6 years, routine maintenance or
renewal will be sufficient unless there are structural/geometrical/ drainage deficiencies that
need to be improved through up-gradation).
Step 4: A rough estimate of the project cost will be made for all the identified roads based on
the previous year’s costs for per km construction/ up-gradation/maintenance. The total
budgetary requirements will be assessed and forwarded to SRRDA for further submission to
State Government as Maintenance Budget requirements.
Step 5: If the budgetary allocation is less than the requirements, either the improvement
interventions will be scaled down or roads shifted from higher-level intervention to lower-
level maintenance options till the total cost of the proposed maintenance interventions is
covered in the zonal allocation.
Step 6: The candidate roads with identified improvement interventions should preferably be
combined for contiguity or nature of maintenance, etc for making zonal contract packages.
a. Where the road maintenance work is relatively low priority, it shall specifically mention the
population benefited by the proposed maintenance work.
b. Where all rural roads including roads under the Panchayati Raj Department come under the
purview of RRNMU, all cases where the proposed road maintenance work is not eligible (e.g.
it is not an engineered rural road; is not the part of Core Network, it is being covered under
some other program, etc.), the specific reason shall be clearly stated.
c. The RRNMU shall prepare its Annual Program and Budget in November/December with its
associated yearly operations activities and the maintenance program based on actual
maintenance needs of the zonal network.
This will be a communication document from RRNMU to the SRRDA and to the Finance Department
for justifying the budget demanded by the RRNMU for its activities in the entire year. A template of
such an APB is given in Annexure B-11.
Since the State’s annual allocation can be broadly estimated before the communication of the actual
allocation from the State Government, the SRRDA may initiate the process that the Zonal Level Lists
are ready by November each year, and the consolidated State list is ready for submission after scrutiny
by SRRDA in December. This will speed up the process without curtailing the consultative element.
On receipt of the zonal proposals list, the SRRDA will scrutinize the list to ensure that:
a. All the road maintenance works are prioritized consistently based on the Core Network
requirements;
b. The total value of the proposed maintenance works based on estimates is as per the likely
budget allocations.
c. After proposals from all the zones have been scrutinized and found to be in order, the list will
be placed before the Management Committee/Board and then to the State Level Standing
Committee as soon as State/Zonal Level allocation for maintenance is available. The SRRDA
will also compile the likely annual or longer-term routine maintenance budgetary needs (e.g.
5, 10, and 15 years).
The State Level Standing Committee shall consider the complete annual maintenance program
proposals for the State including clearance by the Committees and the nature of Administrative
Approval for the works to enable the preparation of a Detailed Maintenance Plan (DMP). The
Committees shall review the progress of ongoing works and ensure that:
b. Adequate contracting capacity will be available for the proposed road works
e. Identify and resolve any policy, funding, and procedural issues impeding the execution
f. Maintenance of the rural roads network in general and PMGSY roads, in particular, are fully
catered to
g. Approve the budgeting of the annual (or multi-annual) routine maintenance fund requirement
The Committee shall then accord their approval to the proposal of maintenance. The Minutes of the
Meetings shall be drawn, and copy endorsed to SRRDA. On receipt of the approval of the SLSC going
through the Management Committee, the SRRDA shall communicate the approval to the RRNMUs
and PIUs, and RRNMUs will coordinate the process of preparation of Detailed Maintenance Plans.
The respective RRNMUs shall then:-
a. Hold a coordination meeting with STAs and PIUs to determine the schedule for scrutiny of
Detailed Maintenance Plans. At this meeting issues of maintenance interventions and
preparation of DMPs can also be usefully discussed;
Like the preparation of DPR for a new road, if the cost of preparing a Detailed Maintenance Plan is
outsourced, investigation, condition survey, testing, etc. will form a part of the project cost and may
be met from the funds in hand with the SRRDA. The detailed estimates will be prepared based on the
State Schedule of Rates (SSR) and using the Book of Specifications and Standard Data Book
published by IRC. This is required to estimate the cost to tender the maintenance works knowing the
likely cost to be incurred by the contractors and to evaluate the bids received.
After the final approval is obtained from MC and SLSC on the Detailed Maintenance Plan (DMP)
prepared based on visual condition inspection, RCR/RCI, traffic, and other essential data, these are to
be entered by the RRNMU into the Proposals module of OMMAS. The following essential data has to
be entered:
Name of the road (selected from DRRP/Core Network) along with road and habitation data.
Detailed Maintenance Plans, whose data have been correctly and completely entered in OMMAS will
be considered further.
The STA will scrutinize Detailed Maintenance Plans on representative basis after checking that it has
been entered in the proposals module of OMMAS. Detailed procedure for scrutiny is given in Chapter
6. After scrutiny, the STA will clear the DMPs, make confirmatory entries in the OMMAS database
for the Maintenance Plans and return the DMP documents duly certified and countersigned. In case
OMMAS data is incomplete or changes are required as a result of the scrutiny, the STA will ask the
RRNMU to make the changes and verify that they have been made before countersigning the Detailed
Maintenance Plans. The RRNMU will forward the DMPs to the SRRDA after ensuring that the STA
has made the confirmatory entry in the OMMAS.
After compilation of Detailed Maintenance Plans by RRNMU, the PIU will prepare bidding
documents for each package as per the standard procedure. These details will be filled up into the
Draft Tender Document module of OMMAS and a draft bidding document will be generated. As soon
as the SRRDA clearance is received and technical sanction is accorded by the competent authority, the
necessary input regarding dates and modifications in respect of other items will be carried out by the
PIU in the draft bidding document and the final bidding document will be published on the website.
In case all required documents are complete and there is no major capacity or institutional deficiency,
and the data in OMMAS is satisfactory, the proposal is placed before the Empowered Committee. The
Empowered Committee may recommend a clearance of the proposals per the requirements of SRRDA
guidelines.
Based on the clearance letter, SRRDA makes confirmatory entry clearing the proposals into Project
Mode, so that further data entry for tendering can be done by the RRNMU.
CHAPTER 6
Preparation of Maintenance
Plan & Program
6 PREPARATION OF MAINTENANCE PLAN & PROGRAM
Various steps are required to be followed and several agencies are responsible for the preparation of a
maintenance plan and program as given in Table 6-1.
Table 6-1: Steps involved and Agency Responsible in Maintenance Planning
5 Preparation of Detailed Maintenance Plans RRNMU with the help from PIUs
A Detailed Maintenance Plan shall be prepared for each proposed rural road in the network-level
maintenance program and not at individual road levels. The DMP should be based on detailed road
condition assessment and inventory, investigations, choice of maintenance interventions, and
technology choice and should be of such detail that the quantities and costs are accurate for assessment
of the cost of the maintenance interventions. Guidance may be taken from IRC: SP:19 for preparing
the normal DPR for new works and suitably adopted for the DMP.
Before the commencement of the preparation of the Detailed Maintenance Plan, a joint meeting of all
concerned Engineers of RRNMU and PIUs shall be convened by RRNMU to discuss the issues and
the data requirements for the preparation of the DMP. The Engineers will also be appraised of the need
for appropriate measures for specific defects ensuring compliance with extant requirements regarding
environmental and social issues.
The Detailed Maintenance Plan shall be prepared as per the provisions of the relevant IRC Codes of
Practice together with necessary investigation data. Senior Engineers from RRNMU and/or PIU shall
inspect all sections of the road subject to the proposed maintenance regime, before the preparation of
the DMP, even if the preparation of the DMP is outsourced. The Detailed Maintenance Plan is
expected to have the estimation of quantities of specific intervention measures for removing the
defects and the associated costs.
6.1.1 DMP with Estimation of Quantities and Costs
A Detailed Maintenance Plan is to be prepared for each proposal after collecting the necessary base
data. The Detailed Maintenance Plan should contain:
b. Type and condition of the existing road and cross drainage (CD) structures.
d. Growth rate adopted and projected traffic for the horizon year based on the design life in the
case of reconstruction or major rehabilitation.
e. Economic factors – population served, the agricultural and economic potential of the area in
the case of reconstruction or major rehabilitation.
f. Layer-wise design of the pavement along with a sketch of dimensioned cross section
indicating the Pavement Layers, Carriageway (CW), Roadway (RW), in the case of
reconstruction according to the provisions of the Rural Roads Manual (RRM) (IRC: SP 20-
2002).
g. Design details of CD works/ Protection work and associated working drawings in case new
works or if complete rehabilitations are involved.
i. Estimation of cost as per standard data analysis based on SDB and State Schedule of Rates
(SSR).
j. Provision for signs with Logo, and other road furniture, wherever required.
k. The total cost of the proposed road maintenance and cost/ km for the same.
Besides this, the following drawings should accompany the Detailed Maintenance Plan in the case of
reconstruction, up-gradation, or major rehabilitation, as Volume II. All chapters for preparation of a
Detailed Maintenance Plan are referred to for completeness, although for most rural road maintenance
programs, not all will be required as noted below in Table 6-2.
Applicability to
Drawings
maintenance
Key Map, showing the position of State with respect to India, Zone of RRNMU in
the State, and an RRNMU Zone map showing all the Blocks, with the names of Required
each Block marked.
A Block road map showing the Master Plan (i.e. DRRP) and the Core Road
Network and the proposed roads for maintenance.
An Index Map of the roads showing all the roads in the RRNMU zone to a
suitable scale, topographical features like rivers, canals, streams, railway lines, Required
villages, Market Centres, other roads, and Legend.
Plan and Longitudinal Sections of the road, showing 1 km in each sheet.
Not required
Typical cross-sections of the roads. Not required
Detailed cross-sections. Not required
Drawings of culverts, submersible bridges, paved dips, and High-Level Bridges, Only required in case of
giving General Arrangement Drawings (GAD), structural details. provision of new or
replacement structure; i.e.
Drawings of protective works like retaining walls, breast walls, check walls, reconstruction or complete
drains. rehabilitation cases.
6.1.2. Specifications
The specifications in the Detailed Maintenance Plan for road maintenance works will be based on the
IRC ‘Specifications for Rural Roads’ 2004 and SBD for PBMC.
The items of work involved in rural road maintenance are not large in number, and therefore, it would
be advantageous if the nomenclature of these items is standardized. In the case of reconstruction, up-
gradation, or major rehabilitation the estimates and BOQ should be based on the standard items, the
State Schedule of Rates (SSR) prepared using the Standard Rate Analysis for Rural Roads published
by the IRC as ‘Standard Data Book: Analysis of Rates for Rural Roads – 2004’.
While preparing schedules of rates in the case of reconstruction, up-gradation, or major rehabilitation
the following principles should be followed:
a. The Schedule of Rates (SOR) shall be prepared by the competent authority of the State
Government as per the prevalent practice of the State either at State level, Revenue Division
Circle level, or District level as appropriate. States may, at their option, switch over to
district/zone-wise Schedule of Rates with the help of the software made available.
b. The nomenclature of all the items of works must be as given in “IRC - Standard Data Book for
Analysis of Rates for Rural Roads” September 2004 (SDB).
c. The coefficients given in the Standard Data Book Analysis shall be used together with the
adopted basic rates for material, labor, and machinery to compute the rate of the complete
items of work as per the Schedule of Rates.
d. Complete items of work include the cost of labor, material, machinery, and transportation/
carriage. General Conditions in the Standard Data Book provide that complete items of work
include the rate of material at source and also the carriage to the site of work including
loading, unloading, and stacking. States have different practices, in some States, the
component of loading, carriage, unloading, and stacking are added separately to the basic rate
at source, while others follow the all-inclusive rate particularly for items like select soil, coarse
and fine aggregates, bricks, stone, etc. It is recommended that the cost of material at source
and the carriage element using analysis given in Chapter 1 of SDB are shown separately in the
analysis so that the cost of each component is easily distinguishable, verifiable, and
accountable.
e. The Schedule of Rates may be updated annually and the updated Schedule used at the time of
estimation/ technical sanction for the annual proposals for maintenance of rural roads.
