SHPP GL Ch3.Full
SHPP GL Ch3.Full
STANDARDS/MANUALS/
GUIDELINES FOR
SMALL HYDRO DEVELOPMENT
Electro-Mechanical Works–
Selection of Turbine And Governing System for Hydroelectric
Project
May 2011
CONTENTS
1.0 OVERVIEW 1
2.0 REFERENCES 1
3.0 SITE DATA 2
3.1 Net Head 2
3.2 Definition of Head 2
4.0 CLASSIFICATION AND TYPES OF TURBINES 5
4.1 Francis Turbines 5
4.2 Axial Flow Turbines 6
4.3 Impulse Turbines 8
4.4 Cross Flow Turbines 17
5.0 SELECTION OF HYDRAULIC TURBINE 21
6.0 SETTING AND CAVITATION OF REACTION TURBINE 44
7.0 TURBINE PERFORMANCE 49
7.1 Pressure Regulation 49
7.2 Speed Regulation 50
7.3 Speed Rise 51
7.4 Pressure Rise and Speed Rise Calculation 52
7.5 Method for Computing Speed Rise 52
8.0 HYDRO TURBINE GOVERNING SYSTEM 56
8.1 Introduction 56
8.2 Type of Governor Control Section 57
8.3 Turbine Control Actuator System 58
8.4 Small Hydro Governor Selection Consideration 59
8.5 Personal Computers (PC)/Programmable Logic Controller (PLC) base Digital 60
Governors
8.6 Governing System used in India 63
8.7 U.S. Practice Regarding Governor and Control 65
8.8 Examples of Typical Governing System 67
ANNEXURES
Annexure – 1 74
Annexure – 2 79
Annexure – 3 80
Annexure – 4.1 81
Annexure – 4.2 82
Annexure – 4.3 83
Annexure – 4.4 84
Annexure – 4.5 85
Annexure – 4.6 86
Annexure – 4.7 87
Annexure – 4.8 88
Annexure – 4.9 89
Annexure – 4.10 90
Annexure – 4.11 91
Annexure – 4.12 92
Annexure – 4.13 93
Annexure – 5 94
Guide for Selection of Turbine and Governing
System for Hydroelectric Generating Units
Up to 25 MW
1. OVERVIEW
Selecting the type, kind, (within type) configuration, (horizontal or vertical) size, and
number of turbine units that best suit a project is a detailed process. This involves
technical, environmental, financial, and other considerations. The most inexpensive
turbine may not be the best solution to the available head and flow. For small hydro up to
5 MW unit size, selection on the basis of typical turbine data furnished by manufacturers
is recommended. For units above 5 MW size information exchange with turbine
manufacturers is recommended for turbine at project stage. The selection procedure is
prepared for selection of turbine based on the techno economic consideration to permit
rapid selection of proper turbine unit, estimation of its major dimensions and prediction
of its performance.
1.1.1 Purpose
The purpose of this guide is to provide guidance for application of hydroelectric turbines
and governing systems by developers, manufacturers, consultants, regulators and others.
The guide includes, planning, investigation, design and execution, manufacture of
equipment and test at work.
2. REFERENCES
This guide shall be used in conjunction with the following publications. When the
following specification are superseded by an approved revision, the revision shall apply.
IS: 12800 (Part 3) – 1991, Guidelines for selection of hydraulic turbine, preliminary
dimensioning and layout of surface hydroelectric powerhouses.
IS: 12837 – 1989, Hydraulic turbines for medium and large power houses – guidelines
for selection
IEC: 60308 – 1970, International code for testing of speed governing system for
hydraulic turbines.
IEC: 545 – 1976, Guide for commissioning, operation and maintenance of hydraulic
turbines.
AHEC/MNRE/SHP Standards/E&M Works – Guidelines for Selection of Turbine and 1
Govering System for Hydroelectric Projects
IEC: 609 – 1978, Cavitation pitting evaluation in hydraulic turbines, storage pumps and
pump-turbines.
IEEE: 1207 – 2004, Guide for the application of turbine governing system for
hydroelectric generating units.
3. SITE DATA
It is presumed that the data with regard to design head, design discharge, number and
types of units and capacity are known. Departure from these guidelines may be necessary
to meet the special requirements and conditions of individual sites.
The effective head available to the turbine unit for power production is called the net
head. Selection of rated and design head requires special attention. Definition of these
heads are given in Para 1.5 and shown in figure 1.1. The turbine rating is given at rated
head.
Determination of rated head, design head and maximum and minimum net head is
important. Permissible departure from design head for reaction turbines for optimum
efficiency and cavitations characteristics based on experience data is shown in table 1.1.
EFFECTIVE HEAD (Net Head) - The effective head is the net head available to the
turbine unit for power production. This head is the static gross head, the difference
between the level of water in the Forebay/impoundment and the tailwater level at the
outlet, less the hydraulic losses of the water passage as shown in Fig. 1.1. The effective
AHEC/MNRE/SHP Standards/E&M Works – Guidelines for Selection of Turbine and 2
Govering System for Hydroelectric Projects
head must be used for all power calculations. The hydraulic losses can vary from
essentially zero for flume-type turbine installations to amounts so significant for
undersized outlet conduit that the energy potential of the site is seriously restricted. The
hydraulic losses in closed conduit can be calculated using the principles set out in general
hydraulic textbooks. In addition to conduit losses, an allowance for a loss through the
intake structure should also be included. In general a hydraulic loss of one velocity head
(velocity squared divided by 2 x acceleration due to gravity) or greater would not be
uncommon. The hydraulic losses through the turbine and draft tube are accounted for in
the turbine efficiency.
Gross Head (Hg) – is the difference in elevation between the water levels of the forebay
and the tailrace.
Maximum Head (Hmax) – is the gross head resulting from the difference in elevation
between the maximum forebay level without surcharge and the tailrace level without
spillway discharge, and with one unit operating at speed no-load (turbine discharge of
approximately 5% of rated flow). Under this condition, hydraulic losses are negligible
and nay be disregarded.
Minimum Head (Hmin) – is the net head resulting from the difference in elevation
between the minimum forebay level and the maximum tailrace level minus losses with all
turbines operating at full gate.
Table 1.1
Weighted Average Head - is the net head determined from reservoir operation
calculations which will produce the same amount of energy in kilowatt-hours between
that head and maximum head as is developed between that same head and minimum
head.
Design Head (hd) – is the net head at which peak efficiency is desired. This head should
preferably approximate the weighted average head, but must be so selected that the
maximum and minimum heads are not beyond the permissible operating range of the
turbine. This is the head which determines the basic dimensions of the turbine and
therefore of the power plant.
AHEC/MNRE/SHP Standards/E&M Works – Guidelines for Selection of Turbine and 3
Govering System for Hydroelectric Projects
MAXIMUM WATER SURFACE
SURCHARGE
REQUIRED
SUBMERGENCE
MINIMUM HEAD, Hmin
(MUST NOT EXCEED 65% OF hd)
INACTIVE AND DEAD
CAPACITY
TAILRACE
Rated head (hr) – is the net head at which the full-gate output of the turbine produce the generator rated output in kilowatts. The turbine
nameplate rating usually is given at this head. Selection of this head requires foresight and deliberation.
Permissible range of head for reaction turbines for optimum efficiency and cavitations characteristics based on experience data is as follows in
table 1.1.
AHEC/MNRE/SHP Standards/E&M Works – Guidelines for Selection of Turbine and 4
Govering System for Hydroelectric Projects
4. CLASSIFICATION AND TYPES OF TURBINES
Turbines can be either reaction or impulse types. The turbines type indicates the manner in
which the water causes the turbine runner to rotate. Reaction turbine operates with their
runners fully flooded and develops torque because of the reaction of water pressure against
runner blades. Impulse turbines operate with their runner in air and convert the water’s
pressure energy into kinetic energy of a jet that impinges onto the runner buckets to develop
torque.
Reaction turbines are classified as Francis (mixed flow) or axial flow. Axial flow turbines are
available with both fixed blades (Propeller) and variable pitch blades (Kaplan). Both axial
flow (Propeller & Kaplan) and Francis turbines may be mounted either horizontally or
vertically. Additionally, Propeller turbines may be slant mounted.
A Francis turbine is one having a runner with fixed blades (vanes), usually nine or more, to
which the water enters the turbine in a radial direction, with respect to the shaft, and is
discharged in an axial direction. Principal components consist of the runner, a water supply
case to convey the water to the runner, wicket gates to control the quantity of water and
distribute it equally to the runner and a draft tube to convey the water away from the turbines.
A Francis turbine may be operated over a range of flows approximately 40 to 110% of rated
discharge. Below 40% rated discharge, there can be an area of operation where vibration
and/or power surges occur. The upper limit generally corresponds to the maximum generator
rating. The approximate head range for operation is from 65% to 125% of design head. In
general, peak efficiencies of Francis turbines, within the capacity range of 25 MW, with
modern design tool like CFD (computational fluid dynamics) have enabled to achieve peak
efficiency in the range of 93 to 94%.
The conventional Francis turbine is provided with a wicket gate assembly to permit placing
the unit on line at synchronous speed, to regulate load and speed, and to shutdown the unit.
The mechanisms of large units are actuated by hydraulic servomotors. Small units may be
actuated by electric motor gate operations. It permits operation of the turbine over the full
range of flows. In special cases, where the flow rate is constant, Francis turbines without
wicket gate mechanisms may be used. These units operate in case of generating units in
Micro Hydel range (upto 100 kW) with Electronic Load Controller or Shunt Load
Governors. Start up and shut down of turbines without a wicket gate is normally
accomplished using the shut off valve at the turbine inlet. Synchronising is done by manual
load control to adjust speed.
Francis turbines may be mounted with vertical or horizontal shafts. Vertical mounting allows
a smaller plan area and permits a deeper setting of the turbine with respect to tailwater
elevation locating the turbine below tailwater. Turbine costs for vertical units are higher than
for horizontal units because of the need for a larger thrust bearing. However, the savings on
construction costs for medium and large units generally offset this equipment cost increase.
Horizontal units are more economical for smaller sets with higher speed applications where
standard horizontal generators are available.
AHEC/MNRE/SHP Standards/E&M Works – Guidelines for Selection of Turbine and 5
Govering System for Hydroelectric Projects
The water supply case is generally fabricated from steel plate. However open flume and
concrete cases may be used for heads below 15 meters for vertical units.
Francis turbines are generally provided with a 90-degree elbow draft tube, which has a
venturi design to minimize head loss. Conical draft tubes are also available, however the head
loss will be higher and excavation may be more costly.
Axial flow turbines are those in which flow through the runner is aligned with the axis of
rotation. Axial flow hydraulic turbines have been used for net heads up to 60 meters with
power output up to 25 MW. However, they are generally used in head applications below 35
meters Tubular turbine (S-type). S-turbines are used below 30 meters head and 8 MW
capacity. Bulb units can be used for low head if runner diameter is more than 1 meter.
Specific mechanical designs, civil construction, and economic factors must be given full
consideration when selecting among these three axial flow turbine arrangements.
A propeller turbine is one having a runner with four, five or six blades in which the water
passes through the runner in an axial direction with respect to the shaft. The pitch of the
blades may be fixed or movable. Principal components consist of a water supply case,
wicket gates, a runner and a draft tube.
The efficiency curve of a typical fixed blade Propeller turbine forms a sharp peak, more
abrupt than a Francis turbine curve. For variable pitch blade units the peak efficiency occurs
at different outputs depending on the blade setting. An envelope of the efficiency
curves cover the range of blade pitch settings forms the variable pitch efficiency curve. This
efficiency curve is broad and flat. Fixed blade units are less costly than variable pitch blade
turbines; however, the power operating ranges are more limited.
In general, peak efficiencies are approximately the same as for Francis turbines.
Propeller turbines may be operated at power outputs with flow from 40-120% of the rated
flow. Discharge rates above 105% may be obtained; however, the higher rates are generally
above the turbine and generator manufacturers’ guarantees. Many units are in satisfactorily
operation is from 60 to 140% of design head. Efficiency loss at higher heads drops 2 to 5%
points below peak efficiency at the design head and as much as 15% points at lower heads.
The conventional propeller or Kaplan (variable pitch blade) turbines are mounted with a
vertical shaft. Horizontal and slant settings will be discussed separately. The vertical units are
equipped with a wicket gate assembly to permit placing the unit on line at synchronous speed,
to regulate speed and load, and to shutdown the unit. The wicket gate mechanism units are
actuated by hydraulic servomotors. Small units may be actuated by electric motor gate
operators. Variable pitch units are equipped with a cam mechanism to coordinate the pitch of
the blade with gate position and head. Digital control envisages Control of wicket gates and
blade angle by independent servomotors co-ordinated by digital control. The special
condition of constant flow, as previously discussed for Francis turbines, can be applied to
propeller turbines. For this case, elimination of the wicket gate assembly may be acceptable.
Variable pitch propeller turbines without wicket gates are called semi Kaplan turbine.
The draft tube designs discussed for Francis turbines apply also to propeller turbines.
AHEC/MNRE/SHP Standards/E&M Works – Guidelines for Selection of Turbine and 6
Govering System for Hydroelectric Projects
4.2.1 Tubular Turbines (S-Type)
Tubular or tube turbines are horizontal or slant mounted units with propeller runners. The
generators are located outside of the water passageway. Tube turbines are available equipped
with fixed or variable pitch runners and with or without wicket gate assemblies.
The performance range of the tube turbine with variable pitch blade and without wicket
gates is greater than for a fixed blade propeller turbine but less than for a Kaplan turbine. The
water flow through the turbine is controlled by changing the pitch of the runner blades.
When it is not required to regulate turbine discharge and power output, a fixed blade runner
may be used. This results in a lower cost of both the turbine and governor system. To
estimate the performance of the fixed blade runner, use the maximum rated power and
discharge for the appropriate net head on the variable pitch blade performance curves.
Several items of auxiliary equipments are often necessary for the operation of tube turbines.
All tube turbines without wicket gates should be equipped with a shut off valve automatically
operated to provide shut-off and start-up functions.
Tube turbines can be connected either directly to the generator or through a speed increaser.
The speed increaser would allow the use of a higher speed generator, typically 750 or 1000
r/min, instead of a generator operating at turbine speed. The choice to utilize a speed
increaser is an economic decision. Speed increasers lower the overall plant efficiency by
about 1% for a single gear increaser and about 2% for double gear increaser. (The
manufacturer can supply exact data regarding the efficiency of speed increasers). This loss of
efficiency and the cost of the speed increaser must be compared to the reduction in cost for
the smaller generator. It is recommended that speed increaser option should not be used for
unit sizes above 5 MW capacity.
The required civil features are different for horizontal units than for vertical units.
Horizontally mounted tube turbines require more floor area than vertically mounted units.
The area required may be lessened by slant mounting, however, additional turbine costs are
incurred as a large axial thrust bearing is required. Excavation and powerhouse height for a
horizontal unit is less than that required for a vertical unit. typical Tube turbines of Bharat
Heavy Electricals based on runner diameter is shown in Figure 4.2.1.
Bulb Turbines are horizontal, which have propeller runners directly connected to the
generator. The generator is enclosed in a water-tight enclosure (bulb) located in the turbine
water passageway. The bulb turbine is available with fixed or variable pitch blades and with
or without a wicket gate mechanism. Performance characteristic are similar to the vertical and
Tube type turbines previously discussed. The bulb turbine will have an improved efficiency
AHEC/MNRE/SHP Standards/E&M Works – Guidelines for Selection of Turbine and 7
Govering System for Hydroelectric Projects
of approximately 2% over a vertical unit and 1% over a tube unit because of the straight
water passageway.
Due to the compact design, powerhouse floor space and height for Bulb turbine installations
are minimized. Maintenance time due to accessibility, however, may be greater than for
either the vertical or the tube type turbines. Figure 4.2.2 shows transverse section of bulb
turbine installation proposed for Mukerain SHP 2 x 9 MW rated and design head 8.23 m.
Low specific speed Vertical semi-Kaplan turbine set above maximum tailrace level with
Syphon intake with adjustable runner blade and fixed guide vane. As the name suggests, the
Vertical Turbine with Syphon Intake operation on the Syphon Principle i.e. the intake flume
chamber valve is closed and made water tight and vacuum is created by a vacuum pump
which enables water to enter flume chamber and energise the runner. Shut down is brought
about by following the reverse procedure i.e. by breaking vacuum. Since turbine operates on
a Syphon Principle, it is not necessary to have Intake and Draft gates thereby reducing the
cost. The Syphon Intake semi Kaplan Vertical Turbine part load efficiency at about 30% load
is about 76%. Turbine is suitable for variable head also. Dewatering and drainage
arrangements are also not requested.
This type of turbine has been found to be most economical for canal drop falls (upto 3-4 m
head). The turbine is set above maximum tailwater level and hence lower specific speed. A
typical installation is shown in fig. 4.2.3.
Pit type turbine is a variation of S-type arrangements. Typical pit Turbines coupled to
standard high speeds generator through step up bevel/helical gears are generally used. Overall
efficiency is lower because of gear box. Maximum size depends upon gear box and is
generally limited to 5 MW. Higher sized units upto 10 MW have been recently installed.
Performance data of these units is not available. Typical installation is shown in figure 4.2.4
(a & b).
An impulse turbine is one having one or more free jets discharging into an aerated space and
impinging on the buckets of a runner. Efficiencies are often 90% and above. In general,
an impulse turbine will not be competitive in cost with a reaction turbine in overlapping range
(Fig. 5.1). However, economic consideration (speed) or surge protection requirements may
warrant investigation into the suitability of an impulse turbine in the overlapping head.
Single nozzle impulse turbine have a very flat efficiency curve and may be operated down to
loads of 20% of rated capacity with good efficiency. For multi-nozzle units, the range is even
broader because the number of operating jets can be varied (figure 4.3.2).
AHEC/MNRE/SHP Standards/E&M Works – Guidelines for Selection of Turbine and 8
Govering System for Hydroelectric Projects
AHEC/MNRE/SHP Standards/E&M Works – Guidelines for Selection of Turbine and 9
Govering System for Hydroelectric Projects
Fig. 4.2.1 Typical Dimension of Tube Turbine (Source: BHEL India)
AHEC/MNRE/SHP Standards/E&M Works – Guidelines for Selection of Turbine and 10
Govering System for Hydroelectric Projects
Fig. 4.2.3: Syphon Intake for Tejpura Project
(Source: AHEC Specification)
AHEC/MNRE/SHP Standards/E&M Works – Guidelines for Selection of Turbine and 12
Govering System for Hydroelectric Projects
Fig. 4.2.4 (a)
AHEC/MNRE/SHP Standards/E&M Works – Guidelines for Selection of Turbine and 13
Govering System for Hydroelectric Projects
Fig. 2.3.4
AHEC/MNRE/SHP Standards/E&M Works – Guidelines for Selection of Turbine and 14
Govering System for Hydroelectric Projects
Fig. 4.3.1 Impulse Turbine for Kitpi Project (2 x 1500 KW) –AHEC Project
AHEC/MNRE/SHP Standards/E&M Works – Guidelines for Selection of Turbine and 15
Govering System for Hydroelectric Projects
Typical Efficiency Versus Load Curves
Fig. 4.3.2 Francis Versus Pelton Performance. Typical efficiency versus load
characteristics for a low specific speed Francis turbine and a six-jet Pelton turbine with
the optimal number of jets in service are compared
Control of the turbine is maintained by hydraulically operated needle nozzles in each jet.
In addition, a jet deflector is provided for emergency shutdown. The deflector diverts the
water jet from the buckets to the wall of the pit liner. This features provides surge
protection for the penstock without the need for a pressure valve because load can be
rapidly removed from the generator without changing the flow rate.
Control of the turbine may also be accomplished by the deflector alone. On these units
the needle nozzle is manually operated and the deflector diverts a portion of the jet for
lower loads. This method is less efficient and normally used for speed regulation of the
turbine under constant load.
Runners on the modern impulse turbine are a one-piece casting. Runners with
individually attached buckets have proved to be les dependable and, on occasion, have
broken away from the wheel causing severe damage to powerhouse. Integral cast runners
are difficult to cast, costly and require long delivery times. However, maintenance costs
for an impulse turbine are less than for a reaction turbine as they are free of cavitation
problems. Excessive silt or sand in the water however, will cause more wear on the
runner of an impulse turbine than on the runner of most reaction turbines.
AHEC/MNRE/SHP Standards/E&M Works – Guidelines for Selection of Turbine and 16
Govering System for Hydroelectric Projects
The runner must be located above maximum tailwater to permit operation at atmospheric
pressure. This requirement exacts an additional head loss for an impulse turbine not
required by a reaction turbine.
Impulse turbines may be mounted horizontally or vertically. The additional floor space
required for the horizontal setting can be compensated for by lower generator costs on
single nozzle units in the lower capacity sizes. Vertical units require less floor space and are
often used for large capacity multi-nozzle units.
Horizontal shaft turbines are suitable for small hydro applications that have less water
available.
Multi-jet turbines are slightly more costly than single jet turbines; however, the more rapid
accumulation of stress cycle alternations justify a more conservative runner design.
Abrasive martial entrained in the water will erode the buckets of a multi-jet turbine more
rapidly than in the case of a single jet per runner.
For the same rated head and flow conditions, increasing the number of jets results in a
smaller runner and a higher operating speed. Therefore, whether vertical or horizontal,
multi-jet turbines tend to be less costly for comparable outputs because the cost of the
runner represents up to 20% of the cost of the entire turbine.
A deflector is normally used to cut into the jet when rapid power reductions are required
such as a complete loss of connected-load. The deflector is mounted close to the runner on
the nozzle assembly and typically is provided with its own servomotor. Cross section of 2
jet pelton turbine of Kitpi project is at figure 4.3.1
Another type of impulse turbine is the Turgo impulse. This turbine is higher in specific
speed than the typical impulse turbine. The difference between a Pelton unit and a Turgo is
that, on a Turgo unit, the jet enters one side of the runner and exits the other side. The
Turgo unit operates at a higher specific speed, which means for the same runner diameter as
a Pelton runner, the rotational speed can be higher. The application head range for a Turgo
unit is 15 meters to 300 meters. Turgo units have been used for application up to 7,500 kW.
Efficiency of turgid impulse turbine is about 82 to 83 %.
A cross flow turbine is an impulse type turbine with partial air admission.
Performance characteristics of this turbine are similar to an impulse turbine, and consist of a
flat efficiency curve over a wide range of flow and head conditions.
Peak efficiency of the cross flow turbine is less than that of other turbine types previously
discussed. Guaranteed maximum efficiency of indigenous available turbines is about 60-
65%.
AHEC/MNRE/SHP Standards/E&M Works – Guidelines for Selection of Turbine and 17
Govering System for Hydroelectric Projects
Fig. 4.4 (i) Cross section view of Jagthana Cross Flow SHP (2 x 50 kW) – AHEC Project
AHEC/MNRE/SHP Standards/E&M Works – Guidelines for Selection of Turbine and 18
Govering System for Hydroelectric Projects
Fig. 4.4 (ii) Side view of Jagthana SHP (2 x 50 kW) with cross flow turbine
(AHEC project)
AHEC/MNRE/SHP Standards/E&M Works – Guidelines for Selection of Turbine and 20
Govering System for Hydroelectric Projects
Floor space requirements are more than for the other turbine types, but a less complex
structure is required and a savings in cost might be realized. Efficiency of cross flow
turbine of standard 300 MW dia. tested in AHEC testing labs is attached as Annexure 2
and average about 54.5%. Cross section and Side view of cross flow turbine of Jagthana
SHP is at figure 4.4 (i) & (ii).
General – The net head available to the turbine dictates the selection of type of turbine
suitable for use at a particular site. The rate of flow determines the capacity of the
turbine. The term specific speed is generally used in classifying types of turbines and
characteristics within type as shown in figure 5.1. This figure is based on ASME guide to
design of hydropower mechanical design 1996 and modified by Indian Projects date
attached as Annexure-1. Exact definition of specific speed is given later. Impulse turbines
have application in high head hydropower installations. Application of impulse turbine in
low head range is limited to very small size units.
Application range of the three types of turbine is overlapping as shown in figure 5.1.
Description & Application of important turbine types is as follows:
Various types of turbines have already been explained in Para 4.0. selection criteria of
hydraulic turbine upto 5 MW units size (including micro hydels) is generally based on
using standard turbines. Hydraulic turbine above 5 MW unit size are generally tailor
made and selection criteria is more specific.
Specification require that the manufacturer be responsible for the mechanical design and
hydraulic efficiency of the turbine. Objective of these guidelines is to prepare designs and
specification so as to obtain a turbine that result in the most economical combination of
turbine, related water passages, and structures. Competitive bidding for the least
expensive turbine that will meet specification requirements is required. In evaluating the
efficiency of a proposed turbine, the performance is estimated on the basis of experience
rather than theoretical turbine design. Relative efficiency of turbine types is shown in
figure 4.3.2 and 5.2. The peak efficiency point of a Francis turbine is established at 90%
of the rated capacity of the turbine. In turn, the peak efficiency at 65% of rated head will
drop to near 75%.
To develop a given power at a specified head for the lowest possible first cost, the turbine
and generator unit should have the highest speed practicable. However, the speed may be
limited by mechanical design, cavitation tendency, vibration, drop in peak efficiency, or
loss of overall efficiency because the best efficiency range of the power efficiency curve
is narrowed. The greater speed also reduces the head range under which the turbine will
satisfactory operate.
AHEC/MNRE/SHP Standards/E&M Works – Guidelines for Selection of Turbine and 21
Govering System for Hydroelectric Projects
Note: Details of SHP marked on the chart are attached as Annexure-1 (Based on ASME–Guide to Hydropower Mechanical Design Book)
Fig. 5.1 Ns Versus Head. This figure shows the various turbine type as a function of specific speed (Ns) and head. This figure should be
used a guideline, as there is overlap between the various turbine types with respect to their operating ranges
AHEC/MNRE/SHP Standards/E&M Works – Guidelines for Selection of Turbine and 22
Govering System for Hydroelectric Projects
The selection of speed and setting described in these guidelines is satisfactory for
conditions normally found at most sites and will usually result in a balance of factors that
will produce power at the least cost.
5.1 Specific Speed (Ns) – The term specific speed used in classifying types of turbines
and characteristics of turbines within types is generally the basis of selection procedure.
This term is specified as the speed in revolutions per minute at which the given turbine
would rotate, if reduced homologically in size, so that it would develop one metric horse
power at full gate opening under one meter head. Low specific speeds are associated with
high heads and high specific speeds are associated with low heads. Moreover, there is a
wide range of specific speeds which may be suitable for a given head.
Selection of a high specific speed for a given head will result in a smaller turbine and
generator, with savings in capital cost. However, the reaction turbine will have to be
placed lower, for which the cost may offset the savings. The values of electrical energy,
plant factor, interest rate, and period of analysis enter into the selection of an economic
specific speed. Commonly used mathematically expression in India for specific speed is
power based (English System) is as follows:
Nr√Pr
Ns = -------------
Hr (5/4)
Where Nr = revolutions per Minute
Pr = power in metric horse power at full gate opening – (1 kW = 0.86
metric hp)
Hr =rated head in m.
The specific speed value defines the approximate head range application for each turbine
type and size. Low head units tend to have a high specific speed, and high-head units to
have a low specific speed.
Flow based metric system for specific speed (Nq) used in Europe is given by equitation
below.
NQ 0.5
Nq =
H 0.75
Where Nq = Specific Speed
N = Speed in rpm
Q = Flow in cubic meters/second
H = Net Head in meters
Following standards and monographs are good guides for selection of hydraulic
Turbines.
ii) IS 12837 – 1989 – Hydraulic Turbines for Medium and Large Power
Houses – Guidelines for Selection
iii) IS 12800 (Part 3) 1991 – Guide lines for selection of hydraulic turbines,
preliminary dimensioning and Layout of surface Hydro-Part 3 Small Mini and
Micro Hydroelectric Power Houses
Engineering Monograph No. 20 entitled ‘Selection of Hydraulic Reaction turbines’
issued by the US Bureau of Reclamation (USBR) is given below.
5.2.1 General : Selection procedure for small hydro (SHP) including micro hydel unit
size is determined from techno-economic consideration as per Para 1.6.
Preliminary selection for type of small hydro turbine can be made from figure 5.2 which
is based on IEC –1116 – 1992 as modified by actual data (Annexure-3) of large no. of
small hydros installed in the country. Kind (within type) and configuration (horizontal or
vertical) may be based on economic consideration including cost of civil works,
efficiency etc. Standard turbines available for discharge and head in the country as per
data given by some manufacturers (table 5.1) and attached in CBI & P publication No.
175 – 1983 entitled “Small Hydro power Stations standardization are attached as
annexure and listed below for guidance.
Rated head; discharge; unit size and runner diameter and configuration. Range of head
and discharge not available in the list may be asked from the manufacturer. Runner
diameter may be used for preliminary layout of the turbine as pre IS 12800 part (3) for
economic evaluation. Relative efficiency of type and configuration is given in Para 2.
AHEC/MNRE/SHP Standards/E&M Works – Guidelines for Selection of Turbine and 24
Govering System for Hydroelectric Projects
3. Efficiency of indigenous cross flow turbine is about 60 - 65%.
4. Peak efficiency at design head and rated output is about 2-5% higher.
Fig. 5.2 Turbine Efficiency Curves (Source IS: 12800)
Typical efficiency curves of the various types of turbines are shown for comparison in
Fig 5.2. These curves are shown to illustrate the variation in efficiency of the turbine
through the load range of the design head. Performances of the various types of turbines
when operated at heads above and below design head are discussed. Approximate
efficiency at rated capacity for the reaction turbines are shown for a turbine with a throat
diameter of 300 mm. Rated efficiency will increase as the size of the turbine increases.
The bottom curve shows the relationship of efficiency to throat diameter. The rated
efficiency for turbines with throat diameters larger than one foot may be calculated in
accordance with this curve. This curve was developed from model test comparison to
apply the step-up value throughout the operating range.
The efficiency curves shown are typical expected efficiencies. Actual efficiencies vary
with manufacturer and design.
To find the approximate efficiency for a turbine refer Figure 5.2 determine the
approximate throat diameter from 6.2 or 6.3 and find the size step up factor in the bottom
curve. Add this value to the rated efficiency values given for the approximate turbine
type. Size step up efficiency factors do not apply to impulse or cross flow type turbines.
The values as shown may be used. Note, that these curves can only be used when the
head on the turbine does not vary and less precise results are warranted. In micro hydel
range turbine efficiencies are lower.
Following determination of the selected turbine capacity the power output at heads and
flows above and below rated head (hr) and flow (Qr) may be determined from the curves
as follows:
Where,
Compute the % discharge, % or and find the % Pr on the approximate hr line. Calculate
the power output.
P = % Pr x Pr (kW)
The thick lines at the boarder of the curves represent limits of satisfactory operation
within normal industry guarantee standards. The top boundary line represents maximum
recommended capacity at rated capacity.
The turbine can be operated beyond these gate openings; however, cavitation guarantee
generally do not apply these points. The bottom boundary line represents the limit of
stable operation. The bottom limits vary with manufacturer. Reaction turbines experience
a rough operation somewhere between 20 to 40% of rated discharge with the vibration
and/or power surge. It is difficult to predict the magnitude and range of the rough
operation as the water passageway configuration of the powerhouse effects this condition.
Where operation is required at lower output, strengthening vanes can be placed in the
draft tube below the discharge of the runner to minimize the magnitude of the
disturbance. These modifications reduce the efficiency at higher loads. The right hand
boundary I established from generator guarantees of 115% of rated capacity. The head
operation boundaries are typical, however, they do vary with manufacturer. It is seemed
that these typical performance curves are satisfactory for preliminary feasibility
assessments.
Where,
Pr = Rated capacity at hr
Hr = Selected Design Head
Qr = Turbine Discharge at h r ε Pr
η t. r = Turbine efficiency at h r ε Pr
η g = Generator efficiency , ( %)
Where,
Pr = Rated capacity at hr
Hr = Selected Design Head
Qr = Turbine Discharge at h r ε Pr
η t. r = Turbine efficiency at h r ε Pr
η g = Generator efficiency , ( %)
The optimum number of turbines may be determined by use of these curves for annual
power consumption. If power is being lost because the % Pr is consistently below the
lower boundaries, the annual produced by lowering the kW rating of each unit and adding
a unit should be computed. If the total construction cost of the powerhouse is assumed to
roughly equal the cost of the turbine and generator, the cost per kWh derived above can
be doubled and compared with the financial value of the energy. If the selection of more
turbines seems favorable from this calculation, it should be pursued in further detail with
more accurate studies. Conversely, the first selection of the number of turbines may be
compared with a lesser number of units and compared on a cost per kWh basis as
described above.
Following the establishment of the numbers of units, the rating point of the turbines can
be optimized. This generally is done after an estimate of the total project cost have been
made. Annual power production of turbines having a higher rating and a lower rating
should be calculated and compared to the annual power production of the turbine
selected. With the annual estimate, cost per kWh may be calculated for the selected. With
the annual estimate, cost per kWh may be calculated for the selected turbine. Total
project cost for the lower and higher capacity ratings may be estimated by connecting the
turbine/generator costs from the cost chart and correcting the remaining costs on a basis
of constant cost per kW capacity. Rates of incremental cost divided by incremental
energy generation indicate economic feasibility.
The rated head of the turbine can be further refined by optimization in a similar manner.
The annual power production is computed for higher and lower heads with the same
capacity rating. The rated head yielding the highest annual output should be used. The
boundaries established on these curves are typical. Should energy output of a particular
site curtailed, it is suggested that turbine manufacturers be consulted as these boundaries
can be expanded under certain conditions.
5.2.4 Micro Hydel Range (upto 100 kW): A large number of micro hydel in remote hilly
areas are being installed to supply power to remote villages.
• Electricity for lighting and appliances (fan, radio, TV, computer, etc), in homes and
public buildings such as schools and clinics
• Electrical or mechanical power for local service and cottage industries
• Electrical or mechanical power for agricultural value-adding industries and labour
saving activities
• Electricity for lighting and general uses in public spaces and for collective events
These are generally high head schemes. A typical micro hydel scheme is shown in figure
5.2.4. Selected turbine efficiency and speed is of paramount importance for cost effective
installation as illustrated below:
5.2.5 Cost Elements in small and micro hydel power projects as per National Consultants
recommendations UNDP – GEF Hilly Projects is shown in figure 5.2.4.
These cost elements are for type of micro hydel in remote hilly area. Efficiency of indigenous
turbines in the microhydel range is approx. as follows:
Pelton - 90%
Turgo Impulse - 80%
Cross flow - 60%
Francis - 90% (Peak Efficiency at 90%)
Minimum weighted average efficiency of turbine and generator set (η Tv) 0.50x ηT100+ 0.5 η
T50 specified in micro hydel standard issued by AHEC (extracts at Annexure 5). Accordingly
weighted average efficiency of different category (size) of micro hydel is as follows:-
P = Q x H x 9.804 x 0.8
3) Fix unit size, number and installed capacity based on data collected and requirement.
4) Using kW; H and Q per unit select usable turbine from figure 5.3.
5) In case of turbine in overlapping range determine speed and specific speed relation and
determine synchronous speed based on applicable range of specific as per Para 5.1.
Higher speed machine is cost effective.
6) Review turbine limitation (Para 4) and fix turbine type as per micro hydel standard
(Annexure-5)
5.4 Cost/kW Comparison of 100 kW 60 m head, Run of the river scheme using
different type of turbine based on cost element as per figure 5.2.2 is given in table 5.3.
The civil works i.e. intake weir, settling tank, canal, penstock and power house costs is
dependant upon quantity of water required for generation i.e. proportional to efficiency.
Rough cost comparison between cross flow; Turgo Impulse and Pelton/Francis turbine
is based on indigenous available turbines.
Table 5.3
i) As per IEC 1116- (Fig. 5.3.1), Francis turbine requiring a discharge of 0.2 cumec per
turbine is feasible. Peak efficiency of Francis turbine as per figure 5.2 is 90% (at 90%
gate).
According Francis turbine requiring a discharge of 0.2 cumecs per turbine and 0.4 cumecs for 2
turbines required. Civil work may be designed for 0.45 cumecs (10% + 5% margin). Pumps as
turbine (mixed flow) can also be used. Check for part load efficiency.
Power (P) = 50 kW
Head = 51 m
i) As per IEC 1116- (Fig. 5.3.1), Francis Turbine requiring a discharge of 0.1 cumec per
turbine is feasible. Peak efficiency of Francis turbine as per figure 5.2 is 90% (at 90%
gate).
ii) Available standard turbine (CBI & P- Annexure 4.1 to 4.12)
Selection Procedure
P = Q x H x 9.804 x 0.8
3) Fix unit size, number and installed capacity based on data collected.
4) Using kW; H and Q per unit select usable turbine from figure 5.3.
5) In case of turbine in overlapping range determine speed and specific speed relation and
determine synchronous speed based on applicable range of specific as per Para 5.1.
Higher speed machine is cost effective.
6) Select standard available turbine with highest synchronous speed and best efficiency
range (Annexure 1.1 to 1.12).
Site Data
A common penstock bifurcating at the powerhouse into a wye branch for each power unit
is proposed. The length of the penstock system including Y-branch length is 340 meters.
Details of hydraulic system and basic data for design of turbine as extracted from the
specifications is given below :
Discharge Data
Stream discharges available for diversion for generation of power at Sobla are given in
Table 5.7.1 A. There is no storage. Inter connection of power plant implies utilisation of
entire power generated for feeding into the grid besides supplying local loads at Sobla
and Dharchulla. Accordingly, power generation based on minimum in flows and loading
of turbine as percentage of installed capacity is shown in Table-5.7.1 B. It is clear that at
no time the part load operation is below 67%. Average plant factor during water shortage
critical months (December-April) is about 73%.
Table –5.7.1 A
SOBLA SMALL HYDEL SCHEME DISCHARGES (m3/sec)
A small 250 kVA transformer to feed local loads at Sobla is also proposed.
Accordingly, it is considered essential to design the turbines for stand alone isolated
operation as well as for parallel operation with grid.
Turbine Selection
As per IEC 1116- (Fig. 5.2.1) it is seen that either an impulse or Francis Turbine may be
suitable.
Specific speed (ns) is related to rotational speed (n) by specific speed ns = n√P/H5/4
ns = n√P/H5/4
= n√3000/(185)5/4
n = 12.45 ns
Runner diameter (D) and speed for various possible values of ns are computed and
compared in Table 5.7.1 C.
Pelton turbines can be coupled directly to 375 r.p.m. (16 pole) generator or 750 r.p.m. (8
pole) generator through speed increasing gears.
For Francis turbine a 6 pole machine 1000 r.p.m. can be set 0.7 m above minimum
tailwater and may be economical to use. Four pole, 1500 r.p.m. generators coupled to 120
(ns) turbines are also feasible and are cavitation free but not recommended due to high
speed low inertia in generators and lower setting.
5.7.2 Comparison of 375 r.p.m. Pelton Turbine and 1000 r.p.m. Francis Turbine
1. Cost of directly coupled pelton turbine generator set will be more (about 2.5
times that of Francis Turbine coupled generators) and those coupled through
speed increasers by about 1.5 – 2 times.
2. Selection of low specific speed Francis turbine (1000 r.p.m.) with a setting of 0.7
m above minimum tailwater level is possible and is liable to be cavitation free.
3. Excessive silt or sand in the water will cause more wear on the runner of an
impulse turbine than on the runners of most reaction turbines.
4. Powerhouse size is liable to be bigger by about 70% for Pelton units. Thereby
increasing Civil Engineering cost.
5. Setting for Pelton turbine nozzle center line is proposed at EL 1737 m and
maximum tail water E.L. is 1734 m. Accordingly, if Francis turbine is used, a
minimum increase in head of 3 meters is possible. Available head will be further
increased during water shortage winter months when tail water is at lower level.
6. Peak efficiency of Pelton turbine is slightly lower than peak efficiency of Rancis
turbine but part load efficiencies of Pelton turbines are higher. The units do not
run below 70% load (Annexure-I) and 80% of the time the units are running
Proposed Pelton turbines were replaced by Francis Turbines and large economies in cost
(25-30%) were made.
Cost element in a low head project such as in canal fall projects is shown in figure 5.8.
Accordingly equipment cost predominate. Cost of generators is reduced by providing speed
increasing gears and accordingly selection of turbine in important for cost affective installation.
Accordingly only high specific speed (Axial flow) is possible. Selection procedure is therefore
is to select type and configuration of axial flow turbine as clarified in example. Low Head canal
fall Schemes. Most of the canal falls in the country are below 4 – 5 meter head. Canal schemes
in the range lower that 3 meters are designed as ultra low head schemes.
Site Data
Efficiency SHP range of turbine and generator has been taken as 0.85
Turbine Selection
As per IEC 1116 (Fig. 5.3) only Kaplan Axial flow turbine is feasible.
Available standard turbine CBI & P Publication (Annexure 4.1 to 4.12) is Tubular turbine S
type (Full Kaplan) or Semi Kaplan turbine with runners dia. About 2200 meter is feasible (Fig.
4.2.1). This type of turbines requires intake valve for shut off (emergency) as well as draft tube
gates for dewatering. It also requires dewatering and drainage arrangement.
Semi Kaplan vertical turbines with siphon intake as shown in fig. 4.2.3 was selected as cheapest
and cost effective alternatives (efficient) which does not require intake and draft gates and
dewatering arrangements. Detailed comparison of S type tubular turbine with vertical syphon
intake turbine is given in table 5.8.1.
Table 5.8.1
Comparison of Tubular type and vertical axis siphon intake for ultra low head (below 3 to 4 meter head)
For a small/medium low head power units reaction turbine are used. For high head multiple
jet Pelton turbine are used selection of turbine type is essential based on specific speed
criteria.
Select trial specific speed from figure 5.1 or from economic analysis. Except for unusual
(
circumstances, the selecting specific speeds is near 2334 / hd metric . )
2. Trial Speed, n′ :
⎜ 1/ 2 ⎟
⎜h ⎟
⎝ d ⎠
where
n′ = trial rotational speed,
n′s = trial specific speed,
hd = design head, and
Pd = turbine full gate capacity at hd
The rotational speed nearest the design speed is selected subject to the following
considerations:
a. A multiple of four poles is preferred, but standard generators are available in some
multiples of two poles.
b. If the head is expected to vary less than 10% from design head, the next greater
speed may be chosen. A head varying in excess of 10% from design head suggests
the next lower speed.
120 . frequency
Rotational speed, n =
number of poles
6000
n= at 50 Hz
number of pole
1/ 2
⎛ P ⎞
n⎜⎜ 1d/ 2 ⎟⎟
n(Pd )
1/ 2
or ⎝ d ⎠
h
ns =
(hd )5 / 4 hd
The design specific speed is the basic parameter to which most other factors of the selection are
made.
2334
Trial Specific Speed (n′s ) = (meteric)
hd
2334
= = 307 (Graph 5.1 shows ns = 250)
57.75
n' s ×(hd ) 5 / 4
Trail Rotational Speed (n′) =
Pd
307 × (57.75) 5 / 4
= = 292.2 ≅ 300 or 250
27980
Head is expected to vary less than 10% from design head and h the next greater speed
may be chosen.
Accordingly 10 pole (5 pairs pole) generator with design speed of 300 rpm is optimum
choice.
n Pd
ns =
(hd )5 / 4
300 27980
= = 315.21
(57.75)5 / 4
= 315
= 0.0211 (315)
2/3
= 0.9768
84.47 × Φ × hd
D3 =
n
84.47 × 0.9768 × 81.37
=
300
= 2.09 m
Manufacturer
M/s BHEL intimated following parameters for the turbine of Matnar project
Highest sped practicable at specified head is required for lowest possible cost. In addition
greater speed requires the reaction turbine (Francis and Propeller/Kaplan) to be placed
lower with respect to the tailwater to avoid cavitation. This generally increases
excavation and structural costs.
Cavitation results from sub-atmospheric pressure at places on runner and runner chamber.
To minimize this problem the turbine runner is set at depths below the minimum tail
Z = (Ha – Hv) – σH
Where,
Z = Depth of centre line of runner below minimum level of tail water
Ha = Atmospheric pressure in meter water column at plant elevation
Hv = Vapour pressure in metres at plant location temperature
H = head on turbine, meters
σ = Plant sigma or cavitation coefficient for the turbine specific speed
The value for σ may be found from the expression which is as follows :
σ=
(ns )1.64
50.327
The value of σ can also be taken from the curves relating ns and σ shown in fig. 6.1.
The value of σ for Francis turbines are lower than those for Propeller of Kaplan turbines.
The setting level for the latter is consequently lower than for Francis turbine. Many low
ns Francis turbines will yield setting levels above minimum tail water level and same may
be the case with Kaplan/ Propeller turbines of very low heads Pelton turbines are set
above the maximum tailwater level.
Lower setting (below tailwater) results in higher speed and hence smaller runner diameter
fig. 6.2 & 6.3 shows correlation runner diameter and settling for Francis and propeller
turbines.
NOTES :
1 Estimated turbine runner diameters D are based upon a plant elevation of 600 m. and a
tailwater height (Hs) of zero. Where Hs = distance between minimum tail water level and
exit of runner blades.
2 The estimated runner diameters may be used for both vertical and horizontal Francis
turbines.
3 For plant elevations higher then 600 m add 1% to D for each 300 m. Subtract 1% from D
for each 300 m. slower then the 600 m plant elevation.
1 Estimated turbine runner diameters D are based upon a plant elevation of 600 m.
and a tailwater height (Hs) of zero. Where Hs = distance between minimum tail water
level and exit of runner blades.
2 The estimated runner diameters may be used for both vertical and horizontal Francis
turbines.
3 For plant elevations higher then 600 m add 1% to D for each 300 m. Subtract 1% from D
for each 300 m. lower then the 600 m plant elevation.
With normal operation i.e. with load accepted or rejected either slowly as the system
requires or rapidly during faults, pressure water system follow slow surge phenomena
and depends upon the rate of closing the guide vanes/nozzle. The wicket gate closing
time is always kept much greater than critical closure time (Tc) i.e. the time of reflection
2l
of the pressure wave, this time, Tc = where l is the length of the pressure water
a
system from tailrace to forebay/ surge tank and a is the velocity of the sound in water
(wave velocity).
Pressure water column inertia is expressed as starting up time (Tw) of water column,
∑ LV
Tw =
gh
Where Tw = starting up time of the water column in seconds
∑ LV = L1 V1 + L2 V2 + ……… Ln Vn + Ld Vd
During preliminary stage of planning simple and short methods of calculating the
pressure regulation as given in following references be adopted.
∆H
H
=
n
2
{
n ± n2 ÷ 4 }
LV Tw
Where n = = or in case of uniform penstock dia.
gHT T
L - length of penstock + ½ the length if the spiral casing
H – head in meter
T – governor closing time in seconds
V – velocity in m./sec.
4L
This formula is sufficiently accurate only of T > where a is the wave velocity.
a
Note – Use plus for pressure rise and minus for pressure drop.
Pressure rise in percentage is also given by
∆H L × HP × 54
= 2
H D × H 2 ×T
Where T, L & H are same as above;
D – diameter of penstock in meter
HP – rated metric Horsepower
The speed regulation or stability of a hydro-electric unit may be defined as its inherent
property to ensure that changes in external conditions as well as in the turbine and
governing equipment result an a periodic or rapidly damped, periodic return to the new
steady state. Stability over the normal operating range with the machine connected to the
system and stability after disconnection can be considered independently. Most hydro-
electric stations are interconnected and as such their satiability is assisted. The more
important factors upon which the stability of interconnected units depend are the flywheel
effect of the unit, the hydraulic design of the water passages and speed and capacity of
the unit. The GD2 should be sufficient to insure prompt response to power demands and
to restrict speed rise following loss of load. But generator GD2 should be restricted to
avoid excessive power swings. Additional GD2 built into the generator increases the cost,
size and weight of the machines and increasing GD2 more than 50 percent above normal
decreases the efficiency.
