Project Proposal For The Construction of Mixed Use Building: Promoter:-Mr - Mohammednazif Aba Mecha
Project Proposal For The Construction of Mixed Use Building: Promoter:-Mr - Mohammednazif Aba Mecha
August, 2021
Project Proposal for Mr.MohammedNazif Aba Mecha G+3 Mixed
use Building construction
Contents pages
1. Executive Summary.........................................................................................................4
2. Introduction......................................................................................................................5
2.1. General Background.....................................................................................................5
2.2. Objective of the project................................................................................................7
2.3. Project description........................................................................................................8
2.4. Project Rationale...........................................................................................................9
2.5. The significance of the project.....................................................................................9
2.6. Project Location..........................................................................................................11
3. The market Study...........................................................................................................11
3.1. Market Analysis..........................................................................................................11
3.2. The Demand-Supply Gap...........................................................................................12
3.3. Current supply of mixed use building........................................................................13
3.4. Future market or Demand of commercial Building rental..........................................14
3.5. Target customers.........................................................................................................15
3.6. Marketing promotion and strategy..............................................................................15
3.7. Competition................................................................................................................16
3.8. The project facilities and Services plan......................................................................17
4. Technical Study.............................................................................................................18
4.1. Description of the project Service/ Product mix.........................................................18
4.2. Construction work and Technology............................................................................19
4.3. Utilities.......................................................................................................................23
5. Engineering and civil works..........................................................................................24
5.1. Land, Building and Civil Works.................................................................................24
5.2.Man Power...................................................................................................................25
5.3. Project implementation...............................................................................................27
5.4.Organizational Structure..............................................................................................27
5.4.1. Organization and management................................................................................27
Project Proposal for Mr.MohammedNazif Aba Mecha G+3 Mixed
use Building construction
List of table
List of Figures
1. Executive Summary
Key information highlights
Production capacity G +3
Products to be manufactured
Rental rooms
Source of fund 30% or 3300024.915 etb from owner equity and the
rest 70% from bank loan.
Social and economic benefit: Provide better building service, employment opportunities,
generation of income and benefits for the local people
Analysis result
The project is technically feasible, financially and commercially viable as well as socially and economically
acceptable. Hence, the project is worth implementing.
2. Introduction
Project Proposal for Mr.MohammedNazif Aba Mecha G+3 Mixed
use Building construction
Sarbo town is one of more economically stable town in Jimma zone popular in
Chat,Cereal Crop,Fruits and Vegetatn Coffee and livestock market. Mixed use building
will be owned and operated by Mr Mohammed Nezif Aba Mecha, whom are resident for
long time in the district planned to construct mixed use building in Sarbo town Thus,This
project feasibility study is undertaken to check the market, technical and financial
feasibility of this project. The business will be operated as a Private ownership and will
offer supermarkets, Beauty salon, shops, offices Computer and mobile Center,
Cafeterias, restaurant, boutiques, textile fashion, baby clothe, assembly hall, guest house
and other activities, pharmaceutical, as well as novelty items. Recently Sarbo town is
becoming convenience for such investment and the growing demand of better economic
service. To realize this mixed use building plays a crucial role to promote the growth of
the town in one hand and to reduce the growing demand of commercial house. The socio-
economic environment of the town
The promoter is very ambitious and committed to realize the project. Hence, they expects
to get the necessary support from the city administration to make the project to be
operational.
Project Proposal for Mr.MohammedNazif Aba Mecha G+3 Mixed
use Building construction
Looking at the past trends and permits issues by the Government to the
construction of real estate properties including the mixed use building in the
major urban areas of the country specially in Addis Ababa one can easily conclude that
the momentum is more likely to continue.
Besides, the government polices and incentives for the private sector investment are very
promising that motivates the promoter to engaged in mixed use building business.
The primary objective of this project is to gives quality and convenient services to the
customer on their demand and to facilitate Urbanization of towns, targeting in
government policies.
Provide restaurant and hotels service to serve growing market demand and to address
the needs of the community;
create an economically viable development that will contributes to the national
economy through creating job opportunities to unemployment, generating tax
revenue to bodies of the government and facilitating supply and service availability
in the market.