6.2 ESTIMATES
The estimates shall reflect the true scope, quantum, and cost of works, based on detailed surveys
wherever applicable and investigations. The following points should be considered in framing the
estimates:
b. The sources of gravel, sand, stone aggregates, bricks, and marginal materials should be
accurately identified, and the availability of required quantity and quality of materials
established.
c. The rates shall be based on the State’s updated Schedule of Rates based on Standard Data
Book: Analysis of Rates for Rural Roads 2004.
Several roads in a Block or the adjacent Blocks (maybe even adjacent districts) can be combined into
packages of a value of Rs. 1-5 crores or as decided by RRNMU.
Though rural roads are generally low volume roads, the technical inputs required may be quite high
because of the need to cater to the sensitivities of the local communities directly affected by the road
and to ensure a practical, durable, timely, and economic maintenance treatment. As such, scrutiny of
the Detailed Maintenance Plan by senior officers is essential to ensure that the road maintenance is not
only technically well-engineered but also well integrated with community requirements and road
usage needs.
The Assistant Engineer (and Deputy Executive Engineer) will check and certify at least 30% of the
roads proposed for maintenance at the site in respect of the accuracy of data and ground realities as
well as the correctness of the design of maintenance interventions and estimation. In this process,
deficiencies should be identified and remedied in all proposals.
The primary responsibility for the accuracy of the provisions in the DMP shall rest with the Executive
Engineer who shall check and certify at least another 20% of the roads proposed for maintenance at
the site to make sure that the investigations are adequate and recommended maintenance actions and
estimation are satisfactory. If any deficiencies are found, these should be identified and corrected
accordingly. S h e / H e shall personally ensure that:
a. The priority criteria are following SRRDA guidelines and are compliant with State’s policy on
maintenance.;
b. Leads of materials, in the case of works other than PBMC, have been assessed correctly;
The estimates for maintenance work on each road shall be made in one or two parts, as appropriate:
a. The first part comprising of the estimate for works to bring the road up to a maintainable
standard. This may involve patching, reconstruction of the road pavement and other elements,
sealing or overlay, or a combination of these measures (i.e. periodic maintenance).
b. The second part comprising of the estimate of year-wise routine maintenance for years. This
may be a PBMC and/or BOQ (i.e. measurement) format as considered appropriate.
The Detailed Maintenance Plan should be personally checked and signed by the Head of the RRNMU
and scrutinized by the SE. The Superintending Engineers (SEs) are required to conduct a scrutiny of
the proposals prepared by the RRNMU, regarding conformance to guidelines, design standards,
specifications, safety requirements, cost, etc. The SEs are expected to examine the proposals
personally, at random, and do a detailed check of at least 10 percent of the proposals. Certification of
checking shall be included in the Detailed Maintenance Plan. Cross-drainage structures having a
length of 15m or more should be inspected at the site by the SEs or higher officers, who shall confirm
the need for the repair/reconstruction/ rehabilitation of the structures and approve the same.
The scrutinized copy of the Detailed Maintenance Plan will be retained with the RRNMU. The
Detailed Maintenance Plan corrected based on scrutiny by STA shall be forwarded to the SRRDA
together with proposals made by elected public representatives, and proposals are accepted/ not
accepted along with specific reasons.
After the compilation of Detailed Maintenance Plans by RRNMU, the PIUs will prepare the bidding
document for every package. The above details will be filled up into the Draft Tender Document
module of OMMAS and a draft bidding document will be generated. As soon as the SRRDA clearance
is received and technical sanction is accorded by the competent authority, the necessary input
regarding dates and modifications in respect of other items will be carried out by the PIU under the
guidance of RRNMU in the draft bidding document and the final bidding document will be published
on the website.
The SRRDA will consolidate the proposals from each RRNMU after Tender Documents have been
uploaded in the Project module of OMMAS.
Table 6-3 below gives the illustrative schedule of activities and the time allotted for undertaking
maintenance works for the prioritized roads.
Table 6-3: Schedule of Activities for Rural Roads Maintenance Programme
Sl. No of Days
Activity Start Finish
No.
RCR Data collection and assessment of RCI by respective
1 01 Oct. 15 Oct. 15 days
PIUs
2 Prioritization on the zonal basis by RRNMU 15 Oct. 30 Oct. 15 days
Preparation of Detailed Maintenance Plan (DMP) by PIU
3 15 Oct. 30 Nov. 45 days
under supervision of RRNMU including Costing
Consolidation of Proposals by Zonal RRNMUs and
4 01 Dec. 07 Dec. 7 days
forwarding to SRRDA
SRRDA will consolidate State level Maintenance Budget
5 08 Dec. 20 Dec. 12 days
Requirements and forward them to the Government
RRNMUs will prepare DMPs matching different expected
6 budget scenarios (at least 3 nos.) – done incrementally and 08 Dec. 25 Dec. 18 days
forwarding to STA
Scrutiny by STA and Presentation of the list of proposals
7 at the zonal level by RRNMU (including obtaining 15 Dec. 30 Dec. 15 days
suggestions from MLAs/MPs et al.)
Clearance by Management Committee & State Level
8 Standing Committee of zonal proposals of RRNMU 01 Jan. 10 Jan. 10 days
(different scenarios)
9 Administrative Approval and Technical Sanction 10 Jan. 20 Jan. 10 days
10 Preparation, Inviting, and Receipts of Tenders 20 Jan. 31 Mar. 70 days
Distribution of RRNMU zone-wise budget by SRRDA
11 30 April
Sl.
Solution Summary
No.
1. Upgrade a road Capital investment to reduce maintenance costs.
Defer an activity for one or more years
2. Suitable if access and safety are not put at risk.
3. Reduce activity frequency Suitable if access and safety are not put at risk.
Carry out a cheaper ‘holding’ treatment for one or more
4. Downgrade a treatment
years.
Provide a minimum level of access at a very low cost, only
5. Apply a Partial Access standard
suitable when no other solutions remain.
These solutions do not explicitly consider standards, selection, and prioritization criteria discussed
above but do require an understanding of alternative treatment approaches and estimated costs.
7.1 UPGRADING
Maintenance
Category Timing Possible Alternative Comments
Activity
Reduce frequency
Usually during or omit for a limited time.
Grass cutting and immediately Cut only at junctions/ Road safety (visibility) should
after rains sightlines not be threatened
pitching).
Erosion control More mitre drains (to reduce Sediment is less likely to
Before and volume of water in accumulate on a smoother drain
during rains longitudinal side drains). profile.
Reduce water speed. Reduce the volume of water and
Wider side drains. speed of flow.
Maintenance
Category Timing Possible Alternative Comments
Activity
Scour checks Before and
Line drain Frequent erosion repair.
during rain
Repair/replace
As necessary - -
road signs
Repair/replace Immediate - -
Maintenance
Category Timing Possible Alternative Comments
Activity
the barrier
Repair/replace
As necessary - -
milestones
a. Maintain all rural roads in good or fair condition (i.e. Roads in maintainable condition);
b. Rehabilitate priority roads in poor condition (i.e. Restore road in un-maintainable condition to
maintainable standard);
c. Consider reduction in access standards (full>basic>partial)
It must be stated clearly that the aim is not the above which illustrates pragmatic options in
response to the budget shortfall. The long-term aim is sound rural road network management along
with raising maintenance standards across the network such that the network is sustainably maintained
at full access standards. This can only be achieved by good management of adequate road maintenance
budgets. The first option must always be no budgetary constraint i.e. the budget is sufficient for
maintenance needs. Thus a suggested procedure is as follows:
a. Prioritize all roads according to condition rating (ie 1 (very poor) to 5 (very good);
d. Estimate quantities of work and costs for the maintenance program according to need.
The proportions vary according to network characteristics but a typical proportion of maintenance
activities is as shown in Table 7-3.
Table 7-3: Relative proportions of different maintenance activities
Condition rating
Activity
1 2 3 4 5
Routine maintenance
Periodic maintenance
Reconstruction/renewal
Establish relative proportions of budgetary need for each maintenance activity. The proportions will
vary according to network characteristics and road conditions, typical characteristics (for a
road/network indicatively of condition rating 3, i.e. fair) may be as shown in Table 7-4.
Table 7-4: Typical proportions of an adequate maintenance budget (condition rating 3)
In case of budgetary insufficiency, the proportions of activities for the annual program need to be
adjusted – indicative figures are shown in Table 7-5.
Table 7-5: Suggested allocations of insufficient maintenance budget (condition rating 3)
% of budget needs available
Activity
100% 80% 60% 40% 20%
Routine maintenance 10% 15% 20% 35%% 75%
Periodic maintenance 40% 45% 50% 50% -
Reconstruction/renewal 45% 30% 20% - -
Emergency 5% 10% 10% 15% 25%
Within a maintenance category with reduced allocation, prioritization should be according to LR/TR
and traffic volume/population served. The indicative proportion of allocations for different condition
ratings and budget sufficiency is indicated in Annexure B-12 and Annexure B-13. shows a typical
example of packaging the roads for improvements.
CHAPTER 8
Road Safety
8 ROAD SAFETY
Road accidents are caused by road users drivers and pedestrians, these usually involve vehicles with
excessive speed, and the road itself (including bridges, structures, junctions, and immediate
surroundings). These road accidents have a significant social and economic impact and therefore, the
primary aim of rural road network management should be to minimize road accidents. Road safety
measures should be considered at the design phase but certain issues may arise later and these need to
be corrected as early as possible.
a. Road safety audits, risk assessments, and response to accident blackspots such as
junctions, village/urban zones, rail crossings, school environs, etc. Response actions could
include clearance or protection of roadside hazards like trees, culvert headwalls, bridge parapets
end posts, improved sightlines, better road alignment, special attention to zones of high non-
vehicular movement e.g. Schools, village areas, movement of farm animals, market areas, social
and administrative facilities.
c. Awareness programs aimed at rural residents, schools, communities along rural roads.
Given the high levels of community collaboration and consultation in the implementation of the
construction of PMGSY roads, community involvement in the delivery of road safety
campaigns can manifestly improve the effectiveness of such campaigns.
The accident characteristics and potential mitigation measures adapted from TRL ORN20:
Management of Rural Roads are in Table 8-2.
Table 8-2: Accident Characteristics and Potential Mitigation Measures
Useable width has been reduced by road Repair damage; continue maintenance
damage Provide temporary signs warning of reduced width
Vehicle hits a tree or another obstacle Remove tree and other vegetation within 1.5m of the
carriageway
Paint the tree trunk white for greater visibility
Re-site all obstacles greater than 1.5m
from carriageway
Provide hazard markers
Junctions
Accident Characteristics Potential Mitigation
Provide protected arrangements for traffic turning to rural roads
(especially the start junction)
Cut vegetation at the junction to increase visibility
Restart – vehicle stops at junction, restarts,
and is then hit from the side Widen shoulder at the junction to increase visibility
Provide signs warning of approaching a junction on major
roads
Provide advance direction information and flag type direction
signs and STOP signs for traffic control
Provide speed breakers at side roads
Junction Control
Provide STOP or GIVE WAY signs and marking as per the
guidance provided in IRC 67 2012.
To ensure the safety of road users during maintenance works it is expected that safety measures will
be taken at works sites including the following:
a. Warning the road users (in the appropriate language) clearly and sufficiently in advance
b. Providing safe and clear lane markings for guiding road users
c. Providing safe and clearly marked buffer zones and work zones
a. Barricades, drums, traffic cones, cylinders, and signs around work zones
b. Flagmen with red flags positioned to regulate and warn the road users
c. Using construction machinery carefully and parking such machinery at locations where
they are no traffic hazards
d. Stacking construction materials such that only the quantity needed for one operation is
stacked along the road, and obstruction to road users is minimized.
e. The details for traffic and axle load surveys are provided in Annexure B-5 and B-6.
