Opgw Installation Manual
Opgw Installation Manual
Opgw Installation Manual
Contents
I. Introduction
7
Drawing for Installing Accessories of Straight Tower
4. Static End (strain) clamp Installation Procedure
(1) Pre-twisted wires are tied up by a color strip at an end to form a bunch that will be put
around optical cable. The color strip can be used as a kind of positioning mark. All the other
pre-twisted wires are also put around the cable and they reel together very tightly in the end
in order to cover all the equipments. Their ends must be arranged very tidily. Any tool should
not be used to cut them from upside as it may damage optical cable.
(2) The color marked place on pre-twisted wire is matched with the colored point on static ends
clamp and about 50 cm of its one side is winded. U type ring must be put inside the hollow
loop and adjusted to fit better in it by moving bolt. The color marked place on the second
static ends must be targeted to the colored point of the first static end that has been partially
around pre-twisted wire layer. The second static end should also be circled around the
external side of pre-twisted wire layer at the same length 50cm. Later, the rest part of static
ends should be fully circled around the pre-twisted layer while the two ends of pre-twisted
wire layer are bounded by tape. All the pre-twisted layers are fixed.
(3) U type ring is fixed to expansion control loop that will be put on the tower.
5. Overhanging Clamp Installation Procedures
Shenzhen SDG Information Co.,Ltd.
(1) A color mark exists in the middle of pre-twisted layer and a supporting wire is arranged in
the middle and spiraled down to two ends. Each supporting wire will be added nearby the
positioning color mark that is particularly used as the supporting wire for pre-twisted layer.
(2) Rubber insert is put on the middle color mark of the arranged pre-twisted layer. The seams
around case must be kept horizontal and adhesive strip is around the middle part of insert to
keep it from moving.
(3) As the middle of pre-twisted layer is over the insert, two entwined wires are positioned on
both sides of the insert and bended to the same extent as the insert is.
(4) Around the insert, other wires are added and should not be entwined with each other. They
should run parallel with the insert and have two ends neat. Please note that no tool is used to
cut them off on the top.
(5) Two halves of AGS case should be arranged on the two sides of assembly center. The AGS
splint must be settled in the right place and then tightened by a bolt passing through its
middle hole. It should not be fixed too tightly as its AGS case may be jammed. Overhanging
loop or fixings.
(6) Overhanging loop or fixings are connected on the tower.
6. Special Ground Wire
The system is grounded to leave a way for short circuit current. It is achieved by a certain
length of twisted aluminum wires to and well connected to hardware fittings and metal towers. Its
installation torch is 15N·M. As the parallel groove clamp can be directly connected with optical
cable, it is suggested to use it in order to ensure the good connection between optical cable and
grounding system.
7.Shock Absorber
Shock absorber is currently a kind of widely used accessory for shock preventing. It can be
positioned more than 50cm away from twisted wires in the hardware fittings while its low
frequency maul should face its head toward tower. During installation, the torque wrench is used
to prevent optical cable from bearing too much side pressure and its value must range around
8-12N·M.
VI. Sag and Tension
Sag is normally measured in the isometric testing method by means of the binding sag board
or in the varying length testing method with a theodolite due to different angles. The sag is
generally measured at somewhere overhead not far away from ground and with a representative
span.
1. After optical cable is installed over each span, sag and tension should be adjusted. The order
of adjusting sag and tension of a span usually from one end of the system to another end. The
general optical cable sag is measured along the whole optical cable line from the cable
spinner. The construction sag of OPGW cable should rely on its tension. Therefore, the sag
and tension of the optical cable between tension towers must be decided on topography and
Shenzhen SDG Information Co.,Ltd.
required headroom. If the headroom distance is below the required one, tension can be
increased to reduce sag. In the meantime, the reduction of sag will increase the tension of
optical cable. Therefore, the supplier’s OPGW optical cable must be tested whether it meets
the requirements for this span.
2. Terminals: enough optical cable is hauled into the generator room and ensured to arrive at
terminals and with enough excess for future connection.
3. erminal tower: pull-down clamp should be employed to fix the optical cable pulled down
from tower.
4. The loose excess cable must be moved and set on the tower among spans and unnecessary
imposed with press or even tension. In order to make room for the temporary static end
leading clamp, the loose excess cable is essentially moved in this way. After the loose optical
cable is removed, the tension machine is started in the inverted direction to pull optical cable
back to the cable coil. At this time, tension should not overpass half of maximum installation
tension.
