MSC GTR's
MSC GTR's
MSC GTR's
Encl: (1) MSC Drawing No. 803-7081122; MSC General Technical Requirements
(2) MSC Drawing No. 803-7081124; MSC Work Item Preparation Guide
2. Scope. The requirements of this instruction apply to all MSC owned, civilian mariner
(CIVMAR) operated ships. Compliance with this instruction shall be required for all work
packages whose preparation begins on or after the effective date of this instruction and for
selected ship operating subcontracts for repair or industrial assistance awarded after the effective
date of this instruction.
3. Background. In recognition of the need for standardization, COMSC has developed a guide
for use in developing work items (enclosure (2)). This guide also includes a standard work
package index. Development of a work package still requires rigorous attention to ensure that
each work requirement is adequately addressed and that the responsibilities of the Government
and the Contractor are clearly delineated.
a. General Technical Requirements (GTR). The standards of performance for the work
directed by work items. The GTRs are controlled by COMSC.
d. Standard Item. Items which are (1) used for repetitive work, (2) invoked by the work
items; they may not be modified except by a formal review and reissue procedure.
e. Work Item. Any item which provides sufficient details dependent on the type of
specification (design or performance) to allow a Contractor to perform work .
f. Work Package. A set of work items for an individual availability which incorporates or
invokes applicable references including but not limited to the GTRs, ABS and Coast Guard
regulations.
5. Action
a. COMSC. COMSC (N7) will maintain enclosures (1) and (2). Revisions to these
documents shall be issued when deemed appropriate.
b. Program Managers
(1) Program Managers shall ensure that the procedures described in this instruction are
employed for work packages developed for MSC owned, CIVMAR operated ships. Repetition
or duplication of requirements shall be avoided.
(2) Program Managers shall ensure that Preparing Activities are provided with copies of
enclosures (1) and (2) and any future revisions of these documents.
c. Preparing Activities. Preparing Activities shall employ enclosures (1) and (2) and the
appropriate Standard Items as prescribed in this instruction. Individual/additional work items
shall be developed as necessary to identify the unique work requirements of the given contract in
the format prescribed in enclosure (2). The first work item of a work package shall invoke
enclosure (1).
2
COMSCINST 4700.16
16 June 1997
d. Effective Date. This instruction shall be fully implemented and utilized in all ship repair
and conversion contracts or subcontracts for MSC owned, CIVMAR operated ships scheduled to
begin work package development on or after the effective date of this instruction and in all
contracts and subcontracts thereafter. All work packages issued by MSC whose preparation
began before this date, including all contracts and subcontracts currently being performed or
awarded prior to the effective date of this instruction, and all solicitations currently being
competed, but not yet awarded will use the GTRs contained in reference (a).
Distribution:
COMSCINST 5000.19
List I (Case A, B)
SNDL 41B (MSC Area Commanders)
41C (MSC Subarea Commanders)
MSC Port Engineers
3
MILITARY SEALIFT COMMAND
GENERAL TECHNICAL REQUIREMENTS
(GTRs)
GTR No. 1
1.0 ABSTRACT
Whether or not specifically required in a work item or GTR, all of the applicable
laws of the United States and the requirements of the various regulatory bodies in force
at the time of contract award shall apply to the work performed under the contract,
including but not limited to those listed below:
3.1 American Bureau of Shipping (ABS), Rules for Building and Classing Steel
Vessels, Requirements for Certification of Construction and Survey of Cargo Gear on
Merchant Vessels, Rules for Building and Classing Steel Vessels Under 200 Feet [61
Meters] in Length, Guide for Certification of Cranes, Guide for Construction of
Shipboard Elevators, and Rules for Building and Classing Underwater Vehicles,
Systems, and Hyperbaric Facilities.