The Head of RRNMU will be the Zonal Rural Roads Safety Officer (ZRRSO) and shall be the
custodian of the inventory of all road safety features and road furniture. He/She will specify the
maintenance interval required for each feature. ZRRSO may delegate this authority to the Head of
PIUs for smooth implementation of the safety objectives. To ensure operational safety, the ZRRSO
shall ensure that:
a. Safety issues are identified during routine maintenance inspection of rural roads regularly
and rectified as top priority;
b. During the inspection of safety features, ensure that signs are in original positions
concerning lateral placement, with adequate vertical clearance and also oriented correctly,
and if not, rectify immediately;
c. Roads signs are washed at six monthly intervals;
d. In all cases of accidents and inquiry/investigation thereof, accident data are be analyzed:
where there are multiple accidents on the same stretch of rural road (300 to 400m),
diagnose the problem, and then propose and implement solutions;
e. All resolutions of panchayats regarding safety issues are acknowledged and action
proposed/taken intimated to the panchayat;
f. Road accidents involving cyclists and pedestrian to be studied, and if necessary, speed
reduction measures shall be applied (or other measures as appropriate);
g. To sensitize villagers, road safety awareness camps should be organized involving
panchayats, schools, rural road users (inhabitants as well as drivers), in accordance with
programmes drawn up by the state quality coordinator;
h. If any temporary road works are carried out, they shall be undertaken with proper traffic
management and shall be an integral part of the contract.
The State Quality Coordinator will be the State Rural Road Safety Officer (SRSO). He/She will be
responsible for:
a. Adequate coordination with the State Road Safety Council and road safety programs;
c. Implementation and coordination of rural road safety awareness programs in the field;
d. Quarterly meeting with ZRRSO and take feedback for improving safety standards.
e. Annual accident data collection and analysis over the entire rural road network of the
State to ensure blackspots responsible for high accident occurrence can be addressed. The
black spot improvements in rural roads shall be undertaken for such a time that all high
accident occurrence locations are rectified in a phased manner. Data must also be
collected for monitoring and assessing the effectiveness of measures implemented.
f. Establish proper coordination with entities involved in the rural road maintenance works
like Panchayat Raj, Zilla Parishad, and other local bodies. Road safety toolkit and other
best practices developed for RRNMU will be shared with them such that they too can
adopt similar road safety items in their rural road maintenance tasks.
Indicatively 5 % of maintenance budgets shall be set aside as provision for road safety items for any
civil work (related to maintenance of rural roads), which would be spent exclusively for road safety
items. Fund allocation shall be such as to enable quick installation of essential safety features without
passing through intricate departmental procedure even for some highly unsafe situations or even
sometimes after a natural calamity. Also, traffic management at the maintenance work zone will be
made as BOQ items, and will not be considered incidental to civil work related to maintenance.
CHAPTER 9
Environment
9 ENVIRONMENT
In rural areas, most dwellers rely on their surroundings for their livelihoods and it is a duty of the road
engineer that the rural road network contributes to the well-being of the rural populations. It is,
therefore, good engineering practice to minimize the negative environmental impacts by identification
of potential adverse effects and apply mitigation measures where appropriate. Environmental
considerations thus influence the design, construction, and maintenance of rural roads.
Site camp construction Land degradation; firewood removal, EMP included as a contractual
and operation contamination of water sources, obligation. NOC of State
Pollution Control Board
Excavations and soil Bare soil can erode; landslips; badly placed spoil Construction walls; bio
stripping can kill vegetation planting leveling spoil or
retaining engineering
Removal of trees Increased chance of erosion; loss of natural Minimising tree felling
Road Work Activities Impact Mitigation Measures
Brick culverts and De-forestation for brick firing Use of other fuels in kilns
surfaces
Borrow material Ponding water where mosquitoes may breed; License for operation
excavation resource depletion; instability if too near to road Reinstatement after use
Quarrying (rock, sound) Loss of top soil; ponding water where mosquitoes Reinstatement pits and quarries of
might breed. Resource depletion; loss of natural borrow
habitats; loss of scenic beauty
Generated traffic Pollution; danger; safety issues; severance of Traffic calming; restricting access
communities on either side of the road or from to heavy vehicles Speed limits.
their fields; severance of natural habitats;
disrupting animal movement and migration
patterns.
9.1.1 Environmental Impact Assessment (EIA)/ Environmental
Management Plan (EMP)
For all major engineering projects, a specific EIA is carried out at the feasibility or design stage to
identify potential impacts. The required mitigation measures are set out in an EMP that is usually
included as a contractual obligation of the construction contract.
For routine maintenance works a specific EIA is not usually required to be carried out for individual
contracts although a thematic environmental assessment is sometimes carried out for rural road
maintenance operations as a whole. Generic mitigation measures specified in maintenance contract
documents are subject to supervision as a component of contract supervision and measurement.
Environmental issues should be included in community consultation measures. Local knowledge can
be especially important in avoiding drainage problems including irrigation systems and in
monitoring contractor performance of environmental mitigation measures.
CHAPTER 10
Social Issues
10 SOCIAL ISSUES
Social Impact Assessment (SIA) is defined as an effect(both positive and negative on a social issue
resulting from rural road development projects. SIA is a process to provide a framework for defining
key relevant social issues or risks for involved stakeholders. It also gives the impact of public/ gov
intervention on the social aspects of the human environment .
10.1 GENDER
Following the national gender policy commitments in the road sector, RRNMU will promote a
Gender Action Plan (GAP) for the promotion of women’s participation in rural road maintenance
works (including affirmative action to ensure participation of women and other marginalized
groups). A preliminary GAP is set out in Table 10-1.
Table 10-1: A Preliminary Gender Action Plan
Activity Target Responsibility Comments
Engagement of women for At least 33% of hired RRNMU/PIU/ Appropriate clauses may be
skilled and unskilled work and workers are women inserted in SCC (Special
Contractor
as supervisors for road Conditions of Contract).
maintenance activities Supervision of contractor by
PIU to include composition
of contractor’s work force.
Prohibit hiring of child labour No child labor RRNMU/ Provision in SCC. Children
Contractor/ ZP/ GP/ are aged under 15
RRI
walk-ways
Figure 11-1: Adaptation and disaster risk management approach for a changing climate (IPCC 2012)
• ⎼ Stabilize slopes on
Reduction in soil either side of the road to
More frequent moisture and • prevent landslides (e.g.
droughts increase in wet/dry vegetating the slopes, putting in
spells leading to place structures to prevent soil
degradation of the movement,
road foundation • etc)
Change in Adaptation Measures
climate/weather Physical
variables and impact on
infrastructure Hard Measures Soft Measures
impacts
• Upgrade coastal drainage
systems to meet threats
Increased • Strengthen the edge of road • Map the areas under
Inundation/flooding embankments. threat
temperatures
of the roads and • Raise the level of roads and • Install an early warning
resulting in sea
associated damage causeways to meet the threat. system
level rise • Use of submergible
to roadway surface • Ensure sufficient
and base layers pavements monitoring stations to
(e.g. from salt • Undertake spot upgrades in collect reliable data
penetration) high-risk areas. • Undertake more regular
• Install an early warning maintenance
system (s) • Improve
• Ensure sufficient hydrological data and
monitoring stations to models
collect reliable data
• Edge- strengthening of
road embankments
• Use submergible
pavements
• Build more redundancy
into the system
The impacts of climate change on the bridge infrastructure of rural roads along with the possible hard
and soft mitigation measures are listed in Table 11-2.
Table 11-2: Mitigation Measures of Climate Change Impacts on Bridges
Change in Adaptation Measures
climate/weather Physical impact on Hard Measures Soft Measures
variables and infrastructure
impacts
Increase in Inundation of • Increase the height of • Prepare hazard maps
precipitation and/or bridges and/or the bridge above the river. and inform regulatory
episodes of heavy damage to bridge • Strengthen the agencies and users.
rainfall resulting in infrastructure bridge (i.e. design to Install equipment that can
flooding (cyclones, (including scour) withstand the highest detect slope failure and
storms, monsoon) potential river flows given debris flow, and systems
projections). that can communicate and
• Implement upstream disseminate information
river bank stabilization and suspend traffic.
measures to stabilize Install guidance
channels (e.g. planting of systems leading to
indigenous trees on banks, detours and alternative
compacting of soils, schemes.
improving channeling, etc). Conduct more frequent
• Protect bridge and improved inspection
piers and abutments and maintenance of the
with riprap. affected locations.
• Implementing wind Assess the
resistance measures. infrastructure’s ability to
• Use more durable withstand the more
material such as corrosion- extreme floods projected
resistant materials (e.g. as a result of climate
reinforced steel)
Change in Adaptation Measures
climate/weather Physical impact on Hard Measures Soft Measures
variables and infrastructure
impacts
change.
Undertake appropriate
contingency planning aimed
at ensuring that resources
are optimally organized for
the areas most affected by
floods. It has been identified
as having a high net benefit
due to the relatively low
capital costs involved in
upfront planning in
comparison to emergency
remediation action. This
will require liaison across
sectors to ensure
interdependencies are
covered.
Keep records of
flooding events and
locations.
Keep in-house
Geographical Information
Systems (GIS) up to date.
Map landslides and
avalanche-prone areas,
including underlying
geology.
Refrain from developing
in areas at risk from
floods and/or landslides
• Change design
Expansion and requirements related to
Increased subsequent
temperatures temperature for bridges
damage to bridges (may need to consider new
heat thresholds for bridge
expansion joints).
CHAPTER 12
Choice Of Technology
12 CHOICE OF TECHNOLOGY
The appropriate use of labor-based (LB) technology should be considered where economically viable
and appropriate as a vehicle for the creation of rural employment and injection of cash into rural
economies. The following maintenance activities as given in Table 12-1 may be considered for the
potential use of LB methods.
Table 12-1: Labour Based Maintenance Activities
Labor-
Activity Equipment-Based
Based
Labor-based technology can bring considerable advantages in certain circumstances but requires
relatively more administrative and managerial effort in comparison with a plant-based approach
and there may be negative perceptions of the approach as ‘old fashioned’ 62. However, advantages of
choice of labor-based methods include:
a. Foreign exchange costs for equipment (fuel, spares, capital cost) are reduced;
b. Much greater employment potential for locally available (often unskilled) labor;
d. Community involvement;
13.3 REPORTS
Reports on maintenance activities should be fully available publicly through OMMS or in State
administration facilities. Reporting should be undertaken monthly, quarterly, and annually (normally
within one month after the end of the reporting period).
The main purpose of reporting is monitoring the progress, the expenditure against approved plans
and budgets, and to document changing road network conditions. Reporting serves as a management
tool and a means for wider dissemination of information.
The community will be encouraged to report road damages to the RRNMU and PIUs and a ‘Level of
service charter’ should be drawn up which outlines response times to such reports.
Communication of Approval 7 56
As a result of the adoption of the Book of Specifications entitled as Ministry of Rural Development –
Specifications for Rural Roads, August 2004 published by Indian Roads Congress, Section 5 of the bidding
document has been modified to define the above publication as ‘Specifications’ to bid for rural road
maintenance works.
While scrutinizing the Detailed Maintenance Plans, the SRRDA should also scrutinize the tender document to
see that the tender document has been prepared per the requirements of the works. As soon as the clearance of
the package and technical sanction has been accorded by the competent authority of the State Government, the
PIU (in consultation with the RRNMU) will make necessary entries regarding the dates or any modifications in
other items. After the above modifications are affected, the tender will be published on OMMAS website. The
tender notice can be printed out and issued for the press advertisement.
15.2 PRE-MOBILIZATION
15.2.1 Insurance:
The Contractor is required to provide insurance cover from the start date to the date of completion as per clause
13 of the GCC. Insurance policies and certificates shall be delivered by the Contractor to the engineer for
approval before the start date. The Contractor and Employer should note that as per clause 52 of GCC, it is a
breach of the Contract if the Contractor fails to provide insurance cover.
