Resource Allocation
Resource Allocation
RESOURCE OPTIMIZATION
TECHNIQUES:
RESOURCE LEVELLING VS
RESOURCE SMOOTHING
RESOURCE ALLOCATION
• Resource allocation is the process of assigning and scheduling available
resources in the most effective and economical manner.
• Projects will always need resources and resources are scarce. The task
therefore lies with the project manager to determine the proper timing
of those resources within the project schedule.
• The resources of an organization consist of people, materials, equipment,
knowledge and time.
• Organizations typically have limited resources; therefore, tradeoffs on
what project resources are expended and when are made every day
within organizations.
• A resource allocation plan is an important tool in effective management
of scarce resources.
RESOURCE ALLOCATION
• With regard to resource constrains, a project manager may face one of
the following two situations, these two techniques known as Resource
optimization techniques-
1. Resource Leveling
2. Resource Smoothing
RESOURCE LEVELING
• In Resource levelling, the objective of the project manager is to level as
far as possible the demand for resources through out the project
execution time.
• By keeping in mind the constraint that the specified project completion
time should not be exceeded.
• The specified project completion time may be minimum possible time by
which the project can be completed a ascertained by identifying the
critical path.
RESOURCE LEVELING
• This technique is used when sharing of critical resources is required
between different projects in an organization, or have been over
allocated to some activities, which are being performed concurrently
within a project, or in other projects in an organization.
• Thus the resource demand exceeds the supply of resources.
• This technique ensures balance between resources demand and their
supply.
• For example, resource A is assigned to an activity on Project XYZ on a day,
for 8 hours. This resource is also allocated to Project LMN for 8 hours in a
day. By resource leveling, resource A is allocated to Project XYZ for 4
hours and to Project LMN for 4 hours a day. By resource leveling, the
duration of Project XYZ will increase. Resource leveling increases the
duration of an activity, and may also change the critical path.
RESOURCE LEVELING
• There are different methods for levelling a resource. Depending on activity
requirements, their priorities, availability of resources, time duration or
considering other constraints we level a resource.
1. Increase activity duration
By increasing the activity duration, the resource's hours will be split on more days,
resulting in lesser hours per day.