3.2 United States Coast Guard (USCG), Code of Federal Regulations, Title 46 -
Shipping (46 CFR), Code of Federal Regulations, Title 33 - Navigation and Navigable
Waters (33 CFR), Code of Federal Regulations, Title 35 - Panama Canal (35 CFR), and
Navigation and Vessel Inspection Circulars.
3.4 United States Public Health Service (USPHS), including Publication No. 393,
"Handbook on Sanitation of Vessel Construction", and USPHS and MARAD's Joint
Publication No. P 161019 "Ratproofing of Ships", to entitle ship to receive Deratization
Exemption Certificate and Certificate of Sanitary Construction.
GTR No. 1
3.6 U.S. Department of Labor, "Safety and Health Regulations for Longshoring”
and “Occupational Safety and Health Act (OSHA)”.
4.1.5 GTR.
General work items in the Work Package (001 through 099) state the
broadest requirements and apply to the complete contract. Specific work items may
require additional or different services or work and shall prevail over the general work
items.
GTR No. 2
1.0 ABSTRACT
2.0 REFERENCES
2.1 American Society for Testing and Materials (ASTM), F1166, Standard
Practice for Human Engineering Design for Marine Systems, Equipment, and Facilities.
3.0 LAYOUT
3.2 Equipment and accompanying local operating panels and gageboards shall
be installed to conform with manufacturer’s requirements for clear access to equipment
for ease of maintenance, repair, inspection, and operation. This includes but is not
limited to providing clearance for opening and closing of operating panels, motor
controller boxes, drawers, and doors.
3.3 Outfitting arrangements shall be designed to allow full opening and closing of
all drawers, doors, and pull down desk tops.
3.5 Installation and modification arrangements shall not degrade the capabilities,
operability, human engineering considerations, safety, alignment, maintainability,
electromagnetic capability, and intended use of new or existing equipment.
GTR No. 2
4.3 Duct access openings shall have bolted cover plates and shall comply with
Reference 2.1. Cover plates shall be of the same thickness and material as the duct,
transition, or trunk to which it is attached. A gasket shall be installed between the cover
plate and the duct, transition piece, or trunk. Access openings shall be as large as
possible but not more than 600 by 600 mm (24 by 24 in) and not less than 200 mm (8
in) by 230 mm (9 in). Access openings in transition sections shall be rectangular,
circular, or trapezoidal. Access openings shall be installed in the bottom of the duct
unless the top side of the duct is more accessible.
GTR No. 3
1.0 ABSTRACT
This Item describes the general requirements associated with performing tests,
inspections and trials and obtaining certificates to demonstrate total compliance with the
Work Package requirements as well as specific testing requirements and procedures for
each type of work being performed (HVAC, electrical, piping, etc.).
2.0 REFERENCES
2.1 Society of Naval Architects and Marine Engineers (SNAME), Technical and
Research Bulletin 3-39, Guide for Shop and Installation Tests.
2.2 Institute for Electrical and Electronic Engineers (IEEE) Standard 45,
Recommended Practice for Electric Installations on Shipboard.
2.4 Institute for Electrical and Electronic Engineers (IEEE) Standard 149-1979,
Standard Test Procedures For Antennas.
2.5 Institute for Electrical and Electronic Engineers (IEEE) Standard 43-1974,
Recommended Practice For Testing Insulation Resistance Of Rotating Machinery.
2.6 Institute for Electrical and Electronic Engineers (IEEE) Standard 112-1991,
Standard Test Procedure For Polyphase Induction Motors And Generators.
2.7 Institute for Electrical and Electronic Engineers (IEEE) Standard 115-1983, Test
Procedures For Synchronous Machines.
2.8 Institute for Electrical and Electronic Engineers (IEEE) Standard 120-1989,
Master Test Guide For Electrical Measurements In Power Circuits.
2.9 U.S. Public Health and Human Services, Standards of Sanitation and
Ratproofing for the Construction Vessels.
2.10 American Society of Mechanical Engineers (ASME), A17.1, Safety Code for
Elevators and Escalators, Part X: Routine, Periodic, and Acceptance and Tests.
