2-Capital Budegeting-GMP
2-Capital Budegeting-GMP
2-Capital Budegeting-GMP
Non-Discounting
Discounting Criteria
Criteria
Discounted Payback
MIRR
Period
Net Present Value (NPV):
Capital Budgeting is the decision making process for accepting or rejecting
the projects. NPV is the 1st method of the process which is considered to be
a classical economic method to evaluate investment proposal. It is based on
DCF technique that explicitly recognises the time value of money.
Example: 1
Suppose project X costs Rs. 2500 now and is expected to generate cash
flow at the end of each year for 5 years by 900, 800, 700, 400 and 500
respectively. If the discount rate or opportunity cost of capital is 10% p.a.,
then calculate NPV of the investment.
Net Present Value (NPV): Time line of the Project
900
800
700
500
400
0 1 2 3 4 5
-2500
𝐶𝐹1 𝐶𝐹2 𝐶𝐹3 𝐶𝐹4 𝐶𝐹5
𝑁𝑃𝑉 = 1
+ 2
+ 3
+ 4
+ 5
− [Initial Investment]
(1 + 𝑖) (1 + 𝑖) (1 + 𝑖) (1 + 𝑖) (1 + 𝑖)
= 2725 – 2500
= Rs. 225
Case 2: Suppose Project Y has the following CFs:
3,50,000
3,00,000 3,00,000
2,00,000 2,00,000
0 1 2 3 4 5
-10,00,000
Now substituting in formula:
= 994200 – 1000000
= (-) Rs. 5800
The basic investment decision rules as follows:
1. If NPV = +ve → Accept the project
2. If NPV = -ve → Reject the project
3. If NPV = 0 → Indifference
NPV rules lead to good decision making because +ve NPV of a project adds
to the value of a firm and hence considered as the contribution of any
project to the value of the firm.
3. Again NPV approach ignores the CFs beyond a particular date, and it
may be considered as a negative aspect of NPV.
Internal Rate of Return
IRR of the project is the discount rate that makes NPV equal to zero. In
other words, IRR is the discount rate that equates PV of the future CF of
the project with its initial investment. If IRR is considered as ‘R’, then
𝑛
𝐶𝐹 𝑡
Investment = 𝑡
𝑡=1 1+IR𝑅
Consider an investment of Rs. 100 that generates Rs. 110 after 1 yr. That is:
110
NPV = − 100 That is R = 10%
1+𝑅
Example : 2
We have to find out ‘r’ with trial and error method, that is:
If r = 15%
802 1359
= 0.37 % or = 0.6289 %
2161 2161
Another method used to evaluate project is Profitability Index (or) Benefits to Cost
ratio.
Example:
Suppose a project has following CFs. If discount rate (r) is 12% then calculate the PI
& NPV
Project CF1 CF2 CF3 PV of CFs PI NPV @ 12%
1 -20 70 10 70.5 3.53 50.5
2 -10 15 40 45.3 4.53 35.3
PV of CFs after subsequent initial investment =
70 10
70.5 = +
1.12 1.122
70.5
PI = = 3.53
20
Decision Rule:
𝑃𝑉𝐵
BCR =
𝐼
NBCR = BCR – 1
PVB = PV of Benefits
I = Initial Investment
NBCR = Net Benefits to Cost Ratio
Example
Consider a project with opportunity cost of 12%. It requires initial
investment of Rs. 1,00,000 and generates CFs for 4 years i.e. Rs. 25,000,
Rs. 40,000, Rs. 40,000 and Rs. 50,000 respectively. Evaluate the project
using BCR technique.
Ans:
𝑃𝑉𝐵
BCR =
𝐼
114500
BCR = = 1.145 or NBCR = BCR – 1 = 0.145
100000
Decision Rule:
1. BCR > 1 or NBCR > 0 → Accept the project
2. BCR < 1 or NBCR < 0 → Reject the project
3. BCR = 1 or NBCR = 0 → Indifference
Payback Period
50,000
PB = = 4 𝑦𝑒𝑎𝑟𝑠
12,500
1000
× 12 = 4 𝑚𝑜𝑛𝑡ℎ𝑠
3000
Hence Payback period is 3 years and 4 months of the above project.
Or
1000
× 365 = 121.666 𝑑𝑎𝑦𝑠
3000
121.666
= 4.05 𝑚𝑜𝑛𝑡ℎ𝑠
30
Limitation of Payback period
1. In some projects, there will be high CFs at early time of the project or there
may be more CFs at latter timeline. The non-discounting approach considers all
the CFs equally. Hence it doesn’t consider the timing of the CFs within the
payback period.
50 50 20
-100, , ,
(1.1) (1.1)2 (1.1)3
In this case (45.45+41.32+15.03 = 101.8) i.e. payback period is slightly less than 3 years.
The difference appeared because CFs are discounted at their respective discounting rate.
Thank You