Schedule Booster Fan

The document provides a schedule for replacing a seal booster fan unit over 24 days. It includes 4 key steps: 1) preparation including safety training and equipment mobilization, 2) relocating the existing fan, 3) installing a new fan foundation with a 7 day curing period, and 4) installing the new fan motor and duct along with electrical work. A staffing plan is also provided listing roles for supervisors, foremen, skilled workers, and other positions needed each day.

Uploaded by

Marhendra
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
149 views1 page

Schedule Booster Fan

The document provides a schedule for replacing a seal booster fan unit over 24 days. It includes 4 key steps: 1) preparation including safety training and equipment mobilization, 2) relocating the existing fan, 3) installing a new fan foundation with a 7 day curing period, and 4) installing the new fan motor and duct along with electrical work. A staffing plan is also provided listing roles for supervisors, foremen, skilled workers, and other positions needed each day.

Uploaded by

Marhendra
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

SITE WORK SCHEDULE FOR REPLACE SEAL BOOSTER FAN UNIT 8 FOR REVIEW

VER : 01 (UPDATE 13/03/22)


DAYS
3/6 3/7 3/8 3/9 3/10 3/11 3/12 3/13 3/14 3/15 3/16 3/17 3/18 3/19 3/20 3/21 3/22 3/23 3/24 3/25 3/26 3/27 3/28
POMI PILAR 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
NO STEP OF WORK
scope scope D N D N D N D N D N D N D N D N D N D N D N D N D N D N D N D N D N D N D N D N D N D N D N

I PREPARATION
1 Safety Induction and Permit to Work 
2 Mobilisasi Equipment, Tools, Material, Labour 

II RELOCATION EXSISTING SEAL BOOSTER FAN


3 Install scaffolding for platform 
4 Disconnect electical wire 
5 Dismatling eksisting seal booster fan motor (include inlet duct) : 
6 Removal Foundation booster fan motor - Existing 

III INSTALL SEAL BOOSTER FAN FOUNDATION


7 Leveling foundation booster fan motor (grouting)  CURING TIME (7 DAYS)

IV INSTALL SEAL BOOSTER FAN MOTOR AND INLET TRANSITION DUCT


8 Mobilisation new inlet transititon duct from workshop to installation area  
9 Mobilisation new booster fan motor from warehouse to installation area  
10 Install new booster fan motor 
11 Install new inlet transititon duct 
12 Electrical installation - Tie in to new booster fan motor 

POMI PILAR 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
NO MANPOWER
scope scope D N D N D N D N D N D N D N D N D N D N D N D N D N D N D N D N D N D N D N D N D N D N D N
A Supervisior / Technical Advisor
1 Seal booster fan assembly SV 
2 Seal booster fan testing SV 
3 Commisioning SV 

B Worker / labor
1 Foreman  1 1 1 1 1 1 1 1 1 1 1 1 1
2 Skiller worker  2 2 4 4 4 4 4 4 4 4 4 3 3
3 Worker  3 3 5 5 5 5 5 5 5 5 5 5 5
4 Wiring specialist 
5 Testing worker  