Final Exam Spring2020

Uploaded by

Raznov -
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
24 views4 pages

Final Exam Spring2020

Uploaded by

Raznov -
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

EASTERN MEDITERRANEAN UNIVERSITY

DOĞU AKDENİZ ÜNİVERSİTESİ

FACULTY OF ENGINEERING

MÜHENDİSLİK FAKÜLTESİ

Department of Industrial Engineering


Endüstri Mühendisliği Bölümü

MANE112/IENG112
Final
20.06.2020 12:30-14:10
The rules of the final are these:
1. You may make an attempt to the solution of every problem.
3. The exam is closed book and notes exam.
4. Exaplanation and clarification of each question is required.

5. The duration of the exam is 100 minutes.


6. Not to write your name, student number, and signature failure will attract -5 points,
each.
7. NO QUESTIONS ARE ANSWERED!!!
1. (10 pts) On a single machine the data of the jobs are as follows:
Job A1 B2 C3 D4 E5 F6 G7
pj 3 5 1 7 15 3 2
dj 11 19 15 32 29 20 35
a. Solve 1||Tmax . What is Tmax ?
b. Solve 1||∑Cj . What is ∑Cj ?

2. (10 pts) There are two machines and four jobs in a flow shop problem. The processing
times are shown in the next table.
Job 1 2 3 4
p1j 13 2 18 4
P2j 5 23 6 15
Prepare the Gantt chart if
a. the order of jobs is the same order;
b. the order of jobs is 2, 3, 1, and 4.

3. (10 pts) The price of barley is 11 TL and 39.5 TL in years 3333 and 3334 respectively. Give
an extrapolative forecast for the year 3335 with 𝜶 = 𝟎. 𝟒.

4. (10 pts) What is the yearly installment of loan if it is paid back in 5 years if the loan is
1200 USD and the interest rate is 12 percent? (draw the time diagram and use compund
interest)

5. (10 pts) Your Company wants to establish a distribution center in a Manhattan-like


city. The distribution center must serve two retailers. The positions of the retailers
are as follows: Retailer 1 (2, 5), Retailer 2 (13, 8). Retailer 1 needs 26 transportation
per week, Retailer 2 needs 10 transportations per week. Where is the optimal position
of the distribution center?
6. (15 pts) Your company’s typical yearly consumption is described by the table below.
Make an ABC analysis.

Item Unit price (USD) Quantity

steel sheet 5.00 10,000

rivet 0.01 1,000,000

large nail 4.03 140,000

small nail 0.01 300,000

gadget 0.55 450,000

motor oil 3.40 35

paint 8.30 8,000

concrete column 100.00 500

hammer 35 300

cleaning liquid 6 100

packing box 70 800

7. (10pts) Complete a flow-process chart (material type) for the following engine
stripping, cleaning and degreasing operation.

Process description Chart symbol

In storeroom

By hoist to stripping bay

Strip engine, parts into basket

Part basket to degreaser

Degrease parts
Degreased parts to cleaning area,
dumped
wait to be cleaned

Put to bench and cleaned

Await transport

To inspection station
8. (10 pts) The product of Good Business Co. is gadget. Gadget is produced in a flow shop
technology of 2 machines. All processing times are 16 minutes. How many pieces of
gadget can be finished in the first hour of the shift if the machines are empty at the
beginning of the shift?

9. (15 pts) The daily production program of a workcenter is 30 pieces from part ST101,
20 pieces of LA98, 12 pieces of BG50, 15 pieces of K23, and 10 pieces of ST105. The set-
up times and the production times in minutes are in the table as follows:

Part Production time/ piece Part


ST101 LA98 BG50 K23 ST105
ST101 4 -- 5 6 7 9
LA98 6 8 -- 8 7 18
BG50 3 7 4 -- 6 5
K23 3 5 10 5 -- 7
ST105 5 5 7 4 4 --

The set-up time from the initial state to any product and from any product back to the
initial state is 5 minutes. The workcenter is in an initial state at the beginning and at
the end it must return to the initial state. What is the total time of the activity of the
machine if the production order

initial state → K23→ BG50 →LA98→ st101→ST105→initial state

is applied?