To construct and develop modern shops, offices, and restaurant, bedroom & cafeteria
facilities that enable to provide standard services to visitors.
To undertake trading and other refuted business activities that enable to generate a
reasonable to the invested capital.
Project Proposal for Mr.MohammedNazif Aba Mecha G+3 Mixed
use Building construction
To develop modern business centre that would provide product and services to meet
the market demand with efficient and quality to attract foreign visitors and thereby
contribute towards the generation of hard currency for the country.
Contribute towards the development of the town through the construction of modern
building infrastructure and facilities.
during this time period. The owner plans the project to render banking and insurance,
shopping facility, and cafeteria services to create high quality class to satisfy the interest
of customers in the town. Based on environmental and other considerations, the
entrepreneur has determined the type and size of the building which is already
determined by the site; conceptual planning and preliminary analysis have been carried
out by analysts.
The Economic growth and rapid urbanization in the country is promising investment
opportunities, the demands of product and service needs along with relatively sound
investment support made by the government in such kinds of feasible projects, compelled
the project promoter to initiate the multipurpose oriented business project to be
established. Despite the promising business opportunities of the town, the trend on such
kinds of investment found to not enough. The mismatch between the demand for and
supply of such kind of services in easily observed in the town.
Therefore, the existing shortage or absence in the supply of these services, along with its
commercial and administrative access, better location and infrastructure access,
escalating trend of urbanization and business activities, thus it is with such reason that
this project is identified and proposed and assumed to be more profitable.
Project Proposal for Mr.MohammedNazif Aba Mecha G+3 Mixed
use Building construction
In general, the country’s privatized and free market economy; good governance creates a
favorable environment for the development of investment for private investors.
A. Source of Revenue
As public policy of any nation, the government collects different forms of taxes from
different business organizations and individuals. Among the different forms of taxes,
business income taxes, payroll income tax and VAT are collected from undertaking
business activities. Therefore, the building will serve as sources of revenue for the town
as well as for the region.
B. Employment opportunity
One of the problems that our country faced is unemployment. Therefore, the current
objective of the government is working on tackling the problem of unemployment and
fostering the development process either through creating self employment or
employment in other organization. Hence, this project will hire 23 individuals and more
than eighty individual during construction.
In addition to serving as a source of employment and income for the region, the project
renders social services for different group of people. Hence, it is also provide the
following services;
Since, the center encompasses different recreational areas; it will divert the attention
of the users from different evil deeds.
Project Proposal for Mr.MohammedNazif Aba Mecha G+3 Mixed
use Building construction
It deemed to minimize the demand for shops and other bundles of services in the area.
Furthermore, it serves as the pilot experience and ground for other investor to enter in to
such kinds of urban development. It also contributes on the efforts made on as a character
given building for physical development pattern of the townscape.
Sarbo town is a have its own administrative unit (municipal) under Kersa woreda in
Jimma zone of the Oromia regional state.Sarbo town is the Capital town of Kersa district
and a center of socio-economic activity The town is surrounded by rural kebele of Kersa
woreda as it is being the administrative center of Kersa woreda.
The envisioned project is intended to be located in Sarbo town at about 335 km from
Addis Ababa to the south west. The town is selected because of strategic economic hub
for different cash crop like Chat,coffee, and also Fruits and vegetation and livestock. The
town have access to basic social service like 24 hr electric service, telecom, post office,
and clean water. The town’s economic catchment extends beyond the Kersa woreda
attracting investor from Tiro Afeta district and Jimma town as well.
The rapid growth of population along with urbanization, Increasing income and
modernity of town dweller and surrounding population residents are currently purchasing
“specialty” items in Jimma town that will be replaced provided by this project in Sarbo
town. Recently the increase in the price of Chat,Fruit and vegetable,Livestock and coffee
has increased the power of population for market. Town residents and surrounding area
population presently purchase everyday “necessity” items from small scale shop ‘Kiosk’
kebele house which does not allow satisfactory commercial activity and poor in
construction. On the other hand it’s not convenient to get goods and service in one
location which will waste time and price as well. People who purchase goods from such
small shop express dissatisfaction with availability and price. People travel to Jimma
town to fulfill their market demand, and the same is true for businessman to get
convenient rental shop they leave the town.