15.2.2 Sub-contracting:
After the issue of Work Order, the engineer (i.e. the Executive Engineer who would be the ‘Engineer’ as
defined in the Contract) would first ascertain whether sub-contracting is allowed within the Contract. As per
clause 4.2(k) of ITB, if the Contractor has proposed to sub-contract the work and the proposal has been
accepted by the competent authority, the sub-contracting will be allowed. The conditions of the sub-contract
will be governed by clause 7 of General Conditions of Contract (GCC).
15.3 MOBILIZATION
The Contractor is required to commence the work within 10 days after the date of issue of the Work Order. The
duration between the date of issue of the work order and the date of the actual commencement of the work is
termed as ‘Mobilization Time’. This is important for the Contractor as well as the ‘Engineer’ for complete
planning of the work and mobilization of resources to ensure timely completion of work with requisite quality.
The activities that are required to be completed, generally in the suggested order, by the ‘Engineer’ and the
Contractor during the Mobilization Time are:
a. Deployment of Contractor’s personnel: As per clause 9 of the GCC, the Contractor is required to
employ the technical personnel enumerated in the Contract. At the start of the Mobilization Time,
technical and administrative instructions will be passed on to the Contractor by the engineer, and to
fully understand the instructions before any further activity is allowed, the Contractor will be
required to employ key technical personnel who will interact with the Engineer. After the
mobilization activities are completed, the requirement of technical personnel will depend on the
items of work being executed. The technical personnel required for the field laboratory should be in
place at the commencement of the work until the completion of the work.
b. Listing of Requirements by Engineer: As per the Bill of Quantities, the Engineer will list the
requirement of material, labor, and machinery during various phases of the construction period. The
‘Engineer’ will also prepare the list of the equipment required to establish the field laboratory. These
will be based on the data entered in Appendix to ITB regarding clause 4.4 B (b) (iii) of the ITB and
the list of equipment given in Contract Data to GCC.
c. Work Programme: Based on the BOQ and the list of requirements of men, material, and
machinery, the ‘Engineer’ is required to guide the Contractor for the preparation of the work
program. The Work Program is the program showing the general methods, arrangements, order, and
timing of all the activities in the works along with monthly cash flow forecasts for the construction
of the works. Based on the guidance of the ‘Engineer’ and availability of resources, the Contractor is
required to prepare his work program and assess the requirement of additional men, material, and
machinery. The work program should be detailed in such a way that the date of start and the date of
completion of every item of work is laid down; the details of requirements for completion of various
items of works including cash flow forecasts should also be captured. A sample PERT chart of
complete activity of construction should be drawn up wherein the details of every large or small
activity should be clearly shown. It is also desirable that in the work program, the Contractor should
indicate the tentative periods during which the presence of the engineer or his representatives will be
required at the site.
d. Handing over of Site to Contractor: The ‘Engineer’ is required to hand over the possession of full
worksite or possession of at least 75% the work site to the Contractor.
e. Working Drawings & Designs: While the ‘Engineer’ is handing over the possession of the work
site, a complete set of working drawings, as decided by the ‘Engineer’ to be appropriate for the
contracted maintenance works, (in case of major repair/rehabilitation/reconstruction, etc) should be
handed over to the Contractor.
f. Specifications & Drawings of Temporary Works: The Contractor has to submit the specifications
in drawings of proposed temporary works (like diversion road, etc) for the approval of the Engineer
as per clause 18 of the GCC. The Contractor shall be responsible for temporary works as well as for
the safety of all the activities on the site.
g. Approval of Work Programme: Once the above activities are complete, the work program will be
submitted by the Contractor for approval of the ‘Engineer’ and the ‘Engineer’ after checking that the
work program is realistic shall accord his approval. The time given for completion of different
portions of the work must be properly checked concerning the availability of machinery and if
necessary the ‘Engineer’ should advise the contractor to redraw the work program before according
his approval. As per Clause 26.2 of GCC not deploying requisite key personnel or equipment is a
breach of contract as per clause 52.2 k.
h. Establishment of Field laboratory: If so specified in the contract, the Contractor will establish the
field laboratory at a convenient location as approved by the Engineer. It will be ensured by the
Contractor that the laboratory has all the equipment as required by the engineer. It should be noted
that the Contractor will not be allowed to commence the work if the field laboratory is not
established in the stipulated time frame. Non- establishment of the Laboratory within the time given
is a breach of the Contract. The Contractor should provide a temporary site office along with the
field laboratory. Such an office would serve as a meeting place between PIU Engineers and the
Contractor’s Engineers. Also, the works program and other day-to-day required information can be
kept in such an office.
15.4.2 Subcontracting
The Contractor may propose sub-contracting any part of the work during execution, beyond what has been
stated in clauses 7.1 and 7.2 of GCC generally to make up for unexpected delays which cannot be made up in
the normal course. To enable the Contractor to complete the work as per terms of the contract, the Employer
will consider the following before according approval.
a. The Contractor shall not sub-contract the entire work.
b. The Contractor shall not sub-contract any part of the work without the prior consent of the
Employer. Any such consent shall not relieve the Contractor from any liability or obligation under
the Contract and he shall be responsible for the acts, defaults, and neglects of any of his sub-
contractor, agents, and workmen.
c. The Engineer should satisfy himself before recommending to the Employer whether
the circumstances warrant such sub-contracting; and
the sub-contractor so proposed for the work possesses the required experience, qualifications,
and equipment necessary for the job proposed to be entrusted to him in proportion to the
quantum of works to be subcontracted.
15.4.3 Liquidated Damages
In the case of a measured work contract or as otherwise specified in the Conditions of Contract if the following
milestones are not achieved by the Contractor, he shall be liable for payment of liquidated damages for the
period that the completion date is later than the intended completion date as per clause 44 of the GCC:
i. If 12.5% of the value of the entire Contract work has not been completed up to 25% of the period
allowed for the completion.
ii. If 37.5% of the value of the entire work has not been completed up to 50% of the period allowed for
completion.
iii. If 75% of the value of the entire Contract work has not been completed up to 75% of the period
allowed for completion.
1% of the initial Contract price, rounded off to the nearest thousand, per week, is the liquidated damages for
delay in completion subjected to the maximum of 10% of the initial contract price.
The Engineer is empowered to withhold the total liquidated damages if the Contractor fails to achieve the
above milestones. However, if the Contractor achieves the subsequent milestone in time, the withheld amounts
would be restored.
The Engineer should note that the quality and time are the essence of the Contract, as such, the delay in
completion of the work constitutes a breach of the Contract as per clause 52. The provision in this respect is
given below:
a. The Contractor stops the work for 28 days when no stoppage of work is shown on the current
program and the stoppage has not been authorized by the Engineer.
b. The Contractor has delayed the completion of the work by the number of days for which the
maximum amount of liquidated damages can be paid, as defined in clause 44.1
c. If the Contractor has not completed at least 30% of the value of work required to be completed after
50% of the completion period has elapsed.
As soon as a delay occurs, the Engineer/Employer needs to issue appropriate notices/ letters giving clear
reference to the specific clauses of the Contract. Since a legal Contract is involved, unofficial/oral warnings to
Contractors should not be resorted to as a substitute for a formal notice. The Employer is empowered to
terminate the Contract if the breach of the Contract occurs due to delay in completion of the work.
15.8 COMPLETION
The Contractor shall request the Engineer to issue a certificate of completion of the construction of the works,
and the Engineer will do so upon deciding that the works are completed.
15.9 TERMINATION
As per clause 52 of the GCC, the employer is empowered to terminate the contract if the Contractor causes a
fundamental breach of the contract. Some of the main conditions of the fundamental breach (mainly for BOQ
based works) are:
a. Contractor stops the work for 28 days without authorization of Engineer;
b. Contractor fails to correct the defect within the time determined by Engineer;
c. The contractor delays the completion of work by the number of days for which the maximum amount
of liquidated damages can be paid;
d. The contractor has not completed 30% of the value of work after half of the completion period;
e. Contractor fails to establish field laboratory;
f. The contractor fails to deploy the required machinery and equipment for construction and personnel as
prescribed in the contract.
If the Contract is terminated, the Engineer shall issue the certificate for the value of work and if the total
amount due to Employer exceeds any payment due to the Contractor, the difference shall be recovered from
the deposits available with the Employer; if the amount is still left un- recovered it will be a debt payable to the
employer. As per clause 54 of GCC, if the Contract is terminated because of Contractor’s default the property
as mentioned in the said clause shall be deemed to be the property of the Employer, and credit of the same will
be given to the Contractor.
CHAPTER 16
Quality Management
16 QUALITY MANAGEMENT
Quality Management covers not only technical specifications but the workmanship, testing, and acceptance
criteria. Quality Control comprises the operational techniques for controlling the quality of finished products.
A Quality Assurance Standard is set when the Quality Control system is operationalized using human
resources, trained to a particular standard. Quality Management includes quality planning to maintain a Quality
Assurance Standard, as well as Quality Control. Quality Management which includes external and internal
Quality Assurance mechanisms to constantly improve the quality system is termed Total Quality Management
(TQM). Quality Control operational procedures described below should be supported by the requisite training
and HRD measures in the SRRDAs, RRNMUs, PIUs, and contracting personnel to generate the requisite
Quality Assurance.
20 percent of the tests are conducted in the presence of the AE in charge of the work.
5 percent of the tests shall be conducted in the presence of the EE in charge of the work.
e. The abstract of the Quality tests conducted shall be maintained in Part II Register. If the test results
do not conform to the prescribed limits, a Non-Conformance Report (NCR) in the format prescribed
in the Register will be issued to the Contractor.
f. The Contractor shall submit monthly returns of the tests to the AE who will submit them to the EE
in the first week of every month. The EE will review this return regularly to see that the Quality
Control tests are being performed at the desired frequency and with the desired accuracy. The EE
will also verify that the Non-Conformance Reports are being issued by the AE whenever non-
conformance occurs and the Contractor is taking action promptly on the Non-Conformance Reports.
Payment to the Contractor shall be regulated by the EE as per the returns of the Quality Control
tests. Any deviation will be the personal responsibility of the EE.
The SE in charge of the Circle and the Chief Engineer having jurisdiction are responsible for the proper
functioning of the PIU as part of their normal administrative duties. Their inspection and quality testing
supervision will therefore be counted as part of effective supervision of the 1st tier of quality management (and
not as a 2nd tier of quality management). The SE/ CE shall:
a. During his visits to the work, oversee the operation of the Quality Control Testing procedure and
record his observation in the Quality Control Register, Part I. The SE and CE will also verify that the
Non-Conformance Reports are issued in time and actions are being taken by the Contractor promptly.
b. Prepare Inspection Reports in the prescribed formats which shall be sent to the PIU for taking
remedial action. A copy of all such reports will be endorsed to the State Quality Coordinator in the
SRRDA. The report shall be detailed and precise and shall cover all aspects of the work inspected,
including:
Design and estimation (for the major repair/rehabilitation/reconstruction, etc)
Detailed Maintenance Plan
Contract Management by PIU
Contractor performance
Quality testing
On line data entry status
Page: of
Road Condition Inventory and Div.
Last major intervention / month-year:
Maintenance Planning
Chainage
0+000 1 2 3 4 5 6 7 8 9 1+000
G/F/P
Subgrade Subbase Base course Surfacing
Side drain Left (depth)
Side drain Right (depth) WBM G
Proposed maintenance interventions PC G
m 0.3
Bush clearing (width) Clear side drains (depth) Clear mitre
m 0.3
drains (depth) Shoulder repair
Side slope repair Unit m Qty
2.0
mm 700
0.30
500
m 0.30
m 150
600
m2
m2
Light grading m2
Camber reshaping m2
m
Culvert/headwall repair Repair retaining
repair no
Road marking renewal m
m
Land Use
Sl. No. To Carriageway Width Shoulders Remarks
Terrain (Built up/
Name of Formati Embankm Subme
(Plan/ Agricultur Details of Crossroads
Village/ on Width ent Height rgence
Rolling/ e/Forest/I Condition* Conditio
Town (m) Type* Type* (m) (cm)
Hilly) ndustrial/ Width * n** Location Road No.
