09 Project Cost Estimation and Budgeting
09 Project Cost Estimation and Budgeting
World Bank, ADB, JICA, DfID, Govt of India, Govt of MP, AP, Bihar,
Countries Clients
India, Sri Lanka, Bangladesh, Nepal, USA, Japan, UAE, Kuwait, Oman, Spain
Today’s
Agenda
4
Project Cost Management Definition
5
Types of Costs
Incurred Costs during a project are the result of Direct or Indirect charges
Type Definition Examples
Overhead items or costs incurred for the Taxes, fringe benefits, janitorial
Indirect
benefit of more than one project. services, etc.
11
Cost Management Processes
Estimate Costs
Determine Budget
Control Costs
12
Estimate Costs Process
7.1
7. Project Cost Estimate Costs - 7.3 -
Management
- Control Costs
7.2
Determine Budget
13
Estimate Costs Terms
Rough Order of
-50% to +50% Initiating
Magnitude (ROM)
Budget or
-10% to +25% Planning
Preliminary
Monitoring &
Definitive or Detailed -10% to +10% Controlling
14
Estimate Costs Tools and Techniques
Expert Obtaining one cost estimate per activity based on expert judgment, historical
Judgment information, or guessing.
Using the actual cost of previous, similar projects as the basis for estimating the
Analogous
cost of the current project. Suitable when there is limited amount of detail. Uses
Estimating
expert judgment. Less costly than other techniques, but also less accurate.
A technique that uses a statistical relationship between historical data and some
Parametric other variable to estimate the cost of an activity.
Estimating
For example: square footage in construction, lines of software code, etc.
Bottom-Up Estimating individual work packages and then summarizing them to a higher level of
Estimating generality. More accurate but also more costly; requires well-defined activities.
A technique that uses three cost estimates to represent the optimistic, most likely,
and pessimistic scenarios. Used to improve the accuracy of the estimates when the
Three Point
underlying activity or cost is uncertain or there is a considerable amount of risk to
Estimating
factor in. Often the estimates are combined by PERT* formula into one probable
estimate
*Note: PERT (Program Evaluation and Review Technique) is an estimating method that uses a weighted
average of three numbers to come up with a final estimate. One of the most used PERT equations
is calculated as (Optimistic + 4Most Likely + Pessimistic)/6, which “weighs” the most likely cost
most heavily, since it is weighted four times as much as the other two values.
15
Estimate Costs Tools and Techniques (cont’d)
Many estimators include contingency reserves as costs in schedule activity cost
estimates. This has the problem of potentially overstating cost estimates.
Reserve Management Reserve: Extra money in the budget to cover the cost of unknown
7.1.2.6
Analysis events that might affect the project.
Contingency Reserve: Extra money in the budget to cover known risks
identified in Risk Management Plan.
The Cost of Quality (Section 8.1.2.2) may be used in the preparation of estimates, by
Cost of
7.1.2.7 showing that if thorough requirements, design and planning are not done, there may
Quality
be increased costs for rework due to lack in initial quality.
Project
Management Tools, such as cost estimating software applications, computerized spreadsheets,
7.1.2.8
Estimating simulation and statistical tools, that can assist with cost estimating.
Software
By comparing multiple bids and using PERT analysis you can determine the most
likely cost for each deliverable, which will give you a more accurate project cost
Vendor Bid
7.1.2.9 estimate. Also understand that when using and managing outside vendors, additional
Analysis
work will be required to examine the prices and proposals of individual deliverables
and manage these vendors throughout the project.
16
What is Cost and Project Cost Management?
23
Contingencies provisions:
– In most construction budgets, there is an allowance for
contingencies or unexpected costs occurring during construction.
This contingency amount may be included within each cost item
or be included in a single category of construction contingency
– The amount of contingency is based on historical experience and
the expected difficulty of a particular construction project
– For example, one construction firm makes estimates of the
expected cost in five different areas:
• Design development changes,
• Schedule adjustments,
• General administration changes (such as wage rates),
• Differing site conditions for those expected, and
• Third party requirements imposed during construction, such as new
permits.
24
Project Cost Management
7.1
7. Project Cost Estimate Costs - 7.3 -
Management
- Control Costs
7.2
Determine Budget
28
Time-Phased Project Costs - “S-Curve Diagram”
Key Notes:
If Project Expenditures exceed the cost baseline, the project is over budget.
Project Funding Requirements need to be negotiated against available cash flow. If
cash flow is not available the project funding needs to be restructured; i.e., Project
Funding Reconciliation process.
– The unit cost for each element in the bill of quantities must be
assessed in order to compute the total construction cost. This
concept is applicable to both design estimates and bid
estimates, although different elements may be selected in the
decomposition.
• Databases for unit cost items such as worker wage rates, equipment rental or
material prices. These databases can be used for any cost estimate required. If
these rates change, cost estimates can be rapidly re-computed after the databases
are updated.
• Import utilities from computer aided design software for automatic quantity-take-
off of components. Alternatively, special user interfaces may exist to enter
geometric descriptions of components to allow automatic quantity-take-off.
• Export utilities to send estimates to cost control and scheduling software. This is
very helpful to begin the management of costs during construction.
• Version control to allow simulation of different construction
processes or design changes for the purpose of tracking changes
in expected costs.
Contact Me
Let me know about your Project Management Moment !
PKSINGH
B Tech IIT BHU Varanasi
MBA IIM Calcutta
99303 44085
47
Thank you
Pramod Kumar Singh: An IIT +IIM Faculty