There are three major customer groups: (1) Local entrepreneurs (2) Diaspora looking for
essential business shop (2) surrounding town businessmen and entrepreneur (3) Whole
sale and distributer of good and service from big city, who look for convenience yet are
relatively price sensitive.
choose a healthy comfortable climate that combines a more traditional type with that of
modern shops, offices, bedrooms restaurants and cafeterias. Even though the town is
older town in the region Sarbo town seems to have no developed mixed use building, the
existing supply is far behind the growing demand for standard service. Hence, the project
will solve the serous demand problem in the town.
Over the last decade, there has been a significant growth in the number of local and
international trades across the country. Merchant from Jimma town from central market
and foreign trader starts to come to the town. This increase is mainly associated with the
stimulation of economic activist and partly due to an increase in the flow of international
and local traders in to the town. Since Sarbo town is an important commercial center in
addition there is a significant increase in business activates and hence increasing the
number of traders to the town. Even though there is a lack of quantitative estimates that
number of traders to the town. Even though there is a lack of quantitative estimates that
depict the actual demand and also the annual growth rate Hotel facilities and urban
commercial facilities are scarce in the city. So far in the town there is no development of
such kind standard building and it is the first of its kind in the town and will promote
other investors from the town and the surrounding areas. They are mostly villa type
premises modified as show rooms and sailing posits. As a result there is a large gap
between the developed and that of the supply for modern bed rooms; Bank and cafeteria
accommodation hence this project would not face any problem of demand scarcity for it
business centre and it would provide good service to customers.
buildings are the large increases in national and international businesses, particularly
firms in the services sector.
The business of multipurpose buildings in Sarbo Town in booming highly due to the
recent rapid growth experienced in Ethiopia. As a result, a good number of local and
international organizational are coming in place. Government offices which used to
operate in limited spaces all over the city are also concentrating on leasing new and
modern buildings. Increasing numbers of international organization and NGOs which in
the past had typically converted residences into office space are now moving towards
renting whole floors or even multiple floors in modern city-center commercial buildings.
Following our survey of office space users in Sarbo town are mainly firms providing
banking, cafeteria and restaurants, bed room, supermarkets service, computer Center
Crevice. The different customers for commercial buildings also include shops and offices
that are currently renting out to provide their goods and services.
Future demand for office space is actually driven from growth in number of offices in the
city which in turn is influenced by the macro-economic growth in the country. Following
the government five year growth and transformation plan (GTP), the Ethiopian economy
is expected to increase by 11% for base case scenario and 14% under the optimistic case
scenario. Assuming that demand for office space is directly related to the growth in the
economy, the forecast for office space demand is shown in the following table;
1. business Community
6. Nongovernmental organizations
In order to penetrate and gain considerable market share, one of the major marketing
strategies for the project is consistently rendering quality service to its tenants. Due
emphasis must be placed on improving quality of service and facilities. The major
marketing strategies to promote the project and gain considerable market share include:
Using advertising means like Banner, Business card, internet channel and pages.
Keeping the quality of its service/ facilities and consistently improving with
changing situations.
3.7. Competition
There are different forms of competition that may face the envisaged mixed use building.
These are price and non price based competition.Moreover, there are different
competitors that will compete with the project either directly or indirectly. Mixed Use
commercial building desires to set a precedent in Sarbo town as a full service
convenience shop, store and service rendering with an economical image, offering a wide
range of competitively priced products and services in one location. Need of residents
and surrounding population combined with the consistent popularity of convenience
market predict a favorable business climate for MohammedNazif Aba Mecha Mixed use
building.