(BT/CC/GR (BT/CC/GR Width (m) (m)
Barren (m) (G/F/P/VP (G/F/P/V (cm) (km)
/ ER) /ER)
) P)
Span
Arrangem
Type of ent and
Carriage Width of Details of Protection works Height above Bed Level Adequacy
Sl. Location Structures Thicknes s Total Presence
way Width Culvert of Remarks
No. (km) (Pipe, Slab, of Slab (m) Ventway of Scour
(m) (m) Waterway
Box, Arch) (No.x
Length)
(m) Return Parapet/ U/S side(
Type D/S side(m)
Condition Head Wall Wing Wall Wall Handrail m)
4
Surveyed by
Note: G=Good F=Fair P=Poor NA=Not Avoidable
VP=Very Poor ………………………………………..
Inventory & Condition Survey for Bridges Sheet No.
Road Name
: Road No :
This Operations Manual deals mainly with programmed maintenance works in response to gradual
deterioration. Emergency response is different in that programming is not usually possible
(immediate and urgent response is necessary which implies that a good communication system
should be in place) and the nature of the defect can be of greater dimension than for normal
maintenance operations. And yet, emergency events are often the result of maintenance neglect (e.g.
a silted culvert overtops and the road is washed out).
The inspection team meets with respective SRRDA, PIU, PIC, and PRI
Inspection Team visits subject roads and conduct RMAs (should be done with the team and PIU
representatives):
a) Take a ride on the road and first fill the general observation checklist
b) Identify each maintenance issue
c) Take a photo of each maintenance issue
d) Provide details of the location of the maintenance issue
e) Determine associated risk of not attending to each maintenance issue
f) Provide recommendations to address each maintenance issue
g) Assess the compliance of the maintenance contractor with the performance standards as
provided in the contract
h) Conduct road maintenance awareness sessions with communities/PRIs
During the RMA Inspection Team meets with the maintenance contractor to discuss planning,
organization, and performance of maintenance inspections, use of local labor and equipment,
adherence to the performance standards, payment arrangements, safety at works, etc, and identify
issues.
The inspection team prepares a formal RMA report for each road. RMA should be concise and to the
point and oriented to achieving results on the ground.
a. Prepare RMA findings and comments using the RMA report template (attached)
c. Prepare Section 2 for decision and action by PIU using the Section 2 template (attached)
e. Inspection Team fills out Section 3 (attached) which checks the compliance of the
maintenance contractor with the performance standards as provided in the contract
The team conducts a wrap-up meeting with respective PIU, maintenance contractor(s), Team, and
SRRDA to:
There are many aspects to a traffic count survey that must be considered at the planning stage,
including when to carry out the survey, the duration of survey, staffing and choice of site, etc. as
given in Figure 1.
2 wheelers Bicycle
LCV Passenger
2 – Axle Truck
Hand Cart 5 1 5
Animal Drawn 2 1 2
Figure 3: Example of daily traffic flow variation (for light and commercial vehicles)
Traffic Composition
Traffic composition shows the percentage share of each type of vehicle in the total flow of traffic, at
a survey point or location. The traffic composition can be either presented in a tabular form or the
form of a pie chart. An example of traffic composition is shown in Figure 4. The composition is
typical of traffic plying on roads getting categorized as MDRs. Also, after the up-gradation of roads
as part of PGSY II, it is quite likely that some roads may start attracting higher category traffic. For
this reason, as part of PMGSY II attention will have to be given to improving the geometrics
standards of these roads. Also, some kind of by-pass to the villages will have to be thought of.
Figure 4: Traffic composition presented in a Pie chart
One or two person(s) to control traffic on the road and direct selected vehicles into the
weighing area.
One person to direct the vehicle slowly onto the weigh pads and position each wheel
centrally on the platform
One person to carry out the driver questionnaire, e.g. origin-destination, type of goods
carried, etc.
One person to record the vehicle details and the wheel or axle loads.
It is recommended that jobs are rotated periodically to reduce tiredness
If a traffic count is being carried out at the same time, then a further two people are
required per shift.
It is often possible to obtain the services of the traffic police to assist in stopping vehicles.
This has the advantage that police are familiar with the problems of stopping and the drivers
are also used to being stopped by them. It is however, important that no vehicles being
surveyed are fined by the police as this can discredit the survey and, more importantly, can
affect the results.
Recommended values for Standard Axle/Standard Axle Group load are given in Table H.2.
Table H.2: Recommended Values of Standard Axle/ Standard Axle Group Load
Axle Type Standard Axle Load (Tonnes)
Rutting mm >50 20 - 50 10 - 20 5 - 10 -
10% -20%
Pavement edge break % length >50% 30% - 50% 20% - 30% <10%
Shoulder (grading,
Condition Very Poor Poor Fair Good Very
vegetation, trees, shrubs)
Good
Low: <500mm/year
1.25
Medium: 500- 1.15
Rainfall 1000mm/year
High: 1000mm/year 1
Mountainous & hill 1
Terrain
areas Plain & rolling 1.25
terrain
Weighted Pavement Condition Score WRCRS = RCRS x Rainfall multiplier x Terrain
multiplier
NB: if the calculated WRCRS > 50, use maximum value of 50
>5 years 0
Age of road pavement 4 - 5 years 5
since last major renewal 3 - 4 years 15
or strenthening
2 - 3 years 25
1 - 2 years 30
Through
Major link Link
road
0 - 50 5 10 20
Traffic volume (commercial vehicles
per day) 51 – 150 4 8 15
151 – 300 2 6 10
>300 0 2 5
RCI (overall condition/serviceability of rural road) = (W)RCR + Age factor score + Traffic
volume score
RCR Age factor score Traffic volume score Total (Overall RCI)
Min. Max. Min. Max. Min. Max. Min. Max.
10 50 0 30 0 20 10 100
Table B-7.3: FORMAT FOR CONDITION SURVEY – BITUMINOUS ROADS CONDITION
ASSESSMENT
Sediment, erosion/nº
Shape, rain cut, side
depressions/% area,
settlement/% area,
Opening, painting,
Camber, rutting &
Edge break/length
shrubs/condition
shrubs/condition
slopes/condition
slopes/condition
Cracking/% area
shoving/% area
silting/nº open
Silting/% silted
Silting/% silted
Potholes/nº,
Start km
Condition
trees,
trees,
1 2 3 4 5 6 7 8 9 10 11 12 13
0-200
200-400
400-600
600-800
800-1000
Average
Comments
Scrutinized By:
JE AE AEE EE Date
JE
YEAR
ROAD
0-200
Start km
600-800
400-600
200-400
Average
800-1000
DISTRICT
Comments
(from/to)
(from/to)
CHAINAGE
Shape, rain cut,
ROAD NAME
side
CONSTRUCTED
Scrutinized By:
LHS drain
slopes/condition
AE
Silting/% silted
2
Grading,
LHS
vegetation, trees,
shoulder
shrubs/condition
3
Cracking & joint
stepping Extension &
width of cracks
4
Carriageway
BLOCK
Joint sealant
defects Length
AEE
5
Spalling & ravelling
6
Edge break/length
7
Grading,
RHS
vegetation, trees,
shoulder
8 shrubs/condition
Shape, rain cut,
EE
side
SURVEY
DATE OF
RHS drain
slopes/condition
9
CONDITION
ROAD LENGTH
Silting/% silted
10
CLASS
CDS
Opening, painting,
silting% open
11
Sediment, erosion%
12
Date
Road
Table B-7.4: FORMAT FOR CONDITION SURVEY – CONCRETE ROADS SITE CONDITION ASSESSMENT
furniture
Condition
13
Table B-8.5: Format for Condition Assesment, Condition Survey, for Bituminous Road
District :- PIU :- Block:-
Road Name :- Raod ID :- Road Length :-
Scrutinized By:
Date of Condition Survey :-
LHS Drain LHS Carriageway RHS RHS Drain CDS Road
Shoulder Shoulder Furniture
Rating/
Start Km Rating
condition Km
/ % blocked
shoving/ % area
Silting/ % silted
Silting / % silted
slopes/ condition
Camber, rutting &
Cracking / % area
slopes/ condition
shrubs/ condition
Sediment, erosion
Potholes/ n settlement/%
Grading, vegetation, trees
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
0-200
200-400
400-600
600-800
800-1000
Average
1000-
1200
1200-
1400
1400-
1600
1600-
1800
1800-
2000
Average
Overall Rating
Comments
Calculation:14={[(1+2)+(9+10)]/2 +3+8+(4+5+6+7)+(11+12)+13}; where the road passes through an open area score for columns, 2, & 10 will be zero. Similarly, where the road passes
through a built up area, which should have side drains, score for columns 1 and 9 shall be zero. rating score for Km long section (column 15) = Average of rating of sub-sections in
column 14; Overall rating = Average of 15 (for whole road length)
Table B-7.5: FORMAT FOR CONDITION SURVEY – BITUMINOUS ROADS CONDITION
TABLE B-6.6: Format for Condition Assesment, Condition Survey, for Concrete Road
JE
District :- PIU :- Block:-
Road Name :- Raod ID :- Road Length :-
Scrutinized By:
Date of Condition Survey :-
AE
Rating/
Start Km Rating
Km
Grading,
Grading,
condition
condition
condition
Spalling &
Raveling/ %
side slopes/
side slopes/
Joint sealant
surface area
Silting / % silted
Cracking & joint
vegetation, trees
Silting / % silted
vegetation, trees,
& width of cracks
Opening painting
Sediment, erosion
shrubs/ condition
shrubs/ condition
stepping Extention
Edge break/ Length
silting / % blocked
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
0-200
AEE
200-400
400-600
600-800
800-1000
Average
1000-1200
1200-1400
1400-1600
1600-1800
EE
1800-2000
Average
Overall Rating
Overall Rating BT + CC
Comments
Calculation:14={[(1+2)+(9+10)]/2 +3+8+(4+5+6+7)+(11+12)+13}; where the road passes through an open area score for columns, 2, & 10 will be zero. Similarly, where the road passes through
a built up area, which should have side drains, score for columns 1 and 9 shall be zero. rating score for Km long section (column 15) = Average of rating of sub-sections in column 14; Overall
rating = Average of 15 (for whole road length)
Date
4. Longitudinal cracking
Isolated crack running longitudinally along the pavement possibly caused by shrinkage due to
excessive width of concrete bay, differential settlement of foundation or exceptional axle loading.
Possible remedial maintenance works include: sealing of narrow cracks with bituminous compound,
‘stitched’ crack repair for medium cracks, slab replacement or full depth repair for wide cracks.
Measurement: Area affected (sqm), crack width (mm) and length (m), crack spacing (mm) (refer
Figure J.12).
6. Transverse cracking
Crack running transversely across the slab possibly due to multiple causes: insufficient slab
thickness, rocking, development out from unmatched joints in parallel slabs, dowel bar restraint at
joints, sub-base restraint (irregularity in top surface of sub-base and/or lack of a separation layer
between slab and road sub-base), shrinkage of slab during curing (possibly due to late sawing of
construction joints or excessive slab dimensions). Possible remedial maintenance works include: Full
bay reconstruction, transverse full depth repair of wide cracks, form groove and seal medium width
cracks.
Measurement: Crack length (m), spacing (m) and width (mm) and affected area (sqm) (refer
Figure J.14).
8. Rocking
Vertical movement of slab when vehicles pass over the slab – sometimes the movement causes water
or slurry to be squeezed upwards through joints or cracks (pumping) which may result in a loss of
support for the slab and aggravate the rocking. Possible causes include: lack of support to slab by the
sub-base; ineffective load transfer at joints (i.e. ineffective or absent dowels or the bars). Possible
remedial maintenance works include full depth reconstruction or grouting.
