Disconnect and Earth Switch Test

The document outlines the steps for testing a disconnect and grounding switch, including: 1) Performing a mechanical check and visual inspection for physical defects, nameplate information, bolt connections, galvanizing, operation, contact pressure, gaps, stops, and grounding. 2) Conducting an electrical test by measuring resistance, testing interlocks, position contacts, motor operation, timing, voltage operation, insulation, and auxiliary contacts. 3) For bus bar isolators, checking main contact function and auxiliary switch contacts used for current transformer schemes during open/close timing tests.

Uploaded by

NAGARAJ
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
270 views2 pages

Disconnect and Earth Switch Test

The document outlines the steps for testing a disconnect and grounding switch, including: 1) Performing a mechanical check and visual inspection for physical defects, nameplate information, bolt connections, galvanizing, operation, contact pressure, gaps, stops, and grounding. 2) Conducting an electrical test by measuring resistance, testing interlocks, position contacts, motor operation, timing, voltage operation, insulation, and auxiliary contacts. 3) For bus bar isolators, checking main contact function and auxiliary switch contacts used for current transformer schemes during open/close timing tests.

Uploaded by

NAGARAJ
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

DISCONNECT AND GROUNDING SWITCH TEST

MECHANICAL CHECK AND VISUAL INSPECTION

ü Inspect for physical damage/defects

ü Check Nameplate Information for Correctness

ü Check Tightness of all Bolt Connections.(torque wrench)

ü Check quality of galvanizing (if applicable)

ü Check Smoothness and Easy Operation

ü Check Simultaneity and Synchronism of all 3poles during


closing

ü Check for Proper Contact, Fingers Spread and contact


Pressure in Fully Closed Position

ü Check Open gap and Min. Clearance Between phase and


to Ground

ü Check that end of travel stops are correctly, adjusted, set


and locked in position

ü Check that Switch is Pad-Lockable in Both Closed and


Open Position

ü Check switch opens more than 90˚(for horizontally


mounted vertical open disconnects)

ü Check switch drive linking toggled in both closed and open


position

ü Check that Grounding Connection is Securely Tightened


ü Check that Switch Operating Handle is Grounded
ü Check Mechanical Interlocking
ü Check that operator’s platform is of adequate size and
properly grounded

ELECTRICAL TEST

ü Measure resistance of main current path (terminal to terminal) at


100A DC.
ü Functional test of all electrical interlocks.
ü Check position-signaling contacts(if applicable)
ü For motor operated mechanisms:

a. Check mechanism cabinet is grounded.


b. Check correct setting of motor limit switched (open/close).
c. Check correct operation of all auxiliary “a” and “b” contacts.
d. Measure switch opening and closing times and motor current at
rated voltage (for fast acting disconnects and grounding switches,
perform a timing test with an oscillograph).
e. Minimum voltage operation (close and open) at 90V DC.
f. Functional checks of thermostat and space heaters. Measure heater
current.
g. Insulation test all control and power wiring /cables at 500V DC
h. Check that in the manual mode, insertion of the operating handle
automatically disconnects the motor DC supply.

ü For bus bar isolators, carefully check make and make before brake
contact function for auxiliary switch contacts used for CT switching
schemes during open close time test on disconnect main contacts.