Transformer Method Statement
Transformer Method Statement
Transformer Method Statement
Installation
The method statement for transformer defines the installation of oil-type transformers as per
quality procedure, project specifications, and health, safety & environmental requirements.
Scope of Work
The scope of this document includes, but not limited to the following:
a) Methodology for installation of transformers
b) Equipment used
c) Inspection and Test Plans
d) HSE Assessment & Job Hazard Assessment
Definitions/Abbreviations
IFC-Issued for Construction
SUB-Subcontractor
IR-Inspection Request
ITP-Inspection and Test Plan
HSE-Health, Safety, and Environment
PPE-Personal Protective Equipment
RA-Risk Assessment
MIR-Material Inspection request
MST-Method Statement
NCR-Non-Conformance report
QA/QC-Quality Assurance/ Quality Control
PQP-Project Quality Plan
RAMS-Risk Assessment Method Statement
PTW-Permit To Work
LV-Low Voltage (415 V)
VFD-Variable Frequency Drive
MV-Medium Voltage
SMDB-Sub Main Distribution Board
Sequence of Works
The following are the step by step procedure for the installation of transformer.
a. All relevant documentation such as (Approved Shop drawings, Checklist and Approved
Method Statement etc.) and the material applicable to a particular section of work will be
checked by the Site engineer prior to the commencement of work ensuring that these are of
the correct type as reviewed by the Engineer
b. Before commencement of installation of transformer, a material inspection of the
transformer will be carried out prior to being withdrawn from the storage area i.e. quantity,
physical damage and brand/make.
c. Before the beginning of the installation, it will be ensured that the approved valid permit to
work (PTW) is available on site.
d. Engineer in charge will ensure that approval and standard tools and tackles are available to
carry out the work.
e. Safe access to work areas will be provided and will be approved by the competent safety
person prior to commencement of works if applicable
f. Check the work area tidy and remove flammable materials if any and a safe environment
will be ensured.
g. Where the Risk Assessment identifies high-risk works a permit to work will be obtained
from the safety department.
h. Competent manpower will be employed to carry out the installation work.
i. Prior to installation, It will be ensured that all the civil works are completed with the
necessary protective floor coating (if needed).
j. Necessary civil clearance will be obtained (if applicable) prior to the start of installation.
k. For loading and unloading operation, the proposed crane location to be ready with the
compacted floor for safe positioning of crane and boom trucks.
l. The boom truck loading capacity and certificates will be ensured prior to the start of the
loading.
m. The transformer will be unloaded in a pre-identified place for necessary material
inspections prior to installation.
n. Once the inspection completed the transformers will be shifted and positioned by using a
boom truck.
Material Transport
a. Transformers and other related accessories will be handled and transported and unloaded at
site strictly as per manufacturers instruction.
b. After delivery, equipment will be inspected for any transport both internal and external
components casing damage, in compliance with project specification & materials submittal.
c. The transformers and accessories will be tagged, crated, and protected for shipping as per
the manufacturer’s recommendation.
d. Approved shop drawings will be posted at the workplace for site reference used and
installation works.
a. When the transformer cannot be installed immediately, Transformers and other related
accessories will be stored at a dry location in the laydown area. They will be protected and
covered by polythene sheeting.
b. The transformers will be handled with care to prevent mechanical damage to the body,
fitments, enclosures, and core-coil assemblies.
c. The transformers are factory packed for transport and will be protected as per
manufacturers’ instruction.
d. Check for the transformer packing for any damages while transportation will be done.
e. A material delivery to the site will be inspected for delivered equipment for approval from
the engineer.
f. On receipt of the transformer, It is necessary to carry out the following check:
1. To check there are no signs of damage on packing or the transformer occurred
probably during the transport.
2. The characteristics of the transformer detailed on the rating plate must correspond to
those of the shipping documents and with those of the test report, which is attached to
the transformer.
3. Check the nameplate details against the technical datasheet to confirm the correct
materials.
4. To check that each transformer is complete with the accessories foreseen in the
contract (wheels, thermo-controller, etc.).
g. All the delivered spare parts as per project specifications to be stored properly till
handover.
h. The transformer should not be placed, close to the ground where water might accumulate.
