Building Management
Fulkerson’s Rule
The starting event (having no predecessor activity is
numbered as 1 )
other events are numbered in increasing order from 1 to
rightwards
if there are more then 1 initial event found in a diagram ,
anywhere they are to be numbered from top to bottom in
increase order.
No two events can have the same number in any case.
Fulkerson’s Rule
Q W
P
T
R X
U
Fulkerson’s Rule
S
3 5
Q W
P
1 2 T 7
R X
U
4 6
Fulkerson’s Rule
For large and complex projects, skip numbering is used
In skip numbering events are numbered as
10,20,30,40,50,…….
This system permits more detailed activities which can be
incorporated in between.
And these activities can be named as 11-12, 12-13, 13-14,
14-15……….
Fulkerson’s Rule
B I
E
A H
C F J
G
Fulkerson’s Rule
D
30 60
B I
E
A H
10 20 50 80
C F J
G
40 70