Equipment : Auxiliary Transformer(<10MVA)


Date:13 Feb,09 Revision: 0

TABLE OF CONTENT

1. Task
a.Work Status----------------------------------------------------------------------------------------------------------2
b.Documentation------------------------------------------------------------------------------------------------------2
c.Personnel-------------------------------------------------------------------------------------------------------------2
d.Measuring Instrumentation---------------------------------------------------------------------------------------2

2. Preconditions---------------------------------------------------------------------------------------------------
--------2
3. Precautions------------------------------------------------------------------------------------------------------
--------2
4. Scope--------------------------------------------------------------------------------------------------------------
--------3
5. Execution---------------------------------------------------------------------------------------------------------
--------3
a.Visual Checks------------------------------------------------------------------------------------------------------3
b.Testing of Transformer
1. insulation resistance / Polarization index test----------------------------------------------------------3
2. Voltage Ratio Measurement--------------------------------------------------------------------------------4
3. Vector Group/Phase Displacement-----------------------------------------------------------------------4
4. Winding Resistance Test------------------------------------------------------------------------------------5
5. Excitation current Measurement---------------------------------------------------------------------------6
6. Temperature indicator and sensor Calibration--------------------------------------------------------7
7. Bushing Current Transformer------------------------------------------------------------------------------7
8. Testing and commissioning of cooler control cabinet------------------------------------------------7
9. Transformer protection devices functional check-----------------------------------------------------7
10. Protective Earthing Checks---------------------------------------------------------------------------------7

6. Documents-------------------------------------------------------------------------------------------------------
--------8
7. Reference--------------------------------------------------------------------------------------------------------
---------8
8. Attachment------------------------------------------------------------------------------------------------------
---------8

The above contents may not be reproduced, transmitted,


or distributed to any form or by any means with out prior
permission of the originator
Page 2 of 9
Equipment : Auxiliary Transformer(<10MVA)
Date:13 Feb,09 Revision: 0

Task
This instruction comprises a complete description of the testing of oil and dry type
distribution or auxiliary transformers.

Preconditions
1.1. Work status
• Erection has been completed.
• Labelling of the equipment and designation of live enclosed plant sections has
been carried out.

1.2. Documentation
• The circuit diagram of Electrical equipment ,cabinets, etc are available
• Test Sheet TS-AT01 is available
• Product manual of the transformer is Available
• Factory Test Results of the transformer is available

1.3. personnel
• Commissioning engineer: - (1) engineer with experience in
commissioning of transformer and switch gear.
• Technician or helper:- (2) skilled worker with adequate on -the-
job training
• Witness from the client‘s concern department

1.4. Measuring instrument


• Ratio meter (calibrated)---1
• Multi Meter (calibrated)—2
• Insulation resistance meter –megger(calibrated)—1
• CT tester-CPC100( calibrated)-1
• DC shunt 100 amps( calibrated)--1
• Mini clamp(calibrated)—2
• Tan delta measurement test equipment—1
• Current injection set(calibrated)—1
• 3 phase relay tester(calibrated)—1

2. Precautions
The work will only proceed when a Permit to Work (PTW) in work permit area has been
obtained. The PTW will be kept on site for consultation during the testing works.
The above contents may not be reproduced, transmitted,
or distributed to any form or by any means with out prior
permission of the originator
Page 3 of 9
Equipment : Auxiliary Transformer(<10MVA)
Date:13 Feb,09 Revision: 0
• Observe the rules for handling electronic components
sensitive to electrostatic discharge (ESD measures).
• Special safety arrangements shall be made for all areas
which are not explicitly designated as” electrical operating areas” when performing
tests at voltages in excess of 50V.
• Closing of the work permit after completion of the work (if
the test area is to be considered in work permit area) is necessary.
• Before test voltages are applied a check shall be carried out to ensure that no
unauthorized persons are working at the corresponding load-where ever necessary
barriers should be provided.

3. Scope
• Testing of Transformer
• Checking Auxiliaries and cooling system
• Checking that the mounting position is correct,
• Testing of bushing CT
• Checking of correct Earthing,

Execution
3.1. Visual Inspection.
Prior to carrying out electrical tests, a visual check of the transformer should be
carried out paying particular attention to the following points
Correct labeling of devices and cables
Equipment and cables are undamaged
Correct execution of the cable gland/sealing end
Name plate data, match with drawing and ambient condition
Firm cable termination/terminal connection and ferruling

3.2. Testing of Transformer


Following tests to be carried out
1. insulation resistance / Polarization index test
2. Voltage Ratio Measurement
3. Vector Group/Phase Displacement
4. Winding Resistance Test
5. Excitation current Mesurment
6. Temperature indicator and sensor Caliberation
a. Winding Temperature
b. Oil Temperature
7. Bushing Current Transformer
8. Testing and commissioning of cooler control cabinet
9. Transformer protection devices functional check
10. Protective Earthing Checks

3.2.1. Insulation resistance/polarization index test


Checking of the insulation resistance and polarization index should be carried
out as under
The above contents may not be reproduced, transmitted,
or distributed to any form or by any means with out prior
permission of the originator
Page 4 of 9
Equipment : Auxiliary Transformer(<10MVA)
Date:13 Feb,09 Revision: 0

Apply the test voltage on following Connection and note down the readings
Two Winding Transformers
HV – LV + Earth
LV – HV + Earth
The insulation resistance Measurement is done from 15 seconds to 1 minute
with 15 seconds interval and then for every minute up to ten minutes. Value
obtained at 10 minute divided by value at 1 minute gives polarization index

Please refer below for connection and test arrangement

3.2.2. Voltage Ratio Measurement


The voltage ratio measurement for two or three winding power transformer
can be done either by conventional method by using Voltmeters or by using
Turns ratio Meter

The test shall be done for each and every phase at all tap position as follows.