Measurement: Number of slabs affected (refer Figure J.16).
77
Unlikely to be used for rural roads.
9. Joint sealant defects
Loss and/or cracking of seal resulting in entry of debris into the joints and damage to joint edges,
extrusion of the sealant. Possible causes include: failure of seals due to cohesion failure (age,
deterioration of sealant especially due to UV radiation, faulty/inappropriate sealant, incorrect size of
sealing groove, lack of bond such that there is a break below the seal, adhesive failure (poor
preparation, incorrect size or moisture in sealing groove, chilling effect of cold concrete); extrusion
(incorrect size or overfilling of sealing groove); lack of compressible caulking below the sealing
groove or leaving the mould in the joint. Possible remedial maintenance works involve removal of
seal, cleaning and preparation of groove and re-sealing.
Measurement: % of the length of joints affected (refer Figure J.17).
12. Ravelling/Scaling
Progressive loss of surface integrity – loss of mortar and aggregate (also known as scaling). Possible
causes are various defects in the construction such as poor quality concrete, inadequate curing, over-
working of surface, wrong concrete mix design, inadequate cement or too high water content. Possible
remedial maintenance works include – full depth reconstruction or thin bonded surface repair (In
practice rural roads would probably not justify such repair except in case of heavier traffic or sensitive
location issues.)
Measurement: Area affected (sqm), depth of ravelling (mm) (refer Figure J.20).
Table-B 9.1 : Condition Rating of Defects, for Filling Table-B 9.5 by Detailed site inspection (Bituminous roads)
Column of Condition Rating (For Length 200 mt. & width 3.75 mt.)= 750m2
DEFECT QUANTUM
Table B-9.5 1 2 3 4 5
>1% 0.5% &1% 0.1%&0.5%
Potholes & depressions 4.1 % area <0.1% (0.75 sqm) -
(7.5m sqm) (3.75 &7.5 Sqm) (0.75 &3.75 sqm)
Rain cuts along side slopes 1, 9 Condition Very Poor Poor Fair Good Very Good
Side drains - (Sitting) 2,10 % silted 100% 75%&100% 50%&75% 25%&50% < 25%
CDS-blocked, sedimented (erosion) 11, 12 % blocked >75% 50 &75% 25 &50% <25% All open
Road furniture & signs 13 Condition Very Poor Poor Fair Good Very Good
Table-B 9.2 : Condition Rating of Defects, for Filling Table-B 9.6 by Detailed site inspection (Concrete roads)
Column
CONDITION RATING (For Length 200 mt. & width 3.75 mt.)= 750m2
of
DEFECT QUANTUM
Table B-
1 2 3 4 5
9.6
Rectangular (block) cracking 4.1 -
High: 1000mm/year 1
4-5 years 5
Age of road pavement,
since last renewal or 3-4 year 15
major upgrade 25
2-3 years
1-2 years 30
>300 0 2 5
Table B-9.5: Format for Determination of Road Condition Index (RCI), from RCR, for 5 + year old Roads, to be Maintened, As on RRNMU -------
S.No. Road ID Road Road District PIU Block Overall Factors, Converting RCR in to RCI Road
name Length (in RCR of Multipller Factor Weighted Road Condition Rating (WRCR) Condition
Km.) B.T. & C.C. Cost as
for Rainfall
Rainfall Terrain Calculated Adopted maximum Add on for
Road, as per
(8x9x10) 50, Age of Road Road
per estimates
( in case of value pavement Traffi c
Table B- recived
of col'n 11 since last volume
7.6 from PIU's
exceeds renewal/majo (in Lakh)
50, otherwise r upgrade
value of col'n 11 )
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Executive Engineer
PIU -------------
Format - B
Table B-9.6 Format for Determination of Road Condition Index (RCI), from RCR, for 5 + year old Roads, to be Maintened, As on RRNMU -----------
S.No. Road ID Road name Road Distt. PIU Block Overall RCR Factors, Converting RCR in to RCI Road
Length (in of B.T. & C.C. Condition
Km.) Road, as per Index
Table B-7.6 Multipller Factor Weighted Road Condition Rating (WRCR) (RCI)
for (12+13+14) Cost as per
Rainfall Terrain Calculated Adopted maximum Add on for estimates
(8x9x10) 50, recived Priority
( in case of value of Age of Road Road from PIU's
col'n 11 exceeds pavement since Traffi c (in Lakh)
50, otherwise value last volume
of col'n 11 ) renewal/major
upgrade
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
ANNEXURE B-10:RCI As Prioritization Tool- Case Study
TABLE B-10.1: HOW RCI CAN BE AN OBJECTIVE TOOL FOR PRIORITISATION CASE STUDY
Calculated
Adopted
+ (11+12)+13} Pavement of road and
Rainfall Terrain
since major traffi c
upgrade volume
1 17.5 1.15 1.25 25.2 25.2 5 4 34.2
2 28 1.15 1.25 40.3 40.3 15 8 63.3
3 26 1.15 1.25 37.4 37.4 15 8 60.4
4 33 1.15 1.25 47.4 47.4 25 15 87.4
5 33 1.15 1.25 47.4 47.4 25 15 87.4
6 21 1.15 1.25 30.2 30.2 5 4 39.2
7 20 1.15 1.25 28.8 28.8 5 4 37.8
8 34.5 1.15 1.25 49.6 49.6 25 15 89.6
9 29 1.15 1.25 41.7 41.7 15 6 62.7
10 35 1.15 1.25 50.3 50 25 15 90
11 29 1.15 1.25 41.7 41.7 15 6 62.7
12 25 1.15 1.25 35.9 35.9 15 8 58.9
13 19 1.15 1.25 27.9 27.9 5 4 36.3
14 32 1.15 1.25 46 46 25 20 91
15 30 1.15 1.25 43.1 43.1 15 8 66.1
16 29.5 1.15 1.25 42.4 42.4 15 8 65.4
17 27 1.15 1.25 38.8 38.8 15 6 59.8
18 15 1.15 1.25 21.6 21.6 1 4 26.6
19 18 1.15 1.25 25.9 25.9 5 4 34.9
20 29 1.15 1.25 41.7 41.7 15 8 64.7
21 32.5 1.15 1.25 46.7 46.7 25 20 91.7
22 27 1.15 1.25 38.8 38.8 15 6 59.8
23 34 1.15 1.25 48.9 48.9 25 20 93.9
24 13 1.15 1.25 18.7 18.7 1 4 23.7
25 36 1.15 1.25 51.75 50 25 20 95
26 29 1.15 1.25 41.7 41.7 15 6 62.7
27 22.5 1.15 1.25 32.3 32.3 5 4 41.3
28 32 1.15 1.25 46 46 25 15 86
29 31 1.15 1.25 44.6 44.6 25 15 84.6
30 36 1.15 1.25 51.75 50 25 15 90
31 40 1.15 1.25 57.5 50 25 15 90
32 27 1.15 1.25 38.8 38.8 15 6 59.8
33 35 1.15 1.25 50.3 50 25 20 95
34 32 1.15 1.25 46 46 25 20 91
35 33 1.15 1.25 47.4 47.4 25 20 92.4
36 15 1.15 1.25 21.6 21.6 1 2 24.6
37 26 1.15 1.25 37.4 37.4 15 8 60.4
38 31 1.15 1.25 44.6 44.6 25 20 89.6
39 32.5 1.15 1.25 46.7 46.7 25 15 86.7
40 26 1.15 1.25 37.4 37.4 15 6 58.4
41 38 1.15 1.25 54.6 50 25 15 90
42 39 1.15 1.25 56 50 25 15 90
43 41.5 1.15 1.25 59.6 50 25 15 90
44 25 1.15 1.25 35.9 35.9 15 6 56.9
45 29 1.15 1.25 41.7 41.7 15 6 62.7
46 34.5 1.15 1.25 49.6 49.6 25 15 89.6
47 33 1.15 1.25 47.4 47.4 25 20 92.4
48 29 1.15 1.25 41.7 41.7 15 6 62.7
49 45 1.15 1.25 64.7 50 25 20 95
50 20 1.15 1.25 28.8 28.8 5 2 35.8
Factors for Converting RCR Score into RCI for Universal
Kilometre-wise Overall
Application
rating based on Condition of Road
Sl. all the parameters - RCR Multiplier Factor WRCR Score Add on Condition
No. Score = value {[(1+2)+ Age of Road Category Index
Calculated
Adopted
(9+10)]/2 + (3+8) + (4+5+6+7) Pavement of road and (RCI)
Rainfall Terrain
+ (11+12)+13} since major traffic
upgrade volume
51 24 1.15 1.25 34.5 34.5 5 2 41.5
52 16.5 1.15 1.25 23.7 23.7 5 2 30.7
53 23 1.15 1.25 33.1 33.1 5 2 40.1
54 24 1.15 1.25 34.5 34.5 5 4 43.5
55 18 1.15 1.25 25.9 25.9 5 2 32.9
56 29 1.15 1.25 41.7 41.7 15 6 62.7
57 26 1.15 1.25 37.4 37.4 15 6 58.4
58 34 1.15 1.25 48.9 48.9 25 20 93.9
59 32 1.15 1.25 46 46 25 15 86
60 31 1.15 1.25 44.6 44.6 25 15 84.6
61 29 1.15 1.25 41.7 41.7 15 6 62.7
62 26 1.15 1.25 37.4 37.4 15 6 58.4
63 28 1.15 1.25 40.3 40.3 15 6 61.3
64 29 1.15 1.25 41.7 41.7 15 8 64.7
65 44 1.15 1.25 63.2 50 25 15 90
66 43 1.15 1.25 61.8 50 25 20 95
67 41.5 1.15 1.25 59.6 50 25 20 95
68 42 1.15 1.25 60.4 50 25 20 95
69 40 1.15 1.25 57.5 50 25 15 90
70 39 1.15 1.25 56 50 25 15 90
71 37.5 1.15 1.25 53.9 50 25 20 95
72 31 1.15 1.25 44.6 44.6 25 20 89.6
73 29 1.15 1.25 41.7 41.7 15 8 64.7
74 27 1.15 1.25 38.8 38.8 15 8 61.8
75 37 1.15 1.25 53.2 50 25 20 95
76 39.5 1.15 1.25 56.8 50 25 15 90
77 40 1.15 1.25 57.5 50 25 15 90
78 39 1.15 1.25 56.1 50 25 15 90
79 36 1.15 1.25 51.8 50 25 20 95
80 41 1.15 1.25 58.9 50 25 15 90
81 46 1.15 1.25 66.1 50 25 20 95
82 47 1.15 1.25 67.6 50 25 15 90
83 21.5 1.15 1.25 30.9 30.9 5 4 39.9
84 21 1.15 1.25 30.2 30.2 5 4 39.2
85 25 1.15 1.25 35.9 35.9 15 8 58.9
86 18.5 1.15 1.25 26.6 26.6 5 4 35.6
87 28 1.15 1.25 40.3 40.3 15 8 63.3
88 31 1.15 1.25 44.6 44.6 25 15 84.6
89 32 1.15 1.25 46 46 25 15 86
90 26 1.15 1.25 37.4 37.4 15 8 60.4
91 28 1.15 1.25 40.3 40.3 15 8 63.3
92 34 1.15 1.25 48.9 48.9 25 15 88.9
93 32 1.15 1.25 46 46 25 15 86
94 15 1.15 1.25 21.6 21.6 0 4 26.6
95 26.5 1.15 1.25 38.1 38.1 15 6 59.1
96 28 1.15 1.25 40.3 40.3 15 8 63.3
97 29 1.15 1.25 41.7 41.7 15 8 64.7
98 31 1.15 1.25 44.6 44.6 25 20 89.6
99 35 1.15 1.25 50.3 50 25 15 90
100 32.5 1.15 1.25 46.7 46.7 25 20 91.7
3
TABLE B-10.2: RCI AS A MONITORING AND AUDIT TOO
RCR RCR RCR RCR
Sl.no. RCI Priority Sl.no. RCI Priority Sl.no. RCI Priority Sl.no. RCI Priority
Score Score Score Score
24 13 23.7 1 95 26.5 59.1 26 15 30 66.1 51 70 39 90 76
Condition Rating
Criteria 1 2 3 4 5
Number of Roads falling in the
various Groups Before 15 14 22 31 18
Improvement Works
As per the existing methodology of rating, as shown above, it is difficult to assess the degree of
improvement for the network from the details of condition rating for various groups before and after
improvement. However with the RCR/RCI procedure assessing the change before and after
improvement, both at individual road level, as well as at the network level, is very easy, as shown in
the following example.
