Topic 3
Topic 3
Project Crashing
Example Problem
3-2
Probabilistic Activity Times
a m b
3-3
Probabilistic Activity Times
= 25 weeks
2 = 62/9
= 6.9 (weeks)2
3-7
Probability Analysis of a Project Network
3-8
Probability Analysis of a Project Network
3-9
Probability Analysis of a Project Network
Table 3.2
3-10
Probability Analysis of a Project Network
What is the probability that the new order processing system will
be ready by 30 weeks?
µ = 25 weeks
2 = 6.9 = 2.63 weeks
Z = (x-)/ = (30 -25)/2.63 = 1.90
Z value of 1.90 corresponds to probability of 0.9713 in Table 3.2.
Probability of completing project in 30 weeks or less = 0.9713.
3-12
Probability Analysis of a Project Network
3-14
Probability Analysis of a Project Network
3-16
Project Crashing
Figure 3.6
3-18
Project Crashing
Table 3.3
3-19
Project Crashing
Figure 3.7: Network with Normal Activity times and weekly crashing
costs 3-20
Project Crashing
As activities are crashed, the critical path may change and several
paths may become critical.
3-22
Project Crashing
Example
j 1 2 3 4 5 6 7 8 9 10 11 12 13 14
8, 10, 12,
Prio. - 1 1 2 3 3 4 5,6 5,6 7
9 11
11
13
pj 5 6 9 12 7 12 10 6 10 9 7 8 7 5
cashj 3 5 7 9 5 9 8 3 7 5 4 5 5 2
cj 7 2 4 3 4 3 4 4 4 5 2 2 4 8
cjcash 20 25 20 15 30 40 35 25 30 20 25 35 20 10
3-24
Project Crashing
6 12 10
2 4 7 9
5 10
12 10 8 5
1
6 9 12 14
9 7 7
3 11 13
7 6
5 8
3-25
Project Crashing
6 12 10 9
processing time
2 4 7 10 8
5
12 10 12 5
S 1
6 9 14 T
9 7 7
3 11 13
7 6
5 8
longest path 56 1 3 6 9 11 12 14
3-26
Project Crashing
Minimum cut sets: {1}, {3}, {6}, {9}, {11}, {12}, {14}
3-27
Project Crashing
3 11
C3=4 C11=2
j 1 2 3 4 5 6 7 8 9 10 11 12 13 14
cj 7 2 4 3 4 3 4 4 4 5 2 2 4 8
3-28
Project Crashing
Activity N.time C.time N.Cost C.Cost Crash cost/pd Crash by Crashing cost
Project 56 37
1 5 3 7 20 6.5 2 13
2 6 5 2 25 23 1 23
3 9 7 4 20 8 2 16
4 12 9 3 15 4 3 12
5 7 5 4 30 13 0 0
6 12 9 3 40 12.33 3 37
7 10 8 4 35 15.5 2 31
8 6 3 4 25 7 0 0
9 10 7 4 30 8.67 3 26
10 9 5 5 20 3.75 4 15
11 7 4 2 25 7.67 3 23
12 8 5 2 35 11 3 33
13 7 5 4 20 8 2 16
14 5 2 8 10 .67 3 2
TOTALS 56 247
3-29
Project Crashing
6 12 10 9 processing time
2 4 7 10 7
5
12 10 12 5
S 1
6 9 14 T
9 7 7
3 11 13
7 6
5 8
3-30
Project Crashing
3 11 13
C3=4 C11=2 C13=4
j 1 2 3 4 5 6 7 8 9 10 11 12 13 14
cj 7 2 4 3 4 3 4 4 4 5 2 2 4 8
3-31
Project Crashing
C1=7
C6=3 C9=4 C12=2 C14=8
1
6 9 12 14
3 11 13
C3=4 C11=2 C13=14
3-32
Project Crashing
6 12 10 9 processing time
2 4 7 10 7
5
12 10 12 5
S 1
6 9 14 T
9 6 7
3 11 13
7 6
5 8
5 8
5 8
3-36
Example Problem
3-37
Example Problem
Solution
Step 1: Compute the expected activity times and variances.
2
b -
a
t a 4m b
v
6 6
3-38
Example Problem
Step 2: Determine the earliest and latest activity times & slacks
3-39
Example Problem
3-40
Example Problem
3-41
Home work
Immediate
Activity Optimistic Most Likely Pessimistic
predecessor
A - 76 86 120
B A 12 15 18
C B 4 5 6
D G 15 18 33
E D 18 21 24
F A 16 26 30
G C, F 10 13 22
H D 24 18 32
I A 22 27 50
J D, I 38 43 60
3-42