For Two winding Transformer

The above contents may not be reproduced, transmitted,


or distributed to any form or by any means with out prior
permission of the originator
Page 5 of 9
Equipment : Auxiliary Transformer(<10MVA)
Date:13 Feb,09 Revision: 0

• Apply 3 phase Voltage more then 220V on HV Winding and measured


the corresponding voltages at the LV winding
• Note down both HV and LV winding side voltages on all the three
phases and all tap positions.

3.2.3. Vector group check


The vector group or phase relationship can be checked by injecting three
phase supply and measuring the voltages as per the figure below.

One of the phase say 1U and 2U between HV and LV should be shorted


together and three phase low voltage is applied on HV terminals.
Then the voltage between various pairs of line terminal should be measured
and compared

Example: condition for Dyn11 is, the voltage between

1W-2V> 1W-2W=1V-2W=1V-2V

3.2.4. Winding Resistance Measurement


The Winding resistance measurement can be done by either conventional
method using 2V DC battery with voltmeter and Ammeter or by Transformer
resistance meter.

The above contents may not be reproduced, transmitted,


or distributed to any form or by any means with out prior
permission of the originator
Page 6 of 9
Equipment : Auxiliary Transformer(<10MVA)
Date:13 Feb,09 Revision: 0
The winding resistance will be measured by a drop of potential method on all
windings by injecting direct current through the phase winding as shown
below.

For the Y connected transformer the measurement should be made between


each line bushing and single phase value is half of the measured value. For
the delta connection, the measurement should be made between each pair of
bushing and then single phase value is three half of the measured value.

The measured values should be compared with factory value, for that, a
conversion for the temperature correction should be done by following
formula.
R75 = Ra x 234.5+75
234.5+Ra

Where as R75 = Corrected Resitance in ohms


Ra = Measured Resistance at ambient temperature in ohms
Ta = Ambient temperature in 0 C
The above contents may not be reproduced, transmitted,
or distributed to any form or by any means with out prior
permission of the originator
Page 7 of 9
Equipment : Auxiliary Transformer(<10MVA)
Date:13 Feb,09 Revision: 0

3.2.5. Magnetization Current Measurement.


The test connection is done as shown in the following drawing. Apply 200 V to
the transformer HV terminals and measure the current and corresponding
voltage for all the tap position.

3.2.6. Oil Testing


Oil sample should be taken from bottom, top of the main tank, OLTC chamber
and also from the conservator tank,

De-electric test for the oil should be performed as per IEC 156 using de-
electric test machine

3.2.7. Temperature indicator and sensor.

3.2.7.1. Oil Temperature


The oil and winding temperature indicators shall be calibrated by heat
sink with thermometer.

3.2.7.2. Winding Temperature


The winding temperature indicator shall be checked by current injection
at the heater element.

3.2.8. Bushing current transformer


Following tests should be done on all the bushing transformers
• Ratio test
• Magnetization curve
• Polarity test
• Insulation test
• Winding resistance test
• Loop resistance test
All the test results shall be entered in the test form No.TS-CT01of the
transformer. Refer TP-CT01 for the test procedure

3.2.9. Testing and commissioning of cooler control cabinet


Prior to power up cooler control cabinet with auxiliary 3 phase/single
phase/dc voltage, following check up shall be carried out.
The above contents may not be reproduced, transmitted,
or distributed to any form or by any means with out prior
permission of the originator
Page 8 of 9
Equipment : Auxiliary Transformer(<10MVA)
Date:13 Feb,09 Revision: 0

 Winding insulation resistance and winding resistance for the fan motors
should be carried out.
 Insulation resistance test for the control circuit should be carried out.
 After obtaining all the results and found satisfactory auxiliary power can be
switched on and voltage/phase sequence measurement should be carried
out.
 Manual/auto operation of the fans should be checked
 Heater and lighting circuit should be checked and made functional.

3.2.10. Transformer protection devices functional check


 Trip and alarm should be simulated from buchholz relay. tripping of
protection relay and breakers should be observed, alarms on local and
remote annunciation shall be observed
 Trip and alarm should be simulated from pressure relay. tripping of
protection relay and breakers should be observed, alarms on local and
remote annunciation shall be observed
 Trip and alarm should be simulated from pressure relief relay. tripping of
protection relay and breakers should be observed, alarms on local and
remote annunciation shall be observed
 Trip and alarm should be simulated from oil and winding temperature
indicator. tripping of protection relay and breakers should be observed,
alarms on local and remote annunciation shall be observed
 Results for above tests shall be entered in the test form No.TS-AT01 of the
power transformer.

3.2.11. Protective Earthing Check


Transformer protective earthing bond must be earthed in order to afford
protection to human beings.

Documents
Test sheet TS-AT01 shall be completed.

References

The above contents may not be reproduced, transmitted,


or distributed to any form or by any means with out prior
permission of the originator
Page 9 of 9
Equipment : Auxiliary Transformer(<10MVA)
Date:13 Feb,09 Revision: 0
Attachment

Test Sheet for oil filled transformer 13.8/4.16KV: TS-AT01A

Test Sheet for oil filled transformer 13.8/0.480KV: TS-AT01B

Test Sheet for oil filled transformer 4.16/48KV: TS-AT01C

Test for Dry Type transformer: TS-AT01/D

***End of the procedure***