Flywheel effect is expressed as starting up time of the unit (Tm). This is the time in
seconds for torque to accelerate the rotating masses from 0 to rotational speed
Where GD2 = Product of weight of rotating parts and square of the diameter
Sudden dropping of load from a unit through opening of the main breaker will cause a
unit to achieve considerable speed rise before the governor can close the gates to the
speed-no-load position. The time required to attain a given over speed is a function of the
flywheel effect and penstock system. The values of speed rise for full load rejection
under governor control is considered an index of speed regulating capability of the unit.
Normally adopted range is from 30 to 60 percent, the former applies to isolated units,
where changes of frequency may be important when sections of distributed load are
rejected by electrical faults. Values from 35 to 60 percent are generally adopted for grid
connected hydro station. Generally units for which length of the penstock is less than five
times the head can be make suitable for stable frequency regulation of the interconnected
system. Also units for which Tm ≥ (Tw)2 can be expected to have good regulating
capacity. This test should be applied over the entire head range. Plants in which more
than one turbine are served from one penstock should be analyzed to determine proper
governor settings and appropriate operating practices. Such plants may be unable to
contribute to system transient speed regulation but adverse effects upon the system may
be avoided by specifying the number of units which may be allowed to operate on free
governor (unblocked) at any one time.
The turbine and generator are designed to withstand runaway speed, but at excessive
speed severe vibrations sometimes develop which snap the shear pins of the gate
mechanism. To minimize vibration, a speed rise not to exceed 60% can be permitted in
contrast to the 35 to 45% desired for satisfactory regulation of independently operated
units.
Considerations for permissible speed rise on full load rejection are as follows:
7.3.1 Small Hydro (grid connected)
Small hydro if grid connected (with no isolated and or islanding provision) cannot take
part in frequency control. Accordingly these should be designed for upto 60% speed rise
on full load rejection. In canal fall or similar units, speed control is required only during
synchronizing. Generator loading should be controlled by level i.e. non speed control
governors can be used and loading on the units is controlled by upstream canal water
level. These are called non speed control governors.
The penstock pressure rise and unit speed rise may be calculated from the references
given in Para 7.1 entitled ‘pressure regulation’. These could also be calculated as follows,
which is based on USBR design monograph no. 20 referred in Para 7.1. Economic studies
required to be carried out to determine whether more than normal GD2, a larger penstock,
a surge tank or a pressure regulator is required. Some examples follow :
Notation :-
To obtain the speed rise for full load rejection, determine the following values :-
TK
(e) Determine SR from fig. 7.5.1 using ns &
Tm
Where,
SR is speed rise in percent of rotational speed,
n1 for full gate load rejection to zero, excluding effect of water hammer.
AHEC/MNRE/SHP Standards/E&M Works – Guidelines for Selection of Turbine and 52
Govering System for Hydroelectric Projects
∑ LV r
(f) TW = (water start up time)
ghr
TW
(g) K=
Tf
(h) S1R = SR (1 + K), speed rise in percent of rotational speed nr for full gate load
rejection to zero, including effect of water hammer.
Example-1
Given :-
= 7.40
TK 5.25
(c) = = 0.709
Tm 7.40
n Pr (94.7) 29851 kW
(d) n sr = = = 302.02
(n )
r
5/ 4
(24.38) 5 / 4
= 302 MkW
103.63 x (4.2)
(f) Tw = = 1.8198
9.81 x 24.38
Tw = 1.82
Tw 1.82
(g) K= = = 0.364
Tf 5
Example-2
Data
P
Rated Discharge (Qr) =
hr × 9.804 × 0.8
1750
=
46.63 × 9.804 × 0.8
= 4.78 cusecs
= 3.662 m/sec.
153.5 × 3.66
=
9.81 × 46.63
= 1.228 second
∆H
H
T
2
{ 2
= w Tw + Tw + 4 }
LV 1.2287
Where Tw = = = 0.2894 = 0.29
gHT 4.25
∆H
H
=
0.29
2
{
0.29 + 0.292 + 4 }
= 33.50%
GD 2 × n 2 7 × 103 × 7502
Mechanical starting up time Tm = = = 6.25 seconds
3.6 × 102 × Pr 3.6 × 105 × 1750
Closing time of servo motor Tk = 4 seconds (full closing time of servomotor)
Tk 4
= = 0.645
Tm 6.2
Tw 1.23
k= = = 0.3075
Tf 4
S'R = (26.6) (1 + 0.3075)
= 34.779 = 34.78%
8.1 Introduction
Governor control system for Hydro Turbines is basically a feed back control system
which senses the speed and power of the generating unit or the water level of the forebay
of the hydroelectric installation etc. and takes control action for operating the
discharge/load controlling devices in accordance with the deviation of actual set point
from the reference point.
Governor control system of all units suitable for isolated operation are a feed back control
system that controls the speed and power output of the hydroelectric turbine. Water level
controllers can be used for grid connected units. Governing system comprises of
following sections.
Speed
Hydraulic
Setpoint Pressure Oil
Power
Water To Turbine Control
Level Turbine Device (Gates,
Governor Control
Unit Speed Controller Blades, Needles, Mechanical Motor
Actuator Deflectors, Load)\
Optional Load
Feedbacks
The control section may be mechanical; analogue electronic or digital. Actuator can be
hydraulic controlled, mechanical (motor) or load actuator. Load actuator are used in
micro hydel range; mechanical (motor operated) may be used say upto 1000 kW unit
size. Hydro actuator are mostly used.
By the middle of 20th century, mechanical governors directly driven by prime movers
through belt were used for small machines. The speed of rotation was sensed by fly-ball
type pendulum. In second-generation mechanical governors, permanent magnet generator
and pendulum motor were utilized for sensing the speed of the machine. The isodrome
settings were achieved through mechanical dashpot and droop setting by link mechanism.
These mechanical governors were fully capable of controlling the speed and output of the
generating unit in stable manner. In case of faulty pendulum, manual control of the units
was possible with handles and knobs. This was PI type controller.
Next came the third generation Electro-Hydraulic Governors where speed sensing,
speed/output setting and stabilizing parameters were controlled electrically and the use of
mechanical components was reduced considerably. They increased the reliability,
stability and life of the equipment and facilitated more functional requirements. The
design of electrical part of the governors kept changing based on the advancement in
electronics and development work by individual manufacturers. In this type of gov3ernor
analogue circuitry is used to develop set point signal that is used to position the control
actuators of hydroelectric units. An electro hydraulic interface is used to connect the
electronic set point signal into a hydraulic oil flow from a hydraulic servo valve system
which determine the position of the turbine control actuators. This sis a PID controller.
In digital governor, digital controller is used in turbine governing system. This is also
PID controller. Digital control hardware running an application programme accomplishes
Present day trend is to use digital governing control system in hydroelectric units. The
major advantages of microprocessor based system over the earlier analogue governors
(based on solid state electronic circuitry) are higher reliability, self diagnostic feature,
modular design, flexibility of changing control functions via software, stability of set
parameters, reduced wiring and easy remote control through optical fibre cables.
Microprocessor based governor control system are capable of carrying out the following
control functions in addition to speed control during idle run , operating in isolated grid;
interconnected operation and islanding operation.
• Control the power output depending on variation in grid frequency i.e. load
frequency control
• Joint power control of a number of generating units in a power station
• Power control as per water levels in Fore-bay and/or Tail-race
• Automatic Starting / Stopping by single command
• Fast response to transient conditions
• Control from remote place Supervisory Control And Data Acquisition (SCADA)
Actuator system compares the desired turbine actuator position command with the actual
actuator position. In most of the hydroelectric units it requires positioning of wicket gates
in reaction turbines, spear in pelton turbines and turbine blades in Kaplan turbines. In
load actuators it shunt load bank is adjusted. Pressure oil system with oil servomotor is
most commonly used actuator.
The size, type, and cost of governors vary with their capacity to perform work which is
measured in (meter-kilograms). Mechanical governor having a capacity of more that
8300 m kg. Are of cabinet actuator type. These having a capacity less than 7000 m kg.
Are gate shaft type.
The capacity is the product of the following factors: turbine gates servomotor area,
governor minimum rated oil pressure, and turbine gates servomotor stroke. For gate shaft
governors, the turbine gates servomotor area is the net area obtained by subtracting the
piston rod area from the gross piston area. For governors controlling two servomotors
mounted directly on the turbine, the effective area is the sum of the net area of the two
servomotors.
Actuator and Control systems for small hydro units especially in developing countries
have to be selected keeping in view the following:
(a) Traditional flow control governor with mechanical hydraulic actuator is complex
demanding maintenance and high first cost. Further performance requirements of
stability and sensitivity i.e. dead band, dead time and dashpot time especially for
interconnected units may not be met by mechanical governors.
(b) Electronic and Digital flow control governors can be take up plant control
functions.
(c) Cost of speed control and automation with currently installed analog flow
governors, unit control and protection systems is high. These systems require
attended operation and are mostly based on large capacity hydro units. This is
making most of the units very costly and uneconomical to operate.
(d) The manpower as available is unskilled and further adequate supervision is not
feasible.
(e) Load factors for stand-alone micro hydels are usually low affecting economic
viability.
(f) Flow Control Turbine Governors are expensive and not recommended for small
hydro units in micro hydel range. Electronic load control governing system with
water cooled hot water tanks as ballast loads for unit size upto 100 kW are cost
effective. This will make a saving of about 40% on capital cost. The generator
flywheel is not required. If the thyristor control (ELC) is used then the alternator
needs to be oversized upto 2%% on kVA to cope with the higher circulating
current induced. Accordingly, in case of small units upto 100-150 kW size
elimination of flow control governors using load actuator with digital speed
Modern control schemes also utilise personal computers (PCs) in conjunction with PLC
control systems. The PCs are utilized with man-machine interface (MMI) software for
control display graphics, historical data and trend displays, computerized maintenance
management systems (CMMS), and remote communication and control. In addition, the
PLC programming software is usually resident on the PC, eliminating the need for a
separate programming terminal implement or change the PLC software coding.
A PC also can be used for graphical displays of plant data, greatly enchancing operational
control. Standard Microsoft-based graphical display software packages are available for
installation on a standard PC. The software package can be utilized on the PC to create
specific powerhouse graphical displays based upon real-time PLC inputs. These displays
typically include control displays with select-before-execute logical, informational
displays for plant RTD temperatures, or historical trending plots of headwater, tailwater,
and flow data.
Programmable Logic Controller (PLC) type plant controllers with a manually operated
back up system combined with PC based SCADA system are used as Governors and for
Plant control and data acquisition. This makes the system costly but reliability is stated to
be good and can be used for small hydro generation control. It is considered that
dedicated digital control systems which is digital P.C. based can perform all functions of
governing, unit control and protection as well as for data storage and can be more
economical, dependable and are being manufactured in U.S.A., Europe, India and other
countries. These dedicated systems with back up manual control facility of speed control
in emergency by dedicated semi automatic digital controllers can be an option and is also
recommended for UNDP-GEF projects in India.
Concept Ease of Sustainability Cost saving Overall MHPG Mead & Hunt AHEC
adoption potential rating
Load Control 3 2 3 2.7 Most useful on non-grid Not considered Most useful on
connect sites, upto 500 kW. unit size upto 200
Could save more than 20% kW on both grid
due to spin effects. & non grid
connected.
Analogue integrated 3 2 2 2.3 Low cost solution for upto Not considered Not recommended
governor and plant 500 kW grid connect. cost high.
control.
Digital integrated 3 2 2 2.3 Preferred solution for large Not considered Preferred solution
governor and plant grid connect schemes. for schemes with
controller Savings where optimisation unit size above
or complex operation 250 kW.
needed.
PLC controller 3 2 1 2 Useful for larger schemes Recommended Recommended
with separate governors.
Data Logger 3 3 2 2.7 Available in India, suitable Data storage Data storage and
for isolated schemes using and retrieval retrieval as part of
analogue or flow control recommended Digital Gov.
governing. by P.C. system.
Basically there is no difference in governors used for large generating units and small
units except for sizes, operating pressure and control features as per requirement of
individual project. Also for smaller units, hydro-mechanical part of governor is built on
the sump of oil pressure plant for compactness. Higher operating pressure is used to
reduce sizes of control elements and pipelines. Nitrogen cylinders are used in place of
pressure air to avoid use of high-pressure air compressors. Oil pipelines of sizes upto 50
mm are used in stainless steel with ermeto (dismantlable) couplings to reduce welding
and maintain cleanliness.
Micro Hydel - Digital speed control system will load actuator is used.
(upto 100 kW)
Small Hydros - Flow control governing system with hydraulic actuator
Upto 3 MW and digital PID speed and power control system. Mechanical
motor type actuator have also been, used upto 1000 kW unit size
with microprocessor based level control PI Controller
Small Hydro - Flow control PID governor with hydraulic actuator
Above 3 MW
Governing system including controller and actuator used for different capacity
powerhouses designed by AHEC and consultants is given in Table 8.2.
Two basic control schemes utilized for small and medium hydro stations are (1) a single
PLC with a manually operated back-up system, and (2) a redundant.
PLC system. There are various modifications of these two basic schemes, which depend
upon the individual plant requirements and owner preference. The single PLC offers the
advantages of low cost and simplicity, and is typically based up by a hardwired system.
With a redundant PLC system, backup control and memory are provided by a second
PLC. Advantages and disadvantages of the two schemes are summarized in Table 8.3 and
8.4.
Table 8.3 : Advantages and Disadvantages of the Redundant PLC Control Scheme
Advantages Disadvantages
• 100 percent backup for the central processing unit • Cost. The cost of a second PLC exceeds the
(CPU). The CPU includes the processor, system cost of a manual backup system.
memory, and system power supply.
• Uniform spare parts. Only one set of I/O cards • Failure of both systems simultaneously.
needs to be maintained. Items such as spare relays Although redundant PLCs do enhance system
and control switches associated with a hard-wired reliability, they can be prone to simultaneous
failure caused by surge. Owners should insist
system are not required. on good surge protection engineering.
• Software problems. If software is non-
standard, software problems will be common
to both PLCs.
Table 8.4 : Advantages and Disadvantages of a Single PLC with Manually Operated
Backup System
Advantages Disadvantages
• Less expensive than a redundant PLC • Headwater level or discharge control (if
system. performed by the PLC) is disabled whenever
the PLC is disabled. When utilizing the
manually.
• Less chance of a common mode failure • Operated backup system for control, the
because the hardwired system is less prone unit’s output is set a the operator’s
to surge-induced failures and more tolerant discretion. An operator will usually allow a
of inadequate grounds. safety margin of approximately 10 percent in
headwater or discharge level to avoid
problems such as drawing air into the
penstock. As a result, maximum possible
revenue for the unit is usually not realized
during manual operation.
• Operator familiarity with trouble shooting • Nonuniform spare parts. Spare parts would
hardwired relay systems. have to provided for both the PLC system
and the manually operated backup system.
However, it should be noted that relatively
few spare parts would be needed for the
manual backup system, due to its simplicity.
In either unit control scheme, all unit protective relays should be independent from the
programmable controllers. This independence will allow the protective relays to function
PC based a digital PID controller with oil pressure servomotor actuator with
synchronous generator suitable for isolated/grid connected operation with back
up manual control and integrated plant control and off site control facility -
Project by Prof. O. D. THAPAR Consultant, AHEC for M/s Jal Viduyat Nigam
Ltd. UP..
PLC Digital PID Controller with oil pressure servomotor actuator with
Synchronous Bulb generator – grid connected with redundancy and redundant PC
based automation (AHEC Project)
GATE
POSIN
TRANSDUCER TILT BLADES
71QP
GATE POWER GOVERNOR UNIT BLADE ON
SETPOINT SETPOINT HIGH PRESS (HYDRAULIC FLATTEN BLADES
ADJUSTER ADJUSTM ENT OIL SYSTEM AM PLIFICATION)
63Q
BLADE POSITION
APPLY GATE S
WICKET GATE ERVO LOCK
SERVOM OTOR
ON-LINE/ GOVERNOR LOCK CONTROLS RELEASE GATE
OFF-LINE POWER SERVO LOCK
SENSING SUPPLY
APPLY GEN
GENERATOR BRAKES
AIR BRAKE
52 27PS CONTROLS SUPPLY AIR
FIRE
DETECTION &
49F
EXTINGUISHING
Fig. 8.6 Electric Hydraulic Turbine Governor Control & Monitoring System
(Mukerian Stage-II canal fall project 2 x 9 MW Bulb turbine)
Sl. POWER CUSTOME NO. OF HEA SPEE YEAR SPECI TYPE OF REMARK
N STATION R UNITS× D D OF FIC TURBIN
o. SIZE(M (M) (RPM COMM’I SPEED E
W) ) NG (Ns)
1. Parbati NHPC 4×200 789.0 375.0 2006 48.57
Stage-II
2. Varahi KPCL 2×115 460.0 250.0 1989 48.20 Generatin
3. Sharavathy KPCL 2×89.1 439.5 300.0 1976 56.55 g
4. Chukha Chukha 4×84 435.0 300.0 1986 53.00
Sets
project
Authority,
with
Bhutan
5. Tillari GOM 1×60 628.8 500.0 1986 47.11
Pelton
6. Bihai Taiwan 1×62.5 416.8 495.0 2005 79.58
Power Co.
Turbine
Taiwan
7. Kuttiyadi KSEB 2×50 625.0 500.0 2005 43.33
AES
8. Pykara TNEB 3×50 1027. 600.0 2005 27.95
Ultimate 0
9. Malana MPCL 2×43 480.0 500.0 2001 55.89
10 Lower National 2×27.68 400.0 428.6 1993 48.28
. Sungai piah Electricity
Board,
Malaysia
11 Bassi HPSEB 4×15 335.7 500.0 1970 51.61
.
Source: Project Design by Alternate Hydro Energy Centre (AHEC), I.I.T. Roorkee
Sl. Power Sponsorer/ No. of Head Speed Year/ Likely Specifi Type of Type of
No. Station Manufactur Units x (M) (RPM year of c Turbine Generator
er Size ) Commissioni Speed
(MW) ng (Ns)
BIHAR
1. Triveni Jyoti Ltd. 2x1.50 4.94 155 1056.7 Horizontal Synchronou
SHP 0 6 Kaplan s Generator
Vertical
2. Nasarganj VA Tech. 2x0.50 3.99 166.66 28.06.2007 759.25 Vertical Synchronou
SHP 0 Semi s Generator
Kaplan Vertical
3. Jainagra VA Tech. 2x0.50 4.18 187.5 783.78 Vertical Synchronou
SHP 0 Semi s Generator
Kaplan Vertical
4. Sebari HPP Energy 2x0.50 3.66 150 745.96 Vertical Synchronou
SHP (India) Pvt. 0 Semi s Generator
Ltd. Kaplan Vertical
5. Shirkhind HPP Energy 2x0.35 3.186 135 744.89 Vertical Synchronou
a SHP (India) Pvt. 0 Semi s Generator
Ltd. Kaplan with Vertical
UTTARAKHAND
13. Dokti Nepal Hydro 1x0.02 62.0 1575 Cross Flow Synchronou
& Electric s Generator
Pvt. Ltd. Horizontal,
Kirloskar
14. Kanolgod Nepal Hydro 2x0.05 24.5 990 Cross Flow Synchronou
& Electric s Generator
Pvt. Ltd. Horizontal,
Kirloskar
15. Karmi-II Nepal Hydro 2x0.02 70 1673 Cross Flow Synchronou
& Electric 5 s Generator
Pvt. Ltd. Horizontal,
Kirloskar
AHEC/MNRE/SHP Standards/E&M Works – Guidelines for Selection of Turbine and 77
Govering System for Hydroelectric Projects
16. Ramgarh Jyoti Ltd. 2x0.05 50 750 Cross Flow Horizontal
Jyoti Ltd.
17. Ratmoli Nepal Hydro 2x0.02 39 1250 Cross Flow Synchronou
& Electric 5 s Generator
Pvt. Ltd. Horizontal,
Kirloskar
18. Gangotri-I Vodini 2x0.05 23.6 836 Cross Flow AVK
Check 0
Republic
ARUNACHAL PRADESH
19. Kitpi-II Guglor 2x1.5 200 600 Pelton 2 Jet Synchronou
Hydro Horizontal s Generator
Energy gmbh Horizontal
S.No. Name of Manufacturer/ Type of water mill Type of runner Runner dia Range of Testing Parameters Maximum Remarks
Supplier (mm) Head range Discharge Power Efficiency
(m) rage (lps) output
(kW)
1. M/s Gita Flopumps India Horizontal shaft Cross flow 300 9.0-12.0 28-125 0.6-8.4 56.00 Accepted
Pvt. Ltd., Saharanpur
(U.P.)
2. M/s Standard Electronic Horizontal shaft Cross flow 300 3.0-14.0 76-135 0.5-8.5 53.00 Accepted
Instruments Corpn., (open type)
Roorkee (UA)
3. M/s SBA Hydro Systems Horizontal shaft Cross flow 300 4.0-12.0 80-132 1.1-6.6 54.00 Accepted
(Pvt) Ltd. New Delhi
4. M/s Gopal Engineering Horizontal shaft Cross flow 300 3.0-8.0 75-117 2.5-9.0 55.00 Accepted
Works, Dharanaula,
Almora (UA)
Runner dia. A B C D E F G
(mm)
Head (m) Unit Output Pt (kW) and discharge Q (m3/sec.)
Runner 900 1150 1400 1650 1900 2150 2400 2650 2900 3200
Dia. (mm)
Head (m) Turbine/Generator Output (kW)
3 100 125 175 280 350 425 550 650 800 1000
4 100 175 275 380 500 650 800 1000 1250 1500
5 150 225 350 500 650 825 1100 1350 1600 1900
6 200 320 450 625 875 1200 1450 1700 2000 2400
7 240 380 550 800 1100 1400 1750 2000 2400 3000
8 275 420 700 950 1250 1650 2000 2375 2900 3500
9 320 520 800 1150 1500 1900 2250 2750 3400 4000
10 380 600 850 1250 1650 2100 2600 3250 3800 4500
12 420 750 1100 1450 1850 2600 3200 4000 4800 6000
14 500 800 1200 1600 2100 3000 3700 4600 5600 6500
16 500 800 1200 1700 2750 3150 4100 4600 5600 6700
P 36 75 125
3
N 170 120 100
P 60 100 200
4
N 220 170 120
Runner 260 600 750 1000 1200 1400 1650 1900 2200 2500
dia.
(mm)
Head Turbine output Pt (kW)
(m)
3 5 28 45 75 125 175 240 330 430 550
4 8 45 80 130 200 280 380 520 730 925
5 11 65 115 190 300 400 560 800 1050 1350
6 15 90 150 250 400 540 750 1000 1400 1800
7 17 115 190 300 460 700 900 1200 1650 2150
8 19 130 210 340 525 750 1000 1400 1900 2500
9 150 240 400 600 825 1150 1600 2150 2900
10 165 270 450 650 920 1250 1750 2350 3200
12.5 205 320 545 800 1200 1600 2200 3100 4000
15 240 380 650 1000 1400 1850 2750 3700 4700
20 320 480 830 1300 1800 2450 3550 4600 6000
25 400 560 900 1450 2250 3150 4200 5900 7200
Note : Pelton will be double of above figures for two jet pelton
Runner dia. 225 275 350 425 450 525 600 675 750
(mm)
Head (m) Turbine Output in Kilowatt
40 17 26 41 61 68 100 131 168 207
50 23 35 57 86 96 140 184 233 290
60 31 48 75 113 126 185 241 308 382
70 40 62 94 141 158 232 304 388 481
80 47 73 115 174 195 284 373 473 587
90 56 87 137 207 232 338 444 564 702
100 - 109 161 242 271 397 521 622 822
110 - 126 186 279 312 458 601 764 948
120 - 144 212 319 357 521 684 868 1078
130 - 161 239 359 402 589 772 982 1217
140 - 180 267 404 450 658 862 1097 1360
150 - - 295 446 500 727 956 1212 1509
160 - - 325 491 549 801 1053 1336 1636
170 - - 356 537 602 878 1152 1465 1822
180 - - 388 585 655 957 1255 1596 1986
190 - - 421 635 711 1038 1367 1731 2153
200 - - 455 687 770 1126 1475 1879 2327
1.75 60 80 120 145 170 185 225 300 350 380 550
2 80 110 160 200 225 250 300 400 475 500 725
3 160 200 300 360 420 465 560 770 885 950 1350
4 225 300 450 535 625 690 825 1140 1315 1400 2025
5 325 440 650 770 900 990 1190 1640 1900 2025 2915
6 400 550 815 965 1130 1245 1500 2050 2375 2550 3660
7 500 685 1015 1200 1400 1550 1850 2550 2950 3160 4550
8 550 750 1100 1300 1500 1675 2000 2770 3200 3420 4925
9 675 920 1350 1600 1875 2060 2480 3420 3950 4225 6080
10 775 1050 1550 1850 2150 2375 2850 3925 4530 4850 7000
12 850 1165 1715 2030 2375 2620 3140 4325 5000 5350 7700
14 1120 1520 2240 2650 3100 3420 4100 5650 6520 6980 10050
STANDARDS/MANUALS/
GUIDELINES FOR
SMALL HYDRO DEVELOPMENT
Electro-Mechanical Works–
Selection of Hydro Generator for SHP
May 2011
CONTENTS
1.0 GENERAL 1
1.1 References and Codes 1
2.0 HYDRO GENERATOR ABOVE 5 MVA 2
2.1 General 2
2.2 Site Operating Conditions 2
2.3 Transient Event and Emergency Duty requirements 4
2.4 Rotor Surface Heating 6
2.5 Types of Generators and Configuration 7
2.6 Capacity and Rating 7
2
3.0 ELECTRICAL CHARATERISTICS 8
3.1 Generator Terminal Voltage 8
3.2 Insulation and Temperature Rise 8
3.3 Short Circuit Ratio 8
3.4 Line Charging and Synchronous Condensing Capacity 9
3.5 Reactance 9
3.6 Damper Winding 9
3.7 Efficiency 10
3.8 Total Harmonic (TH) 10
4.0 MECHANICAL CHARACTERISTICS 10
4.1 Direction of Rotation 10
4.2 Rotor Assembly Critical Speeds 10
4.3 Phase Sequence 11
4.4 Noise Level and Vibration 11
4.5 Over Speed with Stand 11
4.6 Flywheel Effect 11
4.7 Cooling 12
4.8 Thrust Bearing Lubrication 12
4.9 Fire Extinguishing System 13
5.0 SMALL HYDRO GENERATOR UPTO & BELOW 5 MVA 13
5.1 General 13
5.2 Classification of Generators 13
5.3 Selection and Characteristics 17
5.4 Vertical/Horizontal Configuration 18
5.5 Speed 18
5.6 Dimension 18
5.7 Over Speed Withstand 18
5.8 Ratings and Electrical Characteristics 18
5.9 Synchronous Generators 19
5.10 Asynchronous (Induction) Generator 20
5.11 Guide and Thrust Bearings 20
5.12 Generation Efficiencies 21
5.13 Testing of Generator 21
6.0 EXCITATION SYSTEM 22
6.1 General 22
6.2 Excitation System Type 22
3
6.3 Steady State Excitation System Requirement 25
6.4 Transient Requirements 25
6.5 Power System Stabilizer 26
6.6 Under Excitation Limiter 27
6.7 Over Excitation Limiter 27
6.8 Volts per Hertz (V/Hz) Limiter 27
6.9 VAR or PF Control System 27
6.10 Redundancy of Equipment 28
6.11 Environmental Considerations 28
6.12 Equipment Tests 28
7. EXAMPLES 29
ANNEXURES
Annexure – 1 30
Annexure – 2 35
Annexure – 3 36
Annexure – 4 39
Annexure – 5 40
4
Guide for Selection of Hydro-Generators
and Excitation System Upto 25MW
1. GENERAL
The electric generator converts the mechanical energy of the turbine into electrical energy. The
two major components of the generator are the rotor and the stator. The rotor is the rotating
assembly to which the mechanical torque of the turbine shaft is applied. By magnetizing or
“exciting” the rotor, a voltage is induced in the stationary component, the stator. The principal
control mechanism of the generator is the exciter-regulator which sets and stabilizes the output
voltage. The speed of the generator is determined by the turbine selection, except when geared
with a speed increaser. In general, for a fixed value of power, a decrease in speed will increase
the physical size and cost of the generator.
The location and orientation of the generator is influenced by factors such as turbine type and
turbine orientation. For example, the generator for a bulb type turbine is located within the bulb
itself. A horizontal generator is usually required for a tube turbine and a vertical shaft generator
with a thrust bearing is appropriate for vertical turbine installations.
Conventional cooling on a generator is accomplished by passing air through the stator and rotor
coils. Fan blades on the rotating rotor assist in the air flow. For larger generator (generally above
5 MW capacity) and depending on the temperature rise limitations of the winding insulation of
the machine, the cooling may be assisted by passing air through surface air coolers, which have
circulated water as the cooling medium.
The Generators interconnected with the grid should need grid standards issued by CEA Relevant
extracts – Schedule for operation and maintenance are enclosed as annexure-1)
2.1 General
Hydraulic turbine driven generators for hydro plants are salient pole synchronous alternating
current machines. Large salient pole generators are relatively slow speed machines in the range
80-375 rpm with large number of rotor poles. These generators are normally specifically designed
and generally interconnected with grid.
2.2 Site Operating Conditions (as per IEC: 60034 & IEEE C-50-12)
Rated operation condition specified in the standards are as follows: Site operating conditions if
deviating from these value, correction have to be applied as per table 2.2.1.
Maximum Ambient Temperature Steady State duty: Salient-pole open ventilated air-cooled
synchronous generators operate successfully when and where the temperature of the cooling air
does not exceed 400C.
Salient-pole totally enclosed water to air cooled (water) synchronous generators operate
successfully when and where the secondary coolant temperature at the inlet to the machine or
heat exchanger do not exceed 250C.
If the cooling air temperature (ambient) exceeds 400C, or cooling water temperature exceeds 250C
then maximum allowable temperature based on temperature rise on reference temperature
(400/250C) of the insulation class be specified instead of temperature rise. Correction as pre IEC
are shown in table 2.2.1.
The minimum temperature of the air at the operating site is – 150C, the machine being installed
and in operation or at rest and de-energized.
Note: If temperatures different from above are expected. The manufacturer should be informed of
actual site conditions.
Generators: Generators should operate successfully at rated MVA, frequency, power factor, and
terminal voltage. Generators at other service conditions should be specified with the standards of
performance established at rated conditions.
Altitude: Height above sea level not exceeding 1000 m. For machines intended for operation on a
site where the altitude is in excess of 1000 m. correctly should be made asp er table 2.2.1.
Number of starts and application of load: The purchaser should specify the anticipated no. of
starts and maximum MVA, power, and reactive power loading rate of change requirements for
the manufacturer to take into account in the machine design. The method of starting must be
identified in the case of peaking stations.
Variation from rated voltage and frequency: Generators should be thermally capable of
continuous operation within the capability of their reactive capability curves over the ranges of ±
5 % in voltage and ± 2 % in frequency, as defined by the shaded area of figure 2.2.
a) As the operating point moves away from rated values of voltage and frequency, the
temperature rise of total temperatures of components may progressively increase.
Continuous operation near certain parts of the boundary of the shaded area in figure 2.2
(a) at outputs near the limits of the generator’s reactive capability curve may (figure 2.2
Key 1 zone A
X axis frequency p. u. 2 zone B (outside zone A)
Y axis voltage p. u. 3 rating point
Fig. 2.2 (a) Voltage and Frequency Limits for Generators
(As per IEC: 60034)
A generator confirming to these guidelines will be suitable for withstanding exposure to transient
event and emergency duty imposed on a generator because of power system faults.
Sudden short circuit at the generator terminals: A generator will be capable of withstanding,
without injury, a 30 second, 3 phase short circuit at its terminals when operating at rated MVA
and power factor and at 5% over voltage, with fixed excitation. The machine shall also be capable
of withstanding, without injury, any other short circuit at its terminals of 30 s duration or less in
accordance with IEEE C 50. 12-2005. Generator circuit breaker need to be selected accordingly.
OVEREXCITED
(LAGGING)
POWER FACTOR
MEGAWATTS
SHAFT STRESS OR
HYDRAULIC LIMIT
SEE NOTE-1
UNDEREXCITED
MINIMUM
EXCITATION
(LEADING)
LIMIT
SYSTEM STABILITY
LIMIT
SEE NOTE-2
a. Generators are designed to be fit for service without inspection or repair after
synchronizing that is within the limits given below:
Additional information on synchronizing practices can be found in IEEE std. C37. 102TM-
1995.
b. Faulty synchronizing is that which is outside the limits given above. Under some system
conditions, faulty synchronizing can cause intense, short duration currents and torques
that exceed those experienced during sudden short circuits. These currents and torques
may cause damage to the generator.
c. Generators shall be designed so that they are capable of coasting down from synchronous
speed to a stop after being immediately tripped off-line following a faulty
synchronization. Any generator that has been subject to a faulty synchronization shall be
inspected for damage and repaired as necessary before being judged fit for service after
the incident. Any loosening for stator winding bracing and blocking and any deformation
of coupling bolts, couplings, and rotor shafts should be corrected before returning the
generator to service. Even if repairs are made after a severe out-of-phase synchronization,
it should also be expected that repetition of less severe faulty synchronizations might lead
to further deterioration of the components.
d. It should be that the most severe faulty synchronizations, such as 1800 or 1200 out-of-
phase synchronizing to a system with low system reactance to the infinite bus, might
require partial or total rewind of the stator, or extensive or replacement of the rotor, or
both.
Check synchronizing relay and auto synchronizing equipment need to be set accordingly.
Normally synchronizing closing angle is kept ±7%.
Short-time volts/hertz variations: The manufacturer shall provide a curve of safe short-time
volts/hertz capability. Identify the level of overflux above which the machine should never be
operated, to avoid possible machine failure. Unless otherwise specified, the curve apply for time
intervals of less than 10 min.
Continuous phase current unbalance: Generator above 5 MVA are normally capable of
withstanding, without injury, the effects of a continuous phase current unbalance corresponding
to a negative current of the values in table 1, providing the rated MVA is not exceeded and the
maximum as expressed as a percentage of rated stator current.
Vertical shaft generators are generally used. There are two types of vertical shaft hydro
generators distinguished by bearing arrangements.
Umbrella type generators: These generators have combined bottom thrust and guide bearings and
confined to low operating speeds (upto 200 rpm) and is the least expensive generator design. In
semi umbrella type generators a top guide bearing is added. Umbrella/Semi Umbrella design is
being increasingly used for slow speed vertical generator.
kW Rating: kW capacity is fixed by turbine rated output. In a variable head power plant the
turbine output may vary depending upon available head. In general the generator is rated for
turbine output at rated head. In peaking power plant higher generator kW rating could be
specified to take care of possible higher turbine output. Economic analysis is required for this
purpose as the cost will increase and generator capacity remains unutilized when heads are low.
The kilowatt rating of the generator should be compatible with the kW rating of the turbine. The
most common turbine types are Francis, fixed blade propeller, and adjustable blade propeller
(Kaplan). Each turbine type has different operating characteristics and impose a different set of
generator design criteria to correctly match the generator to the turbine. For any turbine type,
however, the generator should have sufficient continuous capacity to handle the maximum kW
available from the turbine at 100-percent gate without the generator exceeding its rated nameplate
temperature rise. In determining generator capacity, any possible future changes to the project,
such as raising the forebay (draw down) level and increasing turbine output capability, should be
considered. Typical hydro generator capability curve is shown in figure 2.2 (b).
kVA Rating and power factor: kVA and power factor is fixed by consideration of
interconnected transmission system and location of the power plant with respect to load centre.
These requirements include a consideration of the anticipated load, the electrical location of the
plant relative to the power system load centers, the transmission lines, substations, and
distribution facilities involved. A load flow study for different operating condition would indicate
operating power factor, which could be specified.
3 ELECTRICAL CHARACTERISTICS
Electrical Characteristics e.g. voltage, short circuit ratio, reactance’s, line charging capacity etc.
must conform to the interconnected transmission system. Large water wheel generators are
custom designed to match hydraulic turbine prime over. Deviation from normal generator
design parameters to meet system stability needs can have a significant effect on cost. The system
stability and other needs can be met by modern state excitation high response systems and it is a
practice to specify normal characteristics for generators and achieve stability requirements if any
by adjusting excitation system parameter (ceiling voltage/exciter response). Generally these
special requirements do not arise in the range under discussion.
Modern hydro units are subjected to a wide variety of operating conditions but specifications
should be prepared with the intention of achieving a winding life expectancy of 35 years or more
under anticipated operating conditions. Class B insulation with organic binding material was
specified with conservative temperature rise for stator and rotor winding insulations in the
machines upto 1965. Present practice is to specified class F insulation system for the stator and
rotor winding with class B temperature rise over the ambient. Ambient temperature rise should be
determined carefully from the temperature of the cooling water etc.
If may be noted that as per IS the temperature rise specified over an ambient of 400C.
Accordingly maximum temperature for the insulation class under site conditions should be
specified.
Thermosetting insulation systems materials are hard and do not readily conform to the stator slot
surface, so special techniques and careful installation procedures must be used in applying these
materials to avoid possible slot discharges. Special coil fabrication techniques, installation,
acceptance and maintenance procedure are required to ensure long, trouble-free winding life.
The short circuit ratio of a generator is the ratio of field current required to produce rated open
circuit voltage to the field current required to produce rated stator current when the generator
terminals are short circuited and is the reciprocal of saturated synchronous reactance. Normal
short circuit ratios around 1.0 at 0.9 pf. Higher than normal short circuit ratio will increase cost
and decrease efficiency.
In general, the requirement for other than nominal short-circuit ratios can be determined only
from a stability study of the system on which the generator is to operate. The generator
parameters which have a bearing on stability are the flywheel effect, transient reactance and short
circuit ratio. Present practice is to specify generators with normal short circuit ratio and other
This is the capacity required to charge an unloaded line. Line charging capacity of a generation
having normal characteristics can be assumed to equal 0.75 of its normal rating multiplied by its
short circuit ratio. If the generator is to be designed to operate as synchronous condenser. The
capacity when operating over excited as condensers can be as follows:
3.5 Reactance
The eight different reactances of a salient-pole generator are of interest in machine design,
machine testing, and in system stability model studies. Lower than normal reactances of the
generator and step-up transformer for system stability will increase cost and is not recommended.
Both rated voltage values of transient and subtransient reactances should be used in computations
for determining momentary rating and the interrupting ratings of circuit breakers.
Typical values of transient reactances for large water wheel generators are given below.
Guaranteed values of transient reactances will be approximately 10% higher.
A short circuit grid copper conductor in face of each of the salient poles is required to prevent
pulling out of step the generator interconnected to large grid. Two types of damper windings may
be connected with each other, except through contact with the rotor metal. In the second, the pole
face windings are connected at the top and bottom to the adjacent damper windings.
The damper winding is of major importance to the stable operation of the generator.
While the generator is operating in exact synchronism with the power system, rotating field and
rotor speed exactly matched, there is no current in the damper winding and it essentially has no
effect on the generator operation. If there is a small disturbance in the power system, and the
frequency tends to change slightly, the rotor speed and the rotating field speed will be slightly
different. This may result in oscillation, which can result in generator pulling out of step with
possible consequential damage.
The damper winding is of importance in all power systems, but more important to systems
that tend toward instability, i. e. systems with large loads distant from generation resources,
and large intertie loads.
The damper winding also indirectly aids in reducing generator voltage swings under some faults
conditions. It does this by contributing to the reduction of the ratio of the quadrature reactance
and the direct axis reactance, X q′′ / X d′′ . This ratio can be as greater than 2.0 for a salient pole
generator with no damper winding, and can be as low as 1.1 if the salient pole generator has a
fully interconnected winding practice is to provide X q′′ / X d′′ > 1.3.
3.7 Efficiency
For a generator of any given speed and power factor rating, design efficiencies are reduced
by the following:
This is required only for synchronous machines having rated outputs of 300 kW (or kVA) or
more with a view minimizing interface caused by the machine.
Limits: When tested on open circuit and at rated speed and voltage, the total harmonic (TH) of
the line-to-line terminal voltage, as measured according to the methods laid down in IEC: 60034
should not exceed 5%.
4 MECHANICAL CHARACTERISTICS
The direction of he rotation of the generator should suit the prime mover requirements.
A rotor dynamic analysis of the entire shaft system should be performed. This analysis should
include the prime mover, generator, and any other rotating components. This analysis should
include lateral and torsional shaft system response to the various excitation that are possible
within the operational duties allowed by the standards. When the turbine generator is purchased
as a set, it would be typical that the manufacturer should perform this analysis. When shaft
components are purchased from different manufacturers, the purchaser should arrange to have
this analysis. Critical speeds of the generator rotor assembly should not cause unsatisfactory
Phase sequence defines the rotor in which the phase voltages reach their positive maximum at the
terminals of the machine, and shall be agreed upon the manufacturer and purchaser. Typically this
is given as a three letter sequence, R, C, L, (right, center, left) or L, C, R (left, center, right), as
defined by an observer looking at the terminals from outside the machine. In the case of terminals
on the top or bottom of the machine, the sequence is defined looking from the end of the machine
nearest the terminals toward the centerline of the machine.
Care must be exercised to ensure that the defined phase sequence of the machine is consistent
with that of the connected equipment, particularly in situations where the plant layout requires
otherwise identical machines to have different phase sequence.
Under all operating conditions, the noise level of generator should be in the range 85-95 dB (A) at
a distance of 1 meter radialy & 1.5 m from floor of operating. In order to prevent undue and
harmful vibrations, all motors shall be statically and dynamically balanced.
It is general practice in India to specify all hydro generators to be designed for full turbine
runaway conditions. The stresses during design runaway speed should not exceed two-thirds of
the yield point.
Generators below 360 rpm and 50,000 kVA and smaller are normally designed for 100% over
speed.
The flywheel effect (GD2) of a machine is expressed as the weight of the rotating parts multiplied
by the square of the radius of gyration. The WR2 of the generator can be increased by adding
weight in the rim of the rotor or by increasing the rotor diameter. Increasing the GD2 increases the
generator cost, size and weight, and lowers the efficiency. The need for above-normal WR2
should be analyzed from two standpoints, the effect on power system stability, and the effect on
speed regulation of the unit. Speed regulation and governor calculation are discussed in
guidelines for turbine selection.
Electrical system stability considerations may in special cases require a high GD2 is only
one of several adjustable factors affecting system stability, all factors in the system design should
be considered in arriving at the minimum overall cost. Sufficient WR2 must be provided to
prevent hunting and afford stability in operation under sudden load changes. The index of the
The inertia constant will range from 2 to 4 for slow-speed (under 200 rpm) water wheel generators.
Transient hydraulic studies of system requirements furnish the best information concerning the
optimum inertia constant, but if data from studies are not available, the necessary GD2 can be
computed or may be estimated from aknowledge of the behavior of other units on the system.
Increased in normal GD2 will increase generator cost.
Mechanical characteristics of the generator are based on the hydraulic turbine data to which the
generator will be coupled. Characteristics regarding speed, flywheel effect have been discussed in
guidelines of tubular selection. Special characteristics are discussed below.
4.7 Cooling
Losses in a generator appear as heat which is dissipated through radiation and ventilation. The
generator rotor is normally constructed to function as an axial flow blower, or is equipped with
fan blades, to circulate air through the windings. Small-generators up to 5 MW may be partially
enclosed, and heated generator air is discharged into the generator hall, or ducted to the outside.
Adequate ventilation of the generator hall preferably thermostatically should be provided in this
case.
Water to air coolers normally are provided for all modern hydro generators rated greater than 5
MVA. The coolers are situated around the outside periphery of the stator core. Generators
equipped with water-t-air coolers can be designed with smaller physical dimensions, reducing the
cost of the generator. Automatic regulation of the cooling water flow in direct relation to the
generator loading results in more uniform machine operating temperatures, increasing the
insulation life of the stator windings. Cooling of the generator can be more easily controlled with
such a system, and the stator windings and ventilating slots in the core kept cleaner, reducing the
rate of deterioration of the stator winding insulation system. The closed system also permits the
addition of automatic fire protection systems, attenuates generator noise, and reduce heat gains
that must be accommodated by the powerhouse HVAC system.
Normally, generators should be furnished with one more cooler than the number required for
operation at rated MVA. This allows one cooler to be removed for maintenance without affecting
the unit output.
The generator cooling water normally is supplied from the penstock via a pressure reducing
station or pumped from the tailrace. In either case, automatic self-cleaning filters must be
provided in the cooling water supply lines to avoid frequent fouling or plugging of the water-to-
air coolers.
Specifications for generators above 5 MW, and for generators in unmanned plants, should require
provisions for automatically pumping oil under high pressure between the shoes and the runner
plate of the thrust just prior to and during machine startup, and when stopping the machine.
All hydroelectric generators greater than 25 MVA should be furnished with either a water deluge
or carbon dioxide (CO2) fire extinguishing system, to minimize the damage caused by a fire
inside the machine. Generators 25 MVA or below should be evaluated individually to ensure
installation on cost effective system.
5.1 General
Standardized or upgraded mass-produced machine should be used where possible. Most “off-the-
shelf” or mass-produced machines are designed for lower over speed values (typically 1,25 to
1,50 times rated speed) than are experienced with hydraulic turbines. Therefore, such generator
designs should be checked for turbine runaway conditions.
Special Design Features as per IEC 1116 for these generators is as follows:
Standard BHEL generators confirming to the IEC standards are given in table 5.1.
There are basically two types of alternating current generator: synchronous and asynchronous (or
induction) generators. The choice of the type to be used depends on the characteristics of the grid to
which the generator will be connected and also on the generator’s operational requirements.
Salient pole Synchronous generators are used in the case of stand alone schemes (isolated
networks). In case of weak grids where the unit may have significant influence on the network
synchronous generator are used.
For grid connected schemes both types of generator can be used. In case grid is weak; Induction
generators be used if there are two units, one of the unit can be synchronous so that in case of grid
failure; supply could still be maintained. Unit size be limited to 250 kW. In case of stronger grids
induction generators upto a 2001 kW or even higher can be used.
In case of isolated units, small capacity Induction generators with variable capacitor bank may be
used upto a capacity of about 20 kW especially if there is no or insignificant Induction motor load
i.e. less than about 20%.
Before making a decision on the type of generator to be used, it is important to take the following
points into consideration:
A. SHP
1. 500 230M20 230M20 183M20 183M20 145M20 145M20 145M20 145M20 132M25
2. 1000 230M25 230M25 183M25 183M25 183M25 145M50 145M38 145M38 132M50
3. 1500 230M35 230M35 183M50 183M50 183M50 145M75 145M57 145M57 132M50
4. 2000 230M45 230M45 183M70 183M70 183M60 145M75 145M57 145M75 132M50
5. 2500 230M70 230M70 230M60 183M70 183M60 203M70 145M75 145M75 132M100
6. 3000 230M70 230M70 230M50 254M50 254M40 203M70 203M50 145M100 132M100
7. 3500 230M90 230M70 230M60 254M50 254M50 203M70 203M50 145M100 132M100
8. 4000 230M90 230M90 230M80 254M65 254M50 203M95 203M70 145M100 -
9. 4500 230M90 230M90 230M80 230M65 254M50 203M95 203M70 - -
10. 5000 230M90 230M90 230M80 230M65 254M50 203M95 203M70 - -
B. Mini Micro: generators 200-500 kW; speed 300 to 1500 RPM; power factor 0.67 lag.; Voltage 415 to 11 kV
(*)
A. M. Gupta BHEL, Bhopal - Small Hydro Generators – International course on technology selection for small hydro power development at
Alternate Hydro Energy Centre (AHEC) during Feb. 18-28, 2003
Climatic conditions (ambient temperature, altitude, humidity) can affect the choice of the class of
insulation level and temperature rises.