Project Proposal for Mr.MohammedNazif Aba Mecha G+3 Mixed
use Building construction
Table 2.The plan is that the ground will be partitioned in to different rooms:
1st floor Beauty salon, shop, Computer Center, Cafeteria & M2 200
Restaurant
Total
Since the project will be engaged in mixed building the main sources of its annual
revenue would be from the rental of building spaces such as shops, offices, and banking,
café & restaurant bedrooms. Therefore, the sources of revenue have been classified in to
one category namely the rental of banking & supermarket, offices, shops, bedrooms
restaurant and café based on these classifications. Based on the market price of similar
mixed use building in the area, the envisioned buildings set the following fair price
Project Proposal for Mr.MohammedNazif Aba Mecha G+3 Mixed
use Building construction
(Before VAT) for its service, hence when the building construction fully get operational
it is assumed to generate a yearly income of ETB 971,662.12.
4. Technical Study
4.1. Description of the project Service/ Product mix
The envisioned mixed purpose building will provide different rental services to the
different customer groups for different purpose. The building will have basement, ground
and eight floors. The purpose of the building explained as follows;
the ground floor, first floor and second floor designed for different business
centers like banks, supermarket, beauty salon(man and women), Computer
center, pharmacy, internet café, boutiques, different shops and other business
activities,
Besides, the buildings will have enough parking facility for its customers and green area
in its compound.
The total land required for the envisioned project is estimated to be 400 m 2 . the total area
for the construction of the building will be 200 m2, as revealed below.
SN Description Land M2
Project Proposal for Mr.MohammedNazif Aba Mecha G+3 Mixed
use Building construction
1 Building (G+3)
Total 400
The Building Enclosure Phase includes erecting the scaffolding that will allow for
exterior sheathing installation and bricklaying.
Mechanical and Electrical install coincide with each other due to the need for
coordination between the two divisions. There are several periods of construction during
the schedule in which there are multiple construction activities occurring at the same
time.
Project Proposal for Mr.MohammedNazif Aba Mecha G+3 Mixed
use Building construction
The construction site must be organized accordingly as these processes take place. As
with any construction project, the goal of the schedule was to complete all construction
activities before the required Date of completion.
This date of completion is practical based on the time of year in which the building will
be completed. The team allowed a two week contingency for any setbacks. Typically,
winter construction tends to cause unforeseen delays that negatively impact a
construction project. These conditions can and will almost undoubtedly impact the
project schedule by causing unforeseen delays and project inefficiency.
Although functional spaces for the project were laid out in significant detail, the rest of
the building had designated spaces but n set layouts. It was at the discretion of the project
promoter to devise typical layouts for the non-detailed commercial and office spaces.
To make sure that the building’s layouts were practical, the project owner researched
typical architectural layouts for laboratory and executive office spaces. The walls and
partitions throughout the floor were congruent with the structural frame and column
locations.
One of principle deliverables of our project is the structural design of the building. The
structural bays were coordinated with the layout of the building adjustments were made
to the bays if specific layouts are necessary. The frame was made up of a grid with
repeating standard structural bays. Included in the structural system are bay sizes, shape
and size of structural members, floor compositions and curtain walls. These elements
were established to resist gravity ad lateral loads as appropriate.
Project Proposal for Mr.MohammedNazif Aba Mecha G+3 Mixed
use Building construction
The gravity load design was completed for two frames; one of structural steel and one of
reinforced concrete. The structural steel frame was chosen for further design based on
cost per square foot, local availability of material and constructability considerations,
such as erection and fabrication. The steel system was then designed for lateral loading
with necessary adjustment being made to framing.
The project group prepared hand structural design calculations for a typical bay of a
reinforced concrete frame. In all reinforced concrete bay designs, a superimposed dead
load of 7.5 pounds per square foot was assumed for mechanical equipment, floor
coverings and ceilings.
Similarly, the design of the typical bay accounted for the use of different commercial
space, in which a live load of 125 pounds per square was assumed. Loads were calculated
based on the requirements of the minimum Design loads for Buildings and other
Structures.
The design of a superstructure may be accurate, have considered all possibilities and still
fail because the substructure is incapable of distributing the applied loads to the
supporting soil.
