AIA Report QQ 2177 Final
AIA Report QQ 2177 Final
AIA Report QQ 2177 Final
1. Precleaners
2. Dehuskers
3. Graders.
4. Bucket elevators
5. Aspirators and Blowers
6. Conditioning and dehusking.
7. Splitting
8. Sortex
9. Polishing and bagging
10. Heaters/ dryers.
Human resources at the industry:
Particulars Quantity Wages (Rs)
Manager 1 15000/month
Labour: 350/day
a) Male 4
b) Female: 0
Mistri 2 350/day
Hamal 5 Varies
The first step in dal milling is pre-cleaning i.e., removing of rocks, dust,
etc. with the help of pre-cleaner machine. The cleaned dal comes up
in tank for drying through cup lines. The dried dal is then coated with
water and oil for further processing. Then the splitting of dal takes
place for dividing dal into two parts. Dehusking process takes place in
dehushker for removing the husk from dal. In one pass or single
operation, about 50% of pulses are de-husked. The husk is converted
into animal feed called as chunni. Then grading of dal takes place in
sortex machine, dal id divided and separated into 3 to 4 qualities. Once
again, the dal is heated and then water polishing of dal is done for
giving shine. Lastly the dal is ready for packaging.
I. RAW PILSES
II. CLEANING
III. DRYING
IV. WATER AND OIL COATING
V. SPILITING
VI. DEHUSKING
VII. GRADING
VIII. HEATING
IX. WATER POLISHING
X. PACKAGING
Economics of the Industry:
➤ Overall
Conclusion