The cooling system of the generator should be evaluated. In the case where heat from the
generator is expelled into the powerhouse sufficient power house ventilation shall be provided.
With all turbines, a vertical or horizontal configuration is possible. The orientation becomes a
function of the turbine selection and of the power plant structural and equipment costs for a
specific layout. As an example, the Francis vertical unit will require a deeper excavation and
higher power plant structure. A horizontal machine will increase the width of the power plant
structure yet decrease the excavation and overall height of the unit. It becomes apparent that
generator orientation and setting are governed by compatibility with turbine selection and an
analysis of overall plant costs.
5.5 Speed (rpm) : The speed of a generator is established by the turbine speed. The
hydraulic turbines should determine the turbine speed for maximum efficiency corresponding to
an even number of generator poles. Generator dimensions and weights vary inversely with the
speed. For a fixed value of power a decrease in speed will increase the physical size and cost of
generators. Low head turbine can be connected either directly to the generator or through to a
speed increaser. The speed increaser would allow the use of a higher speed generator, typically
500, 750 or 1000 (1500) r/min, instead of a generator operating at turbine speed. The choice to
utilize a speed increaser is an economic decision. Speed incresers lower the overall plant
efficiency by about 1% for a single gear increaser and about 2% for double gear increaser. (The
manufacturer can supply exact data regarding the efficiency of speed increasers). This loss of
efficiency and the cost of the speed increaser must be compared to the reduction in cost for the
smaller generator. It is recommended that speed increaser option should not be used for unit sizes
above 3 MW capacity.
5.6 Dimension
Three factors affect the size of generator. These are orientation, kVA requirements and speed. The
turbine choice will dictate all three of these factors for the generator.
The size of the generator for a fixed kVA varies inversely with unit speed. This is due to the
requirements for more rotor field poles to achieve synchronous speed at lower rpm.
In the interest of safety, units with synchronous generators should be designed to withstand
continuous runaway conditions.
5.8.1 kW Rating: The kilowatt rating of the generator should be compatible with the kW
rating of the turbine. The most common turbine types are Francis, fixed blade propeller, and
adjustable blade propeller (Kaplan). Each turbine type has different operating characteristics and
imposes a different set of generator design criteria to correctly match the generator to the turbine.
For any turbine type, however, the generator should have sufficient continuous capacity to handle
the maximum kW available from the turbine at 100-percent gate without the generator exceeding
its rated nameplate temperature rise. In determining generator capacity, any possible future
changes to the project, such as raising the forebay (draw down) level and increasing turbine
output capability, should be considered.
In a variable head power plant the turbine output may vary depending upon available head. In
general the generator is rated for turbine output at rated head.
5.8.3 Frequency and Number of Phases: In India standard frequency is 50 cycle, 3 phase
power supply.
5.8.5 Stator Winding Connection: Star, stator winding connection are providing for both
grounded or ungrounded operation and six terminal (3 on line side and 3 on neutral side) are
brought out, except for small generators below 100 kW unit size when only one neutral is brought
for ground connections.
5.8.6. Excitation Voltage: Rated generator rotor voltage is specified by the manufacturer,
based on the rotor winding resistance and the excitation current required for full load operation at
rated voltage and power factor, including suitable margin. Ceiling voltage is as agreed upon by
the manufacturer and purchaser. Voltage of excitation system should be less than 250 V DC.
5.8.7 Short Circuit Ratio, Line Charging and synchronous condenser capacity and damper
windings considerations are discussed in Para 3.6.
a) Stator:
b) Rotor :
The insulation level should normally be Class-F and temperature rises Class-B.
It is recommended that a system requiring the least maintenance be chosen (e.g. static
brushless excitation). Coupled excitation armature with rotating rectifier assembly and
stationary excitation field suitable for voltage and power factor control is recommended.
The aim should be simplicity with a view to maintenance. This equipment could be
included in the control system.
e) Synchronising equipment :
May be manual and/or automatic. The synchronization should cover the voltage,
frequency and phase. Normally this equipment is included in the automatic control
system.
f) Power Factor :
a) Stator
b) Rotor
Squirrel cage construction, Class F insulation and Class B temperature rises are
recommended.
The selection of voltage and speed affects the possibility of using a standard machine.
The shaft system should be designed to minimize the number of bearings. It is essential to study
the turbine and generator bearings as a systems is the choice between journal, ball or roller
bearings, attention should be given to their ability to withstand vibrations, eddy currents and
runaway conditions including critical speed.
If the unit size is small and for reasons of simplicity, the use of self-lubricating bearings should be
preferred.
The efficiency of an electrical generator is defined as the ratio of output power to input power.
Efficiency values for commercially available generators are included in section 3. There are five
major losses associated with an electrical generator. Various test procedures are used to
determine the magnitude of each loss. Two classes of losses are fixed and therefore independent
of load. These losses are 91) windage and friction and (2) core loss. The variable losses are (3)
field copper loss, (4) armature copper loss and (5) stray loss or load loss.
Windage and friction loss is affected by the size and shape of rotating parts, fan design, bearing
design and the nature of the enclosure. Core loss is associated with power needed to magnetize
the steel core parts of the rotor and stator. Field copper loss represents the power losses through
the dc resistance of the field. Similarly, the armature copper loss is calculated from the dc
resistance of the armature winding. Stray loss for load loss is related to armature current and its
associated flux. Typical values for efficiency range from 90 to 97% depending upon speed and
capacity of machine. This efficiency value is representing throughout the whole loading range of
a particular machine; i.e., the efficiency is approximately the same at ¼ load or at ¾ load.
Following factory and final acceptance tests are recommended to ensure proper performance and
guarantees for category 1 & 2 types of generators.
This should include the polarization index values for both armature and field windings.
a. Stator dielectric tests. These tests consist of: Insulation resistance and polarization index,
Corona probe test, Corona visibility test, Final AC high potential test, Partial discharge
analysis (PDA) test, and Ozone detection (optional).
b. Rotor dielectric tests.
c. Stator and rotor resistance tests.
Special field test (one unit of series). These tests consist of:
a. Efficiency tests.
b. Heat run tests.
c. Machine parameter tests.
d. Excitation test.
e. Overspeed tests (optional)
6 EXCITATION SYSTEM
6.1 General
Excitation systems supply and regulate the amount of D. C. current required by generator field
windings and include all power regulating control and protective elements. The excitation system
should be specified to meet the power requirements and required response characteristics to meet
the power system to which generator will be connected. Overall performance and capacity of the
excitation system represented earlier by excitation response and response ratio is now expressed
as nominal system response (ANSI/IEEE std. 421-1-1996). Standard excitation system voltages
are 62.5, 125, 250.
Modern static excitation have completely replaced older shaft mounted rotating exciters with DC
filed current controlled by motor operated field rheostat. Brushless excitation system and static
excitation systems are being used in modern systems.
Static Excitation System: The static excitation system is the most commonly used excitation
system for hydro generators. It is typically shown in figure 6.2 (b). Static excitation systems
consist of two basic types depending upon the speed of generator field suppression required. The
full inverting bridge type uses six thyristor connected in a three-phase full wave bridge
arrangement. It allows reversed DC voltage to be applied to the generator filed to force faster
field suppression, thereby quickly reducing the generator terminal overvoltage during a full load
rejection. The semi-inverting type uses three thyristor and three diodes connected in a three-phase
full wave bridge. The semi-inverting type drives the positive DC voltage to zero during a full load
rejection, but does not allow negative filed forcing. Potential excitation source systems (from
Fig. 6.2(a)
TABLE 6.2
Note 1: may be possible with special provisions (refer IEEE std. 421.4-2004)
6.3.1 Rated Field Current: The direct current in the field winding of the generator when
operating at rated voltage, current, power factor and speed.
6.3.2 Exciter Rated Current: Continuous current rating should be specified to equal or
exceed the maximum required by the synchronous generator field under any allowed continuous
operating condition including continuous overload rating.
6.3.3. Exciter rated Voltage: Exciter voltage rating should be sufficient to supply necessary
continuous current to generator field at its maximum under rated load conditions.
6.3.4 Rated Field Voltage: The voltage required across the terminals of the field winding of
the synchronous machine under rated continuous load conditions of the synchronous machine
with its filed winding at (1) 750C for field windings designed to operate at rating with a
temperature rise of 600C or less; or (2) 1000C for field windings designed to operate at rating with
a temperature rise greater than 600C.
The stability of a hydro turbine generator set while connected to its power system is critically
important. However, the designer must also consider the unit’s characteristics when operating
alone, or in an isolated “island” much smaller than the normal power system.
One example of a unit operating is a main unit serving as the station service source in a plant that
becomes separated from its power distribution system. The unit will have to accept motor starting
loads, and other station service demands such as gate and valve operation, while maintaining a
safe and stable output voltage and frequency. All this will be accomplished while operating at a
fraction of its rated output.
When operating in an “island” the unit may be required to operate in parallel with other units
while running at speed-no-load in order to provide enough capacity to pick up blocks of load
without tripping off line. In this case, stable operation without the stabilizing effect of a very large
system is critically important to restoring service, and putting the system back together.
The maximum direct voltage, which the excitation system is able to supply from its terminals
under following conditions.
The ceiling voltage of high initial response static excitation system is normally specified directly
after system studies as the ceiling voltage is reached in less than 0.1 second. Ceiling voltage for
potentials source (from generator bus) static excitation system with high initial response for the
generator under considerations may be specified 1.5 – minimum recommended by IEEE Std.
For brushless system, it may be considered a function of the nominal response, which could be
specified.
The excitation system nominal response is defined as the rate of increase of the excitation system
output voltage determined from the excitation system voltage response curve, divided by the rated
field voltage (formerly called exciter response ratio). The rate, if maintained constant, would
develop the same voltage time area as obtained from the actual curve over the first half-second
interval. This may be specified for brushless excitation system only.
Excitation systems response based on a ceiling voltage for high initial response static excitation
system and for the brushless system is compared in 6.4.3.
The excitation system stabilizer is used for fast acting high initial excitation system to stabilize
oscillations that may occur between the machine and the systems by providing damping at power
system frequency to control oscillation in the post fault period. IEEE std. 421.4-2004 requires
power system stabilizer for grid connection at 66 kV and above so as to avoid oscillations in post
fault period.
h c
be = ceiling voltage for
b brushless excitation system
g'h = ceiling voltage of high initial
response static excitation syste
d
a g
ce-ao
EXCITER VOLTAGE E FD
NOMINAL VOLTAGE=
(ao) (oe)
WHERE
oe = 0.5 seconds
ao = synchronous machine
rated field voltage
e
0 g' SECONDS
less than
0.1 seconds
Fig. 6.4.3
Under excitation limiter should be provided on all small hydro generators which are normally
equipped with VAR (power factor control) and disconnected form the system on system
disturbances to feed local loads/station service systems.
Over excitation limiter should be provided on all generators to avoid overheating of the generator
field winding in case of faults.
The Volts-per Hertz (V/Hz) Limiter may be provided to prevent overheating that may arise from
excessive magnetic flux due to under frequency operation or overvoltage operation, or both.
The generators under consideration cannot follow the changes in the system voltage and therefore
must be equipped with power factor control regulators. These Grid connected power units require
a power factor regulator as well as field current regulator with automatic change over from
Power rectifier bridge redundancy is generally provided by providing parallel rectifiers of which
at least one is redundant. Redundant cooler should also be provided to ensure adequate cooling.
This may be provided for generators above 5 MVA.
Complete factory assembly of the excitation system is generally not required. Routine, type and
special tests may be carried out as per IEEE std. 421.4-2004. In addition factory tests and type
tests for the excitation system recommended are given below:
Factory tests may be carried out as per relevant IS: std. Routine tests should include measurement
of following.
i) Winding resistance
ii) Ratio
iii) Polarity and phase relationships
iv) No-load loss 9if capable)
v) Magnetizing current at rated voltage
vi) High potential test in accordance with IEEE std. 421.3-1997
vii) Induced potential
Factory tests may be carried out as per relevant IS: std. Or IEEE std. C57.12.91-2001 Routine
tests should include measurement of following.
a) Factory tests
i) Insulation resistance
ii) Resistance of all windings at a specified temperature
iii) Resistance of all external current limiting resistors and field rheostats, where applicable
iv) Air gap
v) No-load saturation curve, from residual voltage to exciter ceiling voltage
vi) Phase rotation
vii) Continuity of rectifier fuses
viii) Rectifier leakage
ix) Range and stability of rectifier phase control, where applicable
x) High potential test
xi) Operation at anticipated overspeed
b) Type tests
i) Audible noise
ii) Load saturation curve, up to 110% of nominal ceiling voltage
iii) Main exciter regulation
iv) Heat run
v) Exciter time constant
vi) Excitation system voltage response time and response
vii) Operation at anticipated overspeed, at the anticipated maximum
7 EXAMPLE
7.1 Type and rating, electrical characteristics, mechanical characteristics, insulation and
temperature rise and speed rise and run away speed specified for a 10 MVA grid
connected powerhouse is enclosed as Annexure-3.
7.2 Brush less excitation system for 1.5 MW Pacha project in Arunchal Project (grid
connected) is attached Annexure 4.
7.3 Static excitation system – Block diagram for 9 MW, 11 kV, 0.9 PF is at Annexure 5.
1. Brand. The brand and power rating of the generator or motor should be approved by the
manufacturer of the turbines and by the purchaser.
2. Nameplate. The original manufacturer’s nameplate for the generator or motor must be
retained. New nameplates can be added but must not replace the originals.
3. Over-rating. The power rating given on the original nameplate must be at least 10%
more than the scheme rated power.
4. Generator voltage. The “power house voltage” is the voltage at the generator terminals
with powerhouse-consumer isolation switch in off position. This must be between the
nominal national voltage (415 V) and +10% of 415 V.
5. Generator rotational speeds to be selected shall be 1500 rpm (+slip) or lower. In cases of
direct coupling 750 rpm or 1000 rpm generators should be preferred.
B. Synchronous Generators
1. Frequency. The frequency should be between 50 and 52.5 Hz. The frequency should be
within this range under all operating conditions, including minimum and maximum
power output, zero consumer load and worst-case consumer load power factor.
2. The induction generator must be over-voltage protected to avoid excessive currents to
flow through the excitation capacitors and induction machine. A protection system is
required that disconnects all or some of the capacitors, to limit the currents flowing to
below the limits for the induction machine windings and the capacitors. Provide MCBs of
suitable current rating in the series with excitation capacitors.
The generator shall be capable of continuous withstand against runaway speed.
A net capacity of ---------- kVA at rated conditions is required. The generator nameplate rating
shall reflect the necessary additional capacity to supply the excitation equipment. The generator
shall be capable of 10% continuous overload capacity.
B. ELECTRICAL CHARACTERISTICS
C. MECHANICAL CHARACTERISTICS
b. The generator shall be capable of delivering rated output at any voltage and frequency in
the operating range at rated power factor without exceeding the following values of
temperature rise over ambient temp. Cooling air entering the generator at not more than
400C (Cooling water maximum temperature 360C).
c. The maximum temperature rise when the generator is delivering maximum output
corresponding to continuous overload capacity for conditions rated above shall not
The moment of Inertia of the generator together with the moment of inertia of the turbine shall be
such that the maximum momentary speed rise under Governor Control on full load rejection
shall not exceed 45% of rated speed for the grid connected generator as station power is supplied
from main generator and adverse effect of this speed rise on motor driven station auxiliaries is
not desirable. Additional flywheel required shall be built in the rotor. Separate flywheel shall not
be permitted.
The maximum runaway speed shall be stated and guaranteed by the supplier. All rotating parts
and bearings shall be capable of withstanding the forces and stresses occurring during runaway
speed for at least 30 minutes without any damage to any part. The guide bearing and guide cum
thrust bearing shall be capable to withstand runaway speed for 30 minutes without supply of
cooling water and continuously with cooling water without abnormal increase of vibrations and
temperature.
Brushless Excitation System for 1.5 MW, 3.3 kV, 750 RPM, 50 Hz, 0.8 PF, 8 poles Generators (Pacha Project)
Static Excitation System - Block Diagram for 9 MW, 11 kV, 0.9 PF, 125 RPM Generators
STANDARDS/MANUALS/
GUIDELINES FOR
SMALL HYDRO DEVELOPMENT
Electro-Mechanical Works–
Selection of Switchyard Equipment for SHP
(Including Power Transformer and Circuit Breaker)
May 2011
CONTENTS
2
2.7 Switchyard Structures 12
2.8 GIS Substations 15
2.9 Power Line Carrier Equipment 16
2.10 Substation Auxiliary Facilities 17
2.11 Bus Bar Schemes 17
2.12 Inspection and Maintenance 17
ANNEXURE – 1.1 18
ANNEXURE – 1.2 19
Section – 2
Selection of Switchyard Equipment
1.0 BUS BAR 20
2.0 CIRCUIT BREAKERS 21
3.0 ISOLATORS 21
3.1 Temperature Rise 21
3.2 Rating 22
3.3 Isolator Insulation 22
3.4 Arcing Horn & Arcing Contacts 23
3.5 Load Break Switches 23
3.6 Terminal Connectors 23
3.7 Interlocks 23
3.8 Supporting Structures 24
3.9 Fire Extinguishing System 24
4.0 CURRENT TRANSFORMERS 24
4.1 Type and Rating 25
4.2 Details of Current Transformer 25
4.3 General Requirements 26
4.4 Terminal Connectors 33 kV and Above 27
4.5 Type of Mounting 27
4.6 Tests 28
4.7 External Insulation (12 kV & Above) 28
4.8 Fittings and Accessories (12 kV & Above) 28
5.0 POTENTIAL TRANSFORMER AND COUPLING VOLTAGE
TRANSFORMER 28
3
5.1 Type and Rating of Potential Transformer 29
5.2 Temperature Rise 30
5.3 11 kV Voltage Transformer 30
5.4 Coupling Voltage Transformer (36 kV & Above) 31
6.0 TRANSFORMERS 31
7.0 LIGHTNING ARRESTORS 31
8.0 EQUIPMENT FOR CUMMUNICATION, RELAYING AND TELE
METERING AND OFF-SITE CONTROL 35
9.0 AUXILIARIES 35
10.0 REPAIR / INSPECTION FACILITIES 35
11.0 PALE FENCING 36
12.0 SWITCHYARD LAYOUT 36
Section – 3
Selection of Power Transformer
1.0 GENERAL 51
2.0 GENERATOR TRANSFORMERS 52
3.0 TRANSFORMER RATING 52
4.0 STANDARD RATING 53
5.0 COOLING 54
6.0 TEMPERATURE RISE, OVERLOAD CAPACITY AND
CONTINUOUS RATING 55
7.0 TRANSFORMER STUDIES 55
8.0 ELECTRICAL CHARACTERISTICS 55
8.1 Type of Transformer and Operating Conditions 55
8.2 Continuous Maximum Rating and Overloads 56
8.3 Voltage Ratio 56
8.4 Duty Under Fault Condition 56
8.5 Electrical Connections 57
8.6 Flux Density 57
8.7 Current Density 57
8.8 Short Circuit Strength 57
8.9 Frequency and System Voltage 58
8.10 Parallel Operation 58
4
8.11 Vibration and Noise 58
8.12 Basic Insulation Levels (BIL) 58
9. IMPEDANCE 58
10. TRANSFORMER EFFICIENCY 59
11. TERMINAL BUSHINGS 60
12. TANKS 61
13. PRESSURE RELIEF DEVICE 61
14. ANTI EARTHQUAKE CLAMPING DEVICE 61
15. FITTINGS AND ACCESSORIES 61
16. DIELECTRIC TESTS 63
17. ACCESSORIES 63
18. OIL CONTAINMENT AND FIRE PROTECTION SYSTEM 63
19. FACTORY AND FIELD TESTING 64
20. ERECTION, MAINTENANCE TESTING AND COMMISSIONING 64
21. TYPICAL TRANSFORMER RATING AND CHARACTERISTICS 64
ANNEXURE – 3.1 65
ANNEXURE – 3.2 67
ANNEXURE – 3.3 69
ANNEXURE – 3.4 70
Section – 4
Selection of Circuit Breaker
1. INTRODUCTION 71
2. CLASSIFICATION 71
3. TYPE OF CIRCUIT BREAKER 71
3.1 Vacuum Circuit Breaker 73
3.2 Advantages and Disadvantages 73
3.3 Evaluation of SF6 and Vacuum Switching Technologies 73
3.4 Protection Classes for Switchgear Installation 75
4. RATED CHARACTERISTICS 76
5. STANDARD RATINGS OF CIRCUIT BREAKERS 77
6. CO-ORDINATION OF RATED VALUES 84
7. TESTS 86
5
8. FAULT CALCULATION 86
8.1 Staged Short Circuit Tests 87
8.2 Circuit Breaker Rating for Short Circuit Duty 87
8.3 Simplified Methods for Calculation Short Circuit Current 87
8.4 E/X Simplified method as per IEEE std. C37010-1999 88
8.5 Simplified Method 89
6
Section –1
Guide for Design of Outdoor Step up Sub-Station
and Selection of Equipment
1. INTRODUCTION
Outdoor step up substation at hydroelectric stations are provided to step up power at generated
voltage generally for interconnection with the grid to evacuate power. Generation voltage in SHP
varies from 415 volts to 11 kV and step up voltage of small hydro upto 25 MW capacity may not
exceed 145 kV. Guidelines for design and selection of comprises of main equipment, ancillary
equipment, switchyard structures and sub station layout.
2. DESIGN REQUIREMENTS
IS: 9920 Part I to IV – Alternating current switches for rated voltages above 1000 volts and less
than 52 kV
IS: 9921Part 1 to 5 – Alternating currents disconnectors (isolators) and earthing switches rating,
design, construction, tests etc.
IS: 1893 – Criteria for Earthquake resistance design of structures
IS: 2705 Part 1 to 4 – Current transformer
IS: 3156 Part 1 to 4 – voltage transformer
IS: 3070 part 1 to 3 – Lightning arrestors
IS: 2544 – Porcelain insulators for system above 1000 V
IS: 5350 – Part III – post insulator units for systems greater than 1000 V
IS: 5621 – Hollow Insulators for use in electrical equipment
IS: 5556 – Serrated lock washers – specification
IS: 3716 – Application guide for insulation co-ordination
IS: 2165 – Phase to earth insulation co-ordination
Rural electrification Corporation (REC) specification and standards
Power Engineers Hand Book - Tamil Nadu Engineer’s Association
Central Board of Irrigation and Power - Manual on Sub-Station Layout
UPSEB - Construction Manual for Rural Electrification and secondary system planning
2.1 General
The equipment shall be designed and manufactured to provide most optimum functional value
and neat appearance. All major assemblies or equipment shall be designed to facilitate easy and
quick surveillance, maintenance and optimum operation. All control sequences shall be simple
and rational.
All live, moving and rotating parts shall be adequately secured in order to avoid danger to the
operating staff. All electrical components shall be electrically earthed.
Suitable lifting eyes and forcing off bolts shall be provided where required or where they will
be useful for erection and dismantling.
AHEC/MNRE/SHP Standards/E&M Works- Guidelines for Selection of Switchyard SHP Station Page 1
2.2 Seismic Consideration
Forces caused by earthquake which may occur for the seismic intensity of the zone concerned
should be taken into account. Stresses resulting after including these loads should not exceed
permissible stresses. For Himalayan region projects it may be specified as under:-
Insulation coordination is the correlation of the insulation of electrical equipment and system with
the characteristics of protective devices such that the insulation is protected from excessive over
voltages. Thus in a substation the insulation of transformer, circuit breakers, bus supports, etc.
should have insulation strength in excess of the voltage levels that can be provided by protective
equipment such as lightning arrestors and gaps. According to International Electro Technical
Commission Technical Committee No. 28 on Insulation Coordination the same is defined as
follows by IEC:
2.3.1 Over-voltages : The selection of basic insulation level for various components of
switchyard equipment and its coordination is based on the extent of different types of over
voltages and dielectric stresses on insulation of the equipment. Overvoltages are classified as
follows (IS: 3716).
The terms atmospheric overvoltages and switching overvoltages are defined by themselves. The
term temporary overvoltages means overvoltages essentially of power frequency or a frequency
close to it. Switching overvoltages are of consequence only at levels above 220 kV and not
applicable to system under consideration. The protection against overvoltages is essentially made
by Surge diverters (lighting arrestors). Lightning impulse wave is defined as time in microsecond
for the wave to reach crest (1.2 micro second) followed by the time in microsecond for the wave
to reach half magnitude (50 micro second). This has been standardized in the test forms to
establish insulation level on a common basis.
2.3.2 Selection of basic Impulse Insulation Level (BIL) : Equipment insulation must
withstand temporary overvoltages and protected against lightning by suitable lightning arrestor.
The basic impulse insulation level should be selected which can be protected with a suitable
AHEC/MNRE/SHP Standards/E&M Works- Guidelines for Selection of Switchyard SHP Station Page 2
lightning protective device. The best protection is provided by modern type (gapless) lightning
arrestors. The spread margin between the BIL and the protective device, allowing for
manufacturing tolerance, is an economic consideration that must balance the chances of
insulation failure against the cost of greater insulation strength. When using lightning arrestors
the economic factor may be one of greater risk to the arrestor than to the equipment insulation.
The arrestor can be applied so that it will protect the insulation but may under certain extreme
conditions, usually unlikely, be subjected to sustained rms temporary over voltages against which
it cannot recover. Practice has been to apply arrestors so that they have an rms voltage rating
above the maximum possible rms line-to-neutral power frequency voltage under any normal or
expected fault condition with sufficient margin. The BIL of the equipment insulation must
therefore be higher than the maximum expected surge voltage across the selected arrestors
selected to withstand highest credible temporary overvoltage.
2.3.3 Station Design for Lightning and Standardisation of Insulation Levels: Station
design for lightning involves in general, provisions of an adequate insulation level for all
equipment and protective measures to prevent, as for as possible lightning overvoltages
approaching that level from appearing on station lines or on equipment. These levels are given in
table 2.1 & 2.2 as per the Indian Standard IS: 2165. In this standard, table 2.1 covers the standard
insulation levels highest system voltages of 52 kV and below and Table 2.2 for highest system
voltages of more than 52 kV and less than 300 kV.
Table 2.1: Standard Insulation Levels for (equipment in range A 1 kV < Um < 52 kV)
clause (4) for preferred value
For SHP application where temporary overvoltages are high due to speed rise on load throw off
equipment insulation as per list 2 of table 2.1 should be used.
AHEC/MNRE/SHP Standards/E&M Works- Guidelines for Selection of Switchyard SHP Station Page 3
Standard Phase-to-Phase Insulation Levels for 52 kV ≤ Um < 145 kV (IS: 2165)
Table 2.2
Highest Voltage Base for P.U. Rated Lightning Rated Short Duration
for Equipment Values Impulse Withstand Power-Frequency
Withstand Voltage
Um Um 2 / 3
(rms) (peak) (peak) (rms)
kV kV kV kV
72.5 59 325 140
123 100 450 185
550 230
145 118 (450)* (230)*
550 230
650 275
245 200 650* 360*
750* 360*
850 360
950 395
1050 460
An increase of impulse level of 15% above the withstand level to earth is recommended for
disconnecting switches between the terminals of each pole in the open condition. A
corresponding increase of distance may be applied for distances between phases for bus bars and
connections, or between connections which may be located on opposite sides of an open
disconnecting switch.
AHEC/MNRE/SHP Standards/E&M Works- Guidelines for Selection of Switchyard SHP Station Page 4
Table 2.3
1. Basic Data Example 1.
3 Protection Levels
Lightning Impulse
The substation equipments namely the power transformers circuit breakers and disconnecting
switches are considered for detailing the existing practice.
Existing Practice
AHEC/MNRE/SHP Standards/E&M Works- Guidelines for Selection of Switchyard SHP Station Page 5
The commonly adopted insulation levels at present for the above mentioned equipments are given
in table 2.4 with reference to Karnataka and Tamil Nadu (66 kV, 110 kV and 220 kV) and Punjab
(132 kV Bhakra System).
A commonly adopted practice is to locate lightning arrester as near to the transformer as possible.
In large substations additional arresters could be required at suitable locations to protect circuit
breakers, isolators and other equipments. Since each of these equipments cannot be provided with
arrester individually, it is the normal practice to adopt higher insulation to provide the equipment
with as good protection as is economically justified. Insulation level for circuit breaker and other
equipments connected to the busbar together with the bubars themselves are designed for
insulation class about 10% higher than the insulation level for the transformers (one class higher).
Insulation level across the open poles of the isolating switches is kept about 10 to 15 % higher
than that provided between the poles and the earth, so that in the event of a surge at an open
isolating switch, the flashover should pass to earth and not across open poles.
The spark gap is among the cheapest protective devices used for diverting the surges from line to
earth. After the break down of the spark gap the circuit breaker always operates to interrupt the
fault of power frequency current in the circuit. Thus the operation of the gap generally results in
the circuit outage and interruption of supply of the power system. It is therefore used as a back up
to surge arrestor (lightning arrestor).
Spark gaps specified for fitting to the bushings of power transformers, potential and current
transformers, rated 66 kV and above.
The spark gaps are to conform to the following specification, to prevent any damage to the
bushing due to the flashover gazing the petticoats of the bushing:
AHEC/MNRE/SHP Standards/E&M Works- Guidelines for Selection of Switchyard SHP Station Page 6
Fig. 2.3.5
The gap setting furnished below are adopted for all stations whether lightning arresters are
provided or not.
Table 2.5
Note: - The spacing given above are for the standard atmospheric conditions viz:
For non-standard atmospheric conditions the spacing to give the critical flash over voltage should
be modified by dividing the above spacing by ‘d’ where:
P
d = 0.386 ×
(273 + t )
P = barometric pressure in mm Hg.
and t = temperature in 0C.
AHEC/MNRE/SHP Standards/E&M Works- Guidelines for Selection of Switchyard SHP Station Page 7
When the humidity differs the standard spacing should be increased by 1% for each gramme per
cubic meter below the standard value and decreased by 1 % each gramme per cubic meter above
the standard.
Space requirements and layout of electrical equipment in switchyard depends upon various types
of air clearances required to be provided for laying the equipment of different rated voltages.
Following basic clearances govern the sub-station design.
2.4.1 Co-relation between insulation Level and minimum Phase to earth Clearances
Minimum clearances in air between live conductive parts and earthed structures to secure a
specified impulse withstand voltage for dry conditions as per IS 3716-1978 are given in table 2.6.
These minimum clearances are valid for altitudes not exceeding 1000 m and do not include any
addition for construction tolerances, effect of short circuits, safety of personnel etc. these
clearances are suitable for general application, providing as first approximation.
Table 2.6: Correlations between Insulation Levels and Minimum Phase-to- Earth Air
Clearances as per IS: 3716 - 1978
Safety clearance consists of ground clearance and section clearance. The ground clearance is the
minimum clearance from any point on or about the permanent equipment where a man may be
required to stand (measured from the position of feet) to the nearest part not at earth potential of
AHEC/MNRE/SHP Standards/E&M Works- Guidelines for Selection of Switchyard SHP Station Page 8
an insulator supporting a line conductor and the same has been taken as 2.59 meters (i.e. 8.5 feet),
which is the dimensions for a tall man with arms outstretched below the conductor.
The section clearance is the minimum clearance from any point on or about the permanent
equipment where a man may be required to stand (measured from the position of feet) to the
nearest unscreened live conductor in the air. The section clearance system upto 132 kV 650 kV
BIL may be determined by adding 2.5 meters to minimum phase to ground clearance of 1.3 which
works to 3.8 meters for 132 kV system.
The minimum conductor clearance from ground is obtained by adding ground clearance, earth
clearance and height of bus bar supporting clamps on the post insulator. In consideration to it,
minimum height of bus bar for 132 kV may be about 365 mm which may be raised to about 450
mm to correspond to the terminal height of the 132 kV circuit breakers.
Minimum clearance between overhead conductors and roadways within sub-station premises is
computed to be as “Ground clearance plus 625 mm. This dimension provides for a truck with a
man standing on its top 130 + 625 meter = 755 meters app.
2.4.3 Minimum and Safety clearances recommended in Central Board of Irrigation and
Power manual
Clearances from the point of view of system reliability and safety of operating personnel
recommended for sub station upto 245 kv are given in table 2.7. These include the minimum
clearances from live parts to earth, between two live parts of different phases and sectional
clearances between live parts of different phases and sectional clearances between live parts and
work section required for maintenance of an equipment. Besides, it is also necessary that
sufficient clearance to ground is also available within the substation so as to ensure safety of the
personnel moving about within the switchyard.
Table 2.7
Notes:
AHEC/MNRE/SHP Standards/E&M Works- Guidelines for Selection of Switchyard SHP Station Page 9
i) Safety clearances are based on the insulation height of 2.44 m which is the height of
lowest point on the insulator where it meets the earthed metal.
ii) The distances indicated above are not applicable to equipment which has been subjected
to impulse test since mandatory clearances might hamper the design of the equipment,
increase its cost.
iii) The values in table refer to an attitude not exceeding 1000 m and take into account the
most unfavorable conditions which may result from the atmospheric pressure variation,
temperature and moisture. A correction factor of 1.25 % per 100 m is to be applied for
increasing the air clearance for altitude more than 1000 m and upto 3000 m.
iv) No safety clearance is required between the bus-bar isolator or the bus-bar insulator.
However, safety clearance is necessary between the section isolator or the bus-bar itself
and the circuit breaker.
v) For the purpose of computing the vertical clearance of an overhead strung conductor the
maximum sag of any conductor shall be calculated on the basis of the maximum sag in
still and the maximum temperature as specified.
vi) As an alternative to maintain safety clearances in some substation earthed barriers are
used to ensure safety of the maintenance personnel. The use of earthed barriers is quite
common at lower voltages of 36 kV 72.5 kV. In case of paucity of space and if 2.44 m
clearance is not available then localized earthed fencing with clearance can be considered
by the designer.
Following are the normally adopted spacing for the strung bus :
The minimum clearance of live parts to ground in an outdoor sub-station are as follows (Tamil
Nadu Practice) :
The bottom most portion of any insulator or bushing in service should be at an absolute
minimum height of 2500 mm above ground level.
A station which can not be shunt down entirely for maintained purpose must be split into sections
so arranged that any one section can be isolated from its neighbour with adequate clearances as
AHEC/MNRE/SHP Standards/E&M Works- Guidelines for Selection of Switchyard SHP Station Page 10
given below. Where it is impossible to obtain the required safety clearances, earthed screens may
be provided.
The following table gives the sectional clearances for persons to enable inspection cleaning,
repairs; painting and general maintenance works to be carried out in a sub-station.
145 kV 3500 mm
72 kV 3000 mm
36 kV 2800 mm
12 kV 2600 mm
The following minimum clearances should be adopted for enclosed indoor busbars and
connections in air which are not filled with any insulating medium like compound etc.
In indoor kiosks in power stations and main receiving stations, the busbar and connections should
also be taped but the fact of taping should however, be taken into consideration in deciding the
clearances. In addition indoor kiosks etc. should be subjected to a flashover test at works to prove
that clearances are adequate so as to prevent flashovers during surge conditions.
66 kV -7
33kV - 4.6
22 kV - 3.8
11 kV - 3.5
Provision of adequate insulation in a substation is of primary importance from the point of view
of reliability of supply and safety of personnel. However, the station design should be so evolved
that the quantity of isolators required is minimum commensurate with the expected security of
supply. An important consideration in determining the insulation in a sub-station, particularly if it
is located near sea or a thermal power generating station or an industrial plant is the level of
pollution. As a first step to combat this problem, special insulators with higher creepage distance
should be used.
The creepage distances for the different pollution levels are provided according to table 2.8.
AHEC/MNRE/SHP Standards/E&M Works- Guidelines for Selection of Switchyard SHP Station Page 11
Table 2.8: Creepage distance for different pollution levels
Light 16 25 x highest
Medium 20 system voltage
Heavy 25 i.e. 1813 mm for
Very heavy 31 72.5 kV
For determining the creepage distance requirement, the highest line-to-line voltage of the system
forms the basis.
B) Strain Insulators
The cost of structures also is a major consideration while deciding the selection of a substation.
For instance, in the case of the strain/flexible bus-bar arrangement, cost of structures is much
higher than in the case of rigid bus type. Similarly the form of structures also plays an important
part and the choice is usually between using a few heavy structures or a large number of smaller
structures. While finalizing the design, size and single line diagram of structures, safety clearance
requirements should be ensured.
Steel is the most commonly used in India for substation structures. Normally the steel structures
are hot-dip galvanized so as to protect them against corrosion. However, galvanizing sometimes
has not proved effective, particularly in substations located in coastal or industrial areas and in
such cases painting also becomes essential. In other countries special paints have developed
which are applied within the shop and these paints have quite effective.
Design Loads
AHEC/MNRE/SHP Standards/E&M Works- Guidelines for Selection of Switchyard SHP Station Page 12
Maximum for the area on 1.5 times the projected area of one face for latticed structures
and on single projected area in the case of other structures.
iii) Maximum tension of transmission line conductors strung from terminal tower to station
structures or of strung buses for lines 33 kV and above … 226.8 kg. (Tamil Nadu
Electricity Board Practice - TNEB Practice).
Maximum slope (mean of the 3 – phase) at the point of attachment 1 : 8 above horizontal.
The table below gives the values of wind pressure and maximum and minimum temperatures specified in
different states, as per REC for design of structure.
State Wind Pressure Zones Max. Temp. Min. Temp. ICE Loading
Kg/m2 0
C 0
C
Andhra - 75 100 - 60 10 Nil
Pradesh
Assam - - 97.8 - 50 4.44 Nil
Bihar - - 97 - 60 4 Nil
Gujarat - 75 100 - 50 10 Nil
Haryana - - - 150 50 (-) 2.5 Nil
Kerala - 75 - - 55 10 -
Madhya - 75 - - 60 4.4 Nil
Pradesh
Maharashtra 50 75 100 150 65 5 Nil
Karnataka 50 70 - - 54.4 10 Nil
Orissa - 75 100 150 60 5 Nil
Punjab - 100 - - 64.5 (-) 2.5 Nil
Rajasthan - - 100 - 50 (-) 2.5 Nil
Tamil Nadu - 73.25 87.8 122 65.5 (-) 5 Nil
Uttar Pradesh - 75 - 150 60 4.44 Nil
West Bengal - 75 100 150 60 0 Nil
AHEC/MNRE/SHP Standards/E&M Works- Guidelines for Selection of Switchyard SHP Station Page 13
2.7.2 Working Stresses
a) for steel:
Bending .. .. 1265 kg/sq.cm.
Shear .. .. 1265 kg/sq.cm.
b) for concrete – 1 : 2 : 4
Bending .. .. 52.7 kg/sq.cm.
Shear .. .. 5.27 kg/sq.cm.
Bend .. .. 7.03 kg/sq.cm.
Ratio of unsupported length (l) to radius of gyration (r) should not exceed;
2.7.6 Material
Steel employed for structures – open hearth steel with a high yield point and an ultimate strength
of not than 3867 kg/sq.cm.
The following maximum stresses in lbs. per square inch are assumed for outdoor structures,
fabricated out of steel sections manufactured in India;
i. Tension 18,000
ii. Compression 18,000 – 76 l/r where l/r is less than 150 and 13,000 – 48
l/r where l/r is more than 150
iii. Shear on bolts 13,500
iv. Bearing on 27,000
bolts
AHEC/MNRE/SHP Standards/E&M Works- Guidelines for Selection of Switchyard SHP Station Page 14
2.8 GIS Substations
Advancement in the use of SF6 as an insulating and interrupting medium have resulted in the
development of gas insulated substations. Environment and/or space limitations may require the
consideration of GIS (gas insulated substation) equipment. This equipment utilizes SF6 as an
insulating and interrupting medium and permits very compact installations. GIS substation are
preferable to air insulated system ((AIS) because of following reasons:
Three-phase or single-phase bus configurations are normally available up to 145 kV class, and
single phase bus to 500 kV and higher, and all equipment (disconnect/isolating switches,
grounding switches, circuit breakers, metering current, and potential transformers, etc.) are
enclosed within an atmosphere of SF6 insulating gas. The superior insulating properties of SF6
allow very compact installations.
GIS installations are also used in contaminated environments and as a means of deterring animal
intrusions. Although initial costs are higher than conventional substations, a smaller substation
footprint can offset the increased initial costs by reducing the land area necessary for the
substation.
Compact sub-station with gas insulated switchgear may be considered in following cases.
i) Installations in areas with high risk of pollution and corrosion from industrial plants or by
marine and desert climates.
ii) Applications involving use of metal clad switchgear with components of conventional
design to minimize area requirement.
iii) Underground substations
iv) Outdoor installation where space is not easily available
v) Installations in difficult site conditions (e.g. seismically active areas, high altitude areas
etc.).
SF6 – insulated metal enclosed high voltage switchgear upto 145 kV are now available and may
be used where space may be provided. The data of siemens GIS sub station as per Siemens Power
Engineers Guide is given in table 2.10 Feeder control and protection are inbuilt.
Table 2.10
AHEC/MNRE/SHP Standards/E&M Works- Guidelines for Selection of Switchyard SHP Station Page 15
Rated normal current bus Upto 3150
bar (A)
Rated normal current feeder Upto 2500
(A)
Rated breaking current (kA) Upto 40
Rated short-time withstand Upto 40
current (kA)
Rated peak withstand Upto 108
current (kA)
Inspection (years) > 25
Bay width (mm) 800
A compact station is mounted on common base frame with integrated current transformer and
with SF6 insulated dead tank interrupter assembly. Compact air insulated sub-station (CAIS)
factory assembled with dead tank SF6 design is being offered for such-station at 66 kV and 132
kV. Technical particulars of Areva sub station are given in table 2.11 space saving upto 60% is
claimed for H type (single sectionalized bus) substation with two incoming generator
transformers and two outgoing feeders configuration.
Extracts of Siemens Power Engineering guide regarding metal clad switchgear substation upto
145 kV is enclosed as Annexure 1.1.
Table 2.11
Technical Characteristics
Rated voltage kV 72.5 123 145
Rated frequency Hz 50/60
Rated power-frequency withstand kV 140 230 275
voltage
Rated lightning impulse withstand kV 325 550 650
voltage
Rated normal current A 2500
Rated short-circuit breaking current kA 40
Rated short-circuit making current kA 100
Rated duration of short circuit s 3
Circuit Breaker Specific Technical Characteristics
Opening Time ms 38 38 38
Break time ms 50 60 60
Closing time ms 85 106 106
2.9 Power Line Carrier Equipment
The carrier equipment required for communication, relaying and telemetering is connected to line
through high frequency cable, coupling capacitor and wave trap. The wave trap is installed at the
line capacitor. The coupling capacitors are installed on the line side of the wave trap and are
normally base mounted. The wave traps for voltage levels upto 145 kV can be mounted on the
gantry structure on which the line is terminated at the substation or mounted on top of the
AHEC/MNRE/SHP Standards/E&M Works- Guidelines for Selection of Switchyard SHP Station Page 16
capacitor voltage transformer. However, the wave traps for voltage levels of 245 kV and above
generally require separate supporting insulator stacks mounted on structures of appropriate
heights.
Auxiliary facilities for step up sub station in SHP are designed in conjunction with power house
auxiliaries and are discussed in a separate guideline.
Simple single bus bar schemes or single sectionalized bus bars schemes are generally provided in
small hydro scheme.
Adequate facilities must be provided in the substation for inspection and maintenance of various
equipment and at the same time to ensure safety of personnel and maintain proper and other
clearances.
During maintenance, it is essential that the equipment is isolated and earthed. One of the essential
requirements of earthing is that earthing must be actually visible from the point of working in the
substation. Where this is not possible, provision of temporary earthing is made near the
equipment. Besides the permanent illumination, provision should also be made for portable lights
for which purpose power outlets should be provided in marshalling boxes or equipment cubicles.
AHEC/MNRE/SHP Standards/E&M Works- Guidelines for Selection of Switchyard SHP Station Page 17
Annexure-1.1
Metal Clad SF6 Insulated Switchgear up to 145 kV
Three-phase enclosures are used for type 8D9N switchgear in order to achieve extremely low component
dimensions. The low bay weight ensures minimal floorloading and eliminates the need for complex
foundations. Its compact dimensions and low weight enable it to be installed almost anywhere. This
means that capital costs can be reduced by using smaller buildings, or by making use of existing ones, for
instance when medium voltage switchgear is replaced by 145 kV GIS.
The bay is based on a circuit breaker mounted on a supporting frame. A special multifunctional cross-
coupling module combines the functions of the disconnector and earthing device. It can be used as:
The feeder control and protection can be located in a bay-integrated local control cubicle, mounted in the
front of each bay. It goes without saying that we supply our gas-insulated switchgear with all types of
currently available bay control systems - ranging from contactor circuit controls to digital processor bus-
capable bay control systems, for example the modern SICAM HV system based on serial bus
communication. This system offers:
• Online diagnosis and trend analysis enabling early warning, fault recognition and condition
monitoring
• Individual parameterization, ensuring the best possible incorporation of customized control
facilities.
• Use of modern current and voltage sensors. This results in a longer service life and lower
operating costs, in turn attaining a considerable reduction in life cycle costs.
AHEC/MNRE/SHP Standards/E&M Works- Guidelines for Selection of Switchyard SHP Station Page 18
Annexure-1.2
Areva Compact Air Insulated Substation
All components are mounted together on a common base frame. The compact is optimized by combining
single components.
The circuit breaker with an integrated current transformer is the main component of the module. In
addition, the bushings of the breaker also function as insulators for the fixed contacts of the bus and
feeder disconnectrors.
The horizontal interrupter chamber is the determining factor for the low overall height of the entire
module, allowing all energized components to be located on one level.
The three column disconnectors installed in the module allow for a small clearance between phases and a
reduced bay width.
The integrated voltage transformer may substitute the support insulator of the feeder disconnector.
Add-on bus and feeder earthing switches can provide the entire module with additional functions.
AHEC/MNRE/SHP Standards/E&M Works- Guidelines for Selection of Switchyard SHP Station Page 19
Section –2
Selection of Switchyard Equipment
1. BUS BARS
The out door bus-bars are either of the rigid type or the strain type.
In the rigid type, pipes are used for bus-bars and also for making connections among the various
equipments wherever required. The bus-bars and the connections are supported on pedestal
insulators. This leads to a low level type of switchyard wherein equipment as well as the bus-bars
are spread out. Since the bus-bars are rigid. The clearances remain constant. However as the bus-
bars and connections are not very high from the ground, the maintenance is easy. Due to large
diameter of the pipes, the corona loss is also substantially less. It is also claimed that this system
is more reliable than the strain bus. This type is however not suitable for earthquake prone area
due to rigidity.
The strain type bus bars are an overhead system of wires strung between two supporting
structures and supported by strain type insulators. The stringing tension may be limited to 500-
900 kg. depending upon the size of the conductor used. These type of busbras are suitable for
earthquake prone areas.
1.1 Bus bar Material – The materials in common use for bus bars and connections of the
strain type are ACSR and all aluminum conductor. The following sizes are commonly used.