Foundation design takes more into consideration than merely the loading from the
columns. While the main part of the project focused on the structural frame and its
alternate designs, a preliminary foundation plan was designed based upon maximum load
carried from the superstructure through the columns. The foundation design conducted by
the project team consisted of the selection of foundation type, determination of the
bearing capacity and the design for typical interior and exterior spread footings.
The project team developed a coordinated project schedule and construction plans that
would reflect the expectations for an actual construction project. The project schedule
was developed using the preliminary designs given to the project team.
Additionally, the group considered typical construction activities and durations taken
from similar construction projects as well as realistic constraints on building
development. For instance, it is necessary for the structural frame to be completed before
concrete can be placed for the slab on deck. Hand drawn construction plans detailing site
entrances and storage areas were coordinated with the project schedule to give the reader
visualizations of the construction site set up through various periods of the construction
process.
The construction process for this project is normally a disjointed three mages
development by which the conceptualized need of the promoter of this project is
translated into a functional facility that will meet their needs in terms of time, cost and
quality.
Based on a general program of the project owners the consultant who is going to be hired
makes site studies, develops structural designs, prepares drawings and specifications,
determines quantities involved and estimated the resultants costs. All these activities will
be done in the first phase of the project which is the design stage after the document are
produced by the designers have been received, and the works secured the project is
supposed to enter the tendering stage. At this stage contractors study the project
document analyze and subsequently determine the construction methods, built up their
unit rates and submit their bids for the works. The promoter of this project intends to
compare the bids and award the contract for the lowest responsible bidder. This, is of
course, presupposes that the favorable proposal does not exceed the allocated budget.
After the award is made and the contract signed between this project owner and the
contractor, the project constructor is expected to prepare and submits a detailed
Project Proposal for Mr.MohammedNazif Aba Mecha G+3 Mixed
use Building construction
construction program which includes material schedule, manpower requirement and cash
flow forecast.
After the award is made and the contract signed between this project owner and the
contractor, the project constructor is expected to prepare and submits a detailed
construction program which includes material schedule, manpower requirement and cash
flow forecast.
4.3. Utilities
A number of utilities world be put in place in order to ensure smooth functioning of the
project. These utilities include:
Water Supply,
Drainage Facility
A. SUB-
STRACTU
RE
1 excavation and
earth works 110,324.12
B. SUPER
STRACTU
RE
1 Concrete work 1,100,358.45
3 Roofing 110,193.00
4 Carpentry and
joinery 98,760.00
6 Finishing 1,051,379.44
7 Painting 108,398.88
8 Electrical
installation 400,532.00
9 Sanitary
installation 750,057.00
Subtotal 4,411,868.17
A+B 5,868,192.29
As shown on Table 5, the total cost of building and civil work is estimated at Birr
Project Proposal for Mr.MohammedNazif Aba Mecha G+3 Mixed
use Building construction
6,850,000 and out of which the proponent has worked more than birr 5.86 million.
The list of manpower and the annual cost of labor is indicated in Table 5.
Total 23 315,000
Workers for this type of plant are available throughout the year. No foreseeable problems
are expected as most of the work requires no previous skills.
SN Activities Date
5.4.Organizational Structure
5.4.1. Organization and management
The organizational structure should be in a way that the company able to achieve its
objectives as well as the satisfaction of standard requirement. In addition to this, the
structure should fit the dynamics of all customers in the building ranging from small
business to large tenants.
Organizational Structure
The organizational structure of the project is designed by including all the necessary
personnel under the right division. At the top of the organizational structure, there will be
manager with the responsibility of supervising the overall activity of the building.
Depending up on the nature of the center and the amount of work to be performs; there
exist auxiliary units under the general manager.
Employees under each unit will be supervised by the department head that is accountable
for the general manager. General Manager is appointed by owner.
Owner
General
Manager
Building Admin Marketing Technical and
maintenance
Project Proposal for Mr.MohammedNazif Aba Mecha G+3 Mixed
manager
use Building construction
Cashier Purchas
er
Under building admin dept there exist two sections i.e., HRM & finance and general
service. Further sub sections are also organized under technical and maintenance
manager. The following section deals with the duties and responsibilities of each
department.