In such cases, the transformer should be placed on wooden or similar beams in order to
prevent rust formation due to scratches and contact with wet soil/ground directly.
i. Any discrepancies, damage, and etc, found to the materials will be notified and reported to
QA/QC Engineer.
j. Materials found not suitable for site use will be removed immediately.
k. No materials will be permitted to enter the work location without being inspected and
approved by the Engineer.
Handling
a. During the transport or the handling, only the recommended special lifting eyes and tow
attachments are used.
b. All lifting equipment will be rated for the purpose, checked for damage, and certified by a
third party before any attempts are made to lift the transformers.
c. If a crane will be used to lift the equipment, it will be ensured that the slings are harnessed
in such a way that the equipment is centered to the gravitational force to avoid wobbling and
jerking which may cause fatal and serious troubles in unloading.
a. For lifting the upper frame of the transformer is complete with lifting eyes for slings. Lift
with a maximum sling angle of 60 degrees.
b. Always move the transformer in its upright (top end up) position.
c. Lifting operations will be performed by trained people for using cranes.
d. Lifting will also be performed by a forklift with sufficient capacity if the transformer is
placed on a pallet. It will be operated by a trained person.
e. For movement by forklift the position of the forks under the bottom clamping profile will
be as far apart as practicable. This has to be lifted only a small amount above the floor
surface at all times during transit.
f. The transformers cannot be moved to push the coil and the connections.
g. Care will be taken by the site team that no tools or bits of metal hardware are dropped into
the coils or not damage the cast resin during handling and installation.
Methodology
Transformer Installation
a. It will be ensured that installation of the liquid-filled medium voltage transformers will be
strictly in accordance with the manufacturer’s recommendations, as per approved shop
drawings, relevant IEC (International Electrotechnical Commission) standards, and
project specifications.
b. It is ensured that the access is clear to shift the transformer. The substation doors are
checked to ensure that the door openings are enough to move the transformer inside the
substation.
c. The transformers will be unloaded adjacent to the respective substation.
d. Move the transformer manually to the transformer location.
e. For manual handling, rollers are used to facilitate forward motion to find the erection place.
Note: The transformer should not be moved by pushing the coils and connection.
f. After the transformer positioning, all wheels will be locked to arrest any movement of the
transformer by providing the necessary stopper.
g. Recommended shims will be installed if required for transformer leveling.
h. All the incoming and outgoing cable supports, cable ends and termination fittings required
for MV, LV, and control cables will be installed.
i. Inspection request for transformer installation prior to the start of any cable termination
work will be done.
j. The transformers will be mounted on wheels.
k. The transformer skids shall have rounded off beam ends and shall be provided with pulling
lugs/holes to enable site movements.
l. It will be ensured that concrete bases and foundations provided for installation of
equipment are constructed in accordance with approved shop drawings, construction
drawings, and equipment manufacturer’s drawings. All the holes for fixings bolts and
provisions for passage of cables etc. are provided as required.
m. It will be ensured that trench construction and covers provided for installation of power
and control cables are in accordance with approved shop and construction drawings.
n. The installation of cables, wires, raceways, supports, cable ends, and termination fittings
will be done in accordance with the appropriate sections of the project specification and/or as
shown on the approved shop drawings. All the electrical connectors and terminals will be
tightened according to the manufacturer’s published torque-tightening values.
Cable Connections
a. The cables which are connected to the transformer will be fixed properly to avoid any
mechanical stress on the transformer terminals.
b. Cable connecting boxes shall be made of steel and shall be dimensioned to allow
termination of the specified cables.
c. The enclosures will be offered a minimum degree of protection IP55, in accordance with
IEC 60529 and as per project specifications.
d. The cable ends should be flexible enough to prevent mechanical strains that could be
caused by expansion and contraction, which could break the isolators, when available.
e. Contact surface of the cable terminations will be checked. If it is necessary, it will be
brushed and wiped with a dry cloth.
f. Separate cable connecting boxes shall be provided for the connection of the specified
cables to:
g. Auxiliary and low voltage cable connecting boxes shall be air-insulated as per project
specifications.
h. The covers of all cable boxes will be secured, using non-loosening bolts or screws. The
cover of all cable boxes will not be removable without the use of tools.