Code Name Remarks
12 kV = 6 x 4.72 + 7 x 1.76 Dog upto 10 MVA in case line conductor is
36 kV = 6 x 4.72 + 7 x 1.76 Dog upto 10 MVA of higher sizes same be
72.5 kV = 30 x 2.79 + 7 x 2.79 ACSR Panther adopted as bus bar
145 kV = 30 x 4.27 + 7 x 4.27 ACSR Zebra material
245 kV = 54 x 3.53 + 7 x 3.53 ACSR Moose
In the case of rigid bus arrangement, aluminum pipes of Grade 63401 WP confirming to IS: 5082
are commonly used. The sizes of pipes commonly used for various voltages are given below:
Since aluminum oxides rapidly great care is necessary in making connections. In the case of long
spans expansion joints should be provided to avoid strain on the supporting insulators due to
thermal expansion or contraction of pipe.
The bus bar sizes should meet the electrical and mechanical requirements of the specific
application for which they are chosen.
AHEC/MNRE/SHP Standards/E&M Works- Guidelines for Selection of Switchyard SHP Station Page 20
2. CIRCUIT BREAKERS
The circuit breakers should be self supporting type. However, if necessary for the purpose of
minimum ground clearance the circuit breakers should be mounted on raised steel structures
which should be included in the scope of supply of circuit breaker. Information and data for
design of foundations from the supplier of the circuit breaker be obtained.
3. ISOLATORS
Isolating switches are used to isolate equipment for maintenance. Isolating switches on line side
are provided earthing blade for connection to earth in off position for safety. Transfer of load
from one bus to another by isolators is not recommended. The isolating switches are designed for
no load operation. Inadvertent operation of the isolating switch on load will damage the switch.
Although a variety of disconnect switches are available, the factor which has the maximum
influence on the station layout is whether the disconnect switch is of the vertical break type or
horizontal break type. Horizontal break type normally occupies more space than the vertical
Isolators for 12 kV and 36 kV normal system voltage conform to IS: 9920 (Part I to IV) and for
voltage 66 kV and above as per IS: 9921.
Earthing switches is a mechanical switching device for earthing parts of a circuit, capable of
withstanding fir a specified time short-circuit currents, but not required to carry normal rated
currents of the circuit.
In case of double circuit lines the earthing switches shall be capable of switching inductive
(electromagnetically) and capacitive currents (electrostatically induced) as per the values
specified in IEC 62271 – 102 when parallel circuit is energized. The disconnector must also be
capable of interrupting and making parallel circuits when transferring load between main and
reserve bus bars according to IEC requirements.
Maximum temperature attained by any part of the isolating switch/ isolating cum-earth switches
when in service at site under continuous full load conditions and exposed continuously to the
direct rays of the sun and the air has to be evaluated carefully and depends upon site conditions
e.g. for 2 x 10 M Mukerian SHP 72.5 kV switchyard (Punjab Plains), it was specified as follows
and is recommended for similar breakers.
AHEC/MNRE/SHP Standards/E&M Works- Guidelines for Selection of Switchyard SHP Station Page 21
3.2 Rating
Each isolating switch should have the following particulars (table 2.3.2) under the site conditions
for the system under design.
Table 2.3.2
The location of disconnect switches in substations affects substation layouts. Maintenance of the
disconnect contacts is also a consideration in the layout. In some substations, the disconnects are
mounted at high positions either vertically or horizontally. Although such substations occupy
smaller areas, the maintenance of disconnect switch contacts in such substations is more difficult
as the contacts are not easily accessible.
Insulation to ground, insulation between open contacts and the insulation between phases of the
completely assembled isolating switch should be capable of withstanding the dielectric test
voltages specified as per IS: 2026. Insulation between open contacts of a pole should at least 15%
more than the insulation between the live parts of a pole to ground so that if any flashover occurs
when switch is open, it should be to the ground.
The post insulators should consist of no. of stack units conforming to IS: 2544. The insulators
selected should be suitable for use in the type of normally polluted atmosphere of the area as per
AHEC/MNRE/SHP Standards/E&M Works- Guidelines for Selection of Switchyard SHP Station Page 22
relevant IS and should be specifically suited to meet the particular requirements of ultimate
torosional strength and cantilever loads which they will be called upon to resist during service at
the rated voltages. The guaranteed data and particulars of the insulators adopted for the
equipment should be obtained from the supplier.
The porcelain should be homogeneous and free from all cavities and flaws.
Design of the insulators should ensure ample insulation, mechanical strength and rigidity for
satisfactory operation under site conditions. The design should also ensure that the losses caused
by capacitive currents or conduction through dielectric are minimum and that the leakage due to
moist and dirty insulator surface is least.
A set adjustable arcing horns should be mounted on each insulator stack of the isolating switch.
Besides above adjustable arcing horns which are required for the purposes of insulation co-
ordination, the isolators may be provided make before and break after arcing contacts if
considered necessary by the manufacturers.
A graph showing impulse and power frequency spark over voltages for various gap settings of the
arcing horns be obtained from supplier.
Load break switches for sectionalizing or for selection of bus if required may be used as per
following specifications.
Each isolator connected with outgoing lines should be provided with appropriate number of
bimetallic, solderless clamp type of connectors suitable for the transmission line conductor. Each
terminal clamp should be suitable for both vertical & horizontal connection of station bus bars
and jumpers. Each isolator should also be provided with appropriate number of grounding
terminals and clamps for receiving grounding connections. The maximum length of the jumper
that may be safely connected or any special instructions considered necessary to avoid undue
loads on the post insulators should be avoided.
3.7 Interlocks
“For the purpose of making the operation of the isolator dependent upon the position of the
associated circuit breaker or other equipment as may be required at site, a suitable electrical
interlock should be provided on each isolator. The interlocks should be of robust design of some
reputed make and contained in a weather proof and dust tight housing.
Besides the electrical interlocks, the earthing switches should be provided with mechanically
operated interlock so as to ensure that: -
AHEC/MNRE/SHP Standards/E&M Works- Guidelines for Selection of Switchyard SHP Station Page 23
(a) It should be possible to close the earthing switch only when the isolating switch is in the
fully open position.
(b) It should be possible to close the isolating switch only when the earthing switch is in the
fully open position.
(c) The earth switch should not open automatically while attempting to close the isolator.
The operation of the earth switches should also be interlocked with the CVTs/CTs
supplies from the transmission line i.e. it should be possible to close the earth switch only
when the line is dead from the feeding end, and there is no supply from the secondaries
of the line CVTs/CTs.
(d) The operation of earth/isolating switch should not take place when the corresponding
isolator/earth switch is in operating stroke.
In addition to the above, the line and the bus isolators should fulfil the following
requirements :-
Isolators and earth switches should be so designed that the above noted requirements can be
conveniently met.
All isolators and earthing switches should be mounted rigidly in an upright position on their own
galvanised steel supporting structure and not on the bus-bar structures.
3.9 Tests
Each isolator and earth switch should strictly comply with the requirements of all the type tests
and should be subjected to all routine tests stipulated in the latest edition of relevant Indian
standard.
Copies of the type tests already performed on similar type of isolators must be obtained and
scrutinized for adequacy.
4. CURRENT TRANSFORMERS
a) 12 kV and Above
Current transformers may be either of the bushing type or wound type. The bushing types are
normally accommodated within the transformer bushings and the wound types are invariably
separately mounted. The location of the current transformer with respect to associated circuit
AHEC/MNRE/SHP Standards/E&M Works- Guidelines for Selection of Switchyard SHP Station Page 24
breaker has an important bearing upon the protection scheme as well as layout of, substation.
Current transformer class and ratio is determined by electrical protection, metering consideration.
Outdoor Type: The outdoor CTs shall be either oil filled type or of resin cast type which shall be
enclosed in a sealed housing to avoid direct exposure to sun and other atmospheric effects.
Indoor Type: The CTs shall be of resin-cast type suitable for indoor installation.
Current ratings, design, Temperature rise and testing etc. should be in accordance with IS: 2705
(Part I to IV). Unless otherwise specified in these specification.
The current transformer should be of outdoor type, single phase, oil immersed, self cooled and
suitable for operation in 3 phase solidly grounded system (11 kV CTs will be as per Para 1.6
above).
Each current transformers should have the following (table 2.4.1) particulars under the site
conditions for the system under design (typical values upto 72.5 kV system are given).
Table 2.4.1
i) Nominal system voltage 66 kV 33 kV 11 kV
ii) Highest system voltage 72.5 kV 36 kV 12 kV
iii) Frequency 50 Hz 50 Hz 50 Hz
iv) Insulation level (kV Peak)
(based on system insulation coordination)
Impulse withstand test voltage with 1.2/50 325 kV 170 kV 75 kV
micro-second, + ve and – ve wave to earth
and between poles
v) One minute power frequency (wet) withstand 140 kV 70 kV (rms) 28 kV
voltage against ground and between poles. (rms) (rms)
viii) Total minimum creepage of CTs bushings As per Para 2.5 of section 1
(based on environment)
Details of current transformer i.e. current, number, ratio, no. of cores and protection/metering
class based on metering and relaying scheme be specified.
AHEC/MNRE/SHP Standards/E&M Works- Guidelines for Selection of Switchyard SHP Station Page 25
4.2.1 Temperature Rise
a) 36 kV and above
The maximum temperature attained by any part of the equipment in service at site under
continuous overload capacity conditions and exposed continuously to the direct rays of sun
should not exceed the permissible limit fixed by the applicable standard, when corrected for the
difference between the ambient temperature at site and the ambient temperature specified by the
standard.
The maximum temperature rise of windings shall not exceed the following (table 2.4.2):
Table 2.4.2
Indoor Type Outdoor Type
Maximum ambient temp. 450C 600C
Permissible temp. rise for
Class E insulation 700C 500C
Class B insulation 800C 600C
Class F insulation 1050C 850C
Note: The supplier shall furnish evidence to the satisfaction of the purchaser about the class of
insulation used.
a) 36 kV & Above
Current transformers should be of robust design, tested quality and reliable in operation. Only
pure high grade paper, wound evenly under controlled conditions and impregnated with mineral
oil under high vacuum should be used for the main insulation. The assembly of each CT should
be dried, filled with appropriate quality of insulating oil under high vacuum and hermetically
sealed with or without inert gas to eliminate undesirable effect of moisture and oxygen on the
internal insulation. No breathers and/or drying chemicals should be used in the design and
construction of CTs.
The shape of the external metal parts should ensure that rain water runs off and it does not
accumulate. All external surfaces should be resistant to atmospheric corrosion either by the
selection of suitable materials or by proper treatment such as hot dip galvanisation, zinc coating
and suitable enamel painted over rust inhibitive coat of zinc chrome primer etc. Likewise, the
internal metal surfaces coming in contact with oil should be given proper treatment unless the
material used itself is oil resistant. Bolts, nuts and washers to be used as fastners should be
heavily hot dip galvanised throughout. The galvanising should conform to IS: 2629-1966. All
CTs should have an oil level gauge marked with the maximum and minimum levels. Although no
oil samples may be required to be taken for analysis nor any filter connections made for
reconditioning of oil at site but a filling plug at the top and a drain at the bottom of the lower tank
should be provided on each CT for use during initial assembly or any subsequent repair.
The current transformers should be with dead/live tank design. The current transformers should
be of single phase oil immersed, self cooled and suitable for services indicated, complete in all
AHEC/MNRE/SHP Standards/E&M Works- Guidelines for Selection of Switchyard SHP Station Page 26
respects conforming to the latest edition of relevant standard specification. The cores should be of
high grade, non-ageing silicon laminated steel of low hysteresis loss and high permeability to
ensure high accuracy at both normal and fault currents. The CTs should be hermetically sealed
with or without inert gas to eliminate breathing and prevent air and moisture from entering into
the tank. To take care of volumetric variation of oil due to temperature changes-stainless steel
bellows/Nitrogen should be provided. In case Nitrogen is used the supplier should ensure that gas
is filled at suitable pressure to take care of the expansion & compression of nitrogen gas. The
equipment should be provided with oil level gauge and pressure relieving device capable of
releasing abnormal internal pressures. The secondary terminals should be brought out in a
compartment on one side of the equipment for easy access. The secondary taps should be
adequately reinforced to withstand normal handling without damage. Equipment should be
provided with power factor terminals for testing loss angle (Tan delta). The equipment should
also be provided with drain valve, sampling plug to check deterioration of oil characteristics and
replacement of oil at site. Means adopted for sealing the CTs hermetically and to absorb the
variation in volume of oil due to temperature variation by way of provision of stainless steel
volume adjustable bellows or other means should be clearly brought out in the tender. Rubber or
PVC/synthetic bellows for the purpose should not be accepted. The secondary terminal of CTs
should be provided with short circuiting arrangement.
b) 11 kV Class
Windings: Change in the CT ratio shal be obtained by providing tapings in the secondary
winding. The primary bar and secondary windings shall be of copper.
Core: The core of the CT shall invariably be of torroidal type. The magnetic circuit shall be of
high grade, non-ageing electrical silicon laminated steel of low hysterias loss and high
permeability to ensure high accuracy at both normal and over currents.
All current transformers should be provided with appropriate number of solderless clamp type
primary connectors suitable for ACSR conductor and should be suitable for horizontal as well as
vertical take off with single conductor as per actual requirement.
a) 12 kV & Above
The current transformers should be suitable for mounting on steel structures. The necessary
flanged, bolts etc. for the base of CTs should be galvanized.
b) 11 kV Outdoor Type
The CTs shall be provided with bolted type terminals to receive ACRS conductors upto 15 mm
dia (without requiring use of lugs) both in vertical and horizontal directions. The terminals shall
be such as to avoid bimetallic actions.
AHEC/MNRE/SHP Standards/E&M Works- Guidelines for Selection of Switchyard SHP Station Page 27
4.6 Tests
Each current transformer should comply with type and routine test including short time current
test as stipulated in relevant Indian Standard specification.
The external insulation should comprise of a hollow porcelain, which will also serve as a housing
for the main insulation or other internal parts of the CTs. Insulators should be of high grade and
homogeneous procelain made by the wet process. The poreclain should have hard glazing and
should comply with the requirements of IS 5621 in all respects. The skirt forms should be
carefully selected to achieve the necessary flashover distance and total / protected creepage
distances as required.
1. Primary terminals
2. High frequency current surge divertors
3. Terminal connectors for connections from line to the CT primary
4. Oil level gauge
5. Pressure relief device
6. Expansion chamber or other suitable type of device for absorbing variations in the
volume of oil due to change of temperature.
7. Weather proof secondary terminal box fitted with door and complete with terminals and
shorting links.
8. Lifting lugs
9. Fixing lugs with bolts, nuts and washers for holding down the CTs on the supporting steel
structures.
10. Rating and diagram plates
11. First filling of oil
12. Oil filling plug and drain valve
13. Earthing terminals
a) 33 kV & Above
The voltage transformer may be either of the electro-magnetic type or the capacitor type. The
electro-magnetic type VTs are costlier than the capacitor type and are commonly used where
higher accuracy is required as in the case of revenue metering. For other applications capacitor
type is preferred particularly at high voltages due to lower cost and it serves the purpose of a
coupling capacitor also for the carrier equipment. For ground fault relaying an additional core or a
winding is required in the Voltage transformers which can be connected in open delta. The
voltage transformers are connected on the feeder side of the circuit breaker. However, another set
of voltage transformer is normally required on the bus-bars for purpose of synchronization.
Potential transformer class and ratio is determined by electrical protection, metering
consideration.
b) 12 kV
The voltage transformer shall of outdoor, 3 phase either oil filled or resin cast type, which
AHEC/MNRE/SHP Standards/E&M Works- Guidelines for Selection of Switchyard SHP Station Page 28
The voltage transformers shall be of outdoor, 3 phase either oil filled or resin cast type, which
shall be enclosed in a weather-proof housing to avoid direct exposure to sun and other
atmospheric influences. The incoming and outgoing terminals shall be brought out through
suitable porcelain bushings. The voltage transformer shall be suitable for operation in a solidly
grounded system.
Potential transformer, design, Temperature rise and testing etc. should be in accordance with IEC:
186, IS: 3156 (Part I & II).
The PTs should be single phase oil immersed self cooled type suitable for outdoor installation of
kV class required. The core should be of high grade non ageing electrical silicon laminated steel
of high permeability. The PTs sealed hermetically scaled to eliminate breathing and prevent air
and moisture entering the tank. Oil level and pressure releasing device etc. should be provided.
Each potential transformers should have the following (table 2.5.1) particulars under the site
conditions for the system under design (typical values for 72.5 kV system are given).
AHEC/MNRE/SHP Standards/E&M Works- Guidelines for Selection of Switchyard SHP Station Page 29
5.2 Temperature Rise
a) 36 kV & Above
The maximum temperature of the windings, cores etc. should not exceed 45°C over ambient,
while max. temperature of oil at top should not exceed 35°C over ambient. The PTs should be
suitable for mounting on steel structures. All nuts, bolts, flanges and base should be hot dip
galvanized. The terminal connectors should be such as to give intimate contact between
conductor & terminal and offer protection against and effects of electrolytic and atmospheric
corrosion and should also have sufficient mechanical strength. The connectors should conform IS
5556: 1970. The junction boxes should be suitable for terminating all the connections of the PTs
secondaries with other equipments of the power station 400V grade terminal connectors of 15
Amp (continuous) current rating should be provided.
b) 12 kV
When tested in accordance with IS: 3156, the temperature rise of the windings shall not exceed
the following *table 2.5.2) limits:
The tank shall be given three coats of rust preventing paint. The other iron parts shall be hot dip
galvanized. The tank shall be provided with lifting lugs either welded on the sides or top cover
plate of the tank.
The dimensions and electrical characteristics of the 11 kV bushings shall be in accordance with
IS: 2099-1986 or its latest version.
The unit shall have rating and diagram plate and will have suitable base channels to
facilitate mounting of the equipment on the structure.
Terminals: The voltage transformers shall be provided with bolted type terminals on the 11 kV
side to receive ACSR conductors upto 8 mm dia (without requiring use of lugs) both in vertical
and horizontal directions. The terminals shall be such as to avoid bimetallic action.
Indoor Type
The voltage transformer shall be of resin-cast type suitable for indoor installation and shall be
normally mounted on one of the 12 kV incoming circuit breakers.
AHEC/MNRE/SHP Standards/E&M Works- Guidelines for Selection of Switchyard SHP Station Page 30
5.4 Coupling Voltage Transformer (36 kV & Above)
These transformers should be suitable for use on transmission line to pass through the carrier
frequencies for communication and low voltage for protection and metering. The single phase
CVTs should be of suitable ratio (say 66 kV/√3/110V/√3 for 66 kV line) suitable for outdoor
installation on steel structures. The equipment should be supplied with terminal connectors
suitable for vertical take off from line conductor and hot dip galvanized base fasteners. Other
details should be in accordance with the specifications for potential transformers. The secondary
terminals should be provided duly marked for above requirements.
The wave traps should hanged underneath feeder bay structure. The carrier frequencies and wave
trap capacity should be decided in accordance with the other ends of the transmission lines
terminating at sub station.
6. TRANSFORMERS
7. LIGHTNING ARRESTORS
Lightning arrestors are the basis of insulation co-ordination (Para 2.3 of section 1) in the system
and are installed at outdoor transformer terminals for direct protection against lightning impulse
overvoltage spark over (1.2/50 micro second wave) and are capable of withstanding dissipation of
energy associated with lightning impulse only. This implies that temporary overvoltages (at or
near power frequency) which are of the order of mili-second must be withstood to avoid damage.
Taking into consideration high temporary over voltages expected on load throw off 90- 95 %
lightning arrestors should be provided.
Metal oxide (gapless) lightning arrestor confirming to following standards are now being
specified.
IEC: 99-4 - Specification part – 4 for surge arrestor without gap for AC system
IS: 3070 - Specification for lightning arrestors
AHEC/MNRE/SHP Standards/E&M Works- Guidelines for Selection of Switchyard SHP Station Page 31
Table 2.7.0
AHEC/MNRE/SHP Standards/E&M Works- Guidelines for Selection of Switchyard SHP Station Page 32
General Technical Requirements
1 The Surge Arrestors should conform to the technical requirements given in table 2.7.1.
2 The energy handling capability of the Arrestor offered, supported by calculations should
be obtained with offer.
3 The Lightning Arrestor should be fitted with pressure relief devices and arc diverting
ports and should be tested as per the requirements of IEC specification for minimum
prospective symmetrical fault current.
4 The grading ring on each complete Arrestor for proper stress distribution should be
provided if required for attaining all the relevant technical parameters.
Table 2.7.1
Technical Requirements For Metal Oxide (Gapless) Lightning Arrestors
1. System voltage 66 kV 33 kV 11 kV
2. Rated Arrestor Voltage kV rms 60 30 9
3. Max. continuous operating 49
voltage (kV rms)
4. Installation Outdoor Outdoor Outdoor
5. Class Station Class Station Class Station Class
6. Type of construction for 10 kA Single Column, Single Column, Single Column,
rated arrestor Single-phase Single-phase Single-phase
AHEC/MNRE/SHP Standards/E&M Works- Guidelines for Selection of Switchyard SHP Station Page 33
Note 1
Terminal Arrangement: The tope metal cap and the base of the lightning arrestors shall be
galvanized. The line terminal shall have a built-in-clamping device which can be adjusted for
both horizontal and vertical take off to suit ACSR (conductor size to be specified by the
purchaser). The base of the lightning arrestors shall be provided with two separate terminals
distinctly marked for connection to earth.
Sealing: The arrestors shall be hermetically sealed to avoid ingress of moisture. Suitable rubber
gaskets with effective sealing system should be used. Manufacturers should device a suitable
routine production testing to verify the efficiency of sealing.
Disconnective Device: The arrestors for 11 kV system may be provided with a suitable
disconnecting device. This shall be connected in series with the ground lead and should not affect
the sealing system of the arrestors. The disconnecting device shall conform to the requirements
specified in IS: 3070 (Part – 2) – 1985.
Pressure Relief Device: The arrestors for 33 kV and 66 kV system should have a suitable
pressure relief system in order to avoid damage to its porcelain housing.
A substation has to be shielded against direct lightning strokes by provision of overhead earth
wires or spikes. This equipment is essential irrespective of the isoceraunic level of the area due to
.serious consequences and damage to costly equipment in case substation is hit by a direct stroke.
The choice between these two methods depends upon several factors economy being the most im-
portant consideration. Both the methods have been used sometimes even in the same station.
Generally, the spikes method involves taller structures than the alternative of using earth wires.
Another method' comprises the use of separate lightning masts which are provided at location
determined on the basis of sub station area and height of bus-bars. - Besides providing lightning
protection, these masts serve as supports for luminaires required for switchyard illumination.
Spikes and the earth-wire .have to be suitably placed so as to provide coverage to the entire
substation equipment. Generally an angle of shield of about 45° for the area between ground
wires and, 30° for other areas is considered adequate for the design of lightning protection
system.
7.3 Insulators
Provision of adequate insulation in a substation is of primary importance from the point of view
of reliability of supply and safety of personnel. However, the station design should be so evolved
that the quantity of insulators required is the minimum commensurate with the security of supply.
An important consideration in determining the insulation in a substation, particularly if it is
located near sea or a thermal power generating station or an industrial plant is the level of
pollution. As a first step to combat this problem, special insulators with higher leakage distance
should be used. In case this does not suffice, washing the insulators by using live line equipment
has to be resorted to and this aspect has to be kept in mind while deciding the layout of the
substation. Another method which has proved to be successful in other countries involves the
application of suitable type of greases or compounds on the surface of the insulators. This,
however, also requires cleaning of insulation, the frequency depending upon the degree and the
type of pollution.
AHEC/MNRE/SHP Standards/E&M Works- Guidelines for Selection of Switchyard SHP Station Page 34
8. EQUIPMENT FOR COMMUNICATION, RELAYING AND TELE METERING AND
OFF-SITE CONTROL
i) Carrier Equipment
ii) Microwave
iii) VHF wireless
iv) Dedicated fibre optic cable
VHF equipment is normally recommended for 33 kV systems. Fibre optic cable is recommended
when offsite control is provided.
The carrier equipment required for communication, relaying and Tele metering is connected to
line through coupling capacitor and wave trap. The wave trap installed at the line entrance. The
coupling capacitors are installed on the line side of the wave trap and are normally base mounted.
9. AUXILIARIES
Besides the main equipment a number of auxiliary facilities and system as enumerated below
have to be provided. These are discussed alongwith auxiliaries for the powerhouse. In step-up
substations most of the facilities are provided in the powerhouse.
a) Earthing and Grounding – Steel grounding system is provided for earthmat and
interconnection
b) Oil Handling System – portable oil purification system is provided
c) Illumination and lighting system – illumination system is discussed with auxiliaries
system
d) Compressed air system – is required for cleaning etc. and provided in the powerhouse
e) Fire protection system – All substations should be equipped with fire lighting systems
conforming to the requirements given in latest IS: 1646 and Fire protection manual Part –
I issued by Tariff Advisory Committee of Insurance Companies.
f) AC Auxiliary power system – is provided in the power house
g) DC system is provided in the powerhouse
h) Cables – discussed in powerhouse electrical auxiliaries
Large substations sometimes require the facilities of repair bay alongwith a crane of adequate
capacity for handling the heaviest equipment, which is usually the transformer. In hydropower
station powerhouse crane is generally used for this purpose. Repair/service bay of powerhouse is
used for repair of transformer.
Provision of a rail track should be made for movement of transformer from switchyard to the
repair bay. Points for jacking, winching should be provided at the transformer foundations and
900 turn on the rail track for changing the direction of the wheels.
AHEC/MNRE/SHP Standards/E&M Works- Guidelines for Selection of Switchyard SHP Station Page 35
11. PALE FENCING
Pale fencing around switchyard consists of 75 mm wide and 2500 mm high pales fixed on two
members 45 x 45 x 6 mm angle horizontal runners. Vertical supports may be of 50 x 50 x 6 mm
angle. Two meter gates of approximately 4000 mm width (2000 mm wide each leaf) is normally
required for entry/exist of transformers etc.
Low level layout of the switchyard of step up station should be provided. Layout of switchyard
may be generally designed in accordance with Central Board of irrigation and power manual on
Sub-Station layout for 36 kV and above. Rural electrification standard be adopted for 12 kV
substations. Typical layouts of substations are attached as follows:
12.1 12 kV outdoor switchyard with Lattice type structure recommended for hilly areas – 2 x
500 kVA Agnoor SHP
12.2 12 kV outdoor switchyard with pole structure – REC standard layout
12.3 36 kV outdoor switchyard – single sectionalized bus (H-Type) 2 x 3.5 MW Sikasar
Project – 2 sheets
12.4 36 kV outdoor switchyard – single bus (CBI & P Manual) – 2 sheets
12.5 72.5 kV outdoor switchyard – single sectionalized bus – proposed 2 x 10 MW Mukerian
project stage –II – 2 sheets.
12.6 145 kV outdoor switchyard single bus (CBI & P) manual for single sectionalized bus – 2
sheets.
12.7 245 kV outdoor switchyard single bus (CBI & P) manual for single sectionalized bus – 2
sheets.
AHEC/MNRE/SHP Standards/E&M Works- Guidelines for Selection of Switchyard SHP Station Page 36
Fig. 12.1: Layout of 12 kV Agnoor SHP SubStation
AHEC/MNRE/SHP Standards/E&M Works- Guidelines for Selection of Switchyard SHP Station Page 37
11kV LINE
11kV LA LAS
NOTES
1. THE LAYOUT AS SHOWN ENVISAGES THE USE OF 11k V
VACUUM CIRCUIT BREAKERS (REC SPEC. 22/1983).
WHICH SHALL NOT REQUIRE ISOLATING SWITCHES AS
THEIR INTEGRAL PART AS PARTICULARLY NO
M AINTENANCE IS NEEDED ON THESE BREAKERS AND IT
WILL ALSO ECONOM ISE IN THE COST.
11kV LA
11 kV
VCB
11kV
11kV
11kV/0.433kV
STATION TRANSFORMER
Fig. 12.2: 12 kV Outdoor Switchyard with Pole Structure – REC Standard layout
AHEC/MNRE/SHP Standards/E&M Works- Guidelines for Selection of Switchyard SHP Station Page 38
AHEC/MNRE/SHP Standards/E&M Works- Guidelines for Selection of Switchyard SHP Station Page 39
Fig. 12.4 Layout of 72.5 kV Switchyard (Plan) (Sheet 1 of 2)-CBI & P Manual
AHEC/MNRE/SHP Standards/E&M Works- Guidelines for Selection of Switchyard SHP Station Page 40
Fig. 12.4 Layout of 72.5 kV Switchyard (Plan) (Sheet 2 of 2)-CBI & P Manual
AHEC/MNRE/SHP Standards/E&M Works- Guidelines for Selection of Switchyard SHP Station Page 41
46400
6800 7600 3000
LA
3000
WT
8500
LI
3000
1000 3500 2000
L
CT
2500
CB
2500
PT
BI
BI
9500
Z
1200
Y
1500
CT
1800
R
L CB
2000
Y
2000
2250
39750
B
LA
1800
2250
12 M VA 11/66 KV
TRANSFORM ER
7000
X
3500
1500 1500
LEGEND
1 SF 6 CIRCUIT BREAKER
2 ISOLATOR
3 CURRENT TRANSFORM ER
4 WAVE TRAP
5 COUPLING VOLTAGE TRANSFORM ER
6 LIGHTNING ARRESTOR
2250
7 POST INSULATOR
8 POTENTIAL TRANSFORM ER
9 PALE FENCING
10 LIGHTING M AST
11 LIGHTING AND SHIELDING M AST
4250
B Y R B Y R
5000
WATER
2000
8800
TANK
C.L. OF TRACK
PLAN
Fig. 12.5 Layout of 72.5 kV Switchyard (Plan) (Sheet 1 of 2)-Mukerain Stage-II (2 x 10MW)
AHEC/MNRE/SHP Standards/E&M Works- Guidelines for Selection of Switchyard SHP Station Page 42
11
2500
1800 2000 2000 1800
7 6
10000
7500
6000
6000
500
2000
1500 1500 3800 2250 2500 2000 3000 2250 4250 3000
1800 1800 20550
SECTION Y - Y 5000
SECTION Z-Z
2500
10
8
7500
7500
9
500
6000
4000
2000
1800 2000 2000 1800 2300 1500 1500 3050 750 2500 2000 2500 750 2550 2000 2000 1800 1800 2000 2000
7600 9100 7000 9100 7600 2000
40400
SECTION L - L
LEGEND
1 CIRCUIT BREAKER
2500
2 ISOLATOR
3 CURRENT TRANSFORMER
4 WAVE TRAP
8 5 COUPLING VOLTAGE TRANSFORMER
1800 2000 2000 1800 6 LIGHTING ARRESTOR
4 1 7 POST INSULATOR
6 5 3
2 8 POTENTIAL TRANSFORMER
9 PALE FENCING
10 LIGHTING MAST
11 LGHTING AND SHIELDING MAST
10000
6000
7500
1500 1500
1800 1800
SECTION Z-Z
3000 2500 2500 2000 2750 2250 2000 1800
20550
SECTION X -X
AHEC/MNRE/SHP Standards/E&M Works- Guidelines for Selection of Switchyard SHP Station Page 43
Fig. 12.6:145 kV Outdoor Switchyard Single Bus (CBI & P) Manual for Single Sectionalized bus (Sheet 1
of 2)
AHEC/MNRE/SHP Standards/E&M Works- Guidelines for Selection of Switchyard SHP Station Page 44
Fig.12.6: 145 kV Outdoor Switchyard Single Bus (CBI & P) Manual for Single Sectionalized bus (Sheet 2 of 2)
AHEC/MNRE/SHP Standards/E&M Works- Guidelines for Selection of Switchyard SHP Station Page 47
Fig. 12.7: 245 kV Outdoor Switchyard Single Bus (CBI & P) Manual for Single Sectionalized bus (Sheet 1
of 2)
AHEC/MNRE/SHP Standards/E&M Works- Guidelines for Selection of Switchyard SHP Station Page 48
Fig. 12.7: 245 kV Outdoor Switchyard Single Bus (CBI & P) Manual for Single Sectionalized bus (Sheet 2 of 2
AHEC/MNRE/SHP Standards/E&M Works- Guidelines for Selection of Switchyard SHP Station Page 50
Section –3
Selection of Power Transformer
1. GENERAL
Power transformers function is to convert electric power from one voltage level to another. In
hydroelectric plants, step up transformer perform the task of delivering power produced by the
generators to the transmission system. Most of these transformers are unit connected i.e. directly
connected to generators with or without a generator breaker. These power transformers are
generator transformers. Power transformers are liquid immersed. Power transformers are located
outside preferably in the switchyard /or transformer deck in powerhouse. These guidelines are for
generators/power transformers used in SHP for outdoor switching i.e. 11 kV to 220 kV.
1.1 Relevant national and international standards in this connection are as follows :
2. GENERATOR TRANSFORMERS
Power transformer which step up the power produced by hydroelectric generating units (0.415 to
11 kV) to a level which matches the sub transmission/transmission system voltage (typically 12
kV to 245 kV class) for range of power houses under considerations are 2 winding oil immersed
transformers.
Three phase generator transformers should be used unless transport limitations or other
special reasons require use of single-phase transformer because of the following reasons.
3. TRANSFORMER RATING
The full load kVA rating of the generator transformer should be at least equal to the maximum
kVA rating of the generator or generators with which they are associated. Where transformers
with auxiliary cooling facilities have dual kVA ratings. The maximum transformer rating should
match the maximum generator rating.
AHEC/MNRE/SHP Standards/E&M Works Guidelines for Selection of Switchyard SHP Station Page 52
4. STANDARD RATING
Standard rating for power transformer of voltage class commonly used are given in table 1 (A, B,
C & D) may be used if possible.
AHEC/MNRE/SHP Standards/E&M Works Guidelines for Selection of Switchyard SHP Station Page 53
5. COOLING
Transformer cooling system for generator transformers specified table 2.4 (A,B & C) in
accordance with IS: 2026 (part II) are identified according to the cooling method employed.
Letter symbols used in the table are as follows :
a. Natural N
b. Forced (oil not directed) F
Transformer is identified by four symbols for each cooling method for which a rating is assigned
by the manufacturer.
Following cooling systems are used in hydroelectric stations upto 25 MVA capacity
Symbol
ONAN Oil Immersed Natural Air Cooled
ONAF Oil Immersed Forced Air Cooled
OFAF Oil Immersed with forced oil circulation Forced Air Cooled
Transformers when located in powerhouse should be sited so that unrestricted ambient air
circulation is allowed. The maximum transformer rating should match maximum generator rating
with forced cooling in dual rating transformers, which are commonly employed. The rating of
these dual rated transformers is usually as follows:
ONAN/OFAF
ONAN - 60%
OFAF - 100%
The rating under ONAF condition although not guaranteed should be about 80%.
Standby cooling capacity should be provided for different type of forced cooling as follows as per
Central Board of Irrigation and Power Manual on Transformer.
AHEC/MNRE/SHP Standards/E&M Works Guidelines for Selection of Switchyard SHP Station Page 54
ONAN/OFAF -2 – 50% group
2 – 100% pump of which one will be standby, 2 –
Standby fans one in each 50% group
Or
3 – 50% group with independent pump and fans out
of which one group to act as standby.
Conservative value of temperature rise, overload capacity and continuous rating of transformer
located in the switchyard should be specified. For the purpose of standardization of maximum
temperature rise of oil and windings, the following ambient temperatures are recommended by
CBI & P.
With the above ambient temperature condition the temperature rises for power transformers as
per CBI & P are as given below :
Oil 0C Winding 0C
50 55
However more conservative temperature rise are specified for generator, transformers. Reference
ambient temperatures and climatic conditions and temperature rise specified for generators
transformer at Mukerian stage II in Punjab given in Annexure 3.1.
7. TRANSFORMER STUDIES
It is recommended that following studies be carried out for transformers 72.5 kV and above from
economic considerations.
a) Type of cooling
b) Insulation level
c) Departure from normal design impedance
8. ELECTRICAL CHARACTERISTICS
All transformers, should be oil immersed and may be either core or shell type and should be
suitable for outdoor installation. Normally oil immersed transformer should be provided with
conservator vessels. Where sealed transformers are specified, there will be no conservator but
adequate space will be provided for expansion of oil without developing undue pressure.
Transformers designed for mixed cooling should be capable of operating under the natural cooled
condition upto the specified load. The forced cooling equipment shouldl come into operation by
pre-set contacts in WTI and the transformer will operate as forced cooled unit.
AHEC/MNRE/SHP Standards/E&M Works Guidelines for Selection of Switchyard SHP Station Page 55
Transformer should be capable of remaining in operation at full load for 10 minutes after failure
of blowers without the calculated winding hot-spot temperature exceeding 1500 C. Transformer
fitted with two coolers each capable of dissipating 50% of the losses at continuous maximum
rating (CMR) should be capable of remaining in operation for 20 minutes in the event of failure
of the blower associated with one cooler without the calculated winding hot-spot temperature
exceeding 1500C.
Transformers provided with mixed cooling should comply, as regards its rating temperature rise
and overloads, with the appropriate requirements of IS: 2026 when operating with natural cooling
and with mixed cooling.
All transformers, except where stated should be capable of operation continuously, in accordance
with IS: loading guide at their CMR and at any ratio. In case bi-directional flow of power is
required, that should be specifically stated by the purchaser.
Temperature rise test should be performed at the tapping as desired by the purchaser. If nothing
has been stated by the purchaser, the test should be carried out at the tapping with the highest load
losses.
The transformer may be operated without danger an any particular tapping at the rated kVA
provided that the voltage does not vary by more than + 10% of the voltage corresponding to the
tapping.
The transformer should be suitable for continuous operation with a frequency variation of +3 %
from normal 50 Hz. Combined voltage and frequency variation should not exceed the rated V/f
ratio by 10%.
The high voltage rating should be suitable for the voltage of the transmission system to which it
will be connected. The low voltage rating should be suitable for the generator voltage (if unit
connected) or generator bus. Generator transformers are generally provided with Off-circuit taps
on HV side for HV variation from +2.5 to – 7.5 % in steps of 2.5 %. On load taps if provided
should have tapping range of +5% to – 10 % in steps of 1.25%.
For interconnecting 2 transmission voltage system say 66 kV and 132 kV size, auto-transformers
with standard ratings as per IS should be provided. For interconnecting auto-transformers, use of
either regulating transformer or on-load tap changer may be made. Interconnecting transformer
are generally star-star connected with tertiary delta winding for flow of 3rd harmonic current.
Generator transformer should be designed for exceptional circumstances arising due to sudden
disconnection of the load and should be capable of operating at approximately 25 % above
normal rated voltage for a period not exceeding one minute and 40 % above normal rated voltage
for a period of 5 seconds. All transformers above 5 MVA should be provided with over fluxing
protection device.
AHEC/MNRE/SHP Standards/E&M Works Guidelines for Selection of Switchyard SHP Station Page 56
8.5 Electrical Connections
Auto connected and star/star connected transformers shall have delta connected stabilizing
windings if specified in the order. Two leads from one open corner of the delta connection shall
be brought out to separate bushings. Links shall be provided for joining together the two
terminals so as to complete the delta connection and earthing it external to the tank.
The maximum flux density in any part of the core and yokes, of each transformer at normal
voltage and frequency should be such that the flux density in following over voltage conditions
does not exceeds 1.9 tesla/19000 lines per cm2.
i) The above flux density has been specified to meet with the over
fluxing of the core due to temporary over voltage of the order of
31% for 1 min., 44% for 5 sec. That may appear in abnormal
conditions such as those following sudden loss of large loads/
tripping of Generator breaker.
ii) Yoke bolt area and flitch plate areas shall not be counted in the
net core area, if these are provided for fastening of core.
iii) The design of limb and yoke shall be so coordinated that there is
no cross fluxing at the joints.
The flux density at normal voltage frequency and ratio should not exceed 1.57 tesla.
The transformer shall be so designed that the current density of HV windings at the lowest tap
should not exceed 250 A/cm2. And that of LV winding should not exceed 200 A/cm2.
Transformers shall be designed and constructed to withstand without damage the thermal and
dynamic effects on external short circuits for 5 seconds under condition specified in IS: 2026
(Part-I)- 1977.
The transformers shall be provided with separate tapping coil to limit the short circuit forces.
The position of the tapping coil shall be so arranged that at extreme negative tap, the percentage
regulation is less than at normal tap.
The bidders shall submit test certificates of the short circuit test, if already done on the offered
design and rating. However, the thermal and dynamic ability to withstand short-circuit forces
shall be demonstrated by calculations.
Manufacturers shall supply calculation for Thermal & Dynamic withstand capacity of the
transformer as per their design alongwith the tenders.
AHEC/MNRE/SHP Standards/E&M Works Guidelines for Selection of Switchyard SHP Station Page 57
8.9 Frequency and System Voltage
The transformers shall be suitable for continuous operation with a frequency variation of 3% from
normal 50 cycles per second without exceeding the specified temperature rise.
The transformer shall be capable of parallel operation with each other and with existing grid.
Every care shall be taken to ensure that the design and manufacture of all transformers and
auxiliary plant shall be such as to have minimum noise and vibration levels following good
modern manufacturing practices.
The manufacturers will ensure that the noise level shall not exceed the figures as per NEMA Pub.
No. TR-1.
Transformers are the starting point for insulation co-ordination and are as such directly protected
by lightning arrestor. Refer Para 2.3 of section -1.
9. IMPEDANCE
Impedance of the transformers has a material effect on system stability, short circuit currents, and
transmission line regulation, and it is usually desirable to keep the impedance at the lower limit of
normal impedance design values. Detailed study should be made if reduced short circuit level or
line regulation consideration are materials and specific feasible impedance values are required.
Typical values of impedance voltage for transformers with two separate windings (at rated
current, given as a % of the rated voltage of the winding to which the voltage is applied) as per IS
2026 part I – 1977 and for generator transformers as per CBI & P Manuals on Transformers are
given in table 2.
AHEC/MNRE/SHP Standards/E&M Works Guidelines for Selection of Switchyard SHP Station Page 58
Table - 2
Rated Power (kVA) Impedance Impedance Voltage (%) as per CBI & P
Voltage (%) as manual
per IS 2026 Three phase power Impedance
rating voltage (%)
11 kV Trans. (kVA) 5
Upto 1600 kVA
Up to 630 4.0 33 kV Trans. (MVA)
631 to 1250 5.0 1.00 5
1251 to 3150 6.25 1.60 6.25
3151 to 6300 7.15 3.15 6.25
6301 to 12500 8.35 4.00 7.15
12501 to 25000 10.0 5.00 7.15
Above 25001 12.5 6.30 7.15
8.00 8.35
10.00 8.35
66 kV Trans. (MVA)
6.3 8.35
8.0 8.35
10.0 8.35
12.5 8.35
20.0 10.00
16 10
25 10
31.5 12.5
Transformers with lower or higher values of impedance are normally furnished with difference in
cost. The value of transformer impedance should be determined giving consideration to impacts
on selection of interrupting capacities of station breakers and on the ability of the generators to
aid in regulating transmission line voltage. Transformer impedances should be selected based on
system and plant fault study. Impedances shown are subject to a tolerance of plus or minus 10%
as per IS:
Transformer losses represent a considerable economic loss over the life of the power plant.
Standard losses as per CBI & P manual on the basis of optimized design of manufacturer is given
in table 3 for 11 kV to 66 kV class transformers. Based on these losses Capitalization for
transformer losses should be carried out in accordance with CBI & P manual on transformer
Section L enclosed at Annexure 3.3.
AHEC/MNRE/SHP Standards/E&M Works Guidelines for Selection of Switchyard SHP Station Page 59
Table 3: STANDARD LOSSES AT 750C
Sl. Three-phase power rating No-load loss (kW) Load loss (kW)
No.
(a) 11 kV Transformers (kVA)
200 570 (W) 3300 (W)
315 800 (W) 4600 (W)
630 1200 (W) 7500 (W)
1000 1800 (W) 11000 (W)
1600 2400 (W) 15500 (W)
Connections for the generator transformers are mostly by power cables for small hydro stations
upto 10 MVA rating from generator terminals to power transformer in switchyard. Bus ducts
which could be isolated phase for large units or segregated phase bus ducts for smaller units may
be used. Accordingly terminal for the generator transformers should be as follows:
LV Side: LV bushings should be mounted on turrets suitable for connection to bus bar in
bus ducts. For SHP cable boxes may be provided, if cables are used.
HV Side: Solid Porcelain/Oil Communicating and other type bushings upto 36 kV voltage class
in accordance with IS: 3347. The dimensional parameters of the bushings upto and including 36
kV voltage class should be in accordance with IS: 3347. The rated current, voltage, Basic
Insulation Levels should be in accordance with IS: 2099.
66 kV to 220 kV bushings are oil impregnated paper (OIP) type condenser bushings in
accordance with IS 2099 and IEC 137. Dimensions interchange capability current, insulation
level and creepage distance for various classes of the bushings should be in accordance with
CBI & P Manual on transformers Section P.
AHEC/MNRE/SHP Standards/E&M Works Guidelines for Selection of Switchyard SHP Station Page 60
The electrical characteristics of bushing insulator shall be in accordance with IS: 2099 as
amended from time to time. All type and routine tests shall be carried out in accordance with IS:
2099. The test voltage for various tests as stipulated in IS: 2099 – 1986 are as follows:
Nominal Rated voltage of the One minute wet and dry Lightning impulse
system voltage bushing power frequency withstand test 12/50
voltage withstand test micro sec. kV peak
kV kV kV kV
11 12 28 75
33 36 70 170
12. TANKS
The main tank body excluding tap-changing compartments, radiators and coolers shall be capable
of withstanding vacuum given in the following table:
The pressure relief device shall be provided of sufficient sizes for rapid release of any pressure
that may be generated within the tank, and which might result in damage to the equipment. The
device shall operate at a static pressure of less than the hydraulic test pressure for transformer
tank. Means shall be provided to prevent the ingress of rain water.
Unless otherwise approved the relief device shall be mounted on the main tank, and, if on the
cover, shall be fitted with skirt projecting 25 mm inside the tank and of such a design to prevent
gas accumulation.
To prevent transformer movement during earthquake, a claming device shall be provided for
fixing the transformer to the foundations. The contractor shall supply necessary bolts for
embedding in the concrete. The arrangement shall be such that the transformer can be fixed to or
unfastened from these bolts as desired. The fixing of transformer to the foundation shall be
designed to withstand seismic events to the extents that a static coefficient of 0.3g applied in the
direction of least resistance to that of loading will not cause the transformer or clamping device as
well as bolts to be over stressed.
AHEC/MNRE/SHP Standards/E&M Works Guidelines for Selection of Switchyard SHP Station Page 61
(d) Skids and pulling eyes on both directions.
(e) Oil-filling valve with flange
(f) Jacking pads.
(g) Pocket on tank cover for thermometer.
(h) Air release devices.
(i) Conservator with oil filling hole, cap and drain plug-size 19 mm nominal pipe (3/4 in.
BSP/M 20).
1. Plain oil level gauge for all transformers upto and including 1.6 MVA.
2. Magnetic type oil gauge for transformers above 1.6 MVA, with low oil level
alarm contact.
(j) Silica gel breather with oil seal.
(k) Pressure relief device.
(l) Valves:
1. Drain valve with plug or blanking flanges. The same can be used for filtering
purpose.
2. A sampling device or sampling facility on drain valve.
3. 1 No. filter valve on upper side of transformer tank.
(m) Buchholz relay with alarm and trip contacts with one shut-off valve on conservator side.
1. Size of Buchholz relay up to 10 MVA-50 mm
2. 10 MVA and above-80 mm
(n) Oil temperature indicator with one electrical contact shall be provided with anti-vibration
mounting.
(o) Winding temperature indicator with two electrical contacts for alarm and trip purposes.
