Program Narrative Report - 24 March 2011
Program Narrative Report - 24 March 2011
Subcontract‐# T2/22.10A&B Supply and Installation of Acoustic Metal & Gypsum
False Ceiling.
Subcontractor Detailed Program Narrative
Report and Methodology
Mumbai International Airport
Phase II
Subcontract‐# T2/22.10A&B Supply and Installation of Acoustic Metal & Gypsum False Ceiling
Subcontractor Detailed Program Narrative Report and Methodology
1. Introduction.
The intent of this narrative report is to present a description of how the Subcontractor
has formulated his detailed program of work. This narrative when read in conjunction
with the detailed program shall explain the sequence, logic and planning methodology
utilized by the Subcontractor when constructed his baseline program.
The Subcontractor has used a licensed Primavera Project Planner P3.1 Version to
develop this program and all the related manpower calculations and histograms and
resources.
1.1. Contents
This program narrative consists of the following detailed Sections:
• Contractual Compliance.
• Project Phasing Layout and Building Numbering.
• Program Structure and logic.
• Program Constraints – Definitions.
• Resources Loading.
1
Mumbai International Airport
Phase II
Subcontract‐# T2/22.10A&B Supply and Installation of Acoustic Metal & Gypsum False Ceiling
Subcontractor Detailed Program Narrative Report and Methodology
2. Contractual Compliance
This program has been developed based on the correspondences received from the
Contractor which are related to the accessibility to site constraints, also it defines clearly
the contractual milestones specified for the project completion and trials. Also it is to be
noted that all the contractually specified durations have been taken into consideration in
this program.
Moreover the sequence and breakdown structure has been also developed based on
the instructions received from the Contractor’s planning department.
2
Mumbai International Airport
Phase II
Subcontract‐# T2/22.10A&B Supply and Installation of Acoustic Metal & Gypsum False Ceiling
Subcontractor Detailed Program Narrative Report and Methodology
The below schematic Diagram shows the airport phasing according to the priorities
defined by the Contractor.
The entire Subcontractor’s scope of work includes the areas defined as Phase II.
Each Phase of the above phases has been internally divided into areas in which each
area has been later divided into floors/levels as per the following schematic diagram.
3
Mumbai International Airport
Phase II
Subcontract‐# T2/22.10A&B Supply and Installation of Acoustic Metal & Gypsum False Ceiling
Subcontractor Detailed Program Narrative Report and Methodology
4
Mumbai International Airport
Phase II
Subcontract‐# T2/22.10A&B Supply and Installation of Acoustic Metal & Gypsum False Ceiling
Subcontractor Detailed Program Narrative Report and Methodology
The program has been divided in addition to the previous two classifications to three
general global levels, under each level there are different types of classifications
according to the discipline or the physical sequence needed as per the following chart:
Accordingly, the program Layout has been organized using the above different levels of
organization and the activities have been Identified in the same manner as per the
following table.
This structure is also matching with the general structure specified by the Contractor
and sent to the Subcontractor via e-mail sent on 9th March 2011.
5
Mumbai International Airport
Phase II
Subcontract‐# T2/22.10A&B Supply and Installation of Acoustic Metal & Gypsum False Ceiling
Subcontractor Detailed Program Narrative Report and Methodology
6
Mumbai International Airport
Phase II
Subcontract‐# T2/22.10A&B Supply and Installation of Acoustic Metal & Gypsum False Ceiling
Subcontractor Detailed Program Narrative Report and Methodology
05 Area 5 3
1A Area 11A 3
DE Delivery to site 3
07 Area 7 4
7A Area 7A 4
09 Area 9 6
10 Area 10 6
9A Area 9A 6
08 Area 8 (Statue Area) 7
FLOR floor
1F 1st Level 1
P2 Phase II Finish dates 1
SU LD Submission 1
2F 2nd Level 2
AP Client Approval 2
M0 Mockups 2
P3 Phase III Finish dates 2
3F 3rd Level 3
4F 4th Level 4
7
Mumbai International Airport
Phase II
Subcontract‐# T2/22.10A&B Supply and Installation of Acoustic Metal & Gypsum False Ceiling
Subcontractor Detailed Program Narrative Report and Methodology
4. Subcontractor’s Sequence of Work and program constraint definition.
The priority for each building/Area has been defined previously by the Contractor as per
the following graph.
7 5 5 5 7
4 6 4
1 3 1
2 7
The above priority has been incorporated into the program based on the accessibility to
site.
The Accessibility to site also has been provided to the Subcontractor from the
Contractor via an email sent on 7th march 2011, where there is clear identification for
the Access for each individual building and individual level.
8
Mumbai International Airport
Phase II
Subcontract‐# T2/22.10A&B Supply and Installation of Acoustic Metal & Gypsum False Ceiling
Subcontractor Detailed Program Narrative Report and Methodology
The access dates shows in some buildings that the Subcontractor, will be having
access to the same level twice as per the restriction due to the existence of the statue.
It is to be noted that this access in order to be beneficial for the Subcontractor and to
help better progress on site, the access shall be preceding by the completion of all the
following activities to avoid any interruption or disruption of the Subcontractor’s work:
The Subcontractor will not proceed with installation of sub frames or paneling until
access document is officially signed off as being complete, by all responsible interfacing
or preceding Subcontract Trades.
The construction activities have been developed starting from the access date
milestone that has been constrained with an early start constraint as specified by the
Contractor followed by all the subsequent activities.
As per the project specifications and the supplier’s specification with reference to DIN
EN 13964, the installation of any acoustical panels will require a controlled environment
in terms of Temperature as well as the Humidity, this will require the Contractor to give
the Subcontractor the access associated with a closed envelop and supplied with a wild
air in order to control the Temperature and the Humidity.
The regimen of access controls to a great extent the peaks of the Manpower needed as
the access to the all buildings will be mostly given to each bundle of buildings in one
time span, this controls the existence of the Subcontractor’s manpower and creates
peaks and dips in the manpower histogram.
All the subsequent activities are linked to this start milestone as well as to the related
activity that has direct physical relation with this activity. Also all the construction
activities have predecessor activity related to the design, production, and delivery to
9
Mumbai International Airport
Phase II
Subcontract‐# T2/22.10A&B Supply and Installation of Acoustic Metal & Gypsum False Ceiling
Subcontractor Detailed Program Narrative Report and Methodology
site, this have controlled the closure of all open ends and ensures proper critical path
development.
The program has included some control activities that could be the driving factor to
proceed with the next step, in all cases these driving activities are related or should be
given by the Contractor to allow the Subcontractor to proceed forward. One of these
critical control activities is the receipt of the chandleries locations and hanging point that
will be affecting the commencement of design of the Subcontractor’s substructure and
bridging drawings and accordingly will affect the production of the substructure and
panel materials.
At the end of each phase, there is a particular section defining the finish milestone dates
for that particular phase as well as the project opening and trials.
10
Mumbai International Airport
Phase II
Subcontract‐# T2/22.10A&B Supply and Installation of Acoustic Metal & Gypsum False Ceiling
Subcontractor Detailed Program Narrative Report and Methodology
5. Subcontractor’s Material quantity and manpower
Loading
In order for better monitoring and controlling over the project, the program has been
fully loaded with the material quantity. This will help the Subcontractor to clearly
determine the required material from each type of the ceiling material for a certain
period, and to help the control over the inventory.
The Manpower histograms also help the Control over the required number of Manpower
per month or even per week. This will provide a clear image about the peaks that need
special measurements.
11