TABLE B-10.4: EVALUATION AT INDIVIDUAL ROAD LEVEL
RCI Before RCI After RCI Before RCI After RCI Before RCI After RCI Before RCI After
Sl. No. Improvemen Improvemen Sl. No. Improvemen Improvement Sl. No. Improvemen Improvemen Sl. No. Improvement Improvement
t Works t Works t Works Works t Works t Works Works Works
4. Table B-11.3I suggests the tentative costs of office operational expenses, which need to be
examined and appropriately estimated for various office-related expenses during the year. The
respective RCIP State needs to apply mind to get all possible expenditure items to be included
under the Office expenditure budget.
Table B-11.3: Office Operational Cost
Total ………………
4. Besides this a basic/standard write-up with the justification for the RRNMU operations
budget. States need to prepare this as an annual task for Maintenance. This will have to be submitted
to the SRRDA and State Government for obtaining funds under two distinct heads as indicated above.
5. There are other items of expenditure for RRNMU Operations, and the Summary of the
Operations Budget for RRNMU is given in Table B-11.4.
Table B-11.4: Sample Budget
COST ITEM Unit Rate Total Rs.
1. Staff costs for RRNMU as per Annexure B.I 12 month 5,27,000 63,24,000
2. Office expenses as per Annexure B.II 12 month 23,20,000
3. Laboratory Equipment Calibration, Maintenance&AMC 12 months 20,000 2,40,000
4. Laboratory Consumables for Testing 12 months 15,000 1,80,000
5. Vehicles (including motorcycles)
6. Running expenses for vehicles (fuel, maintenance, etc)
7. Data collection costs (for PIUs)– as per NRRDA norms 700 km Rs. 50/km 35,000
8. Costs of Monitoring & Evaluation (M&E)
9. Contingencies 50,000
Total
PLEASE NOTE that this operations budget is to be justified by a convincing and justifiable program
of activities for the RRNMU, which is the work plan of RRNMU for the whole year. Please examine
all possible expenses for operating the RRNMU, which is an organization that will be carrying out all
the activities related to planning, prioritization, and programming for the rural road maintenance (this
will be limited to the 5+ years old PMGSY roads only).
6. While the APB Format or Template justifies generally the RRNMU operations activities, there
will be separate sets of justifications for scientifically planned maintenance operations. That will
briefly be indicating the nature of maintenance interventions required along with the costs for each
road to be maintained.
7. The RCIP States are required to adopt appropriate calculations for estimation of the operations
budget under any of the heads (included in Table B-11.4) and provide any additional reasons or
justifications for the budget requirement. Table B-11.5 to Table B-11.8 show the list of office
equipment included in the list of equipment approved by NRRDA and ADB for procurement under
this project. The State can request for part or full purchase of the list along with sanction of fund from
NRRDA. In addition, if the RRNMU desires to purchase more/other equipment and furnishings for
operationalization of RRNMU, the Head of RRNMU shall be preparing a separate list of
goods/equipment to be procured as indicated in Table B-11.9, which shall be included in the proposed
Budget for funding by the State.
Table B-11.5: List of Equipment for Office of RRNMU
Unit
Sl. Qty Total Cost
Item Specification Rate
No. (nos) (INR)
(INR)
Lot No.: 1
Name: List of Equipment for Office of RRNMU of -------------------
Computer-Server with 8 GB Ram,600 GB
Computer –
SASx6 HDD, OS: Intel Core i3-
1 Server with 1 5,00,000
3110M,2Hhz. speed, 4 GB Ram, 500 GB
OS
HDD
Desktop Intel Core i5, 4Ghz. speed, 4 GB Ram, 500
2 20 15,00,000
Computers GB HDD
UPS 10 kva
3 UPS for power backup 2 2,90,000
online
Network Printer speer-20 pages per minute, printer
4 Printers language-PCL 5e & PCL 6,memory 1GB 2 1,00,000
(A3/A4) RAM
Printer speer-20 pages per minute, printer
Photocopier
5 language-PCL 5e & PCL 6,memory 1GB 1 1,00,000
& Scanner
RAM, Scanning in black and white
1 Vehicles 2 20,00,000*
Sl. Unit Rate Total Cost
Item Specification Qty (nos)
No. (INR) (INR)
10,00,000*
8. PLEASE NOTE that the budget submission to State Government has a standard format for
each State, and the RRNMU Head and Staff will have to prepare that format as well for easy
comprehension of the higher officials and Finance Officer of SRRDA. However, this APB shall also
be prepared as per this Format/Template, which also be attached to the State Government format for
appreciating the justifications and calculations of the budget.
Table B-12.1: Typical proportions of an adequate maintenance budget (for various condition
ratings)
Within a maintenance category with reduced allocation, prioritization should be according to LR/TR
and traffic
As budget sufficiency reduces so the maintenance program becomes increasingly reactive – routine
maintenance becomes heavier and more frequent as needed repairs are not undertaken or are
insufficient and emergency response becomes more frequent. At extreme levels of the budget deficit,
the response is almost entirely emergency response as road condition worsens.
ANNEXURE B-13 Package For Calling Tenders
The improvement plans include Reconstruction, Renewal course provision or simply Routine
Maintenance. The roads that would be reconstructed or provided renewal course will also be afforded
annual routine maintenance. Routine maintenance for roads that would be reconstructed or provided
renewal course should preferably be put on 5 to 7 or 8 years of PBMC. Roads that are in
comparatively in good condition or remain on routine maintenance due to paucity of funds will also be
put on annual maintenance. The detailed costs break-up in the following Table has been prepared
accordingly. There could be many ways of packaging for calling tenders suiting prevailing situations.
Hence, until there is an assessment it will be difficult to identify potential impacts, the degree to which
these are positive or negative and what avoidance or mitigating measures may be appropriate.
Scope and objectives of SIA
Identify key stakeholders and establish an appropriate framework for their participation in the
project selection, design and implementation.
Ensure that project objectives and incentives for change are acceptable to the range of people
intended to benefit and that gender and other social differences are reflected in project design.
Assess the social impact of investment projects and, where adverse impacts are identified,
determine how they can be overcome or at least substantially mitigated.
Develop ability at the appropriate level to enable participation, resolve conflict, permit service
delivery, and carry out mitigation measures as required.
Process of SIA
Social Impact Assessment is a process for ensuring that development activities are informed by and
take into account the key relevant social issues and formulate mitigated measures, and incorporate a
strategy for participation of wide range of stakeholders. Social Assessment is an iterative process that
has to be organised in a phased manner in several stages as briefed herewith:
Analyse Project Context
Identify stakeholders, perform stakeholder analysis
Identify social factors/variables
Analyse data and assess priorities
Consult stakeholders and develop mitigation plans
Implement mitigation plan and public participation
Ensure monitoring with active stakeholder involvement and modify it
2. Policy Guidelines and Legal Framework for Rural Roads
Figure P.1: Policy Guidelines and Legal Framework Applicable for Rural Roads
National Policy on Resettlement and Rehabilitation (NPRR), 2007.
The Right to Fair Compensation and Transparency on Land Acquisition, Rehabilitation and
Resettlement Act, 2013
ADB Safeguards Policy Statement 2009 and other applicable policy framework
Community Participation Framework especially designed for rural roads projects for all RCIP
state projects.
Overview of the Constitution (73rd Amendment) Act, Part IX of the Constitution of India,
1992, which enables the participation of Panchayat level institutions in decision making by
broadening the village level functions and supporting implementation of development scheme.
Reference of the Panchayats Extension to the Scheduled Areas Act (PESA), 1996.
Pradhan Mantri Gram Sadak Yojana (PMGSY) Programme Guidelines, November 2004 and
Operations Manual February 2005.
3: Requisite and Development of the Study and Techniques at Different Stages of Project Cycle
Generally a project cycle follows three stages, i.e. Project planning and design stage, construction,
Implementation stage and post construction and maintenance stage. Social Assessment and impact
assessment are relevant to all the stages of project cycle for which suitable tools and techniques are
required and developed.
The detailed requirements for SIA for the various stages of planning/design (DPR) and
implementation stages of new construction are covered in detail in the NRRDA Operations Manual
for PMGSY.
4: Post Construction/Maintenance Stage
Following the provision of CPF, during construction stage the major tasks shall be:
RCTRC providing on-the-job training and support to PIU by PICs in implementing Social
Safeguards and Community Participation Framework
Identification of temporary impact
RCTRC providing training and support to PIUs for inspection of roads and use of local labours for
maintenance work
Conduct of annual road maintenance workshops reporting the progress, result achieved issues
encountered and proposed counter measures
5: Institutional Arrangements and Capacity Building including
Role and Responsibilities of Key Agencies
Institutional arrangements: Key agencies involved
State Social Safeguard Cells
RRNMU with support of the Project Implementation Unit (PIU)
District level (EE/SE)
Field level (AE/JE)
Project Implementation Consultant (PIC)
Panchayat Raj Institution (PRI)
205
District level (Zilla Parishad)
Field level (Sarpanch and other Panchayat Members)
SRRDA
6: Monitoring and Reporting Procedures Monitoring System
Internal monitoring
RRNMU and Project Implementation Units (PIUs) will be responsible for the internal monitoring
throughout the implementation of the maintenance programme
206
ANNEXURE B-15: Design Measures For Road Safety
Incorporating appropriate safety design standards and features in rural roads can enhance road safety
to a great extent. In view of the lower levels of education in the rural areas, the engineering of roads to
constrain users to follow safe driving and behavioral standards it may be necessary to supplement with
warning signs. Some of the engineering measures that should be in-built into the design of rural roads
are listed below.
Rural roads may have a poor alignment due to the narrow land width available. Nevertheless, the
horizontal curves should be designed scientifically, conforming to the selected design speed and
terrain and provided with smooth transition curves and super- elevation. The carriageway should
be widened at curves.
The vertical profile of the road should be designed such that the required minimum stopping sight
distance is available. Suitable summit and valley curves should be provided.
In hill roads, blind curves are a safety hazard. Suitable vision berms may be cut at such locations.
Passing places must be provided at convenient locations particularly on hill roads.
The provision of rural connectivity leads to the introduction of bus services. Properly designed
bus-bays must be provided at bus stops to ensure that the buses do not hamper the normal traffic.
Where the roads pass through habitations and near schools, it is necessary that the motorized
vehicles travel at low speeds. This can be ensured by providing adequately designed road humps
or rumble strips.
The junction of rural roads with a main road is always a point of conflict and an accident- prone
zone. Such junctions must be designed scientifically by providing minimum turning radii, flaring
of the side road with taper, acceleration/deceleration lanes and adequate sight distances.
Ramps must be provided where field paths and cattle crossings intersect the road.
Traffic signage, incorporating warning and regulatory signs, can enhance road safety, especially
near habitations and school zones, sharp curves, narrow bridges, junctions, submersible bridges
and causeways.
Hazard markers like reflectorized delineators must be provided at dangerous locations.
Submersible bridges and causeways should be provided with water depth gauges and guide-posts
that shall remain at all times above the highest water level.
300mm dia ducts should be provided in the embankment to enable cultivators to thread
agricultural pipes for irrigating their fields lying on both sides of the road.