Switching of fans shall be done by winding temperature indicator for all transformers
having ONAF rating. The winding temperature indicator shall be provided with anti-
vibration mounting.
(p) Tank mounted weather-proof marshalling box for housing control equipment and
terminal connectors. Wiring up to marshalling box with PVC SWA PVC copper cables
660/1100 volts grade.
(q) Rollers-4 Nos.
AHEC/MNRE/SHP Standards/E&M Works Guidelines for Selection of Switchyard SHP Station Page 62
Sl. Rating Type Gauge
No. Shorter axis Longer axis
1. Up to 5 MVA Flat, uni-directional As per manufacturer’s practice,
however, not to exceed 1000 mm
2. 6.3 MVA Flanged, bi-directional 1435 mm 1435 mm
3. 10 MVA and above Flanged, bi-directional 1676 mm 1676 mm
(b) 33 kV winding
17. ACCESSORIES
Normal accessories are arcing horns, oil flow alarm, fans and pumps, dissolved gas monitoring
system, Temperature detectors, Lifting devices.
Provision of Following Oil preservation system are preferred for generator step-up transformer.
(i) Inert gas pressure system. Positive nitrogen gas pressure is maintained in the space
between the top of the oil and the tank cover from a cylinder through a pressure-reducing
valve.
(ii) Air-cell, constant-pressure, reservoir tank system. A system of one or more oil reservoirs,
each containing an air cell arranged to prevent direct contact between the oil and the air.
If any oil filled transformers are used in the power plant, provisions should be made to contain
any oil leakage or spillage resulting from a ruptured tank or a broken drain valve. Physical
separation in the use of fire wall/barriers is also provided in power plants. Specifications for fire
AHEC/MNRE/SHP Standards/E&M Works Guidelines for Selection of Switchyard SHP Station Page 63
protection of power transformers may be provided in accordance with CBI & P Manual on
Transformer in Section ‘O’ or specification refer chapter on mechanical auxiliaries.
Transformer specifications must contain complete and exhaustive section for quality control,
Inspection, factory and field test. Provision for witness testing of factory test and method for type
test should be specified in detail. Various routine, type and special tests are detailed in IS 2026
part I. For explanations, details on the methods and procedure for corrections when ideal test
conditions cannot be achieved reference may be made to test manual for transformers issued by
CBI & P.
Refer CBI & P manual on transformers section K entitle Erection, Maintenance and
Commissioning manual.
Transformer rating and characteristics for a 11/66 kV transformer for Mukerain Stage-II HEP ( 2
x 10 MW) is enclosed as Annexure 3.4.
AHEC/MNRE/SHP Standards/E&M Works Guidelines for Selection of Switchyard SHP Station Page 64
Annexure-3.1
The reference ambient temperatures for which the transformers are to be designed are as under:-
B. ALTITUDE
a) With the above service conditions, given in clause-6.4 each transformer shall be capable
of operating continuously on any tap at normal rating without exceeding following
temperature rises, over maximum ambient temperature of 50 deg. C.
b) The limits of temperature rise mentioned above and over load capacity as per IEC-354
(1993) will have to be satisfied by the manufacturer by carrying out the heat run test at
the lowest negative tap. This test shall be carried out by feeding the following losses: -
(Total max. losses at 75 deg. C at highest current tap) x 1.1
AHEC/MNRE/SHP Standards/E&M Works Guidelines for Selection of Switchyard SHP Station Page 65
c) The safe overload capacity of the transformer and the duration of overload for each type
of cooling (ONAN/ONAF/ ) under maximum temperature conditions (Clause 6.5 above )
without any damage to the winding or harmful effects on the insulation shall be clearly
stated in the tender, which must be as per IEC-354 (1993) – Guide for loading of oil
immersed transformers, suitable for climatic conditions given in clause-6.4 above.
d) The transformer may be operated without exceeding temperature rises, winding gradients
and hot spot at any particular tapping at the rated MVA provided that the voltage does not
vary by more than ±10% of the voltage corresponding to that tappings. Transformer shall
be able to withstand for 30 minutes after achieving steady state at full load rating without
injurious heating to winding/insulation etc. under auxiliary failure condition.
AHEC/MNRE/SHP Standards/E&M Works Guidelines for Selection of Switchyard SHP Station Page 66
Annexure-3.2
Where:
LS is the annual loss factor
LF is the annual load factor
Assuming annual load factor as 60%, annual loss f actor works out to 0.432.
Capitalised Cost of Transformer = Initial cost + Capitalised cost of annual iron losses +
Capitalised cost of annual copper losses + Capitalised
cost of annual auxiliary losses.
r (1 + r )
n
Actual value can be worked out by the purchaser by considering appropriate value of r, EL, LF,
and LC.
AHEC/MNRE/SHP Standards/E&M Works Guidelines for Selection of Switchyard SHP Station Page 67
Example Calculation -1
Generator Transformer
LS = 0.3(LF)+0.7(LF)2
LS = 0.3x0.8+0.7x(0.8)2
= 0.688
= 8400×EC×
(1 + r )n − 1 × LS
r (1 + r )
n
= 8400×2.5×
(1 + 0.1) − 1
35
× 0.688
0.1(1 + 0.1)
35
= Rs. 139338.81
Capitalised cost of additional transformer losses
= 139338.81 x 2.381
= Rs. 331766
AHEC/MNRE/SHP Standards/E&M Works Guidelines for Selection of Switchyard SHP Station Page 68
Annexure-3.3
The values indicated are typical values and the utility may adopt values different from those indicated in
case the rates of interest, cost of energy and the number of hours of operation are different from those
indicated in the example below. A life expectancy of less than 25 years is not recommended.
[{ n
}
A = H × E C × (1 + r ) − 1 / r (1 + r )
n
] = [{(1 + r ) − 1}/ r (1 + r ) ]
n n
Rate of
interest
Expect
ed life
Number of
hours of
Cost of
energy to
1+r (1 + r )n (1 + r )n − 1
⎢
{ }
⎡ (1 + r )n − 1 ⎤
⎥
A = loading
factor per
⎣⎢ / r (1 + r ) ⎦⎥
n
in per operation in a the utility kW of iron
unit year at 11 kV loss
level
r n h Ec
0.08 25 8400 Ec 1.08 6.84847 5.84848 10.97477619 Rs.
5 8966xEc
B = A x LIF
= Rs. 89668 x Ec x 0.3 = Rs. 26900 x Ec
Where,
Note: In case of non-availability of Ec (energy cost per unit) at 11 kV feeder level, utility should
consider the Bulk Rate Tariff plus 5% as the cost of energy at 11 kV feeder level. Load factor
considered for B factor is 0.5, higher load factor may be considered for urban areas.
AHEC/MNRE/SHP Standards/E&M Works Guidelines for Selection of Switchyard SHP Station Page 69
Annexure-3.4
INSULATION LEVELS
The provision of note under clause 5.4 IS: 2026 (Part-III) – 1981 should be kept in view while
offering this parameter. The star connected windings of the transformers shall have graded
insulation. All windings for system voltage lower than 66 KV shall have uniform insulation.
AHEC/MNRE/SHP Standards/E&M Works Guidelines for Selection of Switchyard SHP Station Page 70
Section – 4
Selection of Circuit Breaker
1. INTRODUCTION
Circuit breaker is a mechanical switching device capable of making, carrying and breaking
current under normal circuit condition as well as under specified abnormal circuit condition such
as short circuit etc. Circuit breakers are generally classified according to interrupting medium
used to cool and elongate electrical arc permitting interruption. Selection of outdoor circuit
breakers for switchyards 12 kV and above upto 245 kV (highest system voltage) as regards types,
rating, performance requirements and tests for AC high voltage circuit breakers that are installed
in SHP outdoor switchyard after the step up transformer on outgoing transmission line feeders.
Special requirement for rating of AC high voltage generator circuit breakers between the
generator and transformer terminals are also discussed.
1.1 References
Relevant National and important international standard in this connection are as follows:-
2.1 Following types of circuit breakers formerly used in high voltage outdoor substations
are no longer in use and are being phased out.
i) Bulk oil circuit breakers (Dead Tank Design) – In these circuit breakers oil
contents is used for arc extinction and also for insulating live parts from the tank
which is dead and generally earthed (ground).
ii) Minimum oil breakers (Live Tank Design) – In these circuit breakers oil is
primarily used for arc extinction and not necessarily for insulating live parts from
earth (ground). The tank of these circuit breakers are insulated from earth ground.
The circuit breakers are phase separated. These circuit breaker were widely used
upto 72 kV level and are being phased out from existing installation.
iii) Air blast circuit breaker – circuit breaking in these circuit breakers occurs in a
blast of air under pressure. These circuit breakers were widely used upto 765 kV
system. These circuits breakers are being phased out.
Following types of circuit breakers are in use now-a-days for max. voltage class used for 25 MW
hydro station.
AHEC/MNRE/SHP Standards/E&M Works Guidelines for Selection of Switchyard SHP Station Page 71
ii) Vacuum circuit breakers upto 36 kV class
iii) Air circuit breaker upto 12 kV (Generator circuit breaker)
Sulphar Hexafluoride as an Arc Quenching Agent:- Pure sulphar hexafluoride gas is inert and
thermally stable. It possesses very good arc quenching as well as insulating properties which
make it ideally suitable for use in a circuit breaker. Sulphar hexafluoride remains in a gaseous
state upto a temperature of 90C at 15 kg/cm2 pressure its density is about five times of air and the
free heat convection is 1.6 times as much as that of air. Apart from being a gas, it is non-
inflammable, non-poisonous and odourless. When arcing takes place through the gas, some by-
products are produced due to breakdown of the gas. These by-products are a hazard to the health
of the maintenance personnel therefore should be properly taken care of.
At a pressure of three atmospheres the dielectric strength of sulphar hexafluoride is about 2.4
times that of air and compares very well with that of oil. Even when gas is exposed to electric
arcs for fairly long periods, it has been found that decomposition effects are small and the
dielectric strength is not materially affected. On the other hand the metallic fluorides at the
temperatures of the arc are good insulators and the arc is therefore, not at all harmful to the
breaker.
Gas circuit breaker generally employ SF-6 (sulphar hexafluoride) as an interrupting medium and
sometimes as an insulating medium. In “single puffer” mechanisms, the interrupter is designed to
compress the gas during the opening stroke and use the compressed gas as a transfer mechanism
to cool the arc and to elongate the arc through a grid (arc chutes), allowing extinguisher of the arc
when the current passes through zero. In other designs, the arc heats the SF6 gas and the resulting
pressure is used for elongating and interrupting the arc. Some older low-pressure SF6 breakers
employed a pump to provide the high pressure SF6 gas for arc interruption.
Gas circuit breakers typically operate at pressures between six and seven atmospheres. The
dielectric strength of SF6 gas reduce significantly at lower pressures, normally as a result of
lower ambient temperatures. Monitoring of the density of the SF6 gas is critical and some designs
will block operation of the circuit breaker in the event of low gas density.
Circuit breakers are available as live-tank or dead-tank designs. Dead –tank designs put the
interrupter in a grounded metal enclosure. Interrupter maintenance is at ground level and seismic
withstand is improved versus the live-tank designs. Bushings are used for line and load
connections which permit installation of bushing current transformers for relaying. The dead-tank
breaker does require additional insulating gas to provide the insulation between the interrupter
and the grounded tank enclosure.
Live-tank circuit breakers consist of an interrupter that is mounted on insulators and is at line
potential. This approach allows a modular design as interrupters can be connected in series to
operate at higher voltage levels. Operation of the contacts is usually through an insulated
operating rod or rotation of a porcelain insulator assembly by an operator at ground level. This
design minimizes the quantity of gas used for interrupting the arc as no additional quantity is
required for insulation of a dead-tank enclosure. The design also readily adapts to the addition of
pre-insertion resistors or grading capacitors when they are required. Seismic capability requires
special consideration due to the high center of gravity of the interrupting chamber assembly.
Interrupting times are usually quoted in cycles and are defined as the maximum possible delay
between energizing the trip circuit at rated control voltage and the interruption of the main
contacts in all poles. This applies to all currents from 25 to 100% of the rated short circuit current.
AHEC/MNRE/SHP Standards/E&M Works Guidelines for Selection of Switchyard SHP Station Page 72
Breaker ratings need to be checked for some specific application. Applications requiring
reclosing operation should be reviewed to be sure that the duty cycle of the circuit breaker is not
being exceeded. Some applications for out –of- phase switching or back-to-back switching of
capacitor banks also require review and may require specific duty circuit breakers to insure
proper operation of the circuit breaker during fault interruption.
Vacuum circuit breakers use an interrupter that is a smaller cylinder enclosing the moving
contacts under a high vacuum. When the contacts part, is a formed from contact erosion. The arc
products are immediately forced to and deposited on a metallic shield surrounding the contacts.
Without anything to sustain the arc, it is quickly extinguished.
Vacuum circuit breaker are widely employed for metal-clad switchgear up to 36 kV class. The
small size of the breaker allows significant savings in space and material compared to earlier
designs employing air magnetic technology. When used in out door circuit breaker designs, the
vacuum cylinder is housed in a metal cabinet or oil filled tank for dead tank construction.
Advantages: Advantages of SF6 breakers over the conventional breakers is given below:
i) due to outstanding arc quenching property of SF6, the arcing time is very small. This
reduces contact erosion.
ii) using SF6 gas at low pressure and low velocity; the current chopping can be minimized.
iii) during arcing of SF6 breaker, no carbon dioxide is formed and hence no reduction of
dielectric strength.
iv) SF6 breaker is silent in operation and moisture ingression into the gas cycle is almost nil.
v) SF6 breaker performance is not affected due to variation in atmospheric conditions.
vi) SF6 breaker is compact in size and electrical clearances are drastically reduced.
Disadvantages: The only disadvantage of using SF6 to some extent is suffocation. In case of
leakage in the breaker tank, this gas, being heavier than air settles in the surroundings and may
lead to suffocation of the operating personnel. However, it is non-poisonous.
I. SWITCHING DUTIES
1. Summated breaking To 50 times rated short circuit To 100 times rated short
current capacity breaking current To 10,000 circuit breaking current To
times continuous rated current. 20,000 times continuous
rated current.
AHEC/MNRE/SHP Standards/E&M Works Guidelines for Selection of Switchyard SHP Station Page 73
2. Critical switching Very well suited Over voltage Well suited. Under certain
i. Motor, Reactors generally under 2.5 p.u. circumstances steps may be
small inductive Normally no action necessary to necessary to limit over
current. limit over voltages. voltages because of
possibility of virtual current
chopping. Use of surge
arresters recommended
ii. Capacitors Well suited. Restrike free. In Suited. Generally Restrike
special cases reactors may be free. In special cases reactors
necessary to limit in rush current may be necessary to limit in
- Low over voltage. rush current-Reignition and
restrikes possible in certain
cases due to statistical scatter
of breakdown voltage in
vaccum.
iii. Over head and Very well suited-Restrike free. Very well suited Restrike
cable feeders. free.
iv. Switching of arc Only suitable in applicable with Suitable also for applications
furnaces. comparatively low number of with very high number of
operations per day. operations (over 100 co-per
day.
3. Suitability of single Very well suited Very well suited.
and multi shot auto
reclose cycles.
II. MAINTAINABILITY
AHEC/MNRE/SHP Standards/E&M Works Guidelines for Selection of Switchyard SHP Station Page 74
SI. No. Criteria SF 6 circuit breaker 3 Vacuum circuit breaker
1 2 4
costs.
III. RELIABILITY
IV. COST
1. Cost of production Sightly higher than VCB -
2. Maintenance cost Lowest negligible cost for Lowest negligible cost for
minimum 10 years. minimum 10 years.
The protection classes are identified by a compound symbol made up of the two code letters' EP,
which always remain the same two digits denoting the degree of protection and, if] required, the
supplementary code letter B. The supplementary code letter must be stated if in the case of
switchgear and distribution equipment the protection class is attained only through taking certain
measures when the apparatus is installed. The term 'Production class* denotes the complete
compound symbol (code letters, code digits and the supplementary code letter if applicable)
AHEC/MNRE/SHP Standards/E&M Works Guidelines for Selection of Switchyard SHP Station Page 75
Protection Class
IP 4 3 B
Code
If in addition to the code letters IP only one code digit for the degree of protection is used, the
missing digits a to be replaced by a dash.
eg. IP - 4 (Protection
class : Splash proof)
4. RATED CHARACTERISTICS
The main characteristics of a power circuit breaker including its operating devices and
auxiliary equipment used to determine the rating are as follows :-
• Rated voltage
• Rated insulation level
• Rated frequency
• Rated normal current
AHEC/MNRE/SHP Standards/E&M Works Guidelines for Selection of Switchyard SHP Station Page 76
• Rated short-time withstand current
• Rated short-circuit breaking current
• Rated short-circuit making current
• Rated operating sequence (duty cycle)
• Rated transient recovery voltage (TRV) for terminal fault
• Total breaking time (maximum)
• Rated characteristics for short-time faults, for three pole circuit breakers designed for
direct connection to overhead transmission lines and rated at 52 kV and above and at
more than 12.5 kA rated short breaking current
5.1 Rated Voltage: Voltage rating of the power circuit breaker is in terms of three phase line
to line voltage of the system. The rated voltage of the circuit breaker should be of standard rating
chosen so as to be at least equal to the highest voltage of the system at the point where the circuit
breaker is to be installed. The operating voltage and the power frequency recovery voltage should
not exceed the rated maximum values because this maximum is upper limit for continuous
operation.
It is however considered that operation at altitude above 1000 meters should be given special
considerations and certification from manufacturer be obtained because of possible influence of
altitude on interrupting capacity.
In case of generator circuit breakers the rated maximum should be equal to the maximum
operating voltage of the generator, which is usually equal to 1.05 times rated voltage.
The rated voltage is expressed in kV (rms) and refer to phase to phase voltage.
5.2 Rated Insulation Level: - Insulation level of power circuit breakers should be selected
from standard insulation level listed in IS: 13118. Refer table 2.1 (section-1) for voltage upto 36
kV and table 2.2 (section-1) for voltages upto 245 kV. For insulation co-ordination refer (Para
2.3.4. of section1).
The surge protection of the system should be coordinated with the impulse strength of the
breaker, both across the open contacts and to ground. Attention should also be given to increase
AHEC/MNRE/SHP Standards/E&M Works Guidelines for Selection of Switchyard SHP Station Page 77
in surge voltage because of reflections which occur at breakers when their contacts are open,
especially where cables are involved.
Surge arrestors are generally installed on the bus or on transformers and not on each circuit
breaker, the surge voltage at the breaker can exceed that at the arrestors. The amount of the
excess depends upon the steepness of the wave front and the distance from the circuit breaker to
the surge arrestors. When the circuit breaker is in the open position, either intentionally left open
or during operation, an incoming surge voltage may be doubled by reflection at the open contacts.
Selection of too low an insulation level for circuit breakers, if not individually protected by
arrestors, may result in line-to-ground, or open gap insulation failure of the circuit breaker. Use of
individual line entrance surge arrestors may be required if the lightning trip-out rate of the line
exceeds 1 per year (refer IEEE std. 37.010-1999). Refer section 1 for more details.
5.3 Rated Frequency: standard power circuit breakers are rated at 50 cycles. Service at other
frequencies requires special consideration.
5.4 Rated Normal Current: rated normal current of a circuit breaker is the rms value of the
current which the circuit breaker shall be able to carry continuously at rated frequency. With the
rise in temperature of its different parts not exceeding specified values. Values of rated normal
currents should be selected from standard value of normal currents as per IS: 13118 which are
400A; 630A; 800A; 1250A; 1600A; 2000A; 2500A; 3500A; 4000A; 5000A; 6300A (if required
higher values can be selected). These ratings are based on operation of the circuit breaker or
switchgear assembly where the ambient temperature (measured outside the enclosure) does not
exceed 400C and the altitude does not exceed 1000 m. Standard equipment may be operated at
higher altitude by reducing the continuous current rating in accordance with the following tables
(based on American Practice).
The rated continuous current is based on the maximum permissible total temperature limitations
of the various parts of the circuit breaker when it is carrying rated current at an ambient
temperature of 400C.
When the ambient temperature is greater than 400C, the current must be reduced to less than rated
continuous current to keep temperatures within allowable limits.
Rated short-time withstand current is equal to the rated short circuit breaking current. The rated
peak withstand current is equal to rated short circuit making current. Rated duration of short
circuit should be as per IS 13118.
The rated short circuit breaking current is the highest short circuit current which the circuit
breaker will be capable of breaking in a circuit having power frequency recovery voltage
AHEC/MNRE/SHP Standards/E&M Works Guidelines for Selection of Switchyard SHP Station Page 78
corresponding to rated voltage and transient recovery voltage (refer Para 3.5.7) equal to the rated
value of the circuit breaker as specified in IS. For three pole circuit breakers the AC component
relates to three phase short circuit including short line fault.
Rated short circuit breaking current is characterized by two values Fig. 1 (Annexure-1).
rms value of AC component of the rated short-circuit breaking current should be selected from
standard values given in IS 13118. Percentage DC component is dependant upon the time from
initiation of short circuit current and standard values are given in IS 13118.
The standard values practice of breaking current or being 6.3 kA, 8 kA, 10 kA,12.5 kA kA,16 kA,
20 kA, 25 kA, 31.5 kA, 40 kA, 50 kA, 63 kA, 80 kA, 100 kA. The earlier practice was to express
the rated breaking capacity in MVA.
MVA : 3 kV × kA
MVA : breaking capacity of circuit breaker
kV : rated voltage
kA ; rated breaking current
The circuit breakers some times, close on to a existing fault. In such cases, the current increases
to the maximum values as the peak of first current loop. The circuit breaker must be able to close
without hesitation as contacts touch. The circuit breaker must be able to withstand the high
mechanical forces during such closure.
As per IS: 13118 rated short circuit making current should be at least 2.5 times the rms value of
the A. C. component of its rated short circuit breaking current.
5.8 Transient Recovery Voltage and Restriking Voltage and First Pole to clear Factor
The instantaneous value of the recovery voltage at the Instant of arc extinction is called the active
recovery voltage figure 3.3 (Annexure-3).
5.9 Rated Transient Recovery Voltage (TRV) for terminal faults:- The rated transient
recovery voltage (TRV) for terminal faults relating to the rated short-circuit breaking current
is the reference voltage. This constitutes the limit of the prospective transient recovery voltage of
circuits, which the circuit breaker will be capable of breaking in the event of a short circuit at
its terminals.
Wave form of transient recovery voltage varies according to the arrangement of actual circuit.
Standard value of rated TRV for 3 pole circuit breaker as per in IS: 13118 for the circuit breakers
used in the outdoor substations under consideration are given below table 3.2.
AHEC/MNRE/SHP Standards/E&M Works Guidelines for Selection of Switchyard SHP Station Page 79
Table 3.2
The ratio of transient voltage that appears across the contacts at the instant of arc extinction to
service frequency recovery voltage is called the restriking voltage first pole to clear factor.
In three-phase circuits the restriking voltage refers to the voltage across the first pole to clear
because this voltage is generally higher than that appears across each of the other two.
Effect of power factor on recovery voltage:- With low p.f., for example when the ratio of
reactance to resistance of the circuit is high, the active recovery voltage will be high; whereas
with high p.f. i.e. when the resistance is high as compared to the reactance, the active recovery
voltage would be correspondingly lower. This is illustrated in fig. 3.4. In fig. (a) the p.f. is zero
and at the instant of arc extinction A the active recovery voltage is at peak value equaling to AB
while in Fig (b) the p.f. is 0.5 and the active recovery voltage at the instant of arc extinction is CD
which is less than AB.
In general the active recovery voltage equals the maximum value of the system voltage multiplied
by sin θ where θ is the power factor angle.
AHEC/MNRE/SHP Standards/E&M Works Guidelines for Selection of Switchyard SHP Station Page 80
(a) (b)
Effect of armature reaction on recovery voltage: The recovery voltage is less than the normal
system voltage because of demagnetizing effect of armature reaction. The fault currents flowing
in the generator winding are of lagging power factor. They have a demagnetizing armature
reaction. Hence they reduce the terminal voltage.
Effect of circuit conditions on recovery voltage: Another factor that influences the recovery
voltage is the circuit conditions e.g. three phase faults that are insulated from earth, either at
neutral or at fault, produce recovery voltages in the first phase to clear which are normally more
severe than those produced by single phase or three phase faults on systems with earthed neutrals.
This is explained below.
Consider an unearthed three phase fault, on a three-phase system with the neutral earthed, being
cleared by a circuit-breaker. When the breaker opens, it draws out an arc in each phase. Assume
that the arc in R phase is the first to be cleared (fig. 3.4 a). At the instant of this extinction the Y
and B phases are still acting and have the same instantaneous phase voltage – 0.5v, where v is the
phase to neutral value of the system. Now the resistance of the arcs in the Y and B phases at this
instant are negligible, which means that the fault itself is momentarily at the potential – 0.5V.
Since the fault is common to all three phases the momentary value of the recovery voltage
component in phase R must be V + 0.5V i.e., 1.5V (fig. 3.4 b). This means that the recovery
voltage component in the first phase to clear on a 3-phase unearthed fault is 1.5 times that on an
earth fault assuming an earthed neutral.
Rated characteristics for short line faults are required for three generator pole circuit breakers
designed for direct connection to overhead transmission lines and having a rated voltage of 52 kV
and above and a rated short-circuit breaking current exceeding 12.5 kA. These characteristics
relate to the breaking of a single phase earth fault in a system with earthed neutral.
The short line fault circuit is taken as composed of a supply circuit on the source side of the
circuit breaker and a short line on its load side (fig. 3.5) with the following rated characteristics.
AHEC/MNRE/SHP Standards/E&M Works Guidelines for Selection of Switchyard SHP Station Page 81
L
Xs IL XL
CB Z
G V
Voltage equal to the phase-to-earth voltage V/√3 corresponding to the rated voltage V of the
circuit breaker.
Short circuit current, in case of terminal fault, equal to the rated short circuit breaking current of
the circuit breaker.
Prospective transient recovery voltage, in case of terminal fault, given by the standard values in
IS: 13118.
Standard values of rated surge impedance rated peak factor and time should be taken from IS:
13118.
Rated out –of-phase breaking current is required to be specified for generator breaker and as per
IS 13118. This provision will provide with following.
a. The power frequency recovery voltage should be 2.0/√3 times the rated voltage for
earthed neutral systems and 2.5/√3 times the rated voltage for other systems.
b. The rated out-of-phase breaking current should be 25% of the rated short-circuit breaking
current.
c. Transient recovery voltage as pre IS: 13118.
AHEC/MNRE/SHP Standards/E&M Works Guidelines for Selection of Switchyard SHP Station Page 82
5.16 Rated Line Charging Breaking Current
Rated Line Charging Breaking Current is required to be specified for feeder circuit breakers.
Standard value of line charging capacity of circuit breakers for the commonly used voltages are
as follows:
Table 3.3
This implies for overhead line length equal to 1.2 times the rated voltage of the circuit breaker in
kilovolts. In case line length is longer than it may be necessary to specify a higher value of line
charging capacity.
Rated values to be assigned to the following time quantities (fig. 3.6) will depend upon
rated supply voltage reclosing operations etc.
• Opening time;
• Break time;
• Closing time;
• Open-close time;
• Reclosing time;
• Close-open time;
o – t – co - t´ - co
Where
o - opening operation
co - closing operation followed immediately by an opening operation
(without internal time delay)
t,t´ - time interval between successive operation/ t& t˝ are in minutes or
seconds
Power circuit breakers are rated for interrupting ability on the basis of a standard operating duty.
AHEC/MNRE/SHP Standards/E&M Works Guidelines for Selection of Switchyard SHP Station Page 83
Fig. 3.6 Reclosing – Close Open Reclose Time
The rated interrupting time of a circuit breaker is the maximum permissible interval between the
energization of the trip circuit at rated control voltage and rated mechanism pressure and the
interruption of the current in the main circuit in all poles. It is used to classify breakers of
different speed.
For line-to-ground faults, the interrupting time is estimated to exceed the rated interrupting time
by 0.1 cycle. For asymmetrical faults, it is estimated that the interrupting time may exceed rated
time by an additional 0.2 cycle. Hence, for grounded asymmetrical faults, the last phase to clear is
estimated to be 0.3 cycle slower than the rated interrupting time. Additionally, rated interrupting
time may be exceeded during extreme cold weather or when the breaker has been closed for an
extended period of time. Also, the breaker may be slower at the lower limits of control voltage
and/or mechanism stored energy. These interrupting times are in the range of several milliseconds
have system stability implications.
The rated interrupting time may be exceeded for close-open operations. The increase in
interrupting time on close-open operation may be important from the standpoint of possible
system instability. For low values of current, these considerations are less important.
Co-ordination of rated voltages, short circuit breaking current and rated normal current for
guidance as per IS 13118 for rated voltage 33 kV and above as commonly used are as follows.
(Table 3.4).
AHEC/MNRE/SHP Standards/E&M Works Guidelines for Selection of Switchyard SHP Station Page 84
Table 3.4
Rated Rated short- Rated normal current (A)
voltage circuit breaking
(kV) current (kA)
3.6 10 400
16 630 1250
25 1250 1600 2500
40 1250 1600 2500 4000
7.2 8 400
12.5 400 630 1250
16 630 1250 1600
25 630 1250 1600 2500
60 1250 1600 2500 4000
12 8 400
12.5 400 630 1250
16 630 1250 1600
25 630 1250 1600 2500
40 1250 1600 2500
50 1250 1600 2500
17.5 8 400 630 1250
12.5 630 1250
16 630 1250
25 1250
40 1250 1600 2500
24 8 630
12.5 630 1250
16 630 1250 1600
25 1250 1600 2500
40 1600 2500 4000
36 8 630
12.5 630 1250
16 630 1250 1600
25 1250 1600 2500
40 1600 2500 4000
52 8 800
12.5 1250
20 1250 1600 2000
72.5 12.5 800 1250
16 800 1250
20 1250 1600 2000
31.5 1250 1600 2000
145 12.5 800 1250
20 1250 1600 2000
25 1250 1600 2000
31.5 1250 1600 2000 3150
40 1600 2000 3150
50 2000 3150
245 20 1250 1600 2000
31.5 1250 1600 2000
40 1600 2000 3150
50 2000 3150
AHEC/MNRE/SHP Standards/E&M Works Guidelines for Selection of Switchyard SHP Station Page 85
7. TESTS
Following type tests as applicable in accordance with IS 13118 and IEC 56 are recommended
to determine adequacy of the circuit breaker.
i) Dielectric tests (1.2/50 micro second lightning impulse withstand) and 1 minute power
frequency voltage with stand (dry & wet) test
ii) Radio interface voltage (r.i.v.) tests
iii) Temperature rise tests
iv) Measurement of the resistance of the main circuit
v) Short-time withstand current and peak withstand current tests
vi) Mechanical and environmental tests
vii) Miscellaneous provisions for making and breaking tests
viii) Short circuit making and breaking tests
ix) Basic short circuit test duties
x) Critical current tests
xi) Single phase short making and breaking tests
xii) Capacitive current switching tests
xiii) Magnetizing and small inductive current switching tests
8. FAULT CALCULATION
In order to determine interrupting duty of circuit breakers it is necessity to determine fault current
at each circuit breaker location. Determination of maximum short circuit current is the most
important requirement of circuit breaker application. Rigorous determination of short circuit
current as a function of time involves complex calculations. Growth in interconnecting power
system as systems expand will increase short circuit duty. Accordingly some approximation and
degree of judgment should be used.
Different published methods of determining short circuit currents are available. Reference may be
made to the following for details and selection.
IEEE application guide for AC high voltage circuit breakers rated on a symmetrical current basis
IEEE std. C37010-1999.
First step in carrying out short circuit studies is to determine system impedances with reference to
the point of fault and current distribution for different kind of faults. For present day large
interconnected system this becomes time consuming laborious study.
AC or DC network analyzer for calculation of fault current was previously frequently used for
short circuit studies. In the analyzer all the essential elements of the power system were
AHEC/MNRE/SHP Standards/E&M Works Guidelines for Selection of Switchyard SHP Station Page 86
represented in a miniature replica and fault currents determined from calculation readings. In this
method constant voltage behind sub transient/synchronous reactance were used as required.
Accordingly real time studies to determine DC component of fault current in addition to AC
component to determine the critical current value existing at the time of primary arcing contact
parting can not be calculated. Further network analyzers is a fixed place study. Now-a-day
computer studies are carried out for such application.
Staged fault short circuit tests adequately controlled on actual systems have been carried out
mostly on new equipments and systems to determine circuit breaker capability. These are
accurate, costly and not always possible as selection of circuit breaker precedes power system
installation.
Steps involved in fixing circuit breaker short circuit rating are as follows:
1. Determine normal current duty of the circuit breaker and select higher available rated
current from standard values as per IEC/IS 13118 clause 4.4.
2. Short Circuit studies be carried for following types of faults which are considered worst
according to IEEE std. C37010-1999.
More severe of the short circuit faults be taken for selecting the short circuit rating.
3. Determine short circuit currents for the required accuracy by a suitable method. For line
to ground faults, the required symmetrical interrupting capability is 15% higher.
4. Circuit breaker having the rms value of the ac component of the short circuit higher then
short circuit duty as calculated from table X A of IS 13118 (table 2.4 for commonly used
voltages) be selected.
5. A circuit breaker having adequate symmetrical interrupting capability will normally have
adequate capability to meet normal asymmetrical requirement. Maximum symmetrical
interrupting capacity of new circuit breaker is as follows:
For higher X/R ratio or other special conditions refer the detail methods given in IEEE
std.C37010-1999.
Simplified methods calculating fault current to fix short circuit rating of circuit breakers have
been recommended by standardizing agencies over years as given below.
AHEC/MNRE/SHP Standards/E&M Works Guidelines for Selection of Switchyard SHP Station Page 87
Simplified conservative method of calculation were recommended by protective devices
committee of AIEEE for general use of the industry. It was recommended that rigorous methods
be used when specifically required. The method is based upon determination of an initial value of
rms symmetrical current (ac component) to which following multiflying factor are applied for
application purposes (table 3.5).
Table 3.5
Accordingly the steps involved for determining short circuit rating of circuit breakers are as
follows as per the AIEE simplified method:
1. Determine highest value of rms symmetrical current for any type of fault equal E/X1
phase fault or 3E/2X1+X0 for ground fault whichever is greater.
2. Multiply this current by appropriate factors from table 3.5.
3. The resulting interrupting and momentary current should be used to select the available
normal rated circuit breaker.
The AIEEE simplified method was further referred in IEEE std. 37010-1999. This simplified
method is now recommended. For short circuit duty of circuit breakers unless complex more
accurate studies are warranted.
In these studies generating station and transmission lines interconnected with the system are
represented in detail and the system is represented by equivalent system.
For small hydro say 5 MW unit size connected to regional grids, the grid size can be assumed to
be infinite size and calculation carried out accordingly.
Calculation based on simplified method of calculating short circuit current for the application of
recommended by IEEE std. 37-01-1999 are given as an example and compared with calculation
made according AIEE committee report.
Positive sequence X1 is assumed equal to negative sequence X2 and obtained from design
date or test.
AHEC/MNRE/SHP Standards/E&M Works Guidelines for Selection of Switchyard SHP Station Page 88
X0 = zero sequence reactance obtained from design date or test
E = phase to neutral voltage
3. If phase fault current does not exceed 80% of 100% symmetrical circuit breaker
interrupting capacity or 70% ground fault current then the circuit breaker selection is
adequate.
More exact procedure of calculation with adjustment for AC and DC decrements should be used
if the criteria is not fulfilled. In this method multiplying factors to initial value of
symmetrical short circuit current are given in the factor of curves for 2 cycle to 8 cycle.
Breakers to include effect of ac and dc components for the following types of faults.
8.6 Characteristics specified for 72.5 kV Mukerian Stage II (2 x 10 MW) in Punjab and 36
kV Sikasar HE Project (Chattisgarh 2 x 3.5 MW) are given in table 3.6.
Table 3.6
AHEC/MNRE/SHP Standards/E&M Works Guidelines for Selection of Switchyard SHP Station Page 89
a) rms value of AC component ( rated 31. 5 KA at 72. 5 KV
short circuit current ) 12.5 kA at 36 kV
b) percentage D.C. component As per IEC-56 (Latest (750 MVA) as per IS:
edition) 13118
ix. First pole to clear factor 1.5
x. Rated transient recovery voltage for As per IEC –56 (latest
terminal faults edition)
a) corresponding to rated short circuit
breaking current (Symmetrical & -do-
Asymmetrical)
b) Corresponding to currents below the
rated & short circuit current
xi. Breaking capacity under short line fault -do-
conditions with rated supply side and line
side characteristics
xii. Rated short circuit making current 78. 75 KA peak 2.5 times the rms
at 72. 5 kV value of Ac
component
xiii. Rated operating sequence Break dead Time-Make-
Break (Minimum dead
time should not be more
than 15 cycles at 50 c/s
inclusive of the time for
auto reading relay. Unit of
adjustment of dead time
shall be 15 to 35 cycles.
xiv. Total break time for any current upto rated Not more than 60 ms
breaking current
xv. Min. short time current rating and its 31.5 kA for 3 sec.
duration
xvi Minimum total creepage distance phase to 1700 mm
earth
xvii Difference in the instant of closing/opening
. of contacts of all the 3 pole
a) Opening Not more than 3.33 ms.
b) Closing Not more than 5 ms.
xvii Small inductive current interrupting Any value upto 10A with
i capacity out switching over voltage
exceeding 2.0 p.u.
xix. Whether breaker suitable for single pole Gang operation of three
operation or gang operation of three poles poles through mechanical
linkages
xx. Number of trip coils Two Nos. per breaker
AHEC/MNRE/SHP Standards/E&M Works Guidelines for Selection of Switchyard SHP Station Page 90
Example :- Circuit Breaker Rating for hydro electric power system shown in fig. 3.5 is proposed to
be determined.
G G
100MVA;11/132kVTRANSFORMER
X = 12%
132kV BUS
A
X1 = 8% X1 = 8%
OPEN
132kV BUS
B
EQUIVALENT SYSTEM
X1 = 0.03
Fig. 3.5
Data
AHEC/MNRE/SHP Standards/E&M Works Guidelines for Selection of Switchyard SHP Station Page 91
i) Sub transient reactance of generator on own base - 24%
ii) 100 MVA transformer impedance - 12%
iii) 132 KVA transmission lines impedance - 8%
iv) Power house is interconnected with grid at bus B.
v) Equivalent system X1 = 0.03 of X0 = 0.04
1. Consider the fault at M which is fed by the grid system and the hydro- generators
which is considered worst.
2. Three phase fault calculations:- In the system shown in figure 4.5 per unit
reactances are indicated.
Apparent power is 100 MVA base and nominal voltage 132 kV is used as base at all levels.
⎛ 0.24 0.12 ⎞
⎜ + ⎟ x(0.08 + 0.03)
⎝ 2 2 ⎠ 0.18 x0.11
X1 = = = 0.068
⎛ 0.24 0.12 ⎞ 0.18 + 0.11
⎜ + ⎟ + (0.08 + 0.03)
⎝ 2 2 ⎠
OPEN
X1=0.24 X1=0.12 X1=0.08
X1=0.03
X1=0.08
X1=0.24 X1=0.12
The value of operating voltage corresponding to the highest operating voltage at faults is 145 kV
or 1.098/unit
1.098
Isc = x 437 = 7056A
0.068
Zero sequence impedance would be that of transformers above as 12 % on 100 MVA. Impedance
X of diagram is shown in figure.
AHEC/MNRE/SHP Standards/E&M Works Guidelines for Selection of Switchyard SHP Station Page 92
X0 =
(0.04 + 0.24)x0.12 =
0.28 x0.12
= 0.084
(0.04 + 0.24) + 0.12 0.28 + 0.12
0.24 0.12
X0 = 0.04
0.24
Since X0 is greater than X1, single line to ground fault need not be considered.
Three phase short circuit current is 7056A is less than 80% of symmetrical interrupting capability
( 16,000A) and large growth margin exists; the 132 kV breakers at step up sub station are rated
1250A; with rated short circuit breaking current of 20,000A.
AHEC/MNRE/SHP Standards/E&M Works Guidelines for Selection of Switchyard SHP Station Page 93
Annexure-1
Current wave
I DC x100
= percentage value of the d.c. component
I AC
Fig. 1 short-circuit making and breaking currents, and of percentage d. c. component (IS:
13118).
Annexure-2
AHEC/MNRE/SHP Standards/E&M Works Guidelines for Selection of Switchyard SHP Station Page 94
G
Vr
Vrc
LINE
AHEC/MNRE/SHP Standards/E&M Works Guidelines for Selection of Switchyard SHP Station Page 95
Annexure-3
AHEC/MNRE/SHP Standards/E&M Works Guidelines for Selection of Switchyard SHP Station Page 96
Version 2
STANDARDS/MANUALS/
GUIDELINES FOR
SMALL HYDRO DEVELOPMENT
Electro-Mechanical Works–
Monitoring, Control, Protection and Automation of Small
Hydropower Station
May 2011
GUIDE LINES FOR MONITORING, CONTROL, PROTECTION
AND AUTOMATION OF SMALL HYDROPOWER STATIONS
CONTENTS
SECTION-I
SECTION-II
SECTION-III
SECTION-IV
4.0 Protection of SHP generating units 26
4.1 General 26
4.2 Equipment trouble 27
4.3 Devices used in typical protection system 28
4.4 Criteria of selection of protection system ....................................................................... 333
4.4.1 Requirements of Protection of Turbine................................................................. 33
4.4.2 Requirements of Protection of Generator ............................................................. 33
4.5 Generator Protection System and Relay Selection ........................................................... 34
4.5.1 Categorisation .............................................................................................................. 34
4.5.2Transient overvoltage and surge protection .................................................................. 34
4.5.3 Protection for Micro hydel systems (up to 100 kVA).................................................. 34
4.5.4 Protection for Generating Units above 100 kVA and up to 5 MVA ........................... 35
4.5.5 Protection for generating Units above 5MVA and up to 25 MVA .............................. 41
4.6 GENERATOR CONNECTED IN PARALLEL TO GRID ............................................ 46
4.7 GENERATORS CONNECTED IN PARALLEL ON A COMMON BUS .................... 46
4.8 PROTECTION GROUPS ................................................................................................ 46
4.8.1 CONTROLLED ACTION SHUT DOWN ........................................................... 46
4.8.2 EMERGENCY SHUT DOWN ............................................................................. 47
4.8.3 IMMEDIATE ACTION SHUT DOWN………………………………………....46
4.8.4 ELECTRICAL SHUT DOWN…………………………………………………..46
ANNEXURE-I ............................................................................................................................. 49
COMPUTERISED AUTOMATION AND REMOTE CONTROL OF SMALL HYDRO
POWER PLANT ........................................................................................................................... 49
ANNEXURE-II ........................................................................................................................... 85
LIST OF GENERATOR PANEL INDICATION AND RELAYS .............................................. 85
ANNEXURE-III .......................................................................................................................... 86
LIST OF PROTECTION ELEMENTS IN MICRO PROCESSOR BASED RELAYS .............. 86
1.0 INTRODUCTION
1.1 OBJECTIVES
The purpose of this guide is to provide guidance for selection of monitoring,control and
protection system for SHP up to 25 MW by developers, manufacturers, consultants,
regulators and others. The guide includes selection of technology, extent of automation
and monitoring system for different categories (micro up to100 KW, small up to 5 MW
and above 5 MW to 25 MW) that is economical, easy to adopt and sustainable feasible
and essential for safe operation.
1.2 GENERAL
The generating units of a small hydropower plant may have its shaft vertical, horizontal
or inclined with the type of turbine selected to suit the site’s physical conditions. Small
hydro turbines may be selected as per site conditions, head and discharge available. Small
hydro-generator are of the alternating current type and may be either synchronous or
induction type. Usually small hydro units up to 5 MW are expected to require minimum
amount of field assembly and installation work. While machine having capacity from 5
MW to 25 MW may have slow speed, large diameter and with split generator, stator that
may require final winding assembly in the field.
Mini & micro power stations are generally provided system suiting to these being run
unattended or with few attendants while bigger machines up to 5 MW capacity have more
elaborate arrangement of control monitoring and protection. Machine having capacity up
to 25 MW and provision of parallel operation with other systems will have more
comprehensive control, monitoring & protection system.
This guide will serve as a reference document along with available national &
international codes standards, guide & books. For the purpose of convenience this guide
has been subdivided as follows:
• Monitoring
• Control
• Protection
IEEE Std 1020 - IEEE guide for control of small hydro electric power
plants
IEEE Std 1010 - IEEE guide for control of hydro electric power plants
IEEE Std 60545:1976 - Guide for commissioning operation and maintenance of
AHEC/MNRE/SHP Standards/E&M Works – Guidelines for monitoring, control, protection 3
and automation of SHP Oct. 2009
Hydraulic Turbines
IEC 61116:1992 - Electro mechanical guide for small hydroelectric
installations
IEEE std 1046 - IEEE application guide for distributed digital control
and monitoring for power plants
IEEE std. 1249 - IEEE guide for computer–based control for power plant
automation
IEEE std. C 37101 - IEEE guide for generator ground protection
IEEE std. C 5012 - IEEE standard for salient pole 50 Hz and 60 Hz
synchronous generator and generator / motors for
hydraulic turbine application rated 5 MVA and above
IEEE std 4214 - IEEE guide for preparation of excitation system
specification
ANSI/ IEEE std 242:1996 - IEEE recommended practice for protection and
coordination of industrial and commercial power
systems
ANSI/ IEEE std C 372-1987 - IEEE standard electrical power systems device function
numbers
ANSI/ IEEE std C 37.95 : 1974 - (R1980) IEEE guide for protective relaying of utility
ANSI/ IEEE std C 37.102:1987 - IEEE guide for generator protection
Monitoring of operating parameters of the generating unit and their auxiliaries is very
important for the life and optimum utilization of available discharge for generation. The efficient
running of unit requires regular monitoring. The primary input data and generation output data
are monitored periodically. The details of data required for monitoring performance of a
generating station is as follows.
Current and voltage transformers of rated voltage and appropriate ratio, class of accuracy
are selected as per the requirement of the system.
ii) Sensors
The sensors for temperatures, pressures, levels and speed are installed at the proper
location.
Analogue type of meters, separate for each parameter with selector switches etc were
being used earlier installed on control panels. Now a days digital meters are being used for such
parameters. Digital multifunction meters are now in use, only one meter provides several
parameters on selection, as well as provides routine display.
Digital temperature scanners indicating the temperatures of stator winding, bearing pads,
oil coolers etc. are provided and installed on the generator control panels. These scanners get the
signals from the sensor installed at specific locations preferably through screened cables.
Indicating lamps of suitable colours as per code and practices should be provided on
control panels for indication status of machine and various auxiliaries, pumps, electrical
equipment like breaker, isolator, AC/DC supply system etc. Lists of such indication and relays
are enclosed as Annexure-I&II.
The protection system relays and auxiliary relays also provide signals to alarm and
annunciation system. A set of annunciation windows are provided on control panels for each
fault clearing relay with accept test and reset facility through push buttons. Alarm and trip
annunciation indicate the fault and advise operating personnel of the changed operating
conditions.
Recently control of machine and auxiliaries is done through PLC based control system
automatically in addition to manual systems with local and remote facilities. The data is acquired
through sensors and operation of machine is achieved on preset values through PC Monitors etc.
The PLC will acquire data from generating units, transformers, switchgears and
auxiliaries through transducers / sensors/ CTs / VTs.
Wherever signals are weak, noise level is high shielded cables should be used for
carrying data / signals. For sending output signals PLC will use relays for operating breakers etc
and comparators for giving ON/OFF signal.