2.11 American Society of Mechanical Engineers (ASME), A17.3, Safety Code for
Existing Elevators and Escalators.
2.12 NAVSHIPS Technical Manual (NSTM) 772, Cargo and Weapons Elevators.
GTR No. 3
2.13 ASHRAE Standard 151P, Practices for Measurement, Testing, Adjusting and
Balancing of Shipboard HVAC and Refrigeration Systems.
3.0 DEFINITIONS
3.1 Completion Test - A completion test verifies that all aspects of the work item
have been completed. For compartments, it means all equipment, piping, electrical, deck
coverings, overheads, etc. is installed and tested and proves the compartment is complete
and ready for service. For tanks, it means all cleaning, flushing, installations, testing has
been completed, all temporary services are removed and the tank is ready for service. A
completion test may include a series of functional, operational, and structural tightness
tests.
•= All work has been performed satisfactorily and to the specific instructions
and requirements of the work item, manufacturer, and regulatory bodies.
•= The equipment, material, machinery, or system including all flows, levels,
temperatures, loads, and alarms complies with manufacturer’s parameters.
•= The equipment, material, machinery, or system performs its intended
purpose.
3.4 Tightness Test - A tightness test verifies that all structural work including any
structural attachments which would affect the tightness of the structure, is complete and
ready for service. This may be accomplished using air or water depending on the specific
instructions in the work item, regulatory body requirements and the intended service.
4.0 GENERAL
4.1 Tests and inspections are required on all systems, equipment, machinery,
surfaces, items, and components that are installed, repaired, overhauled, relocated, or
modified. Tests, trials and inspections shall be conducted as indicated in the individual
GTR No. 3
items of this Work Package and in the presence of the MSCREP. All applicable
Regulatory Bodies and required Technical Representation shall attend each test, trial and
inspection.
4.2 Preliminary tests are required to be conducted on all units before calling for an
official test.
4.3 A test, trial, or inspection is successful if it meets the requirements of the test
procedure and if it is completed to the satisfaction of the MSCREP, technical
representatives, and regulatory bodies.
4.4 Ensure that all industrial work which may impact the test, trial, or inspection
outcome is completed before its conduct. The Contractor is responsible for notifying all
applicable regulatory bodies of scheduled testing and retaining of required technical
representatives at contractor expense for verification of test results. Failure to obtain
regulatory body representatives to witness testing, trial, or inspection shall require
rescheduling the test, trial, or inspection at Contractor’s expense.
4.6 Notify the MSCREP at least 4 hours but not more than 24 hours before the test,
trial, or inspection to be witnessed. When work to be witnessed is scheduled to occur
after the normal day shift working hours, on a weekend or holiday, or off-site testing is
required, the MSCREP shall be notified at least 24 hours in advance but not less than 4
hours prior to the end of the last normal day shift.
GTR No. 3
Refrigerant containing chloro-flouro carbons (CFC) shall not be used as a leak test
gas. One of the following leak test gases shall be used:
•= A mixture of trace quantity of non-CFC refrigerant and dry air or nitrogen. In this
case, leak test gas shall be recovered and reused and not released into the
atmosphere.
•= A non-ozone depleting alternative gas.
•= An EPA SNAP (Significant New Alternatives Policy) approved alternative
refrigerant.
7.1 The Contractor and the MSCREP shall conduct a joint inspection of areas to be
prepared and painted before surface preparation begins to ensure that protective
measures are implemented.
7.2 The Contractor shall perform inspections after completion of each stage of
surface preparation, each coat, and each stripe coat, to verify surface condition, DFT and
space cleanliness, and before securing space. At least 2 DFT readings shall be taken per
100 square feet.
7.3 The Contractor shall stop the inspection if surface preparation, coating, or final
inspection fails to meet acceptance criteria of the inspection. The cause of the failure
shall be identified. After failure correction, the complete inspection shall be reconducted.