207
ANNEXURE B-16: Further Details On Performance Contracts (PBMC)
Performance contracts are based upon payment to the contractor subject to maintaining a road to
specified service level as measured against specified indicators (as opposed to measured quantities of
work in a ‘conventional’ ad-measure contract)-
An example of the performance indicators is given in the Table Q.1 given below [This example is
taken from a PBMC format used in Madhya Pradesh. Some PBMCs have a different scoring system
and a lower payment threshold (e.g. >70)].
Payment is only made to the contractor for scoring >80 (and such payment is proportional). Scoring
208
<80 is not paid.
This contract format has been introduced in many countries on the grounds that this form of contract
can reduce the administration and management burden on the maintenance
agency. Contracts can be multi-annual duration compared with ad-measure contracts which are
usually on an annual basis (or more accurately single dry season basis).
It is also suggested that PBMC maintenance regimes may also be more effective. However, there are
some pre-requisites to the successful introduction of this form of contract:
the road must be in a maintainable condition at the start of the PBMC;
the road should not be expected to require major works or periodic maintenance during the
duration of the PBMC (but see below);
the maintenance agency must have a clear appreciation of realistic costs of adequate
maintenance (and an equally good familiarity with the roads subject to PBMC). In fact, both
the maintenance agency and the contractor must have a good understanding of the PBMC
concept Contractors are typically perplexed by the PBMC concept when first introduced and
as a result, their tender rates may be unrealistic
It is often planned to implement a PBMC immediately after new construction or following periodic
maintenance (e.g. overlay) such that the road is in maintainable condition at the outset of the PBMC.
In this case, there are two alternatives:
two separate contracts – one admeasure (for the construction/periodic maintenance) and one
PBMC or;
a ‘hybrid’ combining admeasure and PBMC (A similar concept to the PMGSY construction
contract which includes routine maintenance for the first 5 years post-construction).
209
ANNEXURE B-17: Rural Road Network Management Report (QPR FORMAT)
January - March 2020 (Period of reporting)
The sample network above is for PIU Jabalpur similar one for the complete RRNMU Jabalpur
Jabalpur Rural Roads Network Management Unit
Date:…………………
210
Table of Contents
Section 1 Executive Summary………………… 206
Section 2 Rural Road Assets….…………….. 208
Section 3 Portfolio Performance……………. 211
Section 4 Findings and Recommendations…. 216
211
Section 1
Executive Summary
The Rural Road Network Management Report (Date……….) for the rural road network in District (i)
Katni, (ii) Jabalpur, (iii)..,& (viii) under jurisdiction of PIU (i) Katni, (ii) Jabalpur,….. & (viii) ….is
prepared by the RRNMU Jabalpur, Madhya Pradesh Rural Road Development Agency (MPRRDA).
This quarterly report is disclosed on MPRRDA Web Site on (Date……….) (within one month after
every quarter.)
The purpose of the Report
“To report and record the activities of the responsible management of the Jabalpur RRNMU road
network during the quarter and to communicate and justify funding requirements for the ongoing
works and the asset management complying with regulatory requirements.”
Vision Statement “To ensure accident-free and a good riding surface of all roads of RRNMU
Jabalpur”
Rural Road Assets
There are 8 Districts (i) (ii)…… & (viii) … . and 8 PIUs are responsible for the planning,
construction, and maintenance of the rural roads network forming part of PMGSY-I under the
jurisdiction of RRNMU Jabalpur. Presently, ……Nos of roads are under construction, ……Nos. are
being planned under PMGSY 2.
Having constructed these roads under PMGSY- I . ……roads have completed 10 years and …….roads
have completed more than 5 years. Whereas …..roads are due to complete 5 years of initial
maintenance of the construction contract.
There are ….. km of roads which have been graded as very poor, ……km as poor, …..km as fair,
……km as good, and ….km as very good as per the RCI ratings. (This is in the form of Table in
Section 3)
…… Minor Bridges have been constructed under PMGSY – I. The condition of these bridges is
satisfactory and only in case of 3 bridges the embankment had been damaged due to heavy rainfall and
these are under repairs during the quarter.
The cross drainage works comprise 8000 culvers of different spans and types and 150 causeways.
10000 speed breakers have been provided on the constructed roads. 20 of these have been removed as
they were not as per the standard design and were causing accidents, especially for the 2-wheelers.
Road furniture comprising information boards, km stones, cautionary signs, speed limit signage has
been provided on each road and is part of the inventory of each road. These are maintained as part of
routine maintenance.
212
Portfolio Performance
New Construction:
Completion – 80 roads under PMGSY-1 have been completed during the quarter which has connected
90 habitations.
Upgradation:
DPRs have been prepared for …..km of roads under PMGSY-2 by the DPR consultants during the
quarter.
Contracts Awarded:
(i) 3 Maintenance contracts were awarded for the works to be undertaken from the next quarter. These
pertain to 3 roads categorized as very poor.
(ii) 1 Construction contract under RCIP 1 has been awarded at Rs. …… Cr.
Budget:
For new construction, a total amount of Rs. Cr. was planned for the year 2020-21. Up to 31 March
21, Rs, ….. Cr has been disbursed to the contractors based on their actual work on the ground.
The approved maintenance budget for RRNMU Jabalpur for Financial Year 2020-21 was Rs.……
Crores against a requirement of Rs. ….Crore. Accordingly …roads that were on priority 1 for
maintenance could be maintained partially and ……roads could not be taken up. However, funds to
the tune of Rs.….. Crores were made available by ….Industries for the road leading to the industrial
area/mining area etc.
Ongoing works disbursements during the quarter have been Rs, ….Crores
Maintenance for roads which included …….Rs. ….. Crores were allotted from the state funds and Rs,
….. Crores were disbursed. Rs. …. Crores for maintenance of 5 of the roads were provided by Private
Enterprises and Rs. ….Crores were spent for the purpose.
Findings and Recommendations
Findings:
With budget falling short for maintenance 30 km on 3 roads could not be taken up
Though the RRNMU has carried out its functions as laid down, the transfer without suitable
replacement may affect the efficiency if not done ASAP.
213
Section 2
Rural Road Assets
The RRNMU is presently responsible for all the road assets of PMGSY-I, under construction and
those under maintenance, and is also planning for assets to be created under PMGSY-II. These are
presented in form of Tables below:
Rural Road Network Assets under Planning – PMGSY-II
Dist./PIU No. of Length Major Minor Culverts Causeways Road
roads (km) Bridges Bridges (All Furniture
Nos. Nos. types)
1 2 3 4 5 6 7 8
Row 1 54
Jabalpur
Row 2 100
Katni
Balaghat
Chindwara
Dindori
Mandla
Narsinghpur
Seoni
Total for
RRNMU
Roads including bridges under Construction PMGSY-I (Sample below): Total length of roads is
inclusive of bridges
214
Physical Target and Achievement year 2016-17
Shortfall(-) Excess(+)
RRNMU Jabalpur Physical Target Achieved (km)
PIU Dist Total Qtr. Qtr.
Target For
Achieved Ending Ending 31
2020-21 Qtr. Ending 31 Mar 21
2020-21 31 Mar Mar 21
(km)
(km) 21 (km) (km)
Balaghat
Chhindwara
Dindori
Jabalpur Jabalpur (-) 2.5 km
Katni Katni
Mandla
Narsighpur
Seoni
Total
215
216
Cross drainage works, Road furniture, Speed Breakers Constructed PMGSY-I (Sample Below)
PIU Culverts Causeways Road Furniture Speed
Bridges
(Nos.) (add columns for Breaker
(Nos)
Districts other items)
Major Mi Hume Slab Road Km
nor Pipe Signage stones
Dindori
Jabalpur Jabalpur 25
Katni Katni
Mandla
Total for RRNMU
Jabalpur
217
Section3
Portfolio Performance
The maintenance operations comprise of roads which are under 5 year’s maintenance period, the roads
which have completed between 5-10 years after completion. The road network is classified under
Road conditions 1, 2, 3, 4, and 5 as very poor, poor, fair, good, and very good respectively. Based on
the ratings the maintenance works planned and executed are Rehabilitation, Reconstruction and
Routine Maintenance/ Deferred Improvement, Reseal after major Patch Reconstruction and Routine
Maintenance, Reseal followed by Routine Maintenance, Heavy Patching plus Routine Maintenance,
and Routine Maintenance for the 5 ratings respectively.
Physical Performance during Quarter March 2021
The physical performance of Jabalpur RRNMU for various stages are tabulated below:
Planning for PMGSY – II (sample below)
Dist./ No. of Length DPR Procurement Process Contract
PIU roads (km) Status NITs Issued Tech Fin Awards
(Packages} Evaluated Evaluated
1 2 3 4 5 6 7 8
Row 1 8
Jabalpur
Row 2 6 3
Katni
Total for
RRNMU
Jabalpur
While 8 DPRs have been prepared and sent to NRRDA for approval, 6 bids are under financial
evaluation and 3 contracts were awarded at Rs. ….Cr. for Katni district during the quarter.
218
Roads under Construction including Bridges PMGSY I (Sample)
Physical Target Achieved (km) Shortfall(-)/Excess(+)
(km)
PIU District
Qtr. Ending 31 Qtr. Ending 31
Qtr. Ending 31 Mar 21
Mar 21 Mar 21
Jabalpur Jabalpur
Katni Katni
Mandla 28.5 km
Narsighpur
During the quarter 3 roads, 28.5 km in length in Mandla district were substantially completed
219
Road Network Improvement PMGSY-I
Road Condition Index (RCI)
Rating 1 2 3 4 5
Condition Very Poor Poor Fair Good Very Good
Improvement Rehabilitation, Reseal after Reseal Heavy Routine
Plan Reconstruction major Patch followed by Patching Maintenance
and Routine Reconstruction Routine plus Routine (km)
Maintenance/ and Routine Maintenance Maintenance
Deferred Maintenance (km) (km)
Improvement (km)
(km)
Balaghat
Chhindwara
Dindori
Jabalpur 100 +100
Katni
Mandla
Narsighpur
Seoni
Total for
RRNMU
Jabalpur
During the quarter 50 km of rehabilitation works have been carried out and accordingly the very good
condition road network has increased to 700 km
220
Financial Performance - Construction
PMGSY - I PMGSY - I
Total Expenditure (Rs. Total Received from GoI & State
Quarter Ending Received from GoI StateGovt. Received from GoI
Expenditure. (Rs.Cr) Expenditure (Rs.Cr) State Govt. Share 40% Cr.) Govt. through MPRRDA
thro' MPRRDA (60%) Share 40% thro' MPRRDA (60%)
1 2 3 4 5 6 7 8 (2+5) 9 (4+6+7)
QE Mar 17 120 Cr 60 cr 40 cr Nil Nil 100 cr
QE Jun 17 (Planned)
Financial Performance PMGSY – I: Maintenance
Quarter PIU/Dist. Within 5 year after Constr. Post 5 Years after constr. Rehabilitation/ Total
(Regular Maint. Part of contract) (Periodic Maint) Stregthening Funds
Financial Performance during Quarter March 2017
Katni
……..
……..
221
Outcomes
Jabalpur RRNMU (31 Mar 17) ( Figure as sample only)
S. No. PMGSY-I PMGSY - II Total for RRNMU
Roads Completed
(i) Km
1470.1 1470.1
(ii) No. of roads
3 342 342
(iii) Percentage by roads.
94 94
(iv) Cost in Rs. Crores
586.93 586.93
(v) Habitation connected
457 457
222
Section 4
Findings and Recommendations
routine
maintenance
Length (km)
Total maint.
(Rs Crore)
(Rs Crore)
Renewal
Planned
Amount
Amount
Amount
Amount
Amount
Amount
Routine
renewal
Length
Length
Total
(km)
(km)
1 2 3 4 5 6 7 8 9 10 11 12 13
2016-17 10 50 60 70 130
2017-18
2018-19
2019-20
2020-21
223