• Alarm
• Tripping
In case of manned power plant ‘alarm’ comes first so as to make the operator alert if no
corrective action is possible then tripping command with indication / hooter and annunciation
will be there.
But in case of unattended power plant direct tripping command will be initiated and shut
off the facility to avert possibility of any damage to the plant.
3.1 GENERAL
For small hydro installation simplicity of control system is advised, however, the
sophistication of control should be based on the complexity and size of the installation, without
compromising unit dependability and safety of personnel. Simplicity of control is desirable to
keep total cost of installed equipment as well as cost of maintenance, repair and tests at
economical level. Moreover a simpler system is more reliable as compared to complex one.
3.2 Technology
Modern systems still permit control of the entire plant from a single location.
Modern control rooms utilize the far more cost-effective computer based automation which
implies (IEEE: 1249 definition) use of computer component, such as logic controllers, sequence
controllers, modulating controllers and microprocessors in order to bring plant equipment into
operation, optimize operation in a steady state condition and shut down the equipment in the
proper sequence under safe operating conditions.
This includes programmable logic controllers (PLC’s) for control system and PC
monitor and hard disc for data display and data acquisition system and distributed computer
control systems with graphic display screens to implement a vast array of control schemes. The
SCADA (supervisory control and data acquisition) control scheme also provides flexibility in
control, alarming, sequence of events recording, and remote communication that was not
possible with the hardwired control systems. Data acquisition, storage and retrieval is provided
by the computer.
A detailed write up on computerized automation, remote control and SCADA is
enclosed as Annexure –I for reference.
There are many functions to be controlled in a small hydropower system. For example
turbine governor controls the speed of turbine, plant automation covers operations as auto start,
auto synchronization, remote control startup or water level control and data acquisition and
AHEC/MNRE/SHP Standards/E&M Works – Guidelines for monitoring, control, protection 9
and automation of SHP Oct. 2009
retrieval covers such operation as relaying plant operating status, instantaneous system efficiency
or monthly plant factor.
This is the speed / load control of turbine in which governor adjusts the flow of water
through turbine to balance the input power with load.
In case small plants in the category of micro hydel (100 kW unit size), load controllers
are used, where excess load is diverted to dummy load to maintain constant speed.
With an isolated system, the governor controls the frequency of the system.
In interconnected system, the governor may be used to regulate unit load and may
contribute to the system frequency control. Figure 1 shows the different types of control
applicable to turbines.
This is the excitation control of synchronous generator. The excitation is an integral part
of synchronous generator which is used to regulate operation of generator. The main functions of
excitation system of a synchronous generator are:
Plant control deals with the operation of plant. It includes sequential operation like
startup, excitation control, synchronization, loading unit under specified conditions, normal
shutdown, emergency shutdown etc. The mode of control may be manual or automatic and may
be controlled locally or from remote location. Plant control usually includes monitoring and
display of plant conditions. Different plant controls are given in fig 3.
Governor and control systems for small hydro units especially in developing countries
have to be selected keeping in view the following:
ii) The manpower as available for operation is unskilled and further adequate supervision
is not feasible.
iii) Load factors for stand-alone micro hydels are usually low which affects economic
viability.
iv) Cost of speed control and automation with electronic analaog flow control governors,
unit control and plant control is high. These systems require attended operation and are
mostly based on large capacity hydro units. This is making most of the units very costly
and uneconomical to operate. Experience in successful operation of analog electronic
control system in India for SHP is not good.
v) Electronic digital flow control governors can take up plant control functions.
vi) Flow control turbine governors are expensive and not recommended for small hydro
units in micro hydel range. Electronic load control governing system with water cooled
hot water tanks as ballast loads for unit size upto 100 kW be used. This will make a
saving of about 40% on capital cost. If the thyristor control (ELC) is used then the
alternator needs to be oversized upto 2% on kVA to cope with the higher circulating
current included. Accordingly, in case of small units upto 100-150 kW size elimination of
flow control governors by digital shunt load governor (electronic load controllers) will
make these units economically viable and properly designed will eliminate continuous
attendance requirement.
viii) The dummy loads in the Shunt Load Governors (ELC) can be useful load system or
can be used for supplying domestic energy needs.
ix) Analog electronic governors and plant controllers are also used for small hydro auto
synchronizing and for remote control and monitoring of system.
x) Digital generation controllers were evolved to take care of speed control, unit control
and automation, unit protection and generation scheduling and have been successfully in
operation for over ten years.
xii) Dedicated PC based systems for complete generation control can be easily adopted
for data acquisition and storage at low cost and can also be adapted to SCADA system.
Customized software is used in these systems which inhibits wide spread use. Future
systems using PC as controller and for SCADA with open architecture and use of
commercially available software is recommended for economy and wide spread use.
1. Mech. Flow control Gov. 50-100 Iso. 9 At high extra cost Very high High without Not
SCADA recommendation
Grid 9
100-500 & Iso. 9
above
Grid 9
2. Load control governor 50-100 Iso. 9 Suitable At extra cost Low Low Not considered
Grid 9
Do not available
Digital load
100-500 Iso. See note 3 control governor
may be developed
Grid × Not feasible
for SCADA
3. Analogue, Electronic 50-100 Iso. Suitable At high extra cost Very high cost Not recommended
Gov. & Plant Controller Grid
Above 100 Iso. High Moderate to high
Grid
4. PLC integrated controller SHP 100 kW Iso. Suitable Low Moderate Recommended
with SCADA by PC to 5 MW
Grid
5. PLC digital governor with Above 5 Iso. Suitable High Moderate Recommended for
plant controller and MW See note 2 units above 5 MW
SCADA with redundant Grid
PC
6. Data Logger with PLC 5 to 100 kW Iso. Data not available Low Moderate Recommended
load controller Grid
7. PC based integrated 100 kW to Iso. Suitable – Indigenous system not available Low Medium Recommended with
system for governing; 2500 kW high speed PC
plant control protection suitable for harsh
and metering area
Grid
The control system can further be defined by identifying following three categories of
control:
Relationship of local centralized and off site control function as per IEC: (62270-2004)
guide in fig. 4 & 5.
USER
INTERFACE
SWITCHYARD
CONTROL
PLC
USER
INTERFACE
POWER HOUSE
Fig. 4
PROTECTION
SYSTEM
STATION
COMMUNICATION
LINK
PROCESS
COMPUTER PROCESS (UNIT,
BASED INTERFACE SWITCHGEAR
CONTROL GATES, ETC.)
LOCAL
USER
INTERFACE
BACKUP
CONTROL
Fig. 5
Hardware interconnectivity
Time stamping of data,
Communications
Operating system
User Interface
Data base
ii. Each of these elements should be capable of being replaced by or communicate with
system elements provided by other vendors.
iii. The scope of the bidder is not limited to the parts & components explicitly identified
here in and shall have to provide any and all parts/components needed to meet the
functional requirements laid down herein or are necessary for satisfactory operation
of the plant.
Local area networks (LANs) should be configured to IEEE 802.3 (Ethernet) standard.
The operator’s station of the station controller (SCADA system) should have an elaborate
and friendly man-machine interface. A 19” or larger monitor should be provided for the
display. Provision should be made for connecting a second colour monitor in parallel.
The screen displays should be suitably designed to provide information in most
appropriate forms such as text, tables, curves, bar charts, dynamic mimic diagrams,
graphic symbols, all in colour. An event printer should be connected to PC of the
SCADA system. Events should be printed out spontaneously as they arrive. Provision
should be made to connect and use another printer simultaneously. Touch control screen,
voice and other advanced modes of MMI are desired and should be preferred. The entire
customization of software for MMI and report generation should be carried out. A
window based operating system should be preferred.
i. Portability and the exchange of I/O cards from one I/O location to another. This
can reduce spare parts requirements.
ii. Availability of I/O cards to be replaced under power. This avoids the need to
shutdown an entire I/O location to change one card.
iii. Sequence-of-Events (SOE) time tagging at the I/O locations; accuracy and
resolution.
iv. Availability of I/O signal types and levels that support the field device signals to
be used.
v. Support of redundant field devices, capability for redundant I/O from field device
to the database and operator interface.
vi. I/O diagnostics available at the card, e.g., card failure indicating LEDs, or through
software in the system.
3.10 Grounding
Each equipment rack in which automation system components are located should be
separately connected to the powerhouse ground mat by a large gauge wire.
Shielded cables should be used for analog signals between the transducers and the
automation system. Each shield should be tied to the signal common potential at the
transducer end of the cable. If there are terminations or junction boxes between the
transducers and automation system, each shield circuit should be maintained as a separate
continuous circuit through such junction or termination boxes.
Information and control signal for proper control and monitoring will be acquired from
the following main and auxiliary/associated equipment and shall be provided as
tentatively detailed along with the equipment as out lined in this paragraph. Deviation
will be intimated in the bid 25% spare capacity for inputs and output shall be provided.
The control system shall receive input signals from main equipment such as the turbine
or the generator, and from various other accessory equipments, such as the governor,
exciter, and automatic synchronizer. Status inputs shall be obtained from control
switches, level and function switches indicative of pressure, position etc, throughout the
AHEC/MNRE/SHP Standards/E&M Works – Guidelines for monitoring, control, protection 18
and automation of SHP Oct. 2009
plant. The proper combination of these inputs to the control system logic will provide
outputs to the governor, the exciter, and other equipment to start or shutdown the unit.
Any abnormalities in the inputs must prevent the unit’s startup, or if already on-line,
provide an alarm or initiate its shutdown.
i. Generator
ii. Generator field excitation equipment
iii. Generator terminal equipment (Line and Neutral side)
iv. Unit generator breaker equipment
v. Turbine
vi. Governor
vii. Generator cooling
viii. Service air
ix. Service water
x. DC power supply
xi. AC auxiliary power supply
xii. Water level monitoring
xiii. Fire protection
Following four types of signals are provided between control board and particular
equipment
• Analog inputs for variable signals from CTs, VTs, RTDs, pressure, flow, level, vibration
etc.
• Digital inputs provides digitalized values of variable quantities from the equipment
• Digital outputs – command signals from control boards to equipment
• Analog outputs – transmit variable signals from control to equipment e.g. governor,
voltage regulator etc.
Following methods are available for implementing control from a remote location:
• Hardwired communication circuits (telephone type line, optical cables etc.)
• Leased telephone lines
• Power line carries communication system
• Point to point radio
• Microwave radio
• Satellite
Metallic circuit in hardwired communication circuits and leased telephone lines, requires
special protection for equipments and personals against ground potential rise (GPR) due to
Power line carrier including insulated ground wire system can be used for
communications purposes. This method couples a high frequency signal on the power line or
insulated ground wire and is decoupled at an offsite point.
Space radio can be used, utilizing power frequencies and micro wave radio can be
practical if hydro plant owner has an existing microwave system.
The communication link between control board and equipment should be reliable. Optical
fiber cable, shielded cable and Ethernet are various options
• Fire protection
• AC Power supply
• DC Power supply
• Service water
• Service air
• Water level monitoring
• Turbine flow monitoring
3.14.1 Control for micro hydro power plant (5KW to 100 KW)
Manual control and manual synchronization with ELC is recommended. However,
data logger with PLC load controller may also be provided. Recommendations of “Micro
hydel Standard issued by AHEC, IIT, Roorkee” are also to be reffered.
Integrated governor and plant control system are discussed in “Guidelines for selection of
turbine and governing system”.
PC based system for unit control, governor control and other functions provided for Sobla
SHP in Uttarakhand is attached as Fig.-6 is a cheaper alternative but lacks redundancy
which can be provided by spare cards for each type. The scheme envisages
installation of integrated generation controller, generator and line protection and metering
was however provided by conventional meters and electromagnetic relays as shown in
Fig.-6.
Most of the small powerhouses in the range have the control room at the same level as
the machine hall. Accordingly the unit control and supervisory control functions can be
provided in the control room.
One PLC integrated controller per unit may be provided for unit control, governor
control, plant control, supervisory control and data acquisition and remote control
provision AVR and measuring units and auxiliaries.
Remote/Supervisory control and data acquisition all the unit may be provided by one PC.
The recommended control system is shown in Fig. 7. Manual control facility is provided
on PLC panel.
Fig. 7 -Typical Configuration for Computerized Hydro Station (proposed for SHP)
Note-1 In case machine level and station level is same, manual/automatic control panel
be combined with unit PLC panel
ii) PLC integrated unit controller with PC for supervisory control data acquisition and
remote control facilities for Triveni canal fall SHPs with provision for remote control of
three nearby canal fall power plants have been shown in Fig.-8.
A typical block diagram of computer based control system for 2 x 10 MVA Mukerian
Stage–II power house with offsite control is shown in FIG.9. A provision for a
programming station with back up for operation is also included as redundant system.
The abnormal operating conditions that may arise should be detected automatically and
corrective action taken in a timely fashion to minimize the impact. Relays (utilizing electrical
quantities), temperature sensors, pressure or liquid level sensors, and mechanical contacts
operated by centrifugal force, etc., may be utilized in the detection of abnormal conditions. These
devices in turn operate other electrical and mechanical devices to isolate the equipment from the
system.
Where programmable controllers are provided for unit control, they can also perform
some of the desired protective functions.
Operating problems with the turbine, generator, or associated auxiliary equipment require
an orderly shutdown of the affected unit while the remaining generating units (if more than one
is in the plant) continue to operate. Alarm indicators could be used to advise operating personnel
of the changed operating conditions.
Loss of individual items of auxiliary equipment may or may not be critical to the overall
operation of the small plant, depending upon the extent of redundancy provided in the auxiliary
systems. Many auxiliary equipment problems may necessitate loss of generation until the
abnormal conditions has been determined and corrected by operating or maintenance staff.
The type and extent of the protection provided will depend upon many considerations,
some of which are:
(1) The capacity, number, and type of units in the plant;
(2) The type of power system;
(3) Interconnecting utility requirements;
(4) The owner’s dependence on the plant for power;
(5) Manufacturer’s recommendations;
(6) Equipment capabilities; and
(7) Control location and extent of monitoring.
Overall, though, the design of the protective systems and equipment is intended to detect
abnormal conditions quickly and isolate the affected equipment as rapidly as possible, so as to
minimize the extent of damage and yet retain the maximum amount of equipment in service.
Small hydroelectric power plants generally contain less complex systems than large
stations, and therefore tend to require less protective equipment. On the other hand, the very
small stations should be typically unattended and under automatic control, and frequently have
AHEC/MNRE/SHP Standards/E&M Works – Guidelines for monitoring, control, protection 26
and automation of SHP Oct. 2009
little control and data monitoring at an off-site location. This greater isolation tends to increase
the protection demands of the smaller plants.
An inherent part of the power plant protection is the design of the automatic controls to
recognize and act on abnormal conditions or control failures during startup. Close coordination
of the unit controls and other protection is essential.
Utility line faults and other abnormal utility system conditions should be detected and the
plant be disconnected from the utility system. Abnormal utility system conditions include the
following situations:
There are numerous ways of providing the functional protective requirements of the
plant. While standard devices are generally available that can provide the protective functions
The following section describes components of a typical protection system that might be
applied to a small hydro plant. Discussions and diagrams are included to illustrate location and
arrangement of relays.
Pressure and level switches installed in the turbine air and oil systems, to alarm, block
startup, or trip, as necessary.
Direct-connected or electrically driven speed switches for alarm, control, and tripping.
4.3.1.4 Vibration
Vibration detectors monitoring turbine or generator shaft sections, with alarm and trip
contacts.
A measuring system incorporating level sensors and monitoring equipment, to alarm, trip,
or control turbine output on limiting values of headwater or tail water level, or head.
4.3.1.6 Fire
Sensors located in areas where fire can occur and connected to a central fire monitor for
alarm. Small generators usually do not have fire sensors or suppression equipment, since they are
not usually enclosed.
Sensing devices are integral to the protected systems, such as automatic greasing system,
wicket gate shear pins, transformer cooling and station sump drainage system.
The protective relays stand watch and in the event of failures short circuits or abnormal
operating conditions help de-energize the unhealthy section of power system and restrain
interference with rest of it and limit damage to equipment and ensure safety of personnel. The
protective relays should possess following features:
• Reliability – To ensure correct action even after long period of inactivity and also to offer
repeated operation under sever condition.
• Selectivity – To ensure that only the unhealthy part of system is disconnected
• Sensitivity – Detection of short circuit or abnormal operating condition.
• Speed – To prevent and minimize damage and risk to instability of rotating plant.
• Stability – The ability to operate only under those conditions that calls for its operation
and to remain either passive or biased against operation under all other conditions.
Protective relay technology has changed significantly in recent years. Induction disk
relays for each individual protective function were normally used. Individual solid state static
relays for protective function were introduced in the decade 1980-1990 and IS 3231-1965 was
accordingly revised in 1987.
The old conventional electromagnetic relays were replaced with static relays which are
much faster and maintenance free. These relays are more reliable and sensitive. These days
microprocessor based multifunction relays are available which have different protections
elements and therefore, a separate relay for each protection is not required.
Microprocessor relaying has gained widespread acceptance among both utilities and
consumers. The relay functions are the same as those in electromechanical and solid-state
electronic relaying, but microprocessor relays have features that provide added benefits.
Microprocessor relays may have some disadvantages, however, so that there are additional
considerations when these are applied for protection in SHP.
Microprocessor relay also have communication capability that allows for remote
interrogation of meter and event data and fault oscillography. This also permits relay setting
from a remote location. The relays have low power consumption and low CT and VT burdens.
They also increase the flexibility of CT connections. For instance, microprocessor transformer
differential relays can compensate internally for ratio mismatch and the phase shift associated
with delta-wye connections.
All of these features have economic benefits in addition to the lower initial costs and
potentially reduced maintenance costs that microprocessor relays have when compared to
individual relays.
4.3.2.2.4 Disadvantages:
The operating energy for most electromechanical relays is obtained from the measured
currents and/or voltages, but most microprocessor relays require a source of control power.
Another disadvantage is that the multifunction feature can result in a loss of redundancy. For
instance, the failure of a single-phase over current relay is backed up by the remaining phase and
neutral relays. In a microprocessor scheme, the phase and neutral elements are frequently
combined in one package and a single failure can disable the protection. Similarly, a
microprocessor generator/transformer package that has both differential and over current
relaying provided less redundancy than a scheme comprising separate relays. The self-
diagnostics ability of the microprocessor relay, and its ability to communicate failure alarms,
mitigates some of the loss of redundancy. It may also be economical to use multiple
microprocessor relay.
Microprocessor relays require more engineering in the application and setting of the
relay though less work in the panel design and wiring. The increased relay setting flexibility is
accompanied by an increase in setting complexity that requires diligence to avoid setting errors.
The designer must balance the expense of applying a particular relay against the
consequences of losing a generator. The total loss of generator may not be catastrophic if it
represents a small percentage of the investment in an installation. However, the impact on
service reliability and upset to loads supplied must be considered. Damage to equipment and loss
of product in continuous processes can be dominating concern rather than generating unit.
Accordingly there is no standard solution based on MW-rating. However, it is rather expected
that a 100 kW, 415 V hydro machines will have less protection as compared to 25 MW base load
hydro electric machine.
Two level protections are recommended as per IEC 1116. Elements to be considered are:
Immediate tripping is required for a, c, i, and j. While for item b, d, e, f, g and h only
alarm and annunciation is required to alert the operator and take corrective action, but in case
corrective action is not taken, tripping will eventually follow. Applying brakes at a particular
speed (30% of full speed) is done to reduce time to achieve stand still position of machine.
It is recommended two independent devices must be provided for over speed shut down
on larger machines. One for alarm mostly at 110% and other for tripping at 140%, specially for
machines which are not designed for continuous run away speed.
a. Stator temperature
AHEC/MNRE/SHP Standards/E&M Works – Guidelines for monitoring, control, protection 33
and automation of SHP Oct. 2009
b. Over current (stator and rotor)
c. Earth fault with current limits (stators & rotor)
d. Maximum and minimum voltage
e. Power reversal
f. Over/ under frequency
g. Oil level in bearing sumps
h. Pad & oil temperature of bearings
i. Cooling air temperature
Immediate tripping is required for items b, c, d, e & f while for items a, g, h and i first
alarm and annunciation is required for taking correcting measure and then tripping if correcting
measure is not taken within permissible time.
4.5.1 Categorisation
In view of the economy and plant requirements generator protection for small
hydropower stations is categorized a follows:
Transient over-voltages and lightning surges are controlled by lightning arrestors. Surge
capacitors are provided to restrict rate of rise of surge voltages and their magnitudes. Every
generator is provided with a set of lightning arrestors / surge diverter of appropriate rating and
generated voltage.
Micro hydel (100 kVA) may be provided with series over current and short circuit
protection (MCCB), residual current breakers for earth fault protection and surge protection
equipment. A typical 50 kW micro hydel single line diagram showing protection is attached as
Fig. 10. MCCB could be provided with shunt trip coil for providing over voltage; over current
and unbalance load trip as a part of shunt load governor if possible.
27
81 H
81 L
LEGEND
R esidu al C u rren t
Op erated C ircuit B reaker
Controller
Module
Triacs
H eater Mod u le G
50 kW 415 V
Fig.-10.
4.5.4 Protection for Generating Units above 100 kVA and up to 5 MVA
Monitoring and protection with two levels of protection and recommended as follows in
SHP as per IEC-1116.
4.5.4.1 Turbine
Immediate tripping is required for items a), c), i) and j). Items b), d), e), f), g) and h) may
have an alarm annunciated first if the station is manned allowing corrective action to be
taken, but in any case, in the absence of corrective action, tripping will eventually follow.
In some cases, braking is used to reduce the time to standstill.
It is recommended that two independent over speed shut-down devices be used on larger
units which might not be designed for continuous runaway.
4.5.4.2 Generator
Immediate tripping is required for items (b), (c), (d), (e) and (f). Items (a), (g), (h) and (i)
may have an alarm annunciated if the station is manned allowing corrective action to be
taken, but in any case, in the absence of corrective action, tripping will eventually follow.
It is advisable to consider differential protection when the size of the generator and/or its
environment justifies it.
The instruments and devices generally recommended for monitoring and protection are
as follows: voltmeter, ammeter, wattmeter, energy meter, power factor meter,
tachometer, hours of operation counter, synchronizer, water-level and/or pressure
indicator, turbine opening indicator, emergency stop device, short-circuit current
protection, over current protection, reverse power relay, frequency monitor, voltage
monitor, bearing monitor.
Typical single line diagram for synchronous and asynchronous generators are attached as
figure 11 and figure 12 respectively.
Typical single line diagram for 2×2.5 MW SHP developed by M/S ANDREZ HYDRO is
shown in FIG. 13 for reference
4.5.5.1 Generator
Following additional back up electromagnetic relays from different set of CTs and PTs be
also provided.
A typical single line diagram of metering and relaying is shown as figure 13 and
figure 14.
//
/ P.T.
// / P.T.
59 -------- OVER VOLTAGE RELAY
63 -------- BUCHHOLZ RELAY
64F -------- ROTOR EARTH FAULT RELAY
64G -------- STATOR EARTH FAULT RELAY
PS CLASS FOR BUS
64T -------- BACKUP POWER SYSTEM E/F RELAY
PS CLASS FOR BUS
DIFFERENTIAL DIFFERENTIAL 87G -------- GENERATOR EARTH FAULT RELAY
87GT -------- GEN. TRANSFORMER E/F RELAY
CT CT 25 -------- CHECK SYNCHRONISING
CORE-1, 5P10 CORE-1, 5P10 46 -------- NEGATIVE SEQUENCE RELAY
CT CT
CORE-2, METERING CORE-2, METERING
ACC.CLASS 1-0 ACC.CLASS 1-0
52-3 52-5
LEGEND
331661132 kV BUS 52-6
ISOLATING SWITCH
HV CIRCUIT BREAKER
LINK
CT CT
TRANSFORMER
41G
EXCITATION BREAKER WITH
52-1
DISCHARGE RESISTOR
52-2
CURRENT TRANSFORMER
51 EARTH
87GT 87GT
11 KV BREAKER
DG SET
11 KV CIRCUIT 11 KV CIRCUIT
BREAKER 11-1 BREAKER 11-2
CT TO P.T.
CT TO P.T.
P.T. P.T.
41G
41G
GENERATOR-
G1 GENERATOR-2 G2
45G
PS CT PS CT
5P10 CT
5P10 CT
PS CT CT
PS
FIG. 2.3.1 TYPICAL SINGLE LINE DIAGRAM
DISTRIBUTION DISTRIBUTION
TRANSFORMER TRANSFORMER
GENERATORS
CT
NOTES 12 CENTRIFUGAL SPEED SWITCH
12G ELECTRICAL OVERSPEEDC RELAY
25 CHECK SYNCHRONISING RELAY
1.THE SCHEME MAY BE MODIFIED TO SUIT ACTUAL 26AU/AI AIR COOLER (OUTLET/INLET)
BREAKER EQUIPMENT ORDERED AIR TEMPERATURE
52-1
2.COMMON TRIPPING RELAYS FOR SIMILAR 26G TEMPERATURE DETECTORS FOR
FUNCTIONS WILL BE PROVIDED WITH LOCK FIRE PROTECTION SYSTEM
OUT FACILITIES, SIGNAL TYPE CURRENT 26GS STATOR WINDING TEMPERATURE
RELAYS FOR DISCRIMINATION OF FAULTS ARE
PROPOSED TO BE PROVIDED IN THE 32 REVERSE POWER RELAY
87T INDIVIDUAL CIRCUITS OF COMMON TRIPPING 33AB AIR BRAKE POSITION INDICATION
RELAYS . 33CW/80CW COOLING WATER VALVE POSITION/FL
64T
3.TRIPPING BLOCK DIAGRAM DOES NOT INCLUDE 38 BEARING TEMPERATURE DEVICE
63T FIRST STAGE ALARMS 38-2
5P10
4.DETAILS OF R.T.D. (RESISTANCE
TEMPERATURE 38GT GUIDE BEARING TEMPERATURE
CT
DETECTORS) ARE AS UNDER : 38QB BEARING OIL TEMPERATURE
(A) GENERATOR STATOR WINDINGS - 12 NO. 38THT THRUST BEARING TEMPERATURE
38T (B) GENERATOR THRUST BEARING - 2 NO.
87 GT (C) TURBINE GUIDE BEARING - 2 NO. 40 FIELD FAILURE RELAY
GEN.TRANSFORMER
50/51 5. UNIT-2 IS SAME AS UNIT-1 45F FIELD SURGE PROTECTION
CT 46 NEGATIVE PHASE SEQUENCE RELAY
PS 47 PHASE SEQUENCE CHECK RELAY
LINK (FOR SYNCHRONIZING)
48 INCOMPLETE SEQUENCE RELAY
C.T. 5P10 50/51 T TARNSFORMER OVERCURRENT RELAY
51V INSTANTANEOUS OVERCURRENT
250 kVA
WITH VOLTAGE RESTRAINTRELAY
11/.415 kV
TO 86 EB 11 KV 60 VOLTAGE BALANCE RELAY
11-1 GENERATOR 63 GOVERNOR LOW OIL PRESSURE SWITC
BREAKER 51/64
63FG FIRE EXTIGUISHING SYSTEM OPERATIO
87 GT 51 EX C.T. 63QTH THRUST BEARING HIGH PRESSURE OIL
SYSTEM START INTERLOCK/FAILURE A
RECTIFIER 63 T MAIN TANK OVER PRESURE SWITCH
TRANSFORMER 63 TX AUXILIARY RELAY
64G GROUND VOLTAGE RELAY - STATOR
25 64F ROTOR EARTH FAULT RELAY
47
TO P.T. 65SN SOLENOID SPEED NO LOAD
65SL SOLENOID SHUT DOWN
59 71QBH/L BEARING OIL LEVEL(HIGH/LOW)
THYRISTOR STATIC 86 EA LOCKOUT RELAY ELECT. GROUP "A"
BRIGES EXCITATION LOCKOUT RELAY ELECT. GROUP "B"
86 EB
SYNCH.
VOLTAGE
REGULATOR 86 MA LOCKOUT RELAY MECH. GROUP "A"
AND CONTROL 86 MB LOCKOUT RELAY MECH. GROUP "B"
87G GENERATOR DIFFERENTIAL RELAY
S.S.
FROM EXCITOR 2 87T TRANSFORMER DIFFERENTIAL RELAY
F F SYNCHRONISING
TO 86 EB EXCITERS
. VAR.COMP
L
SOCKET
L
27
V
31
41G
EXCITATION RELAY
GENERATOR FIELD BREAKER
FROM BATTERY
FLASHING
..
S.S.
LDC EX. V V
64F
86 EX
LCD
GROUND VOLTAGE RELAY - FIELD
LOCKOUT RELAY
LINE DROP COMPENSATION
FIELD
CONTROL
RUN INC OER OVER EXCITATION RELAY
.. S.S.
KWH
F F
PAR COMP PARALLEL COMPENSATION
METERING
.. S.S.
38THT
THERMOSTAT
R.T.D.
38QB
60
BLOCKS 50/51V
& 40 ON LOSS
OF RELAY
FM
KVAR
SYN
LINK 86 EA
TRIP 52-1 & 41 G
RELEASE CO2,
TURBINE SHUT
2
1
RESISTOR
RATED 15 SEC.
Whenever generators are running parallel to grid, a comprehensive auto synchronizing &
Grid islanding scheme will be required. This scheme will help in synchronizing the generator to
the bus and opening the incomer breaker of the plant whenever there is a severe grid disturbance,
thus protecting the generator from ill effects of disturbed grid.
• Grid disturbances
9 Under-voltage / Over-voltages
9 Under-frequency/Over-frequency
9 Rapid fall/ rise of frequency (df / dt),
9 Grid failure or other faults
Generator may not be able to operate below a certain power-factor. At low power-factor,
reverse reactive power flow may damage the generator.
Whenever more than one generator is operating in parallel, it is necessary to see that the
plant load is equally shared by the generators in parallel. If there is unequal sharing, there would
be sever hunting amongst the generators and eventually this will lead to cascaded tripping of all
generators, causing a total black out. Specific load sharing relays are available in the market
which provides the most effective, online load sharing system for generators in parallel.
The protective relays and devices of generator and turbine are proposed to be grouped
into following four categories for an orderly shutdown of the affected unit with the remaining
generating units and auxiliaries continue to operate.
Immediate action shut down will be initiated by any of the following conditions
1.0 INTRODUCTION
1.1 Purpose
This Guide is intended to assist in preparation of technical specification for
finalizing automation scheme for control, monitoring and data acquisition of a small
hydro power plant. The guide includes different type of control, control locations,
automation schemes, system architecture, system protocols, network protocols, type of
networks, PLC based, computer based SCADA system, user and plant interfaces, remote
control & power source etc.
2.4.2 Centralized
In this system controls for all units are brought to a centralized control room
located in the plant itself on control panels. Control of all important auxiliary equipments
are also brought to the control panels installed in the control room. All protection,
metering, synchronizing panel and outgoing lines control panels are located in this
centralize control room.
(i) This class uses proprietary hard wares and software and makes little or no provision for
interoperations with other hardware and software. These are called as closed systems
also.
(ii) The other system class is an integrated system, with all plant control and monitoring
components having a common data communication hardware & software structures.
These are the open systems which relates to its ability to replace hardware,
modify software and expand system capability without a wholesale reconfiguration of the
control system. Attributes of open systems are interconnectivity of hardware and
software, possibility of software and interoperability of application and system. From
practical point of view neither fully closed nor truly open system exists, rather a
combination of systems exist with some ability to communicate or function with other
systems.
Examples of applications and majors components of above two general system
classes along with traditional supervisory control system are as under:
(i) Traditional supervisory control system
These are hardwired supervisory control systems. Major components are:
• Master station
• Non programmable remote terminal unit.
(ii) Closed system
There are stand alone systems (proprietary, single function controllers) Major
components are:
• Proprietary controllers
• Proprietary operator’s console
(iii) Open System:
The application examples are:
• Hydroelectric plant controllers (systems)
• Large scale energy management systems,
• SCADA systems (Microprocessor based)
These software are normally available as part of turnkey automation system and as
such sometimes are called proprietary softwares.
These softwares provide flexibility and has many options. In such case owner
may have support from original vendor, other users or possibly other vendors. The most
common options are as follows:
(a) User configurable: The user has all the documents necessary to change the software
operation or to add new code that is linkable to the rest of the software. The user has
the ability to add features or change options, but can not change features in the
original code with out the help of original vendor.
(b) User programmable: The user has the source code as well as the documentation for
the software and can modify it as needed or implement his own software to be added
to the system.
(c) Full graphic: The user has the ability to generate pixels and / or vector graphic image
on the displays in any form. The software has sophisticated art work generation and
real time display of these images under system control. Often full graphics are
implemented in a window operating environment.
(d) On line configurable: The features mentioned can be done by authorized person
sitting in front of the online and running system. That is authorized person can change
the configuration of the running system as they wish.
6.0 NETWORKS
6.1 Control level data networks
Control data network are communication structures that conveys data through out
the system. These networks are used for transmitting time tagged measurements and
status input signals to update live databases. The application program outputs, consists
typically of control commands and alarms are then transmitted in turn, over the network
The control data network should be able to support transfer of long messages (e.g.
file transfer) as well as short messages for data acquisition, reporting and control
commands.
Power plant Engineer should be able to assess the current status of network, to
locate bottlenecks and other problems and to plan action accordingly.
The network should also be able to transmit specific diagnostic and maintenance
trouble shooting data for status display.
Hard wired system should be protected against ground potential rise (GPR), for
which proper shielding of cables is to provided while for fibre optic cables such
protection is not required. Field wiring however, should be protected such that a fault on
these cables does not cause loss of more than a minimum tolerable functionality of the
system.
With the advent of programmable logic controllers (PLC) number of wires needed
for connection is reduced by 80% which improved the reliability and availability of
functionality of the system.
• Star Topology
In a star topology such as Ethernet, each IED is connected to special node
at the centre that can be passive, providing a path for message to traverse or
active regenerating electrical signals. Hub simply repeat and message on all
ports. More intelligent hubs are switches which route the message to the port
where target IED is connected. The arrangement is shown in figure below:
HUB OR SWITCH
• Ring Topology:
In ring each IED is connected to next with entire network forming a closed
circle. Each IED is isolated from all but two IEDs. Ring networks are less
efficient because data travels through more IEDs before reaching the
destination.
Master slave and client server communications are similar. The biggest difference
is that generally there is one master, where as there can be multiple clients.
• Token Passing
Each IED acts as repeater of message called a token and each IED can be both a
master (requesting data from other) and a slave (sending requested data to other IED).
The token may contain some data that is copied by the receiver. If token contain no
data, then an IED can use it and fill in its information in the token.
PLC communication and some other control system use token passing scheme to
give command to IEDs along the bus.
B. 100 KW to 5000 KW
(i) 100 KW to1000 KW PC based integrated system for governing and plant
control
(ii)1000KW to 5000 KW PLC integrated controller and SCADA with PC
C. 5000KW and above PLC digital governor with plant controller and
SCADA with redundant PC
8.1 Conventional Control
The hardware need to perform above functions in a conventional centralized
hardwired control system which is generally similar to that used for individual local unit
control. This consists of equipment such as control panels with discrete control alarm and
indication devices, dedicated data logging, load and voltage control equipment and
anunciators. This equipment interfaces to the units in parallel to the local unit control or
through the local unit control board. Control circuits are with appropriate inter locks.
The computer system interfaces to the plant and to the conventional control
system via input / output (I/O) interface equipment suitable for operation in the harsh
power plant environment. This interface may be parallel to the hardwired control system
and may operate conventional hard wired control circuits.
There are various modification of these two basic schemes which depend on the
individual plant requirement and owners preference. The singe PLC system offers the
advantage of low cost and simplicity and is typically backed up by hard wired system.
With redundant PLC system back-up control and memory are provided by second PLC.
The advantages and disadvantages of both systems are given in following table.
For a single PLC scheme with a manual operated back up system it is usually
preferable to have and independent RTD (Resistance temperature detector) monitor and
annunciation panel functionally operative during manual operation of the unit. It is also
recommended in single PLC scheme, it may have redundancy for power supply in the
same PLC.
Redundant PLC for supervisory control only can also be considered in case it
meets the requirement of the system.
Modems with both dial out and dial in capabilities can be located in either PC or
PLC or both to provide offsite access to plant information. These modems may be
utilized to control the plant operation from a remote location.
For plants having capacity up to 1000 KW PLC having integrated governor and
plant control system with a PC is recommended while for plants having capacity more
than 1000 KW unit control PLC with SCADA is recommended.
The specification should define the acceptable time durations for each of the
above events in both normal leading and high activity loading scenario. Penalty should be
included in specification if vendor can not meet the response time defined. The computer
system response times should be verified at the factory acceptance test to confirm the
system will operate as required by specifications.
(v) Lockout
The controller should include a generator lockout function. Whenever the
lockout function is on it should inhibit the generator from starting. Any alarm
should be configurable as a lockout alarm. The lockout should be reset with a
command entered on the keyboard. When the lockout is on, it should be
displayed on the screen annunciator.
Screen data should be updated promptly whenever actual data changes. Alarm and
status information should be updated within one second of actual changes. Analog
data should be updated within two seconds of a change. Calculated value such as
All DC analog readings on the screen display should have configurable scale
factors. All except speed should have configurable labeling on the screen.
Data shown on the display should have the following minimum accuracies.
AC Voltage 1% of full scale
AC Current 1% of full scale
Frequency ± 0.005 HZ
DC Inputs 25% of full scale
KW, KVAR, PF 25% of full scale
Temperatures + 5 degrees C
The annunciator should display both alarms that are internally generated by the
controller and alarms that are sensed external to the controller. The controller
should be capable of generating a contact closure (option) on selected alarms for
use with a horn or telephone dialer.
(viii) Control status display:
The display should include an indication of the status of the turbine i.e., starting,
stopped, synchronizing, etc...
(ix) Automatic control status display:
The display should show the current automatic control mode, its set point, turbine
gate limit, and any overriding control modes.
(x) DT Keyboard:
The keyboard should be a standard keyboard with upper and lower cases, ten key
numeric pad and at least ten function keys. The function keys should be assigned
important functions.
The operator should be able to start and stop the turbine from the keyboard using
simple commands. The operator should be able to enter set points via keyboard,
(iv) Standardization
The software should reside in non-volatile EPROM memory, which should not
require reloading for routine power interruptions to the controller.
(v) Configurability
Configuring of the control software should be accomplished via a menu driven
user-friendly program that will be run on an IBC PC or compatible computer. The
configuring should be able to be accomplished at an area remote from the
controller and should not prevent operation of the controller during configuring
except during the transfer of the configuring information to the controller.
(vi) Functions
The software should allow the operator to examine and modify those parameters
of the control software that will specify the operating conditions and restrictions
of a particular plant. These features should include but are not limited to:
- Timings
- Decision paths
- Set points
- Equation coefficients
- Enabling functions
- Plant description information
The software should also allow for specifying particular contact inputs, analog
inputs and analog outputs. The software should allow user designation and titling
of contact inputs. Analog scale factors should be set via the configuring program.
(viii) Security
The configuring software should provide a means of preventing unauthorized
access to the configuring information. Further it should provide a means of
differentiating three or more security levels of configuring information to create
three or more depths of configuring accessibility.
(i) Physical
The equipment should be constructed on a modular basis, using plug-in
connection. The controller should be suitable for mounting in a standard 19-inch
wide rack, with a minimum depth of 24 inches. Input/output termination cabinets
should be internally labeled, to permit ready identification of the incoming and
outgoing wiring. The equipment should be of self protecting against surges that
may be generated on power supply bus by contact operation, circuit resonance,
etc. External connections should utilize modular screw terminal blocks which
should be should be suitably mounted and readily accessible. Each terminal
device shall suitably identify all conductors. All wiring should be clearly marked
and so designated on the drawing to permit identification for maintenance. Wire
not colour coded should be identified by a wire number marker on each end. All
cables and jacketing material should be oil, moisture, and heat resistance
thermosetting compounds under operating conditions. Controller AC power
connection should be a standard NEMA PI5-5 plug configuration.
(ii) Environmental
The controller and video display should be capable of withstanding the
environmental conditions of the site of plant during air condition failure.
(iii) Power Requirements
The controller should use standard wall outlet AC power, however an inverter
should be supplied that is powered from the station battery to provide AC power.
The controller including VDT, DTC, printer, and modem other peripheral
equipment should operate from a 250 VA inverter.
In order to make the system acceptable to the operations personnel, care must be
taken in the selection of the hardware and software used. The hardware options are
numerous for input and output devices as well as the workstations to be used.
9.2.1 Types
Examples of plant interfaces include analog transducer signals, dry contacts (i.e.,
contacts without sensing voltages) and digital data. This clause covers several generic
types, however, installations may have special application requirements to meet unique
concerns. This discussion addresses the analysis process for any plant interface.
Contact bounce in the input signal can cause erroneous data in the system. Digital
inputs should have filters to detect only sustained input signals. These filters may be in
the hardware or the software. Filters must be selected in accordance with time tag
accuracy. Simple low-pass filters can introduce undesirable delays. Voltage levels for
logic detection should be sufficient to prevent erroneous readings.
Digital inputs may also serve the functions of pulse accumulators or counters.
This function is normally in software or firmware at the I/O. Accuracy, counting, and
pulse accumulation rates should be sufficient for the intended use.
Another variety of digital inputs comes in the form of a parallel (e.g., binary
coded decimal) data. The quantity of wire conductors, noise immunity, and hand shaking
requirements should be considered when making accommodations for these inputs.
Digital input status indicators, often LEDs, may be provided. These indicators
ease I/O and control circuit troubleshooting.
Where higher current ratings are required, interposing relays are typically
installed. The current ratings are then those of the interposing relays.
The failure state of digital outputs should be defined and specified. Digital output
failure may be critical in some applications.
The I/O is often capable of providing the loop power supply for analog inputs.
Voltage, tolerance, stability, and loading should be considered.
9.2.2 Sources
The sources of information to be interfaced to control systems are numerous and
not all are covered in this clause. The most common ones are highlighted, as follows:
a) Digital Input Signal Monitoring.
Usually accomplished by sensing the state of relay contacts using the station
battery or a voltage supply to detect the opened or closed status of the contact.
The output devices are normally solid-state or electromechanical relays that are
energized or de-energized by the control system.
b) Analog Input Devices.
Normally transducers that convert potential transformer (PT) and current
transformer (CT) signals to quantities such as megawatts or megavars. In existing
plants, control system analog outputs may drive display panels or strip chart
recorders for operator observation.
c) Parallel Input Devices.
Usually shaft encoders or digital panel meters. The output devices are digital
panel meters or process controller modules. These interface sources are in many
cases bidirectional, i.e., they are both input and output devices.
d) Serial Sources.
Normally bidirectional devices with built-in intelligence, providing both input and
output capability. The devices consist of smart watthour meters, shaft encoders,
temperature transducers, etc.
For items of 1 & 2 arrangements of special protection for equipment and personnel
against ground potential rise & lightening surges are essential.
It is seen that optical fiber cable, PLCC, Satellite communication links are the most
preferred options as these are more reliable.
In case one side contacts is connected to power source from station battery, the
automation system should provide electrical isolation between the inputs to prevent sneak
paths between inputs when either side of the battery is disconnected from one of them.
The characteristic of each output point supervised should be determined. The old
break trip circuits, speed level motors require high level inductive current to be switched
as such output circuits must be capable of reliably switching this current through out the
life of automotive system alternatively interposing auxiliary machine tool type relays can
be used on such outputs.
11.4 Grounding
Each equipment rack of automation systems is required to be separately
connected to the power house ground mat. During power system fault conditions, a large
potential rise can occur between different locations with in power house due to large
current flowing through ground.
In case of large power stations two sets of batteries of full required capacity are
required to make availability of D.C. more reliable.
UPS of proper capacity are preferred for SHP as these require less maintenance
and are considered more reliable.
Uninterruptible Power Supply System in SHP are required to provide electricity for
computerized control and data acquisition system, communication system etc. when
normal plant power system fail. As per IEEE: 944 – Recommended practice for
application and testing of uninterruptible power supplies for power generating stations;
UPS systems are used to provide electricity for essential loads when normal plant power
system fails. Loss of power to such loads as the plant computers, communication
networks, security system and emergency lights.
DC BATTERY (48/110V)
FUSE
FLOATED BOOST
CHARGER
AC FROM
STATION
SERVICE
D.C. BUS
TO COMPUTER
CONTROL SYSTEM
FEEDER
MCB BREAKER TO
EMERGENCY
SUPPLY
UPS SYSTEM
D.C. FEEDERS
AC-220V FROM
STATION SERVICE
UPS system is defined as one designed to automatically provide power without delay or
transient during any period when normal power supply is in capable of performing
acceptably.
Symbol Description
21 Under Impedance
24 Over Fluxing
26 Field Winding Temp
27 Under Voltage
27NT 100% Stator E/F
32 Reverse Power
38 Bearing Temp
40 Loss of Field
46 Negative Phase Sequence
49 Stator Winding Temp
50BF Breaker Failure
50P Instantaneous Phase Over Current
50N Instantaneous Neutral Over Current
50/27 Unintentional Energisation at Stand Still
51P Time Delayed Phase Over Current
51N Time Delayed Neutral Over Current
51N Voltage Controlled Over Current
59 Over Voltage
59N Residual Over Voltage
64R Restricted E/F
78 Pole Slipping Protection
81 Over/ Under Frequency
87G Generator Differential
CTS Current Transformer Supervision
VTS Voltage Transformer Supervision
STANDARDS/MANUALS/
GUIDELINES FOR
SMALL HYDRO DEVELOPMENT
Electro-Mechanical Works–
Selection of Auxiliaries for SHP Stations
May 2011
CONTENTS
1.0 GENERAL 1
2.0 GENERAL CONSIDERATION FOR SELECTION OF
ELECTRICALAND ECHANICAL AUXILIARIES 1
2.1 General Design Considerations Electrical Auxiliaries 1
2.2 General Consideration for Mechanical Auxiliaries 7
3.0 ELECTRICAL AUXILARIES 9
3.1 Auxiliary Power Supply System 9
3.2 D.C. Auxiliary Power System 14
3.3 Uninterruptible Power Supply System (UPS) 19
3.4 Power and Control Cables 20
3.5 Lighting System 26
3.6 Grounding System and Lightning Protection 30
3.7 Communication System 32
3.8 Transformer Oil Purifier 34
4.0 MECHANICAL AUXILIARIES 34
4.1 E.O.T. Crane 34
4.2 Cooling Water System 34
4.3 Dewatering and Drainage System 36
4.4 Compressed Air System 38
4.5 Fire Protection System 40
4.6 Ventilation and Air Conditioning 49
4.7 Water Level Sensing 54
Guide for Selection of Auxiliaries
for SHP up to 25 MW
1. GENERAL
Electrical and mechanical unit and station auxiliaries integrity is important for successful
operation of hydro station. Major considerations for selection and provision of auxiliaries
in SHP station are: i) economic viability, ii) lack of skilled operators iii) unattended
operation. Provision and selection of auxiliaries in SHP upto 25 MW capacity is
discussed as follows:
a) Selection of auxiliaries and system for SHP above 5 MW and upto 25 MW unit
size
b) Auxiliaries for SHP above 100 kW to 5 MW
c) Micro hydels upto 100 kW
All component of the electrical items of Works of the auxiliary systems should be of
reliable design.
The equipment should be suitable for the prevailing climatic conditions and insensitive
to any signals emitted by wireless communication equipment.
Clearances: The layout of the equipment in the power house should provide ready access
for operation and maintenance whilst the remaining sections of equipment are alive.