The Contractor shall remedy failed areas at no additional cost to the Government.
7.4 The Contractor shall conduct a final inspection of space, surfaces, and tanks to
ensure that spaces are clean.
New, repaired, and modified ship's tanks, cofferdams, void spaces, and structures
designated as oiltight, watertight, airtight, or fumetight shall be tested to ensure tightness.
New weather decks and interior steel decks, coamings, and deck connections of steel
bulkheads, in way of toilets, washrooms, and other wet spaces shall be tested to ensure
tightness before installing deck or bulkhead covering.
GTR No. 3
a. Air tests (either an air hose test or an air pressure test), hydrostatic
tests, or vacuum box tests shall be used to test the tightness of oiltight, watertight, or
airtight compartments.
c. If air testing (air hose or air pressure) is used, structural integrity and
tightness shall be considered satisfactory if no bubbles develop in the leak indicator
solution.
d. Where an air hose test is used, the nozzle shall be 300 mm (12
GTR No. 3
inches) from the tested item and the stream directed against all compartment boundaries,
plate connections, closures, fittings, and boundary penetrations in the manner most likely
to reveal leaks. The nozzle diameter shall be at least 10 mm (.375 in), and the pressure
at the nozzle at least 620 kPa (90 psi). A soap solution shall be applied on the opposite
side of the structure and the structure inspected to detect leakage.
The rigging of the Pilot's Ladder at port and starboard deployment stations shall
be demonstrated to the MSCREP.
GTR No. 3
At least one liferail end stanchion and one other liferail stanchion on each
platform or deck shall be tested by a 136 kg (300 lb.) horizontal load, outboard at the
stanchion's top, and perpendicular to the railings. The load shall be held for 10 minutes.
20 % of top liferail sections on each platform or deck (one of which shall be an end
section), as selected by the MSCREP, shall be tested by applying a 136 kg (300 lb.) load
horizontally outboard and perpendicular to the rail at the rail’s midpoint. The load shall be
held for 10 minutes. Permanent deformation or damage shall not be visible after load
release from the liferails and stanchions.
9.4 Padeyes
Padeyes shall be given a static test of twice the design working load for a period
of 10 minutes without damage or permanent distortion occurring to the fitting. The weight
of power hoists shall be considered as part of the design working load for test purposes.
10.0 ELECTRICAL AND ELECTRONICS
10.1 General
10.2.1 End to end continuity and electrical insulation resistance tests on new,
modified, overhauled, or repaired system cables shall be performed in accordance with
Reference 2.2.
GTR No. 3
10.7.2 Individual line amperes shall not differ from the nameplate average value
by more than +10 %. The motor nameplate full load ampere value shall be compared with
the value indicated on the motor controller overload heater coils to ensure that the heater
coil is of the correct rating to provide motor protection.
10.8 Lighting
New, modified, overhauled, and repaired ship's service lighting circuits shall be
tested in accordance with Reference 2.2.
The Contractor shall test new storage batteries and their associated battery
charging units in accordance with manufacturer’s recommendations. Voltage and specific
gravity values for each cell for the fully discharged and fully charged conditions shall
comply with manufacturer's specified values for each condition.
GTR No. 3
10.10 HF Antennas
11.1.2 Potable water systems shall be tested by filling from shore and also by
transferring water from one tank to an overboard connection using the ship's pumps. To
demonstrate that the specified water delivery (pressure and quantity) is met, the water
supply to groups of fixtures at the most remote forward, after, and topside location shall be
checked. The capacity of the pump or pumps used to supply the group of fixtures shall
meet the flow requirements for these fixtures.
