This document provides details to get you quickly connected to RTU2020 controller
from RTU Builder. It does not provide any detailed instructions, programming advice or
expansion I/O configuration. Please see the listed references for additional details.
Various other documents are available in the RTU2020 Software Media Kit.
References
The following list identifies publications that may contain information relevant to the
information in this document.
Table of Contents
What You Need................................................................................................................... 3
RTU2020 Factory Default Network Settings ....................................................................... 3
Step 1: Install RTU Builder ........................................................................................... 3
Step 2: Power up RTU2020 ......................................................................................... 3
Step 3: Prepare to Change RTU2020’s IP Address ..................................................... 4
Step 4: Connect to RTU2020 and Download Project ................................................... 5
Step 5: You are Ready to Configure and Program Your RTU ...................................... 6
2. According to the RTU factory default network settings for Ethernet port
1 and Ethernet port 2 in the above table, connect an Ethernet cable to
the port most appropriate for your situation.
3. Connect the other end of the Ethernet cable to your RTU Builder
computer directly or through a switch.
For full instructions on how to install RTU2020 controller, see the RTU2020
Hardware Planning and Installation User’s Guide.
2. From Start Page, click Create Project. The Create New Project from
Template window appears.
3. In the Available Templates list, click the default template.
5. From Home Page, click the arrow next to Configure Ethernet Ports
under Communication.
6. Select the target port and the corresponding configuration interface
appears.
7. Under Network Setting, select Use the following IP address and
type IP Address, Subnet Mask and Gateway.
8. Under Protocol Binding, make sure to select RTU Configuration
Protocol check box.
This is the protocol RTU Builder uses to communicate to RTU2020. If it
is not selected, RTU Builder cannot communicate to the RTU through
that port.
9. If you need a SCADA system or other devices to communicate to this
RTU, then you should select the other relevant protocols. E.g.,
‘Modbus TCP Slave’ might be used for a SCADA system.
TIP: If an Ethernet port is not required, if you do not plug a cable into
that port, then the RTU will consume less power. This is irrespective of
the configuration of that port. Port 1 consumes more power than port 2.
If only one port is required and power consumption is important, then
we recommend using port 2.
10. Click Save to save the changes and click Back to return to Home Page.