Working clearance provided between isolated equipment and nearest live metal work should
be as per Indian Electricity rules & Standards.
2.1.1 Electrical Supplies for Auxiliary Equipment: The electricity supplies available
for various auxiliary equipment are :
(i) 415 V, ± 10%, 3-phase 50Hz, 4-wire for A.C. power supply,
(ii) 230 V, ±10%, single phase, 50 Hz for lighting, indication, and anti-condensation
heaters,
(iii) DC for essential indication, controls, protection, alarms and circuit breaker closing
and tripping supplies, emergency power supply system
(iv) UPS system for computerized controls and SCADA
2.1.2 Alternating Current Supply Practice: All mains supplies should be through
MCBs of appropriate rating. Double-pole switches should be used to break single-phase
A.C. mains supplies. For multi-phase supplies, each phase should be switched simultaneously
and the neutral should preferably not be switched.
2.1.3 Direct Current Supply Practice: Power supply bus bars in cubicles should be
carefully routed and each bus bar should be shrouded. It should not be possible to
inadvertently short bus bars either between themselves or to earth. It should be possible to
remove/replace cards from/to electronic equipment without damage and without interfering
with the operation of the rest of the equipment or system.
2.1.4.1 General: All motors should conform to IS 325 induction motors with suitable
eyebolts. AC motors should have squirrel cage type rotors. The insulation of all the
motors should be of class F but temperature rise during operation should be limited to
class B insulation. It should be suitable for operation in damp locations and for occasional
contact with corrosive gases/vapors.
2.1.4.2 Ventilation and Type of Enclosure: All motors should be of the totally
enclosed fan-cooled type, protection class IP 54 according to IEC Recommendation 144.
Cable termination points should be of class IP55. Vertical motors should be provided
with a top cover to prevent the ingress of dirt and droplets etc.
2.1.4.3 Terminal Boxes and Earthing: The terminals, terminal boxes and associated
equipment should be suitable for terminating the power cables. The terminal boxes should
be of ample size to enable connections to be made in a satisfactory manner. For earthing
2.1.4.4 Motor Voltages and Power Ratings: The service voltages and corresponding
power ratings for electric motors to be used should be as follows:
Motors up to 1 kW
− Service voltage : single-phase a.c. 240 V, 50 HZ
− Mode of starting : condenser
Motors above 1 kW and up to 75 kW
Service voltage : 3-phase a.c. 415/240 V, 50 HZ
Mode of starting : direct-on-line up
Motors intended to work on the D.C. System
− Service voltage : As per battery voltage
− Mode of starting : resistor
2.1.4.5 Rating: The rating of the motors should be adequate to meet the requirements of
its associated driven equipment. The service factor, being the ratio of the installed motor
output to the required power at the shaft of the driven machine at its expected maximum
power demand, should be applied as follows:
A.C. motors should be capable of operating continuously under rated output conditions
at any frequency between 95% and 105% of the rated frequency and/or with any volt-
age variation between 90% and 110% of the nominal voltage. A transient over voltage
of 130% of the nominal voltage should be sustained.
The motors should be capable of maintaining stable operation when running at 70%
nominal voltage for a period of 10 seconds. The pullout torque for continuously loaded
motors should be at least 160% of the rated torque and for intermittently loaded motors
200% of the rated torque.
D.C. motors should be capable of operating continuously under rated output conditions
at any voltage between 90% and 110% of the nominal voltage with a fixed brush setting
for all loads. The speed drop between no-load and full-load should not exceed 10% of
no-load speed.
2.1.4.6 Starting: A.C. motors should be designed for direct on-line starting. They
should be capable of being switched on without damage to an infinite busbar at 110% of
the nominal voltage with an inherent residual voltage of 100% even in phase opposition.
For starting the motors from the individual main and auxiliary busbars, a momentary
voltage drop of 20% referred to nominal voltage should be taken into consideration. With
85% of the nominal voltage applied to the motor terminals, each motor should be capable
of accelerating its associated load to full speed with a minimum accelerating torque of 5%
of full load torque.
The maximum starting currents (without any tolerance) should not exceed the following
values:
Generally, all motors should be able to withstand five cold starts per hour, equally
spaced. Each motor should be capable of withstanding three successive starts under the
same conditions or once every fifteen minutes without detrimental heating. Motors for
frequent automatic starting should have an adequate rating.
2.1.4.7 Bearings
As far as possible, the motors should have sealed ball or roller bearings lubricated for
life. All other motors with ratings of about 1 kW and above should be equipped with
lubricators permitting greasing while the motor is running and preventing over-lubrica-
tion. Additionally, the bearings should be fitted with grease nipples permitting the use
of a universal grease gun. Vertical motors should have approved thrust bearings.
The terminal leads, terminals, terminal boxes and associated equipment should be suit-
able for terminating the respective type of cables as specified in these General Tech-
nical Specifications and in the Particular Technical Specifications.
2.1.4.9 Noise-Level and Vibrations: Under all operating conditions, the noise level of
motors should not exceed 75 dB (A) at any place 1.0 m away from operating equipment.
All motors should be statically and dynamically balanced. The vibration amplitude
should not exceed values specified in IS 4729.
2.1.4.10 Tests: Each motor should be factory tested and should undergo a test at site. The
following tests should be performed under full responsibility of the Contractor.
Workshop Tests :
A.C. motors should be designed for direct on-line starting. They should be capable of
being switched on without damage to an infinite busbar at 110% of the nominal voltage
with an inherent residual voltage of 100% even in phase opposition. For starting the
motors from the individual main and auxiliary busbars, a momentary voltage drop of
20% referred to nominal voltage should be taken into consideration.
With 85% of the nominal voltage applied to the motor terminals, each motor should be
capable of accelerating its associated load to full speed with a minimum accelerating
torque of 5% of full load torque.
Motor starters and contactors should be equipped with short circuit protection and local
disconnecting devices. The control circuit voltage should be obtained from a 415/240 V
isolating transformer with primary circuit breaker and secondary fuse. The secondary
winding of this transformer should be grounded. The operating coils of the contactor
should be connected between the grounded side of the transformer and the control
contacts.
Starters and contactors should comply with IEC 292.1 or National Electrical
Manufacturer Association USA standard NEMA IC 1 and be suitable for direct on-line
starting, uninterrupted electrical duty, and capable of 30 operations per hour. They should
be installed in ventilated enclosures for indoor installation and weatherproof enclosures
for outdoor installation. The enclosures should be complete with locks, cable sealing
boxes, conduit entries, cable gland plates, bus bars, internal wiring, terminal boards, etc.
as required by the duty of the starter.
Thermal type overload and phase failure relays should be supplied with starters for
motors of 7.5 kW or greater. For motors of less than 7.5 kW, suitable rated 3-phase
thermal overloads may be provided. Ammeters to read current in one phase should be
provided for motors above 7.5 kW.
All moulded case circuit breakers should be of 2 or 3-pole type as required, with requisite
short time rating having thermal time delay and instantaneous trips with "On-Trip-Off",
indicating/operating mechanism. Circuit breakers used in combination type motor starters
or contactors should have the operating mechanisms interlocked with the starter or
contactor cover so that the cover cannot be opened unless the circuit breaker is open.
Cubicles and control panel enclosures should be of sheet steel with minimum thickness of
1.5 mm, vermin proof, rigid self-supporting construction and supplied with channel bases.
Cubicles should be fitted with close fitting gasketted and hinged doors capable of being
opened through 180 deg. The doors of all cabinets/panels should be provided with similar
integral lock.
Design Criteria
Shielded cables should be provided for the control and supervisory equipment where
required.
Each gauge, pressure switch and transmitter for absolute or differential pressure should
be equipped with a pressure gauge isolating valve including a test connection of the
screwed type M20 x 1.5 mm so that such device can be removed without any distur-
bance of the plant operation. If the pressure is pulsating, the devices concerned should
be connected via flexible tubes or other pulse-absorbing means.
The liquid level measurements in reservoirs and tanks with atmospheric pressure should
be made by means of capacitance measurement type. The errors should not exceed ±
1.0% of the total measuring range.
All Electrical instruments should be of flush mounted design, dust and moisture-proof.
A.C. ammeters and voltmeters should have digital type system of not less than 1.5
accuracy class. D.C. measuring instruments should also be digital type of the same
accuracy. Wattmeters should be suitable for unbalanced systems and accuracy of energy
meters should be of 0.2 % accuracy class.
When more than one measured value is indicated on the same instrument, a measuring
point selector switch should be provided next to the instrument and should be engraved
with a legend specifying each selected measuring point.
All instruments mounted on the same panel should be of same style and appearance.
Limit switches should be mounted suitable for easy adjustment and for rigidly locking
in position after being adjusted. They should be of heavy-duty rating and have two
changeover contacts suitable for station DC voltage operation.
2.2.1 General
Bolts, Screws, Nuts etc.: All bolts, studs, screws, nuts, and washers should be as per
ISO metric system. Mild steel bolts and nuts should be of the precision cold forged or hot
forged type with machined faces parallel to one another. All bolts and studs which will
be subject to high stress and/or temperature should be of high tensile material with nuts of
appropriate material.
Fitted bolts should be a driving fit in the reamed holes and should have the screwed portion
of a diameter such that it will not be damaged during driving. They should be properly
marked in a conspicuous position to ensure correct assembly at site.
All parts (other than structural steel work) bolted together, should be spot faced on the
back to ensure that nuts and bolt heads bed down satisfactorily. Mild steel nuts and bolts
should be zinc or cadmium plated. Stainless steel bolts, nuts, washers and screws should
be used for holding renewable parts in water or when exposed to high humidity.
Seals : Rubber seals should be made of synthetic rubber suitable for particular application
and should be designed in such a manner that they are adjustable, water tight and readily
replaceable. Seals should be manufactured by molding process and not extruded. All
adjusting screws and bolts for securing the seals and seal assembly should be of non-
corrosive stainless steel.
Oils and Lubricants : Different types of oils, lubricants, etc. should be subject to the
written approval of the Engineer. Unless otherwise stated in the Particular Technical
Specifications, the oil or grease for bearings, pressure oil systems, transformers, etc.,
including the necessary quantity for flushing and quantity for first oil change with 20%
extra should be obtained.
General : All required piping should be furnished complete with flanges, joints,
expansion joints, gaskets, packing, valves, drains, vents, pipe suspensions, supports, etc.
Flanged joints or connections should be provided only as required for transport,
installation or for dismantling and reassembly. Standard metric flanges and connections
should be used for all pipe works. Adequate clearance should be given to parallel pipes
to allow for easy maintenance without disturbing other lines. All overhead piping
should have a minimum clearance of 2.1 m from operating floors and platforms.
Materials of Pipes & Fittings : Water, air and drain piping less than 25 mm nominal
bore should be of galvanised heavy grade to IS-1239, Part-I or equivalent standards steel
pipe. Pipes equal to or greater than 25 mm nominal bore should be galvanized heavy
grade to IS-1239, Part I/IS-3589 or equivalent.
Oil piping greater than 25 mm nominal bore should be of seamless high quality steel pipe
conforming to IS 1239 or API-5L GR.B or equivalent grade as per process requirement,
whereas pipes less than 25mm bore should be of stainless steel.
Steel pipes of diameter 100 mm and above for a pressure upto PN 10, may be used in
welded type. The minimum wall thickness of pipes should be the "normal" or "standard"
wall thickness as per applicable standards.
Pipe Work Fabrication: Steel pipe work smaller than 25 NB and for operating pressure
more than PN 10 should be joined by screwed fittings and pipe work for 25 NB and over
should be joined by welded flanges. Pipe work for operating pressure upto PN 10 may be
joined by screwed fittings upto 50 NB size. Tig welding must be used for fabricating pipe
work.
Pipe work Cleaning: Oil pipe work internal bores should be chemically cleaned and
passivated prior to use.. Water, air and drain piping should be blown through with high
pressure air and flushed with water prior to use.
Pressure Testing: All pressure piping should be pressure tested at a pressure 50% greater
than maximum operating pressure after erection and cleaning but before painting at site. The
test pressure should be maintained without loss for half an hour.
Painting: All steel piping should be painted on the exterior to prevent rusting. The paint
treatment should be of the same system as used for the turbine exterior. Colour coding of
pipe work should be adopted as per applicable Indian Standard. Paint damaged during
erection and commissioning should be repaired prior to handing - over the plant.
Protection for Transport and Storage: Oil piping should have a protective coating
applied to prevent corrosion occurring during transport and storage. The ends of the pipe
lengths should be plugged to prevent ingress of water.
Valves & Gates: Generally, valves should be leak-proof in either flow direction
(except for non-return valves) when the nominal pressure is applied. All valves with
design pressures higher than PN 10 and diameters larger than DN 100 should be
workshop-tested for tightness and soundness of materials. Valves should close
clockwise and be provided with position indicators/marks on hand wheel. The drive
units of motor-driven valves should also be provided with hand wheels for manual
operation. To facilitate operation, large valves and gates should be provided with by-
pass lines for pressure balancing, if required. Valves spindles and pins should be of
stainless steel, spindle nuts and bushes of bronze, the body of cast steel. No valve in
cast iron body will be accepted.
Miscellaneous Metalwork
3. ELECTRICAL AUXILIRIES
3.1.1 General
Station service power supply system capacity includes supply of power to following
• Unit and station auxiliaries i.e. governor oil pumps, cooling water pumps,
transformer cooling fan, sump pumps, air compressors, battery chargers,
ventilation and air conditioning equipment
• Dam/weir byepass etc. auxiliaries
a) Station service power supply system should have a minimum of two full capacity
redundant power sources
b) Service should not be interrupted by system disturbances.
c) Service continuity be maintained under all conditions.
d) There should be provision for starting the station from cold.
e) First cost, maintenance cost and operating cost should be low.
f) Safety of personnel, simplicity of operation and ease of maintenance be ensured.
g) Provision of black start in emergency
h) Source of Power
3.1.3 Auxiliary Power Supply System for SHP Interconnected with the Grid
The design of the auxiliary power supply system of small hydroelectric power plants may
vary significantly depending on consideration of a combination of factors including, but
not limited to :
A Single Power Supply System : This is recommended for a single unit plant non-
critical plant whose loss of generation can be tolerated, and which would suffer no harm
due to loss of auxiliary systems. A typical single line diagram is shown in figure 3.1.
When the unit is feeding power into the power system, it also feeds plant ac station
service. If the generator in Fig. 3.1 is out of service, station service can be fed from the
transmission line. If the main transformer is out of service, station service may be fed
from the generator, with the isolating switch open, provided the generator is synchronous
type and hydraulic conditions permit stable operation at low loads.
The flexibility for restoring auxiliary ac supply can be of prime importance if there are
critical loads that must be energized quickly. Examples of such loads are sump pump,
spillway gates, and headgate motors. The need for rapid restoration of station service
power may justify a stand-by source such as a small diesel engine generator or a separate
feed from the utility.
Multiple Auxiliary Supply System : In the case of plants with multiple auxiliary
supplies, the single line diagram would typically be as in fig.3.2 (Mukerain Stage-2).
Emergency power supply is obtained from grid s/s at Dasuya. Figure 3.3 shows Auxiliary
power supply for Dhoba SHP in Bihar, where two units are shown feeding station service.
The second supply could alternatively be obtained from a separate utility connection
AHEC/MNRE/SHP Standards/E&M Works – Guide for Selection of Auxiliaries for Page 10
SHP up to 25 MW
rather than a second generator. Another possibility for station service supply is by
provision of an emergency generator connected to the plants distribution system. The
station service supply configuration will depend on the degree of reliability of station.
For Micro hydel auxiliary power refers Micro hydel standard issued by AHEC.
The power supply and control cables should be laid up to the common terminal blocks.
Various control/protection devices and instruments should be uniform, interchangeable
and connected as per system requirement.
TO TRANS LINE
MAIN
TRANSFORMER
SWITCH OR
SOLID LINK
STATION
SERVICE MAIN
BREAKER
STATION SERVICE BUS
FUSE DISC 5W
STATION
SERVICE
TRANSFORMER
GENERATOR
BREAKER
GENERATOR
D7 D 11
D6 D 10 D 13
SPARE SPAR E C UR R EN T TRAN SFOR MER
D12
D8 NOTE
1 BR EAKER S D 1, D2, D 3 SH ALL N OR MALLY B E 'ON '
SPARE
GEN . IN TER LOCK B R EAK ER D 8 SH ALL B E PR OVID ED SO AS TO AVOID
B LOW ER D E- H UMID IFYIN G B LOW ER GEN . PAR ALLELIN G OF UN SYNC H R ON ISED SOU RC ES
SPAC E
HEATER S EQUIPMEN T SPACE
TU R B INE B EARIN G H EATERS
TUR B IN E B EAR IN G 5 W H EN D3 IS OFF D 5 W ILL B E ON W H EN D1 IS OFF D 4
LU BR IC ATIN G LU B R ICATIN G
PU MP W ILL B E ON
C ON TR OL CON TR OL PU MP
POW ER POW ER 6 ALL CIR C U IT B R EAK ER S AR E AIR B R EAK , D R AW OU T TYPE
SUPPL Y SUPPLY AN D FITTED W ITH SER IES OVER LOAD AN D
IN STANTAN IOUS SHOR T C IR C UIT PR OTEC TION
UNIT DISTRIBUTION BOARD-1 UNIT DISTRIBUTION BOARD-2 7 TH E D R AW IN G IS TEN TATIVE ON LY FOR TEND ER
PU R POSE
D9 R EVISION 1 - N OTE
C HAN GES IN IN TERLOC K IN G AND N OTES 2 TO 5
DR AF T IN LET SPARE D RAIN AGE AIR COMPR - A/C AND POW ER SPARE
VEN TILATION
CAN AL TU BE GATE D EW ATER ING PU MP ESSOR
SYSTEM
DR AINAGE OU TLET LIGHTIN G IN LET D RAFT
C AN AL
H OIST LIGH TIN G PUMP TU B E
P/H CRANE
HOIST PU MP B ATTER Y CK T. GATE
P/H CRANE
LIGHTNING ARRESTOR
CURRENT TRANSFORMER
Vs V MCCB
DG SET
60k W
MCB
CONTACTOR
5P10,10V A 50/51 64
CT 120/1-1A
CL0.5,10VA k Wh As A
Vs V
G-2 G-2
INTERLOCK ACB
200A 400A,45k A
CONTACTOR
400A,45kA LT BOARD
M CCB
GROUNDING GROUNDING
TRANSFORM ER TRANSFORM ER
UNIT-2 UNIT-2
(SAME AS UNIT-1) (SAME AS UNIT-1)
All Works should be suitable for the prevailing climatic conditions and insensitive to
any signals emitted by wireless communication equipment.
3.1.5.2 Switchgear
The high voltage switchgear in power station for 3.3, 6.6 and 11 kV is almost universally
specified as air-break switchgear. High degree of safety of air-break switchgear, suitable
performance characteristics and high degree of availability combine to make it so
acceptable for the job. The fire fighting equipment can therefore be dispensed with.
Further absence of current chopping reduces the overvoltages in the system and
minimizes outages due to insulation failures. Withdrawable type, cubicle mounted,
solenoid operated from the battery is usually specified to be provided. A total opening of
approx. 5-8 cycles is usually satisfactory for protection of equipment and for maintenance
of system stability under fault conditions.
Epoxy cast/resin encapsulated air cooled transformer are recommend. These can be
located inside the powerhouse. Oil filled auxiliary transformer will be required to be
placed in outside switchyard alongwith main transformers requiring long cables; fire
protection arrangements etc. for fire hazards.
Standards
3.2.1 General
Direct current system in hydro generating stations and step up sub station is one of the
most crucial electrical system in a hydro plant because it provides power to critical
controls, protective relays and uninterruptiopn power system (UPS) associated with
computers that control plant operation and is provided for following functions.
a) Supply to trip coils and closing coils of switchgear for switching operations.
b) Indication: Indicating lamps, facial, semaphores, alarm and annunciation etc. For
energizing the holding and operating coils in control and interlock schemes, and
in protection schemes.
c) Supervisory control and data acquisition system (SCADA)
d) For power supply to communication equipments
e) Emergency lighting
The system consists of a storage battery with its associated eliminator type chargers,
providing the stored energy system required to ensure adequate and uninterruptible power
for critical power plant equipment. The battery and battery circuits should be properly
designed, safeguard maintained, and the requirements should be carefully estimated to
ensure adequate battery performance during emergencies.
AC supply from station service or generator leads can be used for this purpose if the cost
of DC system cannot be justified.
3.2.2.1 Type
Table 3.2.1 list commonly used battery types and their normal expected life, approximate
number of full discharges, ampere-hour range, approximate cost range, frequency of use,
advantages and disadvantages. Latest applicable Indian standard specification mentioned
in the table 3.2.1 and be referred for confirmation.
Type of battery or batteries generally used in hydro generating stations are of the lead-
acid type in vented cells or a sealed cell.
Following types of lead acid batteries are commonly used in power plants.
Plante positive plate batteries are costly and preferred for large hydro station above 5 MW
as they have longer life and these cells are suited for applications requiring supply of
large currents for short durations as required in unattended stations whereas the cells with
tubular positive plates are suitable for the supply of smaller currents for medium to long
durations. Use of glass containers is preferable over the other types as these facilitate
checking up of sedimentation, electrolyte level, condition of plates, separators etc.
3.2.3 Standard
Each battery should have a static battery charger, rated to fully recharge the battery from a
completely discharged condition in not more than ten (10) hours in boost charging mode.
Each battery charger should be capable of float charging the batteries while supplying at
normal voltage. Voltage regulators shall have following facilities.
(a) Manual selection facility for battery charging mode i.e. whether trickle or boost.
A separate room with lockable doors provides adequate protection against accidental
contact or malicious tampering. The room or area should be ventilated in such a manner
that exhaust air from the room does not enter any other room in the plant. If necessary,
heat should be provided to obtain full rated performance out of the cells. The cells should
be mounted in rows on racks permitting viewing the edges of plates and the bottom of the
cells from one side of the battery. The tops of all cells should preferably be of the same
height above the floor. The height should be convenient for adding water to the cells.
Tiered arrangements of cells should be avoided. Space should be provided permitting
removal of a cell from its row onto a truck without reaching over any other cells. The
lighting fixtures in the room should be of the vapor-proof type, with the local control
switch mounted outside by the entrance to the room. Battery charging equipment and
controls should not be located in the battery room.
At plants smaller than 3 MW, a ventilated battery room is not always required except for
a flooded liquid electrolyte (lead acid) battery, because the small ampere-hour size means
that the battery produces a minimal amount of hydrogen gas during charging.
Furthermore, typically only qualified personnel (usually the operators) have access to the
powerhouse. Therefore, a separate battery rooms is not required.
For very small SHP and micro hydel station AC may be used.
Rated voltage of the DC control supply for electrical installations can be selected out of
the fairly standardized values of 110, 48 and 24 volts. Higher voltage leads to more
economical configurations as the total load of the DC system, lengths of circuits and
number of DC cables increases. Usually 110 V turn out to be the optimum choice for SHP
above 3 MW capacity. For smaller plant 48 V may be provided. For micro hydels
interconnected with grid –12V UPS system may be sufficient for emergency lighting and
PC.
The voltage of a lead acid cell being 2 volts per cell, the number of cells in the battery
would be half of the rated DC voltage adopted.
Selection of a one-or two – battery system will depend not only on comparative costs of different
battery sizes and combinations, including circuits and charging facilities, but consideration of
maximum dependability, performance, and flexibility during periods of plant expansion.
a) CBI & P Technical Report No. 79 entitled specification of sub station battery, charging
equipment and DC switchyard.
b) IEEE 485 – IEEE recommend practice for sizing lead acid batteries
i) Momentary loads
• Continuous load
• Emergency light load: Duration of light load may be required for duration of 1 –
12 hours. Modern computerized control system require uninterruptible power supply (UPS)
system and emergency power is supplied from these UPS system (see Para 3.5).
For hydro stations the following durations are assumed for computation of battery capacity (as
per CBI &P Manual) for attended stations.
Standard rack performance criteria should be evaluated to ensure compliance with plant
requirements. Seismic considerations and other factors may dictate the need for special racks and
special anchoring needs.
Static charger sets are preferred for battery charging service. Two sets should be provided so one
will always be available. The charger capacity should be sufficient for float operation as well as
boost charging capability.
This term applies to the method of operation in which battery remains connected to the load and
the charger continuously. Voltage of charger is substantially constant and just higher than open
circuit voltage of the battery. To keep the battery in a fully charged condition, the charger sends
through the battery charging current of a few mili amperes at a voltage which is sufficient to
compensate for local action and leakage losses. The magnitudes of the charging current and the
voltage should be recommended by the battery suppliers. The charger also supplies the entire DC
load under normal condition.
3.2.13 DC Switchgear
For reliability and flexibility, a dc distribution board with several outlets is preferable as this
board provides connection of battery and charger to the various load circuits. Each circuit beaker
is protected by a fuse and controlled by a switch or circuit breaker which should be suitable for
making and breaking inductive loads at voltages upto the maximum floating voltage and not
merely the rated voltage. Cartridge fuses are recommended to be used as back up even when
circuit breakers with protective releases are installed. The breakers and fuses should be carefully
chosen from the consideration of recovery voltage after interruption of faults. The fuses where
used should be properly coordinated to ensure operation even for the farthest faults and each
circuit should be properly segregated. The dc switchgear should have short circuit rating equal to
about 10 times the maximum rated current if the associated equipment, without the current
limiting feature on, and about 1.1 times, with the current timing feature ‘on’. However, with the
available standard dc switchgear usually having much higher short circuit ratings (4 kA), the
above requirement poses no problem.
3.2.14 A typical single line diagram with single battery system is shown in Fig. 3.3 which can be
used on smaller unit. Fused disconnecting switch may be used instead of circuit beakers. For
larger unit above 5 MW 2 batteries may be provided.
Uninterruptible Power Supply System in SHP are required to provide electricity for
computerized control and data acquisition system, communication system etc. when normal plant
power system fail. As per IEEE: 944 – Recommended practice for application and testing of
uninterruptible power supplies for power generating stations; UPS systems are used to provide
electricity for essential loads when normal plant power system fails. Loss of power to such loads
as the plant computers, communication networks, security system and emergency lights.
FUSE
FLOATED BOOST
CHARGER
AC FROM
STATION
SERVICE
D.C. BUS
TO COMPUTER
CONTROL SYSTEM
FEEDER
MCB BREAKER TO
EMERGENCY
SUPPLY
UPS SYSTEM
D.C. FEEDERS
AC-220V FROM
STATION SERVICE
UPS system is defined as one designed to automatically provide power without delay or transient
during any period when normal power supply is in capable of performing acceptably.
On line static (solid state) UPS system with sine wave output are required. An off line system
take about 25 ms for transfer to DC which may impair critical control by computer system.
Normal range of sizes for hydro plant upto 25 MW uninterruptible power supplies is given
below:
Standards
IEC: 60502 Extruded solid dielectric insulated power cables for rated voltages from
1.00 kV up to 30 kV.
AHEC/MNRE/SHP Standards/E&M Works – Guide for Selection of Auxiliaries for Page 20
SHP up to 25 MW
IEC: 60331 Fire resisting characteristics of electric cables.
IS: 1554 (Part-1) PVC insulated (heavy-duty) electric cables for working -1988
voltage up to and including 1100 V.
IS: 1554 (Part-11) PVC insulated (heavy-duty) electric cables for working 1988
voltage from 3.3kV up to and including 11 kV.
IS: 7098(Part-11) Cross-linked polyethylene insulated PVC sheathed cables 1985
for working voltages from 3.3 KV up to and including 33 kV.
IS: 3961 Recommended current ratings for cables.
IS: 8130 -1984 Conductors for insulated electric cables and flexible cords.
IS: 5831- 1984 PVC insulation and sheath of electric cables.
A. The cables should be suitable for installation in a tropical monsoon area having a hot
humid climate. The reference ambient temperature to be considered for the purpose of
this specification is 500C (depend upon site).
B. The derating factor for the various conditions of installation including the following
should be considered while choosing the conductor size:
C. The allowable voltage drop at terminals of the connected equipment should be maximum
1.0% at full load for choosing the conductor size. In case of squirrel cage induction
motors, the cable size should be so chosen that the motor terminal" voltage does not fall
below 90% of the rated voltage, at the time of starting, if the motor is started with a
D.O.L. starter.
D. The maximum continuous conductor temperature and the maximum allowable conductor
temperature during short circuit are taken as 700C and 1600C respectively in case of PVC
insulated cables and 900C and 2500C respectively in case of XLPE insulated cables.
E. The minimum size of all 11 kV grade power cables and 415 V power cables connected to
circuit breakers are chosen taking into account the following factors.
G. The cables should in general comply with the requirements of the latest revision of
IS:7098 (part-11) for the 11 kV grade XLPE insulated cables and IS-1554 (part-1) for the
L.T. PVC insulated power and control cables or the relevant IEC Standard. The design,
manufacture, installation, testing and performance of the cables, should comply with the
latest revisions of IS/IEC/ NEMA/ASTM standard.
H. For 11 kV cables, conductor screen and insulation screen should both be extruded semi-
conducting compound and should be applied along with XLPE insulation in a single
operation by triple extrusion process. Method of curing for 11 kV cables should “Dry
curing/gas curing/steam curing". 11 kV cables should provided with copper metallic screen
I. Calculations should be made for selection of cables showing type of cable and conductor
size selected voltage drop, temperature rise, under rated load and short-circuit conditions,
to meet the design requirement.
J. Cable schedule showing the various interconnections and also the routing diagram giving
details of various openings are requirement to be prepared.
K. For the sake of reliability, it is required to use only copper conductor cables for the
following services :
i. Generator- Generator transformer/ Bus Bar connections (used in small hydro plants) should
be by armoured power cables of copper conductors with unearthed grade EPR insulation
Non PVC jacket HD – HOFR (high density, heat, oil and flame retardant.
The cable should be 11 kV grade, heavy duty, stranded, aluminium conductor, XLPE
insulated, provided with conductor screening and insulation screening, galvanised steel
wire/strip armoured, flame retardant low smoke (FRLS) extruded PVC of type ST 2 outer
sheathed.
The cable should be 1.1 kV grade, heavy duty, stranded aluminium conductor, PVC type.
An insulated galvanised steel wire/strip armoured, flame retardent low smoke (FRLS)
extruded PVC of type ST1 outer sheathed. Cables may be either single or multi-core or
both.
The cable should he 1.1 kV grade, heavy duty, stranded copper conductor, PVC type-A
insulated galvanised steel wire/strip armoured, flame retardant low smoke (FRLS) extruded
PVC of type- ST1 outers, sheathed Cables may be multi-core; depending upon the circuit
requirements or both.
Size of control cables should not be smaller then:
The complete cable support system should enable proper laying of all power, control,
instrumentation and telephone cables, and should provide necessary mechanical protection,
ventilation and segregation for them. All hardware and anchoring arrangement should be provided.
All steel members should be hot dip galvanised.
Cabling from powerhouse to hydro-mechanical equipment e.g. intake and draft tube gates and gates
for power & control from power house. Power and control panels to control panels of hydro
mechanical equipment should be properly provided.
Design
General requirements
No sub zero level cable vault/trenches should be provided below control building/switchgear rooms
in main plant and switchyard areas.
Interplant cabling for main routes should be laid along overhead trestles/duct banks/directly buried.
However, for tap-offs, same can be through shouldow trenches. Directly buried cable, if essential,
should not have concentration of more than four (4) cables. Cables in switchyard area from main
plant to switchyard control room are laid in duct bank/cable trenches. In switchyard area, cables are
laid in RCC concrete trenches.
Cable entry from outdoor underground/cable routes to the buildings, if any should be above the
finished floor level inside the building. PCC flooring of built up trenches should be sloped for
effective drainage with sump pits and sump pumps.
a) support system for cable Prefabricated out of sheet steel and fully galvanised flexible type
trays consisting of channels, cantilever arms and associated brackets &
hardware, installed at site by bolting or clamping. These should be
rigid enough to withstand max. possible loads during and after
installation.
b) Type of cable trays Cable trap for power cables are perforated. Separate trays are
provided for control instrumentation cables.
c) Material of cable trays Rolled mild steel, min. 2 mm thick for trays and 3 mm thick for
coupler plate.
d) Finish of cable trays Hot tip galvanised.
e) Duct banks (if provided) Heavy duty GI pipes/heavy duty PE pipes (10% spare of each size,
subject to min 1) with suitable water-proof manholes. For corrosive
areas, pipes should have anti-corrosion coating both inside &
outside.
f) Pipe size Suitable with 40% fill criteria
Junction and Pull boxes Hot dip galvanised sheet steel of 2 mm thickness.
Cable glands Nickelchromium plated brass, heavy duty, single compression type
for unarmored, and double compression type for armoured cables
conforming to BS: 6121.
Cable lugs Solderless tinned copper crimping type. For HT cables, lugs should
be as per DIN 46329/IS
HT cable terminations and Proven design and type tested as per VDE 0278. Elastimold or
joints equivalent fully insulated moulded terminations are preferred.
Cable Laying
a) Identification tags for To be provided at all terminations, on both sides of wall or floor
cables crossing, on each conduit/duct/pipe entry/exit, and at every 20 m in
cable trench/tray or buried run.
b) Cable tray numbering To be provided at every 10 m and at each end of cable way &
branch connection.
c) Joints Joints for less than 250 m run of cable should not be permitted.
d) Buried cable protection With concrete slabs; Route markers at every 20 m along the route
& at every bend.
e) Road crossings Cables to pass through buried RCC hume pipes.
f) Transformer yard Handling RCC trenches to be filled with sand after cable laying
area
g) Separation At least 300 mm between HT power & LT power cables, LT
power & LT control/instrumentation cables.
h) Segregation All cables associated with the unit should be segregated from
A. Cables should be laid on overhead cable trays and supports, pulled through conduits/GI
pipes and on racks in built up cable trenches and vertical race ways and clamped with
aluminium clamps on walls, ceiling and structures and may be directly buried in ground.
B. Cable laying should include termination of power and control cables (i.e on both ends of
the cables), at equipment terminals, switchgear, control panels etc. All electrical
equipments after installation are completed with cable terminal boxes, cables glands,
cable trays, lugs and terminal blocks.
C. All power and control cables are provided with aluminium tag of an approved type,
bearing cable reference. Cable routing is done in such way that cables are accessible for
any maintenance and for easy identification. Power and control cables are laid in
separate cable racks/trays, power cables being on upper most racks/trays. Asbestos sheets
are laid beneath power cable where they are running over control cables
F. Buried cables are avoided as far as possible but if necessary it is covered with alternate
layer of bricks and sand for mechanical protection. Steel markers are provided at every
20 meters along the cable route.
H. All cables laid on trays/racks are neatly dressed up and clamped/tied to the tray/rack.
Suitable Trefoil clamps are provided for single core cables.
Galvanising
Angles, flats, channels, hangers, brackets clamps, nuts, bolts and other anchorage material are
used for the installation of cables, cable trays, race ways and conduits. All steel members are
suitably treated and galvanised or painted with 2 coats of approved paint.
A comprehensive illumination system should be provided in the entire project i.e. all areas within the
plant boundary. The system should include lighting fixtures, distribution boards, lighting panels,
junction boxes, lighting poles, receptacles, switchboards, cables and wires, conduits, poles and
masts, etc. The system should cover all interior and exterior lighting such as area lighting, yard
lighting, street lighting, security lighting, etc.
3.5.2 Standards
3.5.3.1 General
The illumination system should be designed on basis of best engineering practice to facilitate normal
operation and maintenance activities as per IS: 3646 part-II and should ensure uniform, reliable,
aesthetically pleasing, glare free illumination. The design should prevent glare/luminous patch seen
on VDU screens, when viewed from an angle.
Table 3.5.3.1 gives the recommended values for different parts of power house and switchyard.
Table 3.5.3.1: Recommended Illuminator Values
SI. No. Particulars Average illumination level Limiting Glare Index
'Lux'
1. Control rooms:
Vertical control 200 to 300 19
panels 150 19
Rear of control panels 300 19
Control desks 150 25
2. Battery room 100 -
3. Carrier room 300 -
4. Offices and reception 300 19
5. Cloak rooms 100 -
6. Workshop/Repair bay 300 25
7. Test room 450 19
8. Outdoor switchyard 20 -
9. Stairs 100 -
10 Corridors 70 16
11 Approach roads 20 -
12 Pathways 20 -
Out door switchyard average illumination level shall be 50 lux on main equipment and 20 lux on balance
area of switchyard. In the out door switchyard, the area covered by transformer/reactor should have 50 lux.
3.5.3.2 The lighting system of a particular area whether outdoor or indoor should be designed in
such a way that uniform illumination is achieved. As far as possible any dark spots should be
avoided. This requires careful placing of the luminaries, selection of proper mounting heights and
provision of sockets in the marshalling kiosks and mechanism boxes of circuit breakers/disconnect
switches for providing supplementary lighting wherever required. In outdoor switchyards, only the
equipment/bus bar areas are illuminated. In outdoor area, luminaries should be directed as far as
possible towards transformers, circuit breakers/disconnect switches, their mechanism boxes etc.,
where some operations may be necessary during emergency at night.
3.5.3.3 There are several classifications of the types of lighting such as direct, indirect, semi-
indirect, diffusion, etc., The types of lighting or the combinations should be so chosen as would
provide adequate level of glare-free illumination without creating undesirable shadows.
3.5.3.4 Direct lighting system is the most commonly used and it employs open dispersive reflectors,
silver glass reflectors and angle reflectors. The simplest form of general diffusion fitting is the plain
sphere of opal glass. The spherical form may be modified and any form, which the designer can
think of may be used. The efficiency of the general diffusion fitting depends partly on shape but
much more on the properties of the diffusing material used.
3.5.3.5 The choice of lamps, i.e., incandescent, fluorescent, mercury vapour, sodium vapour
halogen etc., depends mainly on the nature of work, the number of hour of utilization annually, the
cost of energy and the power available for illumination. Table 3.2 gives different types of lamps and
fittings that may be used in different area of a substation.
3.5.3.6 Flood light fittings are in essence, projectors with parabolic reflectors. There are two types
of floodlights: the wide beam type and the narrow beam type. Wide beam type is suitable where
accurate control is not necessary and the light is projected only over a short distance. The harrow
beam type is used where light is required to be projected over longer distances.
3.5.3.7 The foremost criterion in the design of illumination system of indoor area such as control
room, workshop, repair bay, offices, etc., is that illumination at the working height throughout the
area should be as uniform as possible so as to avoid eye fatigue. In practice, complete uniformity of
illumination is difficult to achieve and a ratio of the minimum intensity to the maximum equal to
about 70 percent is usually nsidered acceptable.
3.5.3.8 Energy conservation requirement. has to be kept in view while selecting type of lamp and
type of fitting. While designing the lux level requirement Utilization coefficient factor may be
considered to take care effect of dust, pollution etc. on reflectors used in the lighting fixtures.
The night time lighting of exterior areas is necessitated by operational requirement, security or
decorative purposes or a combination of these. It is used for illuminating outdoor switchyards
transformer yards, approach roads to substations, etc., Use of flood lights has been in practice for
illumination of switchyards. However, floor lights generally cause glare, if not properly positioned
and mounted at proper heights. As the lumen output of mercury/sodium vapour lamps is quite
appreciable as compared to incandescent lamps, flood light units having mercury/sodium vapour
3.5.3.9 The purpose of street lighting in substations is to promote safety and convenience on the
approach roads, service roads and side walls inside switchyard, etc., The aim should be to provide
conditions of visibility adequate for accurate, certain and comfortable seeing.
Power supply should be fed from 415/240 V normal ac power supply, station service board, and
UPS system for emergency lighting. Lighting panels should be located at different convenient
locations for feeding various circuits. These panels should be robut in construction with lockable
arrangements and MCB for different circuits.
All outdoor fixtures should be weather proof type. Fluorescent fixtures, installed in other than
control room areas should have electronic ballasts. For control rooms, the ballasts should be copper
wound inductive, heavy duty type, filled with thermo-setting insulating moisture repellent polyester.
All luminaries and their accessories and components should be of the type readily replaceable by the
available Indian makes. All fixtures and accessories should be of reputed make and non-corrosive
type. Acrylic covers/louvres should be of non-yellowing type.
The constructional features of lighting distribution boards should be similar to AC/Dc distribution
boards described elsewhere. Outgoing circuits in PLS should be provided with MCBs of adequate
ratings.
Wiring should be by multi-stranded PVC insulated colour code cable laid in GI conduits. Wiring for
lighting circuits of ac, and dc systems should be run in separate conduits throughout. Minimum size
of the wire should not be less than 1.5 sq.mm copper. Wire should conform to IS: 694 and wiring
installation should be as per IS: 732.
Conduits should be of heavy duty type, hot dip galvanised steel conforming to IS: 9537. In corrosive
areas, conduits should have additional suitable epoxy coating.
At least one 5/15A, 240 V universal socket outlet should be provided in offices, stores, cabins, etc.
15A 240 V ac industrial type receptacles should be provided strategically in all other areas. All these
receptacles should be 3 pin type and controlled with a switch. Suitable numbers of 63 A, 3 phase,
415 V ac industrial type receptacles with control switches should be provided for the entire plant for
welding purposes, particularly near all major equipment and at an average distance of 15 m. At least
one 63 A receptacle should be provided in each off-site building.
Suitable number of ceiling fans in areas not covered by air-conditioning and ventilation system
should be provided.
Street lighting should be with swaged/steeped tubular steel poles of swan new construction. The
poles should be coated with anti-corrosive treatment and paint.
Area lighting should be with suitable lighting masts. Masts of adequate height should have lattice
structure with ladder, cage and top platform. Alternatively they should have lantern carriage of
raise/lower type with electrical winch provided inside the tubular mast.
Earthing system consisiting of ground mat and equipment earthing. The grounding conductor
consists of galvanised mild steel trips for ground network and mild steel rounds for ground rods and
shall be designed as per IS: 3043 and IEEE: 80. Earthing system network/earthmat shall be
interconnected mesh of mild steel rods buried in ground in the plant. All off-site areas shall be
interconnected together by minimum two parallel conductors.
All steel structures should be duly earthed. Metallic sheaths and armour of all multicore cables
should also be earthed at both equipment and switchgear end.
Earthing connections with equipment earthing pads should be bolted type with at least two bolts, and
joint surfaces should be galvanised. The connections should be painted with anti-corrosive paint
after testing and checking.
Neutral of power transformers should be directly connected to two rod electrodes in treated earth
pits, which in turn should be connected to station earthling grid.
The earthing terminal of surge arresters and voltage transformers, and lightning protection down
conductors shall also be connected to station earthing grid through separate rod electrode.
Two 20 mm dia GI rods or 40 mm dia pipe may be provided. For details refer micro hydels
standard.
3.6.4 Lightning Protection
The lightning protection system should be designed as per IS: 2309. It should cover all buildings and
structures in the plant, and switchyard areas. It should comprise horizontal/vertical air terminations,
down conductors, test links and earth connections to the station earthing grid. All conductors should
be of minimum 25x6 mm size and should be of galvanised steel only.
The down conductors of lightning protection system should have a test joint at about 1500 mm
above ground level. Each down conductor should be connected to a 40 mm dia, 3 m long mild steel
earth electrode as well as station earthing grid.
The lightning protection system should not be in direct contact with under ground metallic service
ducts and cables, and should not be connected above ground level to other earthing conductors. All
joints in the down conductors should be of welded type.
Hazardous areas handling inflammable/explosive materials and associated storage areas should be
protected by a system of aerial earths as per IEEE: 142.
i) Voice communication
ii) Dedicated communication system for SCADA, circuit types of line protective relaying
and telemetering etc.
Communication between the central or distributed processor and the to other computer system
(remote control stations) is a main function in system performance. Fibre optic cable is preferred
because of fast transmission speed best noise immunity. In case of difficult terrain – radio
communication can be considered.
In larger powerhouse or these controlling remote stations or a group of stations internal telephone
system may be provided.
Selection of communication media for transmission lines interconnecting powerhouse with grid can
be chosen based on site limitation cost etc. Fibre optic cable is preferred.
Voice communication between powerhouse and interconnected receiving station may be PLCC;
radio frequency; communication; Landline (leased) based telephone line or mobile network based
dedicated line.
The contractor shall furnish detailed design and calculation for approval by purchaser.
Govt. regulatory requirement and sanctions for the communication system shall be obtained by
Contractor. Necessary assistance will be provided by Purchaser.
An electronic telephone exchange suitable for 10-15 subscribers should be provided in the
powerhouse above 3 MW. The subscribers shall be located at various vulnerable positions to
facilitate the communication. Standard PVC cables should be laid for these subscribers. Some of the
important locations for subscribers may be as follows.
i) Control room
ii) Switchgear room
iii) Turbine pit
iv) Machine hall
v) Unloading/erection bay
vi) Cable spreading room
vii) Drainage/dewatering motor starter panel
viii) Switchyard
ix) Compressor room near switchyard.
x) Fore Bay
xi) Bye pass gates control room
xii) Pump house
xiii) Security gates
xiv) Offices
For small transformer portable transformer oil purifier may be provided for cluster of nearby
powerhouses as feasible.
4. MECHANICAL AUXILIARIES
Cranes are used in the power house for operational function and for maintenance and repair.
Power house bridge crane (electrical over head traveling crane EOT) is the principal overhead
traveling crane for turbines, generators and auxiliaries in typical surface power house.
The crane comprises of main hoist consisting or one or more cranes with combined capacity to
lift the heaviest assembly of the generating units. An auxiliary hoist of much lower capacity is
provided for handling smaller parts.
Number of Cranes: The choice of providing one or two cranes with a lifting beam is an
important consideration in power house because of following reasons especially in power house
with large number of units (generally 5 units or more).
In small hydro stations for the range under discussion only one crane is sufficient.
Crane Capacity: Crane capacity is SHP is based conventionally on estimated load -weight
heaviest part to be lifted with about 25% overload capacity. The rated load capacity of the main
hoist should be capable of lifting the heaviest assembly specified and not less than weight of the
generator rotor assembly including poles, shaft and turbine runner.
Standard: IS: 3177 – 1999 –Code of practice for Electrical Overhead Traveling Cranes and
Gantry Cranes
IS: 807 – Structural design of crane
For very small powerhouses, manual monorail hoist may be used. In micro hydel range EOT
crane is not provided. Erection may be done by chain pulley block, mobile crane or manually.
EOT Cranes Specification – Refer guidelines for E & M works entitled ‘specification for
procurement of auxiliary for SHP.
(i) The water flow requirements are determined by generator and turbine suppliers but are
dependant on water supply temperature and should take into account extremes in climate
conditions for the site. Flow requirements are usually large and require dependable
sources. Purity requirements are moderate permitting non potable supplies with limited
silt content.
ii) Gland and wearing ring requirements are obtained from turbine supplier. Quality
requirements are nominal requiring the removal of abrasive material.
iii) Transformer Cooling: Most plant in the SHP range under discussion utilize air cooled
transformer.
4.2.2 Sources
(1) Spiral Case – For units with heads upto about 75 m, the preferred source of cooling water is
a gravity supply from an inlet in the spiral case spiral case extension. In multiunit plants, an inlet
is provided for each unit with a crossover header connecting all units to provide a backup water
supply to any one unit. Cross-overs between pairs of units only are not regarded as adequate
since there would be no emergency source from an unwatered unit. The spiral case source is
usually satisfactory for unit bearing coolers, as well as the generator air coolers, and can be
adequate for gland and wearing ring use with proper filtering and adequate head.
(2) Tailwater – For higher head projects, above 76 m, the usual source of cooling water is a
pumped supply from tailwater. This normally provides water of essentially the same quality as
the spiral case gravity system.