11.1.3 The Contractor shall disinfect the potable water tank in accordance with
Reference 2.9. After the Contractor has disinfected the potable water tank, the Contractor
shall conduct the tests required by Reference 2.9 and submit results to the MSCREP. If
tests results do not comply with the limits established in Reference 2.9, the Contractor
shall repeat the tank flushing, superchlorinating, and testing. The operation of the
disinfection system shall be demonstrated after potable tank disinfection and again before
the sea trials. Minimum residual concentration readiness shall be determined by taking
water samples from each installed sampling connection.
11.1.4 The hot potable water system shall be tested to demonstrate the ability of
the system to deliver hot water at a minimum of 49 °C (120 °F) at the most remote
plumbing fixtures of each heater loop within 10 seconds.
11.1.5 The chilled water system shall be tested to insure that, with all valves in
the open position, the measured water flow (gpm) at each plant is within 90-110 % of the
connected load.
GTR No. 3
11.2 High and Low Pressure Evaporators, Distillers, Auxiliary Steam Generators, and
Miscellaneous Heat Exchange Equipment
The Contractor shall test dumbwaiters and passenger, cargo and stores
elevators in accordance with References 2.10, 2.11, and 2.12.
11.4 Firemain, Flushing, Sprinkling, Washdown and Salt Water Service Systems
After installation or repair and prior to sea trials, the firemain, flushing,
sprinkling, washdown and salt water service systems shall be hydrostatically tested at 150
percent of maximum working pressure as required for USCG certification.
GTR No. 3
c. The discharge alarm must be checked and operated with dry air or
nitrogen. The alarm shall be audible throughout the space with machinery operating.
The nitrogen pressurization piping of the galley APC system shall be gas
pressure tested for tightness and strength to 135 percent of design pressure.
GTR No. 3
The system piping for AFFF stations shall be hydrostatically tested for
strength and tightness. Compressed air at 85 to 100 psi shall be used to demonstrate
unobstructed flow through piping and sprinkling nozzles. Outlets may be temporarily
capped if necessary to allow testing of one or two outlets at a time. All AFFF concentrate
tanks shall be tested for strength and tightness by a hydrostatic pressure of 10 psi. All
installed AFFF systems shall be operationally tested for AFFF making ability. Duration of
the test shall be 1 minute, after which an AFFF sample shall be taken. The AFFF
(seawater) solution produced shall be checked by the refractometer method for 4 percent
minimum concentration. AFFF hose reel units shall be test-operated with the AFFF
station set up in the AFFF recirculation mode. Seawater shall be discharged overboard.
During the test, the local and remote controls shall be operated.
GTR No. 3
11.7.1 Hydrostatic tests shall be conducted after cleaning. Fuel piping shall be
hydrostatically tested after installation with clean fresh water or the service fluid to 150
percent of the design pressure or 50 psi, whichever is greater. Pumps in fuel stripping,
transfer and service systems shall be isolated during hydrostatic tests of the system
piping.
11.7.2 An operational test of the filling and transfer system shall be performed to
demonstrate compliance of in-port fueling with service fluid rates.
11.7.3 Power operated system and tank valves shall be operated. Operation of
the valves shall be confirmed by actual observation of each valve. Correct operation of
valve position indicators shall be observed during this test.
11.8.1 Shop tests on a standard production air compressors are not required
except for the usual tests performed by the manufacturer for production line units.
11.8.2 Air compressors shall be tested with the diving equipment after all
necessary piping and accumulator tanks have been installed and pressure tested. Tests
shall be conducted for one hour to demonstrate satisfactory operation of the compressor
and its automatic controls and safety devices.
GTR No. 3
After installation, the auxiliary steam, exhaust steam and steam drain systems
shall be tested hydrostatically at 150 percent of maximum allowable working pressure.
The exhaust steam shall be tested at the maximum pressure under full load conditions
using the working fluid.
The distilling plant should be operated with sea water feed to demonstrate the
specified capacities. The ability of the distilling plant to produce the maximum quantity
and required distillate for period of not less than six (6) hours should be demonstrated in
its normal underway mode of operation. Record operating data from the ship’s
instrumentation at 30 minute intervals for not less than six (6) hours.