5. Loose cable is removed to make room for temporary static end components a distance 1.5-2
times as long as the length of static end assembly (about 2-4 meters). Before installing the
permanent static end components, tension adjusting clamp should be used to maintain the sag
and tension among spans. As for towers and temporary static end, a set of equipments
connected to tension adjustment, including a chain winder, dynamometer and large size of
chains. After referring to the sheet of sag and tension, the loading is added and the tension
among spans started to be adjusted.
6. Generally, the order adjustment is required to go toward where cable coils are arranged one
span after another. The tensions in several spans can be adjusted at the same time, even if
several towers are existing in a series of spans. After the span tension is adjusted,
overhanging and straight hardware fittings in a span can be installed while temporary static
ends can be connected to towers in one time. When too large spans appear in the tension
adjustment on temporary static ends, the adjustment devices must be moved more often and
cost a longer time.
7. After the above procedures are done, permanent static ends can be overhung and how far the
colored band away from expansion control loop, inserted U type ring and static end hollow
loop can be measured. All the results will be recorded and used as reference to determine
whether permanent static ends can be installed there. As soon as the span tension is adjusted,
the reference distance between the span and tower should be measured. From this point,
structural enforcing layer (pre-twisted wire) is set and colored band is put at the measured
place on the optical cable. Once static ends are installed and hardware fittings are connected
to towers, the tension on the tension machine can be released and temporary static ends can
be removed. When permanent static ends should be installed on the nearby span, the
expansion control loop can be set under the static ends to help bend optical cable and keep its
Shenzhen SDG Information Co.,Ltd.
minimum bending radius, which means the shaped optical cable must located 14 inches lower
than the cable rack. The procedure will be repeated till sag and tension are adjusted for all the
spans in the whole system.
VII. Line Signal
Some striking signals should be used to differentiate optical cable from electrical cable.
These signals have two main functions or targets: one is to provide the directions of optical cable
for the line maintenance while the other is to prevent it from being stolen. The tags with
non-metallic optical cable or protection cable can be hung at somewhere more striking.
VIII. Data Storage
1. Suggestions for files: it is suggested to record and put in files all the following materials in
every system of optical cable
(1) Key maps: A key map refers to one geological drawing that contains the relationship
between the routing of this system and roads, it and highways. It is intended to provide rough
locations for us to find out some crucial areas in the system, for instance, connecting points
and where it crosses over main roads. The units (meter) of length must be put down on the
drawing in order to help find out connecting points and its intersections with roads and
rivers.
(2) Coil Distribution Chart: It is a linear chart to demonstrate the order of cable coil distribution
by the number of cable coils as well as marks for the lengths (meter) of major construction
places, such as connecting places and major road intersections. The length of every cable
coil in each section and the total length of optical cable should be marked on the chart.
Meanwhile, types and quantities of optical cable and optical fiber should be marked on every
section of cable coil.
(3) Construction Form: this form must present actual equipments in every tower, as well as other
materials about the tower types and specifications, the total distance from tower to each end
and other details about connection to ground and connection shield. In these forms, the
construction details can help correct and adjust any change happened in the installation.
(4) Line Form: it contains the line, system and quantity of optical fiber and the important results
of repairing the buffer
(5) Testing Record Sheet (Form): it records the output power, input power and the attenuation
level tested in the case of receiving. The OTDR curves or pictures of each optical fiber and
terminal pigtail should also be recorded in this sheet, which are acquired by inputting lights
of 1310nm and 1550nm wavelength from two directions. It is suggested that other materials
should include the average bidirectional loss at every connection and the pigtail continuous
loss containing the loss of inserting a connector.
(6) Materials proved by supplier: They conclude the data sheet of every coil of cable, the
electrical field strengths between different types of towers, suitable places for optical cable
installation as well as a chart of sag and tension.
Shenzhen SDG Information Co.,Ltd.
(7) Annual System Checking: After a cycle, the attenuation of this system will be identifiable,
steady and different from that in a test. It is suggested to find out reasons if the attenuation
has gone on seriously and even endangered the safety and reliability of communications.
After the optical cable line installation is finished and accepted, it becomes important to
collect and store all kinds of materials. These materials include (1) key map that demonstrate the
direction of optical cable in this line, (2) all kinds of forms used in the installation, (3) layout and
powerhouse distribution drawing that are generally provided by measure and design company, (4)
it is also essential to acquire the data sheet of optical cable and the sheet of sag and tension that are
provided by supplier and fulfilled with installation tension, operation tension and short circuit
current, etc. (5) the records of annually checking the attenuation of system, and so on. If the loss is
changing at 1dB/km, all the parts in this system should be carefully checked.