Final Works
Emergency Preparedness
The Project Manager & Project HSE Manager shall ensure that all employees are aware of
the correct response to various emergency situations.
The response guidelines applicable for these works are the following:
Upon discovering the incident, take the time to assess the situation to make the area safe and
to prevent further injury to those involved. Take appropriate precautions according to the type
of damage and cause of accident like:
Vehicle Accident
a) Switch off the vehicle’s ignition and warn the people not to smoke.
b) Make use of bystanders to control traffic or crowds, to call for help, and if they are
capable, to assist with first aid.
Electrical Accident
a) Switch off the current or break contact between the injured person and the power source.
b) Do not touch the victim or any live wires! Use non-conducting material, such as dry sticks
to remove wires from the casualty.
c) Ensure that the current is turned off or that loose wires are kept at a safe distance until the
casualty is removed to the safe area.
d) Do not approach fallen high-tension power lines until a power company official gives
permission.
e) Apply artificial respiration if necessary.
Machinery Accident
a) Shut off the source and remove the casualty to fresh air.
b) Do not enter a confined space and become another victim.
Electricity
a. Before using an electric tool, check the tool and its plug and connecting cable.
b. Do not use damaged tools.
c. Do not use an electric tool unless its connecting cable is well protected.
a. Unless you are a worker concerned, do not work in an area where a lifter, crane
(mobile/tower), etc. is in operation.
b. Do not operate any load shifting machinery without training and approval.
c. Operators of forklift trucks, bulldozers, loaders, excavators, trucks should possess
appropriate certificates/ Passes.
a. Power tools inspection program will be in place with periodic training and skill
development for operators.
b. Where ever possible battery-operated tools or 110V power tools will be used which will
reduce the risk levels.
Do not panic, the first priority in the case of any accident is to obtain proper medical
assistance for the victim. The following steps should be followed in the event of an accident.
a. Upon discovering an accident, call to attract the attention of others nearby to assist and
ensure any injured person is no further danger.
b. Assess the hazards at the scene and make the area safe for yourself, the victim, and others.
c. Typical hazards to be aware of are; live electrical lines, moving equipment or machinery,
traffic, hazardous chemicals, and fire. Only moved the victim if they are in immediate danger.
d. Send someone to call for emergency help. Locate the nearest First Aiders or any personnel
trained in first aid. If no available qualified personnel, locate the nearest radio or telephone
and call the office or ambulance.
Fire
Raise the alarm at once. Proceed to the nearest telephone or radio and ask whoever is present
to call the fire services or do so yourself. Attack the fore with correct firefighting
extinguishers or other suitable firefighting equipment.
A roll call of all employees shall be taken when premises have had to be evacuated. Each
section shall nominate a Fire Warden who, in case of an emergency shall undertake the
following duties:
a. Keep a check of personnel movements so that an accurate roll call can be made.
b. Alert the remainder of the office of the emergency.
c. Supervise the orderly exit as per the emergency exit plan.
d. Check the staff numbers.
e. Ensure the personnel does not leave the assembly area until counted.
f. Advise emergency services if any person remains unaccounted for. The emergency exit
plan shall be prepared by the HSE Manager and will show the positions of all exits.
Noise Control
Dust Control
PPE is the last line of defense not the first: however, every contractor should provide
adequate
suitable, sufficient PPE to protect the workforce wherever possible. As a minimum for all
personal during the abutment works will be the hat, safety boots, coveralls, goggles, and
gloves will
be provided and used at all times. Additional task-specific PPE will be provided and worn in
line
with risk assessments.
Emergency Procedures
This procedure describes the company’s guidelines on emergency responses to ensure prompt
and safe action is taken. This procedure applies to all health, safety, and environmental
emergencies with particular emphasis on the company’s requirement in the event of personal
injury accidents or fire emergencies.
