Method Statement For Conduits Wiring
Method Statement For Conduits Wiring
PROJECT NAME
Page 1 of 8
CONTENTS
Page
Cover 1
Contents 2
1. Purpose 3
2. Scope of work 3
2.1 Activities Covered by This Method Statement 3
3. Standards & References 3
4. Resources 3
Materials 3
Manpower 3
5. Safety precautions 4
6. Responsibility 4
7. Pre-Construction Requirements 4
8. Equipment and Tools 4
9. Inspection of Incoming materials 4
10. Work Procedure 5
General 5
Bends 6
Pre-Installation 6
Installation of PVC Conduit and Boxes – Cast in Situ 6
Embedded conduits on walls 7
Exposed Conduit Installation 7
Bunching of wires 7
11. Inspections 8
12. Verification Records 8
Page 2 of 8
1. PURPOSE
The purpose of this document is to detail the Procedure for installation of conduits and
electrical switch boxes. This procedure applies to the same in concrete walls, slabs and
masonry walls. The documentation will apply to all Engineers, Workmen, QC personnel
and other concerned persons associated with the work.
2. SCOPE OF WORK
This Procedure covers the applicable codes, specification and standards, sequence of work
to be followed for the fixing of electrical trades preliminary installation items, manpower
requirements, tools and equipment required for the proper execution of works, quality and
required to complete the work in compliance to the satisfaction of consultant/client.
Materials
PVC Conduits of heavy-duty category or as per the specification.
MS Conduits - Solid drawn or lap welded, stove enamelled inside and outside with
minimum wall thickness of 1.6 mm up to 25 mm diameter and 2 mm for conduits
above 25 mm diameter associated with Equipment.
Saddles, junction boxes, sockets, and other accessories
Manpower
QC Engineers, Electricians, Supervisors and helpers and others who directly deal with the
responsibility of handling concrete from plant to the site.
Page 3 of 8
5. SAFETY PRECAUTIONS
Safety of the personnel and properties is to be given prime importance and all
works to be carried out without causing any accidents or property damages.
Materials shall be stacked properly near the place of work (Do not stack too
large quantity near the work area thereby causing safety hazard).
Height of the stack should not be more than one and half meter.
Working space to be clear of rubbish, waste mortar etc so that easy access and
cleanliness is ensured.
7. PRECONSTRUCTION REQUIREMENTS
Approved Good for construction drawing with latest revision issued shall be
available with the construction team
Shop drawings: Shop drawings for formwork shall be approved, stamped for GFC
by all the concerned parties for architectural floor plans,
8. EQUIPMENT & TOOL
Tube Level
Equipment to enable safe working at height.
Page 4 of 8
10. WORK PROCEDURE
10.1 General
After the conduits, junction boxes, outlet boxes and switch boxes are
installed in position, their outlets shall be properly plugged or covered so
that water, mortar, insects, or any other foreign matter does not enter the
conduit system.
The threads of pipe and sockets shall be free from grease and oil and shall
be thoroughly cleaned before making the screwed joints. All joints shall be
fully watertight.
Junction boxes and running joints shall be provided at suitable places to
allow for subsequent extension if any, without undue dismantling of conduit
system. As far as possible, diagonal run of conduits and adaptable boxes,
back outlet boxes, switch boxes and the like must be provided with entry
spouts and smooth PVC bushes.
Joint between conduit and iron clad distribution boards and control gear
shall be effected by means of conduit couplers into each of which will be
coupled smooth PVC bushes from the inside of box or case.
Conduit system shall be erect and straight as far as possible. To avoid traps
where water may accumulate from condensation and is unavoidable,
suitable provision for draining the water shall be made.
Separate conduits shall be run for 15 amps power outlet wiring. Separate
conduits connections for MS conduits shall be screwed metal to metal and
be painted with one coat of self-etching zinc chromate primer and two coats
of enamel paint. The threads and sockets shall be free from grease and oil.
Conduits for telephone system shall be at least 150 mm away from the
electrical conduits.
Page 5 of 8
10.2 Bends
Construction Manager/ Project (Site) Engineer shall check that proper tools
and equipment are available to carry out the work and are in compliance
with contract specification.
Safety Induction on HSE precautions to be given to all the
workers/Engineers carrying out the work. Daily toolbox talks shall be
conducted.
Only sufficient materials for a day’s work shall be shifted from store to site
for ensuring that extra materials are not dumped at site to avoid congestion
of working area.
10.4 Installation of PVC Conduit and Boxes – Cast In Situ
Marking the route of the conduit and position of boxes on the shuttering as
per approved drawings with proper measurement.
Fix the boxes at the exact locations. Boxes are to be filled with polystyrene
or suitable materials to avoid accumulation and hardening of cement
slurry/concrete.
Allow bottom layer of reinforcement to lay by civil contractor.
Page 6 of 8
of bends between boxes and maximum run of conduits in straight line
between boxes shall be maintained as per the standards/codes and details.
Conduit stubs in floor slabs shall be kept as short as possible above the
finished floor level, in order to avoid any damage to them
After installation of conduits pull strings/nylon ropes shall be pulled in the
conduit run for future purpose. A slack of 300mm minimum on both ends of
the conduits is considered.
After the installation of conduits top layer of the rebar works may
proceeded with.
Install the conduits as per the profile marked. Installation shall permit easy
drawing in of cables.
Outlets exposed to the weather shall be fully water tight, complete with
rubber gasketed covers; glass where used shall be heat resistant.
Wires carrying current shall be so bunched in the conduit that the outgoing and
return cables are drawn into the same conduit. Cables originating from two different
phases shall not be run in the same conduit.
Page 7 of 8
11. INSPECTIONS
Inspection to be carried out as per the Approved Inspection Test Plan and relevant
checklists as per Inspection Checklist is to be signed off.
Page 8 of 8