He/she will plan, organize, direct and control the overall activities of the building.
Project Proposal for Mr.MohammedNazif Aba Mecha G+3 Mixed
use Building construction
He/she will devise policies and strategies that will enable the center to be profitable.
He/she will incorporate modern technological innovation that will facilitate the
service delivery of the building to increase customer’s satisfaction.
He/she will plan, organize, direct and control the human and non-human resources of
the building so as to achieve the short and long run objectives of the organization.
The building Administration Department of the multipurpose building has two main
sections (HRM and Finance and General Service section). It has responsible for
undertaking the following activities;
Well non human resources of the project, which include; effective handling of the
different resources of the building, and devise strategies of controlling against
fraud and damage.
Will provide the right material or inventory to the center with right price at the
right time.
Will plan, organize direct and control the financial transaction of the building by
using all the necessary documents.
Accountant and casher that will collect money from the customers.
Will prepare the annual financial statements and prepare condensed reports for
both the General Manager and other concerned government body.
Project Proposal for Mr.MohammedNazif Aba Mecha G+3 Mixed
use Building construction
Follow the overall status of the business and provide maintenance and repair
services
Will handle the overall marketing activities of the organization which include
planning, organizing, directing, and controlling.
Works in collaboration with general service to make sure tenants are well served
Total 7,060,396.50
6 Total 394,800.00
C. Vehicle
Total 1,500,000.00
D. Office Equipments
Total 186,500.00
5.5.2..Working Capital
1 Audit and legal SN Audit and legal 24,000.00 2000 br/per ,month
fee fee
10 Oil & Iubricants 9 Oil & Iubricants 6,300.00 10% of fuel cost
11 Telephone & fax 10 Telephone & fax 18,000.00 1500 per month
Total 50,000.00
3 Vehicle 1,500,000.00
The financial analysis of the mixed use building is based on the data provided in the
preceding sections and the following assumptions.
B. depreciation
Project Proposal for Mr.MohammedNazif Aba Mecha G+3 Mixed
use Building construction
Building 10%
The source of fund to finance the project is planned to be from two sources. These are
promoter’s equity and bank loan. The loan is expected to be obtained from one of the
local lending institutions. Since the project is expected to take some times to repay all its
debts, the bank loan is assumed to obtain on long term credit basis. Taking the financial
position of the promoters into account, equity contribution and bank loan to finance the
total investment outlays of the project are assumed to be 30% and 70% respectively.
Accordingly, the total financial requirement from the two sources will be;
Total annual
yea Principal Interest rate year ending
Payment in
r payment (8.5%) balance
ETB
Project Proposal for Mr.MohammedNazif Aba Mecha G+3 Mixed
use Building construction
0 7700058.135
10 63356.09415 0
Assumtion
Equipments
Expenses
Cash payment
Investment 9,141,697 0 0 0 0
Project Proposal for Mr.MohammedNazif Aba Mecha G+3 Mixed
use Building construction
According to the projected income statement, the building will start generating profit in
the 2nd year of operation. Important ration such as profit to total sales, net profit to equity
(Return on equity) and net profit plus interest on total investment (return on total
investment) show as increasing trend during the lifetime of the project. The income
statement and the other indicators of profitability show that the project is viable.
The EIA of the project activities was determined by identifying the environmental aspects
and then undertaking an environmental risk assessment to determine the significant
environmental aspects. The environmental impact assessment has included all phases of
the project namely construction phase and operational phase.
Being exemplary for other investors who want to engage in the same business
line.
There are some noises during the construction due to the construction operation
and the company will use construct the construction during the day time. Again
there is the emission of dust which will be mitigated by sprinkling water on the
service.
During construction there are some problems that will materialize on workers. These are:
damage on operation by using machines, construction materials and others. To mitigate
such impact the company will provide safety insurance and safety equipments.
Project Proposal for Mr.MohammedNazif Aba Mecha G+3 Mixed
use Building construction
During operation there are some wastes emitting from the mixed use building. These are
wastes from the latrine and will be mitigated by using modern waste treatment
technology.