General
The Project Manager in coordination with the Project HSE Manager shall ensure that the
project has in place a viable and up-to-date Emergency Response plan. This plan shall
include allocated responsibilities, contact detail for project personnel, contact details for local
authorities, contact details for group personnel off-site, emergency response action, and maps
as a minimum.
Communication
As a minimum HSE manager shall ensure that HSE communication Flow and Emergency
Telephone numbers are complete, kept up to date, and circulated on Project HSE Notice
Boards. The PM with close coordination with the HSE manager shall take all necessary steps
to ensure that this information is communicated and understood by all employees and sub-
contractors working on site. It takes all necessary steps to ensure that the workplace has
adequate reliable means of communication internally and as required outside communication.
Emergency Response
The emergency response shall be initiated by Authorized Person. Emergency response as per
the HSE plan shall be followed.
In case of an emergency, the following actions shall be activated: Stop the activity.
Call the emergency number for help.
Provide first aid and call an ambulance.
Alert site clinic / Nurse/ First aider.
Quality Controls
The Inspection and Test Plan (ITP) for this Method Statement For Transformer Installation
summarizes various characteristics to be checked. The concerned Site Engineer or Site
Supervisor will be responsible to ensure compliance for these operations and the site QA/QC
Engineer will carry out quality control checks and report the inspection results.
Quality Records
Quality records will be provided as identified in the ITP and maintained as per ISO
9001/2015 & Standard form of records, quality checklists, and QA/QC reports requirements
are defined in the Inspection and Test Plan.
Submission of as-built records will be done after completion.
a. All works will be undertaken in compliance with the quality requirements of the Contract
and “Project Quality Management Plan”. Where non-conformances are found/identified to
demonstrate its conformity. All works requiring inspection and testing to demonstrate
conformity with requirements will be undertaken in accordance with the “Control of
Inspection and Testing”.
b. Where non-conformities are found/identified, they will be addressed in accordance with
“Procedure for Control of Non-Conformances”. The quality control activities associated with
the works will be conveyed to all personnel involved in the execution of the works by the
Project QA/QC Manager prior to the commencement of the work.
c. The equipment and instruments used for measurements on-site will be calibrated and
certified. The relevant documents will accompany the corresponding equipment and
instruments. Necessary internal and external training are provided to the staff carrying out the
job to ensure that the quality standards required on the project are met. Skilled and competent
personnel are deployed to undertake the job.
Resource Planning
Project Manager
a. Project Manager (MEP) will be responsible to manage, execute, complete and handover the
construction activities within approved budgets and resources in compliance with Project
requirements as specified in Project Specifications. He will be overall in charge of
implementing the method statement for transformer installation in accordance with QA/QC
and HSE requirements.
b. Responsible for controlling the project’s entire activities & for the overall coordination
with the consultant/client.
c. Ensure that adequate welfare facilities and equipment are provided to the project to avoid
injury, health impairment, or damage & to ensure providing quality works within the planned
time scale.
d. All responsibilities stated in the Project’s Quality Assurance Plan.
Construction Manager
a. Organize the site so that work is carried out to the required specifications with minimum
risk to men, equipment, and materials.
b. Coordination with different functions with the project.
c. Expediting area of concern to achieve project schedule.
d. Adhere to the project-specific quality management program and HSE requirements.
e. Delivering the overall works in a safe and timely manner, ensuring conformance with the
approved design. Leading the team of engineers and surveyors, guiding them in the delivery
of the works. Acquire, allocate and maintain resources.
QA/QC Manager
a. Responsible for the work of entire quality assurance, quality control & inspection
programs.
b. Produce all quality-related documents & reports necessary as requested by the
Owner/Consultant/Engineer.
c. Provide written procedures & to coordinate in formalizing the Method Statements with the
Project Manager/ Construction Managers/Site Engineers to describe the job-specific work for
each stage/activity.
d. All responsibilities stated in the Project’s Quality Assurance Plan.