GTR No. 3
5) Check setting of control limit stops and copper and steel hard-
over stops for proper rudder motion limits.
GTR No. 3
4) Operate steering gear from either power unit and check the
rapidity of shifting from one power unit to the other. Where
specified, demonstrate operation of steering gear on both
power units.
11.12 Pumps
11.12.2 The pumping equipment shall be operated with all governors and
control apparatus in place and operating.
11.12.4 All pumps shall be given a continuous test for a period of at least
one hour, or longer if required, for the test of the source of motive power. Not less than
three sets of readings at approximately equal time intervals shall be taken on all
instruments and shall be recorded on data sheets.
11.12.5 All pumps shall be operated as near to the rated suction pressure,
discharge pressure and capacity as practicable; for units such as main and auxiliary feed
pumps and main condensate pumps, capacities obtained when the main machinery is
operating under dock trial conditions will be satisfactory.
a. The ability of the unit to take its suction through each suction
connection and to discharge through each discharge connection shall be demonstrated.
GTR No. 3
All navigation equipment should be proven operational during dock trials and
any calibration or adjustments necessary shall be performed during initial phases of the
sea trials.
12.1 General
12.2.1 General
GTR No. 3
a. Equipment Tests
b. System Tests
2) All data taken shall be corrected for standard air and compared
with design criteria for adequacy. The following air delivery rates are considered
satisfactory unless otherwise specified.
GTR No. 3
e. Draft Survey
a. All dehumidification plants shall be operated for six hours, with the
entire connected load and maintaining the temperature, humidity, and air supply to the
cargo holds and or other areas.
GTR No. 3
GTR No. 4
1.0 ABSTRACT
When CFM is required and specified by brand name in the contract or work item,
equivalent material may be proposed. The salient physical, functional, and other
characteristics which "equal" products meet shall include but are not limited to:
3.2 Data that demonstrates that the proposed item, equipment, component, or
material meets or exceeds the specified performance requirements.
3.3 Data that demonstrates that the proposed item, equipment, component, or
material has functionally equivalent:
a. Dimensions.
b. Weight.
c. Power, HVAC, cooling water, and other required services.
d. Suitability for marine service.
e. Material.
f. Maintenance features and requirements.
g. Vendor furnished training.
h. Life cycle cost and maintenance cost.
i. Structureborne and airborne noise characteristics.
j. Warranty provisions.
k. Maintenance manpower requirements.
l. Worldwide support and service infrastructure.
m. Spare parts availability.
n. Prior provisioning through the Naval Supply System.
o. Estimated spare parts costs for one year's use.
p. Compatibility with interrelated systems and arrangements.
GTR No. 4
GTR No. 5
1.0 ABSTRACT
2.0 REFERENCES
3.0 DRAWINGS
After contract award, MSC will provide the Contractor a copy of any ship's
drawing applicable to the contract and currently in the MSC library in either conventional
or digital format, as available, within fourteen days after receipt of request.
3.2.1 When updating MSC drawings, the MSC Master drawing will be
provided upon request in either conventional or digital format and transmitted via a
guaranteed, insured, and traceable delivery method.
3.2.3 Loaned drawings shall not be altered or modified in any manner other
than as specifically tasked in the contract.
3.3.1 The Contract Guidance Drawings are for guidance only. They disclose
the basic technical information and performance requirements necessary for a
GTR No. 5
Contractor to complete the detailed design required to develop and produce a working
drawing.
3.3.2 The Contract Guidance Drawings are not intended to restrict the
Contractor to the procedures and details shown therein. Equivalent details and
procedures which may make use of more readily available material or permit the use of
Contractor's standards or procedures of equal merit are acceptable. The Contractor
shall submit to the MSCREP for approval his alternate method, materials, or
procedures along with documentation to substantiate the claim of merit. Approval of
the drawings, methods, materials, or procedures and supporting documentation will
indicate only that the general method of construction and detailing is satisfactory and
will not relieve the Contractor of the responsibility for any error. The Contractor shall
assume the risk and cost to remove unapproved substitutions for materials, methods, or
procedures.
