Saudi Aramco Inspection Checklist: Inspection of Structural Alignment During Erection SAIC-M-2007 30-Apr-13 Mech

1) The document is a checklist for inspecting the structural alignment during erection of equipment. It contains acceptance criteria and references standards for items like vertical tolerance, leveling, bracing, and welding. 2) The checklist evaluates things like if columns are plumbed and leveled before final connections, if base plates are set correctly, and if erection drawings show mark numbers and positions. 3) Attachments provide details on tolerances from standards like the AISC Code of Standard Practice for tolerances during erection and AWS D1.1 for welding distortion tolerances.

Uploaded by

pookkoya thangal
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
599 views15 pages

Saudi Aramco Inspection Checklist: Inspection of Structural Alignment During Erection SAIC-M-2007 30-Apr-13 Mech

1) The document is a checklist for inspecting the structural alignment during erection of equipment. It contains acceptance criteria and references standards for items like vertical tolerance, leveling, bracing, and welding. 2) The checklist evaluates things like if columns are plumbed and leveled before final connections, if base plates are set correctly, and if erection drawings show mark numbers and positions. 3) Attachments provide details on tolerances from standards like the AISC Code of Standard Practice for tolerances during erection and AWS D1.1 for welding distortion tolerances.

Uploaded by

pookkoya thangal
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 15

SAUDI ARAMCO ID/PID - REV 0- 18-May-05 (Standards Cutoff -March 2012) Rev 6 31-Mar-12

SAUDI ARAMCO INSPECTION CHECKLIST SAIC NUMBER DATE APPROVED QR NUMBER

Inspection Of Structural Alignment During Erection SAIC-M-2007 30-Apr-13 MECH -


PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.

LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.

SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?

SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

A General Requirements

Vertical Tolerance - Erected individual column & pieces:


The angular variation of the working line from a plumb line shall
12-SAMSS-008,
A1 be equal to or less than 1/500 of distance between working points.
Sec. I
AISC Code of Std Practice - Steel Bldgs & Bridges, Para.
7.13.1.1 & PIP STS0 5130, Para. 6.2.1.

Structure shall be plumbed, leveled, and braced before any final bolted or
12-SAMSS-008,
A2 welded connections are made (PIP STS05130, Par. 6.3.2). SATR-M-2001
Sec. I
or equivalent shall be used for record purpose.

Leveling plates, leveling nuts and washers and loose baseplates and
bearing plates are set in their correct alignment and elevation.
Variation in elevation relative to 12-SAMSS-008,
A3
established grade is equal to or less than plus or minus 1/8" (3mm). Sec. I
(AISC Code of Std Practice for Steel
Buildings & Bridges, Para. 7.6, & PIP STS05130, Para. 6.4.1) .

Columns or structures with attached base plates are temporarily supported


on leveling nuts, shims and other leveling devices and plumbed before 12-SAMSS-008,
A4
grouting. (AISC Code of Standard Practice for Steel Buildings and Bridges, Sec. I
Para. 7.7 & PIP STS05130, Para. 6.2.1)

All column splices shall be FIELD BOLTED & shall conform to:
AISC Detailing for Steel Construction, Appendix D. 12-SAMSS-007,
A5
Field Welded Column Splices (AISC Case VIII) Para.6.2.5.21
are prohibited.

Local Weld Distortion not addressed by AISC Code of Std Practice for Steel
Buildings & Bridges shall be found in the AWS D1.1 tolerances for welding. SAES-M-001 &
A6 Welding distortion & assessment shall 12-SAMSS-007
also be considered. AISC tolerances exceeded shall be Para. 6.1.6
approved by CSD.

Erection drawings shall clearly show the mark number and position for each
structure or yard area.
12-SAMSS-007
A7
Para. 6.4.5

REMARKS:

NOTES: 1. All survey and dimensional reports shall be recorded in the Structural Steel Alignment Report.
ATTACHMENTS FOR REFERENCE: Attachment 1 - AISC Code of Std Practice for Steel Bldgs & Bridges, (Erection & Other Tolerances)
Attachment 2 - Structural Steel Welding Reqmts & Tolerances at Saudi Aramco (Per AWS D1.1)
REFERENCE DOCUMENTS: 1- 12-SAMSS-008 -- Erection of Structural and Miscellaneous Steel, 09 May 2011
2- 12-SAMSS-007 -- Fabrication of Structural and Miscellaneous Steel, 17 May 2011
3- PIP STS05130 -- Erection of Structural and Miscellaneous Steel Specification, February 2002
4- AISC 303 -- Code of Standard Practice for Steel Buildings and Bridges, 18 March 2005

Contractor / Third-Party Saudi Aramco


Construction Representative* PMT Representative
Work is Complete and Ready for Inspection: T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Inspector PID Representative


Performed Inspection Work / Rework May Proceed T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Supervisor Proponent and Others


Quality Record Approved: T&I Witnessed QC Record Reviewed Work Verified
Name, Organization,
Name, Sign and Date:
Initials and Date:

*Person Responsible for Completion of Quality Work / Test Y = YES N = NO F = FAILED

Page 1 of 15
SAUDI ARAMCO ID/PID - REV 0- 18-May-05 (Standards Cutoff -March 2012) Rev 6 31-Mar-12

SAUDI ARAMCO INSPECTION CHECKLIST SAIC NUMBER DATE APPROVED QR NUMBER

Inspection Of Structural Alignment During Erection SAIC-M-2007 30-Apr-13 MECH -


Attachment 1 - AISC Code of Std Practice for Steel Bldgs & Bridges, (Erection & Other Tolerances)

Page 2 of 15
Page 3 of 15
Page 4 of 15
Page 5 of 15
Page 6 of 15
Page 7 of 15
Page 8 of 15
Page 9 of 15
Page 10 of 15
Page 11 of 15
Page 12 of 15
SAUDI ARAMCO ID/PID - REV 0- 18-May-05 (Standards Cutoff -March 2012) Rev 6 31-Mar-12

SAUDI ARAMCO INSPECTION CHECKLIST SAIC NUMBER DATE APPROVED QR NUMBER

Inspection Of Structural Alignment During Erection SAIC-M-2007 30-Apr-13 MECH -


Attachment 2 - Structural Steel Welding Reqmts & Tolerances at Saudi Aramco (Per AWS D1.1)
Erection Tolerances are in Attachment 1 (Per AISC Code). This is for Information Only.
AWS D1.1 WELDING DISTORTION TOLERANCES ARE LISTED BELOW (& 12-SAMSS-007 BASIS)

Attachment 2 - Structural Steel Welding Reqmts & Tolerances at Saudi Aramco (Per AWS D1.1)

Page 13 of 15
Attachment 2 - Structural Steel Welding Reqmts & Tolerances at Saudi Aramco (Per AWS D1.1)

Page 14 of 15
Page 15 of 15