(3) Other sources – It is unlikely that other suitable sources will be available or required for
cooling requirements, but alternate sources should be considered for gland requirements. Silt or
other abrasive material is usually present in varying degrees in reservoir water, at least
seasonally, and since abrasive material is injurious to glands, an alternate source or additional
treatment is usually required. The potable water system is normally the best alternate if the
supply is adequate or could be economically increased. This would usually be in the case of a
tube well supply requiring little chlorination. Where potable water is used, cross connections
from the cooling water source, with backflow protection, should be provided for emergency use.
Normally the cooling water supply should provide a minimum of 68.9-kPa differential across the
connection to the individual cooler headers. Available gravity head, cost of a pumped supply,
and cost of coolers all enter into an optimum cooler differential requirement and require early
design consideration to assure a reasonable figure for the generator and turbine specification.
Gland and wearing ring differential head requirements should be obtained from the turbine
supplier.
4.2.4 Treatment
Water for coolers, glands, and wearing rings will normally require only straining or filtration.
This should be verified from operating experience at nearby existing plants on the same stream.
Where existing plants are remote or the project is on a previously undeveloped stream, a water
analysis should be the basis of determining the likelihood of corrosion or scale deposits and the
need of additional treatment. Typical strainer requirements for coolers permit 3-mm
perforations, but strainer specifications for existing projects should be obtained as a guide to
complete design requirements. Strainers should be the automatic type unless the system provides
other backup provisions for continuous water supply or the p. h. is small. Unnecessarily fine
4.2.5 Pumps
A pumped cooling water supply requires a standby supply for a pump out of service. This can be
provided with two pumps per unit, each of which is capable of supplying cooler requirements, or
one pump per unit consisting of a common pump discharge header to all units and one or more
backup pumps. Other arrangements to provide backup capacity may also be acceptable. Pumps
should be located such that flooded suctions occur at minimum tailwater. Continuously rising
pump performance curves are required, and the pump should not exceed 1,500 rpm.
4.2.6 Piping
i) Design considerations for piping include, velocity, pressure loss, pumping costs,
corrosion allowance, equipment connection sizes and requirement, mechanical strength,
temperature, expansion etc. .
ii) Water takeoffs from the spiral case or the spiral case extension should be within 30 deg
of horizontal center line to minimize debris and air.
iii) A valve should be located as close to the casing as practicable for emergency shutoff.
iv) Balancing valves should be located in cooler supply lines.
v) A removable 0.9-m section of straight pipe should be provided in the generator bearing
supply line for temporary installation of a flow meter.
4.3.1 General
The Dewatering system provides the means for dewatering main unit turbines and their
associated water passages for inspection and maintenance purposes. Drainage system provides
for the collection and disposal of all powerhouse leakage and wastewater other than sanitary. The
safety of personnel and plant is of vital concern in this system and should have continuing
priority throughout the design. It may be noted that following type of turbine will not require
dewatering arrangement because they are set above maximum tail water level and can be
accessed without dewatering.
a) Impulse turbine
b) Vertical Kaplan/Francis turbine with siphon intake
General. The principal volumes to be dewatered in all powerhouses are the spiral case and draft
tube. In addition, there is usually a considerable volume down stream of the headgates or the
penstock valve.
Dewatering Procedure. Normal procedure after unit shutdown requires: closing of the
headgates or penstock valve; drainage of all unit water above tailwater to tailwater elevation
through the drain; and spiral case or spiral case extension drain; placement of draft tube gates or
stoplogs; and draining the remaining unit water to sump with the sump pumps operating.
Dewatering Sumps. Sump provision in most projects require either joint usage in both the
dewatering and drainage systems, or separate sumps with the dewatering sump serving as a
backup or overflow for the drainage sump. Sumps should be designed for maximum tailwater
head.
Dewatering Pumps. Two dewatering pumps should be provided. Dewatering pump capacity
should permit unwatering in 3 hr or less of pumping time with total capacity divided in two
pumps of the same capacity. Either pump used alone should be capable of accomplishing the
dewatering. Since unit dewatering will not be scheduled under powerhouse design flood
conditions, rated dewatering pump discharge should be for a maximum planned tailwater under
which dewatering will occur.
Pumps of the deep well water lubricated type are normally used. Submersible motor and pump
combinations units mounted on guide rails permitting the pump units to be raised or lowered by
the powerhouse crane have also been used.
Generally float-type controls are used for pump control. Automatic lead-lag with manual
selection of the lead pump is provided.
The drainage system handles three general types of drainage as follows: rain and snow water
from roofs and decks, leakage through structural cracks and contraction joints, and wastewater
from equipment. Discharge is to tailwater either by gravity or by pumping from a drainage sump.
Roof and Deck drainage should normally be directly to tailwater by gravity. Drainage of water
sprinkler fire protection system if used should be included in the drainage system in the design.
Float Drainage: Drainage galleries should be provided for float drainage and conduits and pipes
connecting the trenches to the drainage sump should be provided.
Oil Storage or Purifier Rooms: Oil Storage or Purifier Rooms provided with water sprinkler
fire protection system should have chilling drain with a gravel pocket of sufficient capacity to
handle the sprinkling system flow.
Battery Room: Battery room floor and sink drains should be of acid resisting material, have a
minimum 2% slope.
Miscellaneous Area Floor Drains: Miscellaneous floor areas i.e. turbine room, galleries,
machine shop, toilet rooms etc. where leakage rainwater water from disassembly, flushing, etc. is
normally expected should have floors with continuous slope to the drain location. Any drains that
come from a source that can add oil to the water should not drain directly to tailwater but should
first be routed to an oil separator facility.
Pressure wastewater: wastewater from generator air coolers and bearing coolers etc. are
normally piped directly to the tailrace. Some powerhouses also require pressure drains for
transformer cooling water and air conditioning cooling water.
Drainage Sump: The drainage sump or joint unwatering- drainage sump should be located low
enough to provide gravity flow from all drained areas under all dry powerhouse design tailwater
conditions and up to the float-operated alarm, sump water elevation.
Drainage and Dewatering Systems Specification - refer guidelines for procurement of SHP
auxiliaries.
Compressed air system are required in powerhouse for operation and to facilitate maintenance
and repair. Service air, brake air and governor air comprises the three systems needed in all
powerhouses. Reliability, flexibility and safety are prime design considerations. This system is
generally not provided for mini and micro hydro sets upto 1000 kW capacity.
a. General . The brake air system comprises one or more semi-independent storage and
distribution installation for providing a reliable of supply of air to actuate the generator
braking systems. Air is supplied from the service air system, stored in receivers, and
distributed through the governor actuator cabinets to the generator brake systems.
b. Air Requirement. Air is required in the system to stop all generator-turbine units
simultaneously without adding air to the system and without reducing system pressure
below 520kPa (75 psi). Storage capacity and pressure depends upon number of brake
applications per stop, brake cylinder capacity and volume required for piping and
verified by generator manufacturer.
c. Piping-Receivers. Each subsystem includes a receiver, piping from the service air
system to the receiver, piping from the receiver to the governor cabinets, and piping from
each governor cabinet to the respective generator brake system normally.
d. Control. Control for application of the brakes is normally included in the governor
cabinets and provided by the governor supplier.
a. General. The governor air system provides the air cushion in the governor pressure
tanks. When the governor system is to be placed in operation, the pressure tank is filled
approximately one-fourth full with oil, and the tank is then pressurized to governor-
operating pressure from the governor air system. Corrections to maintain the proper oil-
air ratio are required at intervals during plant operation. The governor pressure tank size
and operating pressure will be determined by the turbine servomotor volume.
b. Air requirements. i) Quantity: Compressor delivery should be sufficient to effect a
complete pressurization of a governor tank with the proper oil level in 4-6 hr. ii) System
Pressure. The operating pressure should be approximately 10% above the rated
governor system pressure. iii) Compressor. The total air-delivery requirement should be
provided by two identical compressor, each rated at not less than 50% of the
requirement. Compressor should be heavy duty, reciprocating, water or air cooled, and
rated for continuous duty.
a) General. The service air system is a nominal 700-kPa system providing air for
maintenance and repair, control air, hydropenumatic tank air, charging air for the brake
air system, and in some cases, air for ice control bubblers.
b) Service Air Requirement. i) Routine Maintenance. Supply 25-40 L/s for wrenches,
grinders, hammers, winches, drills, vibrators, cleaning, unplugging intakes and lines, etc.
ii) Major Maintenance and Repair. Supply 140-190 L/s (300-400 cfm) for
sandblasting, painting, cleaning etc. Normally this capacity should be provided with
portable equipment. For projects too remote from a government or commercial source of
temporary portable equipment, installed capacity be provided. iii) Ice Control Bubblers.
Thjis may be required for SHP located high altitude ice prone areas. Supply 1-2 L/s per
3- width of trashrack with bubblers opaerting on intakes for upto four units
simultaneously (if required). iv) Operational Requirements. Supply 7-12 L/s (15-25
cfm) with individual assumption as follows:
v) Standard Provision Basis. It is found that the computed basis will usually require several
arbitrary assumption and service factors to arrive at a total service air requirement. in lieu
of the compound basis, the following standard provisions may be used as the basis of
total air requirement:
In addition, provide 175 L/s (375 cfm) for major maintenance and repair. If this will be
supplied with portable equipment, add computed ice control bubbler requirement to the
above standard provisions. If the 175 L/s is to be installed, assume that ice control and
major maintenance will be nonsimultaneous requirements, and the 175 L/s will cover the
ice control bubbler requirements.
v) Service Air Pressure. A nominal 700-kPa pressure with system variations from 580-760
kPa is satisfactory.
c) Compressors. Compressors should be heavy duty, water cooled, flood lubricated, and
cooled rotary screw type rated for continuous duty. Normally, aside from major
maintenance, service air should be supplied by two identical compressors each of which
is capable of supplying approximately 75% of the requirement. where ice control bubbler
demand exceeds 12 L/s and there is no installed major maintenance compressor, it will
usually be preferably to supply the bubbler demand from separate compressor. Installed
major maintenance and repair capacity should be provided with a single compressor.
d) Receivers. Each air receiver should conform to design construction, and testing
requirements of the ASME, “ Boiler and pressure Vessel Code.” Receiver capacity
should provide a minimum 5 min-running time with no air being used from the system
for the largest connected compressor on automatic start-stop control. One or more
receivers may be used for the system. However, galvanized receivers are preferred, and
sizes should be checked against galvanizing plant capabilities.
4.4.4 For typical procurement specification refer guidelines foe procurement of SHP
auxiliaries.
4.5.1 General
Arrangement of fire protection in hydro power station and switchyard is normally divided into
following three groups.
i) IS: 1646 – Code of Practice for Fire Safety of Building (General) Electrical Installation
ii) IS: 2189 – Code of Practice – Selection, Installation and Maintenance of Automatic Fire
Detection and Alarm System
iii) IS: 3844 – Code of Practice for installation and Maintenance of Internal Fire Hydrants
and hose reels on Premises
iv) CBI & P Manual on Transformer
v) IS: 6382 – Code of Practice for Design and Installation of fixed Carbon Dioxide Fire
Extinguishing System
i) The spacing of the equipment should be considered. Extra space is not usually provided
for fire isolation, but the space available is taken into account in deciding other isolation
measures.
ii) Fire isolation walls should be provided between large oil-filled equipments such as two
or more transformers placed adjacent to each other. These should be of adequate strength
and of such size that the adjacent equipment is reasonably safe from the risk due to
burning oil flying from the equipment on fire.
4.5.3.2 A well coordinated system of fire protection should be provided to cover all areas of the
power house and substation and all types of likely fires. The details of fire protection have to be
worked out on the basis of size, type and location of the substation, accessibility and degree of
attendance. Care should be taken any fire can be fought from more than one source and
dependence is not placed on single equipment for this purpose.
4.5.3.3 The subject of fire safety involving electrical equipment is exhaustively covered in latest
code and practice mentioned in 4.5.2.
4.5.4.1 All substations should be equipped with fire fighting systems conforming to the
requirements given in latest IS: 1646 and fire protection manual Part-I issued by Tariff
Committee of Insurance Companies.
4.5.4.2 Trailer pumps where provided should draw their water supply from ground tanks of
suitable sizes, the location and distribution of which shall be such that no item to be protected is
more than about 90 m away from any ground tank.
4.5.4.3 The more valuable equipment or areas forming concentrated fire risk should be covered
by special fire protective systems. In this class are:
i) Generators
ii) Transformers, both indoor and outdoor:
iii) Oil filled switchgear
iv) Oil tanks and oil pumps
v) Oil, grease and paint stores
4.5.4.4 Although the substitution of bulk-oil and minimum oil circuit breakers by SF6 gas circuit
breakers has reduced the risk of fires in electrical installations, considerable risk still exists on
account of transformers, cables etc., which contain combustible insulating materials. Fires in live
electrical equipment, motors, machinery etc. fall in class C according to the tariff Advisory
Committee Classification of Fires. It is necessary to provide efficient Fire Protection Systems in
the electrical installations. Fire protection system consists of the following :
i) Fire prevention
ii) Fire Detection and annunciation
iii) Fire extinguishing
4.5.5.1 Fire prevention is of utmost importance and should be given its due if risk of occurrence
of fires has to be eliminated/minimized. The safety and preventive measures applicable for hydro
4.5.6.1 Fire detection if carried out at the incipient stage can help in timely containment and
extinguishing of fire speedily. Detection can either be done visually by the personnel present in
vicinity of the site of occurrence or automatically with the use of detectors operating on the
principles of fixed temperature, resistance variation, differential thermal expansion, rate of rise of
temperature, presence of smoke, gas, flame etc. Fire detectors of the following types are usually
used:
4.5.6.2 Ionization type detectors are used more commonly. However in areas like cable vaults,
lionization smoke and linear heat detection type detectors are used. Smoke type detector is
effective for invisible smoke, and photoelectric type for visible smoke. Smoke type detectors
incorporate LEDs, which start glowing in the event of fire.
4.5.6.3 Detectors are located at strategic positions and arranged in zones to facilitate proper
indication of fire location, transmission of Audio-visual signals to Fire control panels and
actuation of the appropriate Fire Fighting Systems. In the rooms with false ceilings, these are
provided above the ceiling as well as below it. For the detectors located above the false ceilings,
remote response indicators should also be provided.
4.5.6.4 Detectors are provided at the rate of one for a maximum area of 80 m2 in the zones to be
covered by the Fire Protection System
The Fire Extinguishing Systems used for fire protection of the various equipments/building in
substations are the following:
4.5.8.1 Hydrant System is installed for the protection of the following areas from fire:
4.5.8.2 Hydrants are the backbone of Fire Fighting System as these can help fighting fires of all
intensities in all classes of fires and continue to be in service even if the affected
buildings/structures have collapsed. These keep the adjoining properties/buildings cool and
thereby save them from the serious effects of fire and minimize the risk of explosions.
4.5.8.3 The Hydrant System is supplied water from Fire Water Pump House. Fire Water Pump
House is located by the side of Fire Water Storage Tanks constructed within the substation
boundary limits. These tanks are made of RCC above ground such that these are easily
accessible. Water from these tanks is pumped into the Fire Hydrant System with horizontal
centrifugal pumps.
4.5.8.4 The Hydrant System essentially consists of a network of pipes, laid both above ground
and underground, which feed water under pressure to a number of hydrant valves located at
strategic locations throughout the substation. Pressure in the piping is maintained with the help of
hydro-pneumatic tanks and jockey pumps. Jockey pumps compensate for minor leakages also.
The hydro-pneumatic tanks are pressurized with compressed air supplied by two air-compressors
of which one is working at a time and other acts as standby.
Adjacent to the Hydrants, hosepipes, branch pipes and nozzles are kept in Hose Boxes. In case of
fire, the hoses with nozzles are coupled to the respective hydrants and water jet is directed
towards the seat of fire.
4.5.8.5 On drop of pressure in the piping network below a preset value, the Hydrant Pump starts
automatically and continues to run till it is stopped manually after fire has been extinguished.
4.5.8.6 The quantity of water to be available for fire protection and the number of fire water
pumps depend on the total number of hydrants which are provided as per guidelines of Tariff
Advisory Committee Manual, according to which substations fall in "Light Fire Hazard"
category. The parameters of Fire Water Pumps as per TAG guidelines are given below.
(a) For the total number of hydrants upto twenty, one no pump of 96 m3/hr capacity with a
pressure of 5.6 kg/cm2 (gauge)
(b) For the total number of hydrants exceeding twenty upto fifty five, one no. pump of 137
m3/hr capacity with a pressure of 7.0 kg/cm (gauge)
(c) For the total number of hydrants exceeding fifty five, upto hundred, one no. pump of 171
m3/hr with a pressure of 7.0 kg/cm (gauge)
4.5.8.7 As per TAG guidelines, the jockey pump should have a capacity of 10.8 m3/hr. and the
hydro-pneumatic tank should have a capacity of 18 m3. The effective capacity of the Fire Water
Tank should be not less than one hour of aggregate pumping capacity, with a minimum of 135
m3
4.5.8.8 All components of the Hydrant System such as piping, valves, fittings, hoses, branch
pipes, nozzles etc. should be of approved make acceptable to TAG.
4.5.9.1 This type of Fire Protection System is provided for the following types of equipment:
This system is designed on the assumption that one reactor/transformer is on fire at a time. For
this assumption, the largest piece of equipment forms the basis.
4.5.9.2 High Velocity Water Spray System consists of a network of projectors arranged around
the equipment to be protected. Water under pressure is directed into the projector network
through a deluge valve from a piping network exclusively laid for the Spray System. Water
leaves the projectors in the form of conical spray of water droplets travelling at high velocity.
4.5.9.3 The high velocity droplets bombard the surface of oil and form an emulsion of oil and
water which does not support combustion. This emulsion converts a flammable liquid into a non-
inflammable one. However, this emulsion is not of a stable character and therefore shortly after
the water is shut off, oil starts to separate out from water which can be drained away, leaving the
oil behind unimpaired.
4.5.9.4 The rate of burning of a flammable liquid depends upon the rate at which it vaporizes and
the supply of oxygen to support combustion. It is the maximum when the rate of burning of the
flammable liquid is the maximum and the surface of the liquid is near boiling point. The fcjigh
velocity water spray system while forming an emulsion, intersperses cold water with the liquid,
cools it and lowers down the rate of vapourisation which prevents further escape of flammable
vapours. During passage of water droplets through flames, some of the water gets converted into
steam, which dilutes oxygen in the air supporting the fire and creates a smoothering effect, which
aids in extinguishing the fire.
4.5.9.5 An automatic deluge valve triggered by a separate system of quartzoid bulb detector
heads mounted on a pipe work array charged with water, at HVW spray mains pressure, initiates
the HVW Spray System operation. When a fire causes one or more of the quartzoid bulbs to
operate, pressure in the detector pipe work falls and this allows the deluge valve to open thereby
permitting water to flow to all the projectors in the open pipe array covering the risk.
(a) Two pumps are provided for HVW Spray System. Of these, one is electric motor driven
and the other diesel engine driven. The capacity and head of the pumps is selected to
protect the biggest risk. It has been experienced that each pump having a capacity of 410
m3/hr is usually adequate for the biggest risk in substations.
(b) These pumps are located in Fire Water Pump House. Suitable connection with the
Hydrant System is provided so as to allow flow of water from Hydrant System to HVW
Spray System but not in the reverse direction.
c) Standby diesel engine driven pump is a common standby facility for HVW spray as well
as Hydrant System,
d) These pumps are automatically started through pressure switches located sequentially in
headers. However, stopping of the pumps is done manually after the fire gets
extinguished.
(e) The values of pressure of running water and discharge density given below are
recommended for HVW Spray System :
(i) Minimum pressure of running = 3.5
Bar at any projector at any instance.
(ii) Maximum pressure of running water = 5.0
Bar at any projector at any instance
(iii) Discharge density on ground surface = 6.1 Ipm/m2
(iv) Discharge density on other surface = Not less than
10.2 Ipm/m2
4.5.10.1 Water for fire fighting purposes should be supplied from the water storage tanks meant
exclusively for the purpose. The aggregate storage capacity of these tanks should be equal to the
sum of the following:
The water storage tank made of RCC construction over ground should be in two parts.
4.5.10.2 Fire Water pumps located in the Fire Water Pump House should have pumping head
suitable to cover the facilities for future stages also. The piping system should be designed to
permit extensions without disruption in the existing system. The material of piping is mild steel
as per IS: 1239/IS: 3589 medium grade. The piping laid, underground is coated and wrapped
against corrosion as per IS: 10221 and the piping laid over ground consists of galvanised mild
steel.
4.5.10.3 All equipment and accessories, constituting the HVW Spray System, such as flow
control valve, heat detectors, projector nozzles, piping, valves, fittings, instrumentation etc.,
should be of approved makes acceptable to TAG.
Portable and Mobile Fire Extinguishers are provided at suitable locations for indoor/outdoor
applications. These extinguishers are used during early stages of localised fires to prevent them
from spreading. Following types of these extinguishers are usually provided.
For the quantities of these types and their applications, the norms given in TAG manual should
be followed.
4.5.12.1 Fire Protection System should include suitable instrumentation and necessary controls to
render the system efficient and reliable. There should be local control panels for each of the
pumps individually as also for the operation of deluge valve of the HVW Spray System. There
should be a common control panel for the Jockey Pump and Air Compressors. Main annunciation
4.5.12.2 The following Annunciation is usually provided in the Fire Water Pump House :
4.5.12.3 The following Annunciations should be available in the control room also:
4.5.12.4 All fire protection equipment should be covered by a regular and strict maintenance and
test routine. The hydrant systems should be checked every week which may be possible during
night shifts. Sprinkler systems should be checked at regular intervals. Portable equipment should
be charged at specified intervals and checked regularly for loss of charge, damage, etc. Records
of all tests and checks must be maintained.
4.5.12.5 Provision should be made to switch off the air conditioning equipment in case of
fire.
4.5.12.6 Cable entry openings shall be sealed to prevent the spreading of fire.
A flow diagram of a typical HVW Spray and Hydrant System is enclosed as Fig. 4.5
4.5.3 Generators
a) General : Generators with closed air-circulation systems are normally provided with
automatic CO2 extinguishing systems. Up to four generators may be on one system, with
CO2 cylinder storage based on discharge in a single unit (generally above 5 MW
capacity). Standard generator are recommended upto 5 MW and these are open
ventilated and not suitable for carbon dioxide fire protection.
b) System design :
The CO2 fire extinguishing system normally consist of a sufficient amount of CO2 to maintain an
inert atmosphere during the deceleration of the machine. Two rates of discharge of CO2, are
provided by two groups of CO2 cylinders one group of cylinders, providing the initial discharge,
to ensure a rapid build-up of CO2 concentration, to put out fire and other group of cylinders,
providing the delayed discharge to ensure concentration of CO2 maintained for an extended
period. Capacity of the bank is sized for protection of only one individual generator and CO2
cylinders is arranged for the discharge to any one of the main units. The amount of CO2, for
initial and delayed discharge, should be determined by the manufacturer, taking into account the
volume of the air spaces in the generator enclosure and the deceleration time of the machine. Size
and the number of cylinders required in each bank are accordingly determined. A set of identical
reasons set of cylinders is provided for immediate replacement after use.
iii) Open ventilated generators upto 5 MW capacity may be provided water sprinkler system
or portable system.
4.5.4 Transformers
b) Outdoor transformers :
2) System design
i) The system Emulsifier Water Sprinkler System. Deluge valves should be
actuated automatically by a thermo-stat, manually by a switch in a
break-glass station located in a safe location near the transformer, or
manually at the valve. Where exposed transformers (without isolating
walls) are located closer together than the greater of 2-1/2 times
transformer height or 9 m, the system should be designed for spraying
the adjoining transformers simultaneously with the transformer-initiating
deluge.
ii) The water sprinkler system system water supply is normally from the
pool or water tank and should be a gravity supply if practicable. A
booster pump should be provided if required. a pumped tailwater source
is an acceptable alternate. Two water intakes are required either of
which can supply the rated delivery of the pump. Consideration must be
Portable CO2 handheld extinguishers are the first line of fire protection for powerhouse areas and
quipment other than those specifically covered above and should be provided in locations as per
relevant Indian Standard.
a. Thermal detectors: Thermal detectors are best suited for locations within equipment
such as generators or near flammable fluids.
b. Ionization detectors: Ionization detectors are best suited for gases given off by
overheating, such as electrical cables or a smoldering fire. Location near arc-producing
equipment should be avoided. They are not suited for activating CO2 systems.
c. Photoelectric detectors: Photoelectric detectors are best suited for the particles given off
by an open fire as caused by a short circuit in electrical cables. Their use in staggered
locations with ionization detectors along a cable tray installation would provide earliest
detection. They are not suited for activating CO2 systems.
d. Location: Detectors should be located at or near the probable fire source such as near
cable trays or in the path of heating and ventilating air movement. In areas where
combustible materials are not normally present, such as lower inspection galleries, no
coverage may be appropriate.
e. Reliable detection: The earliest “reliable” detection is required. The detector type or
types, location and adjustment should be carefully considered. The detector sensitivity
adjustment should be adjusted to eliminate all false alarms. A fire detector system
should be provided in the cable gallery and spreading rooms of all powerhouse.
f. Alarm system: The power plant annunciation and, if applicable, the remote alarm system
should be used to monitor the fire detection alarms. An alarm system should be provided
for each area. Properly applied, these systems will provide more reliable and useful
alarm data than the alarm monitor specified in the fire codes.
Smoke and fire isolation is probably the most important fire control item. Smoke inhalation is
one of the major causes for loss of life. The toxic fumes from a minor fire could required total
evacuation of the powerhouse. Many of the existing heating, ventilating, and air conditioning
systems contribute to spreading the smoke as they encompass the entire powerhouse or have a
vertical zone composed of several floors. The fire area should be isolated by shutting down the
ventilating system or exhausting the air to the outside where feasible to prevent the spread of
smoke and to provide visibility for fire fighting reentry to the area. In most cases, the available
oxygen is sufficient to support combustion, and little can be gained by not exhausting the smoke.
Smoke and fire isolation should be provided in areas where isolation can provide a real benefit.
The requirements for fire stops should be considered on a case-by-case basis. Where cable tray
i) Generator – CO2 protection if CO2 protection is not feasible then water sprinkler system
be provided.
ii) Generator transformer – Provide water sprinkler system protection
iii) Fire detectors, portable fire extinguishers, fire buckets and hydrants as per relevant IS
i) Generator – Water sprinkler system for generator above 1000 kW unit size
ii) Generator Transformer – water sprinkler system above 1000 kW unit size
iii) Fire detectors, portable fire extinguishers, fire buckets and hydrants as per relevant IS
Portable fire extinguishers, fire detectors and hydrants as considered figures and as per Indian
standard requirements.
Fire Protection System specification - refer guidelines for procurement of auxiliaries.
4.6.1 General
Power house and ventilation and air conditioning is required to maintain temperature and quality
air conditions suitable for operating requirement, plant personnel and visitors. Ventilation and air
conditioning system for surface hydel power stations should be designed in accordance with IS:
4720 – 1982 entitled code of practice for ventilation of surface hydel power stations as given
below.
a) Natural, that is, by forces set in motion by the heat of sun, namely, winds; and
b) Forced or artificial, that is, by extraction or propulsion.
i) Forced ventilation system is designed keeping the inlet fan capacity 10 percent more than
the exhaust fan capacity.
*Code of practice for industrial ventilation
Steel doors, windows and ventilators (second revision).
Steel windows for industrial buildings (first revision).
ii) Unassigned rooms and storage rooms should be carefully considered, so that sufficient
ventilation may be provided in those which might be used for purpose requiring
additional ventilation in the future.
iii) In portions of the power station building where moisture condensation is anticipated,
dehumidified air should be supplied to prevent condensation, as condensation causes
deterioration of point, corrosion of metal surfaces and breakdown of insulation on
electrical equipment.
iv) The quantity of air required for the power station building should be worked out from the
number of air changes preferred for the various premises of the building as given in
Table 1. In addition to this the points given in 4.6.3.1 to 4.6.3.2 should also be kept in
mind.
v) One air change per hour means that the quantity of air equivalent to the total volume of
the room is supplied to and exhausted from the room each hour. This air may be all
outside air or a part of the-circulated air, depending upon the oxygen content.
vi) The proportion of outside air to the circulated air supplied to a room depends upon
temperature conditions, number of occupants and kind of equipment installed in the
room.
4.6.4 Fans
Forced air ventilation is provided by propeller, axial or centrifugal type fans powered by electric
motors. Propeller fans may be used either to supply or exhaust where no duct system, filters or
other restrictions are in the air passage. When duct system is used, axial or centrifugal fans may
be used for any type of operation involving the movement of air and may be accompanied by
filters, and coolers or heaters where cleaning and tempering of supply air is required. Choice
of a particular type of fan may be made by consulting the fan manufacturers data, which give
full operating characteristics with a preferred range of operation for a particular fan.
4.6.5.1 Openings are provided for intake and exhaust of air where outside air is required for
ventilation. Where natural ventilation is used, the opening of windows is sometimes
sufficient. For forced ventilation, special openings are required. The number of openings
for intake and exhaust of air depends on the space arrangement in the .building, on the
size of the building and the design of the ventilation system. Small
power plants may have one opening of each type. For larger power plants, separate
outside air intake should be installed for the control, service and main unit bays. Each
intake should be provided with storm louvers, screens, and dampers for controlling the
mixture of outside and circulated air. The obstructive effect of the louvers should be
compensated for by making the gross area of the initial intake twice the area of the
connecting duct. When filters are used, the area should be increased to accommodate the
required filter area.
4.6.5.2 Air opening may be placed any where on the exposed walls or roof of the power plant
building, except that, in order to reduce dust intake, air intake should be at least 1*25 m
above ground or deck level.
4.6.5.4 The size of air openings is dependent on noise level, and to a lesser degree, on horse
power requirements, since the smaller the opening the higher will be the noise level and
the resistance. The size of air openings may also be worked out from the air velocity as
recommended in Table 2, which will be found to give satisfactory results in designing
conventional systems.
It is desirable to clean the air entering the power plant building in order to remove the air-borne
dust particles which, if allowed to enter the building, may have an abrasive effect on rotating
machinery, interfere with the operation of electric or electronic devices, and may, otherwise
settle on equipment, giving a dirty appearance. The air filters are usually located upstream of the
fan. The size of the air filters may be determined by the recommended velocity of air passing as
given in Table 2. The choice of the air filter may be made by reference to the manufacturer's
catalogues.
4.6.7 Air-Conditioning
4.6.7.1 When the desired temperatures and humidities inside the hydel power station are not
obtainable by ordinary ventilation, air-conditioning may be resorted to bv heating or
cooling the entering air to the desired temperature to maintain comfortable working
conditions in the premises occupied by working personnel. The premises where it will be
desirable to provide air-conditioning are control, room, machine shop, offices, reception
room, first-aid room, dark room, electrical laboratory, switchgear -and terminal board
room and telephone and carrier communication room. For air-conditioning reference
may be made to IS: 659-1964*.
4.6.7.2 In general, all rooms, used by sedentary personnel should be maintained at 22°C with a
relative humidity of about 50 percent, or in special cases local radiant type portable
heaters may be used for the space actually occupied. Operation of the air-conditioning
system should be independent of the main ventilating system and the control of the
system should be automatic by means of thermostatic devices. Heating and cooling load
computations may be based on currently accepted standard practice.
*These velocities are for total face area and not the net free area; other velocities in the table are
for net free area. The net free area is the total minimum area of the opening in the face of a coil,
grille, register or louver through which air can pass.
4.6.8 Ducts
4.6.8.1 Where positive ventilation requires ducts for proper air distribution, considerable
advantage may be achieved by incorporating the ducts into the building structure and by
having the interior surfaces carefully finished to render them smooth and air-tight.
4.6.8.2 Where metal duct work is installed, it’ should be fabricated from galvanized steel or
aluminum sheets, and should conform to IS: 655-1963*.
4.6.8.3 The transfer of air by ducts; from source to delivery point, should be as direct as
practicable with the fewest possible bends. Flexible connections should be provided
between fans and ductwork to prevent the noise of fan vibration being transmitted
directly to the sheet-metal ducts.
4.6.8.4 The size of the air ducts should be worked out from the permissible air velocities given
in Table 2.
4.6.8.5 Supply and exhaust ducts of acid battery rooms should be painted with acid resistant
paint both inside and outside.
To regulate the flow of air in a ventilating system, control dampers should be provided
throughout. At outside air intakes, multi-louver dampers should be used to control the amount of
air admitted. A similar damper is required on inside air intakes to control the amount of
rectrculated air. These two dampers should be interconnected to permit regulation of the
proportion of outside air to inside air used in the ventilating system. These may be operated
manually or automatically. Back-draft dampers are used where it is desired to prevent a reverse
flow of the air, such as the air supply duct to a battery room. Exhaust ducts from rooms
containing a fire hazard should have dampers which can be automatically and manually closed in
case of fire. Discharge openings, provided with propeller exhaust fans, should be fitted with
motor or mechanically operated type multi-louver dampers, which will open and close
automatically when the fan motor starts and stops.
AHEC/MNRE/SHP Standards/E&M Works – Guide for Selection of Auxiliaries for Page 53
SHP up to 25 MW
4.6.10 Air Conditioning and Ventilation System Recommended
Provide ventilation system for required no. of air changes by exhaust fans or forced air fans.
Tailrace level sensing is required for all canal fall powerhouses for a optimum power generation
or avoid.
STANDARDS/MANUALS/
GUIDELINES FOR
SMALL HYDRO DEVELOPMENT
Electro-Mechanical Works –
Specifications for Procurement of Auxiliary Equipment for SHP
Stations
May 2011
CONTENTS
ITEMS PAGE NO
1. INTRODUCTION 1
1.1 Purpose 1
1.2 Standards and Reference documents 1
1.3 Technical requirements 1
2. SPECIFICATIONS OF MECHANICAL AUXILIARIES 3
2.1 Overhead Traveling Crane 3
2.2 Drainage and Dewatering System 6
2.3 Cooling Water System 8
2.4 High Pressure and Low Pressure Compressed Air System 10
2.5 Water Level Measuring & Transmitting Device 11
2.6 Oil Filteration Unit 12
2.7 Fire Protection Scheme 14
2.8 Ventilation and Air Conditioning 14
3. SPECIFICATIONS OF INDIVIDUAL ELECTRICAL AUXILIARIES 14
3.1 Auxiliary Transformers 14
SPECIFICATIONS FOR PROCUREMENT OF AUXILIARIES
FOR SMALL HYDRO POWER STATIONS
1. INTRODUCTION
1.1 Purpose
These purchase specifications are produced in the form of recommendations/guide for utilities
and may be used in the form of standard as no National Standard has been issued so far by
BIS for this product. This Guide is intended to assist in the preparation of technical
specifications for the procurement of auxiliary equipment for the power house. The guide
includes, scope, design conditions, performance guarantee, general arrangement and
constructional feature, shop assembly & tests, site installation testing and commissioning of
different type of auxiliaries and commissioning of the same.
The document being only a guide line, AHEC cannot be rendered responsible for any
equipment declared to be in conformity with these guide lines.
1.2 Standards and Reference documents
All equipment shall comply with the latest edition of the relevant Indian Standards
specifications or relevant International Standards. When the equipments do not comply with
the above standards, the salient points of difference between the standards adopted and the
relevant Indian Standards or relevant International Standards shall be clearly brought out.
1. 3 Technical requirements
Following technical requirements should be elaborated in tendering documents :
1.3.1 Scope of work
This sub clause should describe the scope of work and the responsibilities which are to be
conferred upon the Contractor.
The scope of work should begin with a general statement which outlines the various elements
of the work including (where applicable) the design, material selection, manufacture, quality
assurance, quality control, shop assembly and testing, transportation and delivery to site,
insurance, storage ate site, installation, commissioning, field acceptance tests, warrantee and
other services as specified or required. The general statement should be followed by a specific
and detailed list of the major items which the Employer wishes to have as separate payment
items in the tender form.
Detailed list of major items should be given for each equipment.
1.3.2 Limits of the Contract
This sub clause, by making reference to the Employer's drawings and data, should describe in
detail the limits of the Contract considering the following:.
– details of the design and supply limits of the high and low pressure sides of the
equipment;
– details, location and responsibility for field connection to equipment under supply
– details and location of gate(s) or valve(s) on low-pressure side;
– responsibility for supply and installation of bolts, nuts, gaskets at piping termination;
– termination of connecting piping;
1.3.3 Supply by Employer
This sub clause should list the items and services which will be the responsibility of the
Employer. The following items should be considered:
AHEC/MNRE/SHP Standards/E&M Works – Specifications for Auxiliaries for Small Page 1
Hydro Power Stations
– services during site installation and testing;
– connections to powerhouse air, oil and water piping systems;
– electrical wiring and hardware external to specified termination points;
– electric motor starters and controls;
– lubricants
It should be stated that any materials or services like electricity, water and office/storage
space etc required for installation and commissioning of the equipment is to be provided by
the Contractor under the contract free of charges or with specific costs.
1.3.4 Design Conditions
1.3.4.1 Project arrangement
The Tender documents should contain the Employer's detailed description together with general
arrangement drawings (by the Employer) of the powerhouse, galleries, valves/gates, etc. The
description should be an extension of the applicable data provided in Chapter "Project
information". The data shall be sufficiently clear so that the Contractor can become fully aware
of physical conditions which may influence its detailed design.
1.3.4.2 Project Information
The specifications should state the principal characteristics of individual auxiliary system, for
example :
– capacity,
– power rating of driving electric motors,
– frequency of operations,
– space available for installation
1.3.4.3 Noise Level
Noise level limits may be legislated by national or local statutes. Noise abatement measures
may be the combined responsibility of the Employer and the Contractor. Reference should be
made by the Employer to ISO 3740 together with other standards, statutes and guides to
establish noise measurement and acceptance criteria. The limits and the means by which they
can be achieved should be specified
1.3.4.4 Vibrations
The specifications should specify that the equipment operate without vibrations which would
be detrimental to its service life. Reference should be made to IEC 60994, together with other
suitable standards or guides to establish the acceptable limits of deflections / vibrations, their
measurement and acceptance criteria.
1.3.4.5 Safety requirements
The specifications should state specific safety requirements which shall be met in the design
of the auxiliary equipment.
1.3.4.6 Technical Performance and Other Guarantees
The specifications should establish and specify the parameters on which the performance
guarantees are to be based.
The Employer should select the appropriate level and type of performance guarantees for each
equipment, The Employer should specify measurement methods to be applied and the
relevant standards which explain the measurement error.
2.1.8 Controls
Master controllers shall be located in the operators cabin. Indication and protections shall be
provided on the control panel.
2.1.9 Hoisting Ropes, Hooks, Lifting Beam
Hoisting ropes shall be extra flexible having a breaking strength at least five times that of the
maximum working load.
The crane shall be provided with a main hoist double hook of the ramshorn type and the
auxiliary hoist hooks of the single type with a safety latch. Main hook block shall incorporate a
hole and pin for attaching lifting devices. All the hooks shall be 360 o swivel type rotating on
antifriction bearings.
One lifting beam adequate to lift the heaviest load shall be provided.
2.1.10 Runway Rails
One set of runway rails and associated clamping devices with base plates, splice plates shall be
included in the supply.
2.1.11 Walkways, Platforms & Lighting
Walkways, ladders, inspection platforms for allowing access to all parts of the crane shall be
provided. Interior and exterior lighting inside the operators cabin and on bridge shall be
provided.
2.1.12 Special Tools & Devices
One set of all erection and maintenance tools special erection devices and testing devices shall be
provided.
2.2 Drainage and Dewatering System
2.2.1 Scope of Supply
• Vertical Turbine / Submersible Pumps for dewatering - one or two sets
• Level Controller for dewatering pit. - one set
• Vertical Turbine / Submersible Pumps for Drainage - two sets
• Level controller for drainage pit. - 1 set
• Pipes, valves & fittings. - 1 lot
• Special tools and devices for assembly / dismantling of pumps
NOTE :
i) Dewatering system is not required for surface power houses utilizing Pelton, cross flow,
tubular and small horizontal Francis type of turbines.
ii) Capacity of pumps shall be adequate for the power station.
iii) Submersible type pump-motor sets may be offered as alternative in place of Vertical
Turbine pumps.
2.2.2 Standards and Codes
• The transformer shall be capable of with standing the specified impulse test
voltage.
• One minute power frequency Test voltage for which the transformer shall be
designed, should be specified
3.1.5 Tests
The transformer shall be subjected to all the relevant tests on works and site as per relevant
IS/IEC and copies of the same shall be supplied the purchaser for approval.
3.2 Station Batteries and Battery Chargers
3.2.1 Scope of Supply
The battery system shall meet the complete requirements for control, protection and interlocks,
emergency DC drives, emergency lighting, annunciation and field flashing etc and SCADA
system. The following data should be specified :
• No of Battery sets :
• Type of Battery sets :
• Nos and type of battery Charger :
• Voltage and AH rating of each battery set :
3.2.2 Codes and Standards
IS 13300
3.2.3 Construction Features
The batteries shall be of Nickel-Cadmium and high discharge type. Each battery shall have a
static battery charger, rated to fully recharge the battery from a completely discharged condition
in not more than ten (10) hours in boost charging mode. Each battery charger shall be capable of
float charging the two batteries while supplying the normal voltage regulators and shall have
following facilities as per drawing no. E-257-5.
(a) Manual selection facility for battery charging mode i.e. whether trickle or boost.
(b) Automatic and manual control of output voltage and current. Selector switch shall be
provided for auto/manual selection. Auto to manual changeover shall not result in any
harmful surges.
(c) Effective current limiting feature and filters on both input and output to minimise
harmonics, RFT, EMT etc.
(d) When on automatic control mode during trickle charging, the charger voltage shall
remain within 1% of set value for maximum permissible voltage, frequency and
The specification covers design, supply, insulation, testing and commissioning of cabling,
earthing and lightning protection at the powerhouse
The complete cable support system shall be supplied and installed for the entire project. The
system shall enable proper laying of all power, control, instrumentation and telephone cables, and
shall provide necessary mechanical protection, ventilation and segregation for them. All
hardware and anchoring arrangement shall be included. All steel members shall be hot dip
galvanised.
ii) Design
The contractor shall furnish detailed design and calculation for owner’s approval.
iii) General requirements
No sub zero level cable vault/trenches shall be provided below control building/switchgear
rooms in main plant and switchyard areas.
Interplant cabling for main routes shall be laid along overhead trestles/duct banks/directly buried.
However, from tap-offs, same can be through shallow trenches with approval of Owner. Directly
buried cable, if essential, shall not have concentration of more than four (4) cables. However,
cables in switchyard area shall not be buried. Cables from main plant to switchyard control room
shall be laid in duct bank/cable trenches.
In switchyard area, cables shall be laid in RCC concrete trenches. Wherever false floors are
envisaged for cabling, the cables can be directly laid on ground, neatly routed along grid spacing.
The false floor shall be atleast 1000 mm deep. False floor requirement shall be subject to Owner's
approval.
Cable entry from outdoor underground/cable routes to the buildings, if any shall be above the
finished floor level inside the building.
PCC flooring of built up trenches shall be sloped for effective drainage with sump pits and sump
pumps.
Cable trays, support system and pipes.
a) support system for cable Prefabricated out of sheet steel and fully galvanised flexible type
trays consisting of channels, cantilever arms and associated brackets &
hardware, installed at site by bolting or clamping. These shall be
rigid enough to withstand max. possible loads during and after
installation.
b) Type of cable trays Ladder for power cables and perforated for control instrumentation
cables, complete with all accessories, fittings and hardware.
c) Material of cable trays Rolled mild steel, min. 2 mm thick for trays and 3 mm thick for
coupler plate .
d) Finish of cable trays Hot tip galvanised.
3.6.2 Earthing/Grounding
Earthing system shall be designed as per IS: 3043 and IEEE: 80. The earth resistance of the earth
mats for the P.H. and switchyard will be of the order of 0.5 ohms and 1 ohm respectively. The
two mats will be joined together through 3 parallel conductors of the same cross section as those
of conductors used in the mats.
Earthing system network/earthmat shall be interconnected mesh of mild steel rods buried in
ground in the plant. All off-site areas shall be interconnected together by minimum two parallel
conductors. The contractor shall furnish the detailed design and calculations for Owner's
approval. Contractor shall obtain all necessary statutory approvals for the system.
Enclosures of all electrical equipment as well as all cabinets/boxes/panels/etc. shall be earthed by
two separate and distinct earth connections. Metallic pipes, conduits, cable tray section, etc. shall
be bonded to ensure electrical continuity and earthed at regular intervals as well as at both ends.
Metallic conduits, pipes, etc. shall not be used as earth continuity conductor. All hinged doors
shall be earthed by flexible braids of adequate size.
All steel structures shall be duly earthed. Metallic sheaths and armour of all multicore cables
shall also be earthed at both equipment and switchgear end. Earthing conductor shall be buried at
least 2000 mm outside the fence of electrical installations. Every alternate post of the fences and
all gates shall be connected to earthing grid by one lead. Earthing conductor embedded in the
concrete floor shall have at least 50 mm concrete cover.
Earthing connections with equipment earthing pads shall be bolted type with at least two bolts,
and joint surfaces shall be galvanised. The connections shall be painted with anti-corrosive paint
after testing and checking.
Neutral of power transformers shall be directly connected to two rod electrodes in treated earth
pits, which in turn shall be connected to station earthling grid.
The earthing terminal of surge arresters and voltage transformers, and lightning protection down
conductors shall also be connected to station earthing grid through separate rod electrode.
3.6.3 Lightning Protection
The lightning protection system shall be designed as per IS: 2309. It shall cover all buildings and
structures in the plant, and switchyard areas. It shall comprise horizontal/vertical air terminations,
down conductors, test links and earth connections to the station earthing grid. All conductors
shall be of minimum 25x6 mm size and shall be of galvanised steel only.
The down conductors of lightning protection system shall have a test joint at about 1500 mm
above ground level. Each down conductor shall be connected to a 40 mm dia, 3 m long mild steel
earth electrode as well as station earthing grid.
The lightning protection system shall not be in direct contact with under ground metallic service
ducts and cables, and shall not be connected above ground level to other earthing conductors. All
joints in the down conductors shall be of welded type. Pulser system for lightning shall not be
accepted.
Hazardous areas handling inflammable/explosive materials and associated storage areas shall be
protected by a system of aerial earths as per IEEE: 142. Other requirements for Earthing system
a. Standard/Code EE-80, IS: 2309
b. Earthing system life expectancy 40 years
p) Voltage control
Total range of variation
Ratio plus -----------------%
Ratio minus ------------------%
Number and size of steps -------------------%
q) General
Maximum flux density in iron at
normal voltage and frequency and
at normal ratio.
i. Cores Tesla
ii Yokes Tesla
magnetising current --------------------%
(i) Manufacturer
(ii) Continuous Current Rating -------------------A
(iii) Rated voltage -------------------V
(iv) Cable Type (PVC/SWA/PVC MIAC,XLPE,etc)
(v) Number of Cores
(vi) Cross Section sectional area -------------------mm2
(vii) Core Material
(viii) No. of strands/core
(ix) Nominal strand diameter -------------------mm
(x) Conductor Insulation
-Material
-Thickness -------------------mm
(xi) Aromour /material
(xii) Armour wires diameter -------------------mm
(xiii) Sheathing Material
(xiv) Sheath thickness -------------------mm
(xv) Completed cable
- Diameter -------------------mm
- Weight per meter -------------------kg
- Max. drum length -------------------m
(xvi) Application (connected plant )
5. Lighting system
7. Communication system
Internal Communication System
(i) Make
(ii) Type
(iii) No. of subscriber