QA/QC Engineer
a. Responsible for the work of entire Quality Assurance, Quality Control & inspection
programs.
b. Produce all Quality related documents & necessary quality reports as requested.
c. Provide written procedures & coordinate in formalizing the Method Statements with the
Construction Manager/Site Engineers to describe the job-specific work for each
stage/activity.
d. Will make sure that all the works mentioned in this method statement will carry out in
approved shop drawings and as per the project specification.
e. Will make sure IR for all these activities are raised and approved by the consultant and
recording those documents for testing, commissioning, and for handing over the procedure.
Safety Manager
a. Manage Safety Engineers and Safety Officers to be in strict conformance with project
policies and procedures.
b. Must ensure safe work method of stated in the method statement for transformer
installation and RA is fully implemented during activity.
c. Responsible for controlling HSE personnel for effective monitoring of work.
d. Over-see site safety orientations/inductions, toolbox talks, safety training certifications, job
site inspections, working at heights, scaffolding tagging systems are fully functional, rigging,
etc.
e. Report to Project Manager all personal injuries and near-miss incidents (aligned with
Safety Engineers / Officers) as well as property damages immediately. Produce investigative
reports and summaries to senior management.
Safety Officer
a. Provide advice and coordination in line with the project HSE Plan, legislation, and
standards to workgroups as required/directed.
b. Input into the preparation and maintenance Risk Register at the project level which will
form the basis of risk management on the project for the RAMS.
c. Monitoring and reporting compliance with the Project HSE Plan.
d. Conducting regular HSE inspections and participating in HSE audits.
e. Reporting as required, HSE incidents, including near-miss events, injuries, and any other
HSE issues.
f. Regularly attending toolbox and other HSE meetings.
g. Will ensure that the work site has been examined, and all precautions specified to be taken
in the PTW before work commences have in fact been taken.
h. Will ensure that the works are examined on completion of the works and the PTW is
correctly closed.
Site Engineer
a. Adheres to the project-specific method statements, procedures, inspection programs &
HSE instructions to get the activities performed to Client satisfaction with full coordination
with the HSE & Quality personnel.
b. Responsible to ensure that correct drawings, materials, tools, and equipment are provided
site.
c. Liaising with sub-contractors, supervisors, planners, quantity surveyors, and the general
workforce involved in the project.
d. Responsible for planning the work and efficiently organizing the plan and site facilities in
order to meet agreed-on deadlines.
e. Site engineer is responsible to coordinate with QA/QC Team engineers/ inspectors, and to
handover daily site progress works report/highlighted drawings & present during
inspection/site visit with QA/QC Inspectors & consultant/client.
Foreman
a. Performed the activities instructed by the Supervisor/Engineer at the site and follow the
safety procedures to make it safe for his workers.
b. In charged to lead the work execution send the focal point in coordinating with the site
Supervisor/Engineer related to overall site activity, materials, tools, and equipment.
Technician
a. Carry out Installation work as per the concerned foreman’s instructions with all the safety
requirements.
b. The workforce to attend daily toolbox talks, morning task brief briefs prior to starting any
works EHS (Environment Health Standard) plans and policies.
Workforce
a. Carry out their work in such a way that they don’t create for themselves or any other
person risk to health safety, and don’t impact the environment to the maximum extent
possible or affect the quality of work.
Document Controller
a. Documenting, distributing, and maintaining data in the prescribed format.
b. Making the necessary data available as requested by the team or the client.
Tools and Equipment
a. Hand tools box (Spanner set, cutting pliers, tube cutter, screwdriver set, hammer, hacksaw
frame & flat file, cleaning brush, spirit levels)
b. Adjustable wrench
c. Splice kit
d. Mobile scaffold
e. Ladder
f. Pallet jack
g. Drilling machine
h. Crowbars
i. Torque wrench
j. Plumb bob, nylon thread
k. Heavy air compressor/vacuum cleaner
l. Sling ropes
m. Ratchet and spanners-various sizes and extensions
n. Crimping tool
o. 3rd party certified lifting equipment (Chain pulley, A-frame chain hoist and etc.)
p. Boom truck
q. Forklift
The foremen and engineers on-site will ensure that all necessary equipment is available as
well as fit and safe prior to commencement of work.
a. All Equipment used on the works will have a valid certificate of operation provided by a
recognized licensing authority.