3.3.3 The original Contract Guidance Drawings shall not be altered by the
Contractor in any manner. Where a Contract Guidance Plan is used as the basis for a
new drawing, the copy shall be identified as a new drawing with a new file name.
b. Arrangement drawings.
GTR No. 5
d. Assembly drawings.
e. Installation drawings.
g. Layout drawings.
h. Electrical/Electronic diagrams.
3.5.2 The final revision of the working drawings are "as-built" drawings and
reflect the condition of all areas covered by the Work Package upon ship redelivery.
4.1 All CAD drawings shall be prepared in accordance with Reference 2.1.
4.2 Drawings shall have a COMSC title block in accordance with the title block
requirements of Reference 2.1. A Contractor's title block shall be included on the
bottom of the first sheet to the left of and adjacent to the COMSC title block.
4.3 The initial approval authority for all drawings shall be the Port Engineer or
other on-site MSCREP.
GTR No. 5
GTR No. 6
1.0 ABSTRACT
This Item establishes the requirements for Contractor Furnished Material (CFM) and
workmanship.
2.0 REFERENCES
2.1 American Society for Testing and Materials (ASTM), F1182, Standard Specification
for Anodes, Sacrificial Zinc Alloy.
2.2 American Society for Testing and Materials (ASTM), F1053, Standard Guide for
Steel Hull Construction Tolerances.
3.0 MATERIAL
3.1 All material shall be free from manufacturing imperfections and defects which
adversely affect appearance, serviceability, performance, or safety. CFM shall be new. All
material, machinery, and equipment shall be suitable for the intended marine service. Spare
parts and services shall be readily obtainable worldwide.
3.3 If galvanizing is required, the hot dip process shall be used. If materials cannot be
hot dip galvanized, zinc silicate coating may be substituted. Zinc silicate coating should be
approved by MSCREP on a case-by-case basis.
3.6 The faying surfaces of dissimilar metals which are attached, shall be separated with
a dielectric material at least 1.6 mm (0.0625 in) thick extending 6.3 mm (0.25 in) beyond the
edge of the faying surface. The dielectric material shall be attached by adhesive to provide a
watertight seal and also provide a barrier between the dissimilar metals.
GTR No. 6
3.8 For weather exposed equipment and machinery, CRES or monel metal pressure
grease fittings shall be used. Fittings shall be accessible, either with elbow bodies or
extensions, and shall be threaded and suitable for use with high pressure grease guns.
4.0 WORKMANSHIP
Plate and hull fitting workmanship shall have fair lines, smooth surfaces, and sound
welding with minimum distortion and warpage in accordance with Reference 2.2. Plating shall
be closely fitted and free from buckles or uneven edges. Permanent shims shall not be used to
correct improper fit. To avoid a patchwork effect, new and replaced shapes and plates shall be
of standard mill size rather than fabricated from smaller pieces.
5.0 SAFETY
5.1 Where guards are required for personnel protection around shafting, couplings,
gears, flexible shafts, and other rotating and oscillating equipment and machinery they shall be
removable without dismantling the machinery. Guards shall be durable, lightweight, rigid, and
constructed to minimize maintenance.
5.2 Guards shall prevent personnel from contacting energized and exposed electrical
circuits, components, and terminals which present shock and high voltage hazards.
5.3 Equipment shall be installed so that the hazard of personnel brushing or being
thrown against it under heavy sea conditions is minimized.
GTR No. 7
GENERAL PAINTING
1.0 ABSTRACT
This Item establishes general requirements for surface preparation and painting.
