100% found this document useful (1 vote)
444 views3 pages

Total Quality Management Multiple Choice Questions and Answers. Page 9

This document contains multiple choice questions and answers about total quality management. It discusses key topics like the focal point of quality control being the customer, key process variables being developed during the measurement phase, and the probability of rolling a die and getting a number greater than 4 being 1/3. Cause and effect diagrams can be used in the analyze and improve steps of DMAIC. Acceptance sampling is not useful when 100% inspection cost is very low. If only natural causes of variation are present, the output of a process forms a predictable distribution over time. For an x-bar chart, beta risk can be defined as the probability of not detecting a shift in the process mean from the in-control value to a new value.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
444 views3 pages

Total Quality Management Multiple Choice Questions and Answers. Page 9

This document contains multiple choice questions and answers about total quality management. It discusses key topics like the focal point of quality control being the customer, key process variables being developed during the measurement phase, and the probability of rolling a die and getting a number greater than 4 being 1/3. Cause and effect diagrams can be used in the analyze and improve steps of DMAIC. Acceptance sampling is not useful when 100% inspection cost is very low. If only natural causes of variation are present, the output of a process forms a predictable distribution over time. For an x-bar chart, beta risk can be defined as the probability of not detecting a shift in the process mean from the in-control value to a new value.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

01/03/2022, 09:09 Total Quality Management Multiple choice Questions and Answers. Page 9.

Home
Home > Total Quality Management > Page 9

Accounting for Managers


Total Quality Management
Advertising and Sales Promotion

81. The focal point of all quality control should be:


Behavioural and Allied Sciences

A. Price focus
Brand Management
B. Cost Focus
Business Communication
C. Customer Focus

Business Economics D. Manufacturing Focus

Business Environment View answer

Business Ethics and Governance


Correct answer: (C)

Customer Focus
Business Law

Business Mathematics
82. The key process input variables (KPIV) and key process output variables are developed during the ______________ phase.

Business Statistics
A. Define

Computers In Management B. Analyze

C. Measure
Cost and Managerial Accounting
D. Improve
E-Business
View answer
English Language

Correct answer: (C)

Entrepreneurship Management
Measure

Financial Management

83. An unbiased dice is rolled once. The probability of getting a number greater than 4 is:
Human Resource Management

Insurance and Risk Management A. ¼

B. 1/6
Management Information Systems
C. ½
Marketing Management D. 1/3

Media Planning View answer

Operations Research
Correct answer: (D)

Organisational Behavior 1/3

Principles and Practices of


84. Which of the following statement is false:
Management

Production and Operations A. Important step of strategic quality management is identification of those dimensions in which the organization will compete
Management
B. Selection of suppliers should be based on quality, schedule, and cost, rather than on cost alone

System Analysis and Design C. All of the individuals in the organization must have an understanding of the basic tools of quality improvement

D. Manufacturing Unit should be the unit focusing on Quality Improvement among all units in an organization
Total Quality Management

View answer

Correct answer: (D)

Manufacturing Unit should be the unit focusing on Quality Improvement among all units in an organization

85. Cause and Effect Diagram can be used in the ______________ and ______________ step of DMAIC.

A. Define, Measure

B. Analyze, Control

C. Analyze, Improve

D. Define, Improve

View answer

https://www.mbamcq.com/total-quality-management/9.php 1/3
01/03/2022, 09:09 Total Quality Management Multiple choice Questions and Answers. Page 9.

Correct answer: (C)

Analyze, Improve

86. Which of the following is false regarding when acceptance sampling is useful:

A. When testing is destructive

B. When 100% inspection cost is very low

C. When there are potentially serious product liability risk

D. When 100% inspection is not technically feasible

View answer

Correct answer: (B)

When 100% inspection cost is very low

87. Let p0 be the incoming fraction defective and p1 be the outgoing fraction defective (Assume both p1 and p0 is greater than
0). If rectifying inspection is performed then:

A. P0<p1

B. P1<p0

C. None of the above

D. Cannot be determined

View answer

Correct answer: (B)

P1<p0

88. A company wants to measure the length of a fan as a part of its quality control exercise. The type of data collected will be:

A. Variable

B. Attribute

C. Cannot be determined

D. None of the above

View answer

Correct answer: (B)

Attribute

89. If only ______________ causes of variation are present, the output of a process forms a distribution that is table over time and is
predictable.

A. Assignable

B. Non-Random

C. Natural

D. Cannot be said

View answer

Correct answer: (C)

Natural

90. For an x bar chart, β risk can be defined as:

A. The probability of detecting the shift in process mean from μo (in control value) to μ1

B. The probability of not detecting the shift in process mean from μ0 (in control value) to μ1

C. The probability of detecting the shift in process range from μ0 (in control value) to μ1

D. The probability of not detecting the shift in process range from μ0 (in control value) to μ1

View answer

https://www.mbamcq.com/total-quality-management/9.php 2/3
01/03/2022, 09:09 Total Quality Management Multiple choice Questions and Answers. Page 9.

Correct answer: (B)

The probability of not detecting the shift in process mean from μ0 (in control value) to μ1

Previous Next
Page 9 of 52

https://www.mbamcq.com/total-quality-management/9.php 3/3

You might also like