Operation Analytics MCQ
Operation Analytics MCQ
(1) If the number of rows and columns in an assignment problem are not equal
than it is called problem.
(a) prohibited
(b) infeasible
(c) unbounded
(d) unbalanced
(2) The method of solution of assignment problems is called
method.
(a) NWCR
(b) VAM
(c) LCM
(d) Hungarian
(3) When a maximization assignment problem is converted in minimization
problem, the resulting matrix is called .
(a) Cost matrix
(b) Profit matrix
(c) Regret matrix
(d) Dummy matrix
(4) The extra row or column which is added to balance an assignment problem
is called .
(a) regret
(b) epsilon
(c) dummy
(d) extra
(5) When a particular assignment in the given problem is not possible or
restricted as a condition, it is called a problem.
(a) infeasible
(b) degenerate
(c) unbalanced
(d) prohibited
(6) If in an assignment problem, number of rows is not equal to number of
columns then .
(a) Problem is degenerate
(b) Problem is unbalanced
(c) It is a maximization problem
(d) Optimal solution is not possible
[Ans.: (1 – unbalanced); (2 – Hungarian); (3 – Regret matrix);
(4 – Dummy); (5 – Prohibited); (6 – Problem is unbalanced)]
(1) The two types of costs involved in project crashing are and
costs.
(a) direct and indirect
(b) total and partial
(c) visible and invisible
(d) measurable and non-measurable
(2) In project crashing, rent and overheads are treated as costs.
(a) significant
(b) insignificant
(c) direct
(d) indirect
(3) In project crashing, the costs associated with actual activities (e.g.
manpower, materials, machinery etc.) are called costs.
(a) visible
(b) measurable
(c) direct
(d) indirect
(4) In project crashing, as we systematically crash the project, direct cost of
project and indirect cost of project .
(a) increases - decreases
(b) decreases - increases
(c) increases - remains same
(d) remain same - decreases
(5) In project crashing, as we systematically crash the project, total project cost
initially and after the optimal point, it .
(a) increases - decreases
(b) decreases - increases
(c) remains same - decreases
(d) decreases - remains same
[Ans.: (1 – direct, indirect); (2 – indirect); (3 – direct); (4 – increases,
decreases); (5 – decreases, increases)]
(1) The time required by each job on each machine is called time.
(a) elapsed
(b) idle
(c) processing
(d) average
(2) The order in which machines are required for completing the jobs is called
.
(a) machines order
(b) working order
(c) processing order
(d) job order
(3) The time between the starting of the first job and completion of the last job
in sequencing problems is called .
(a) total time
(b) assignment time
(c) elapsed time
(d) idle time
(4) The time during which a machine remains waiting or vacant in sequencing
problem is called time.
(a) processing
(b) waiting
(c) idle
(d) free
(5) In sequencing problem, the order of completion of jobs is called
.
(a) completion sequence
(b) job sequence
(c) processing order
(d) job order
(6) The total time required to complete all the jobs in a job sequencing problem
is known as .
(a) idle time
(b) processing time
(c) elapsed time
(d) processing order
[Ans.: (1 – processing); (2 – processing order); (3 – elapsed time); (4 – idle);
(5 – job sequence); (6 – elapsed time)]