2.0 REFERENCES
2.1 Steel Structures Painting Council (SSPC), Systems and Specifications, Volume II.
3.0 DEFINITIONS
3.2 Interior - Surface area inside the ship not directly exposed to the weather.
3.3 Approved System - A coating system, approved by MSC for the required service.
3.4 Surface Preparation Standards - Specified levels of surface preparation are defined in
Reference 2.1 and include but are not limited to:
GTR No. 7
GENERAL PAINTING
3.5 Low Pressure Hose Washing - Normal water pressure periodically applied when a ship is
dry-docked using a 38 mm (1.5 in) fire hose at normal shoremain pressure.
4.1 Paint shall only be applied when the environmental conditions, including but not limited to
temperature, humidity, and steel temperature are within the published limits established by the paint
manufacturer.
4.2 Manufacturer’s established drying times between coats shall be followed to ensure
adhesion of the subsequent coats.
4.3 Each undercoat shall be of a different color to make holidays and inadequate coverage
readily apparent.
4.4 Unless preparing for inorganic zinc application or unless otherwise specified, blasting shall
not be used to prepare surfaces for painting.
4.5 A commercial antifouling coating that is specifically formulated for existing fiberglass or
aluminum hulls shall be applied on workboats or launches that are normally wet stowed.
4.6 The airless spray paint application method shall be used when painting fiberglass.
5.0 PROHIBITIONS
5.1 Only paints that comply with all federal, state, and local volatile organic compound (VOC)
and any other environmental laws and regulations shall be used.
5.2 Only paints that comply with all federal, state, and other occupational safety and health
laws and regulations shall be used. Areas of concern are lead, chromate, coal tar, etc.
5.3 The following types of paint or paint products shall not be used:
5.3.2 Lead based paints. (Totally “lead free” paints are generally not available because
trace amounts of lead can be found in the paint’s constituents. “Lead free” paint is defined by the
Consumer Product Safety Commission’s Ban of Lead-Containing Paint and Certain Consumer
Products Bearing Lead-Containing Paint (16 CFR 1303) as containing .06 % lead by weight in the dry
paint film.)
GTR No. 7
GENERAL PAINTING
5.3.6 Antifouling paints shall not be applied to any aluminum craft, lifeboats, workboats,
or launches that are normally dry stowed (such as aboard ship).
Interior machinery (in engine room or auxiliary spaces) and hot machinery whether
(exposed or interior) shall be painted as follows:
6.1.1 Interior machinery: Equipment Gray (Fed Std Color 26307); trimmed out with
Black (Fed Std Color 27038).
6.2.1 Two coats of polyamid epoxy, final coat shall be Terracotta Red (Fed Std Color
20109), at 5 mils DFT per coat shall be applied to bilges, deck plating, foundations, and bulkheads
below the grating. These coatings shall extend to 150 mm (6 in) above the grating level.
6.2.2 Color for bulkheads and overheads shall be applied to 150 mm (6 in) above the
grating level.
6.2.3 Valves and piping shall be color-coded for the particular cargo system to which
they belong.
6.3.1 Bulkheads in way of cargo spaces, interior of cargo hatch coamings, cargo trunks,
etc., shall be painted White (Fed Std Color 17875).
6.3.2 Wooden cargo battens shall be Dark Gray (Fed Std Color 26008).
GTR No. 7
GENERAL PAINTING
6.3.3 Vertical ladders, and bulkheads in way of ladders, shall be Gloss Black (Fed Std
Color 17038).
6.3.4 All U-bolts, D-rings, padeyes, and other fittings intended for use during cargo
handling shall be painted with Gloss Red (Fed Std Color 11105), and be stenciled alongside with
"ATTACH BLOCK HERE", also in Gloss Red.
6.4.1 All interior piping (except fire systems) shall be painted to match surrounding
areas, and stenciled with contrasting color lettering to identify flow direction and service. Valve
bodies and valve wheels shall be painted in accordance with 6.4.3.
6.4.2 Steam piping on weather decks exposed to green seas shall be coated with 4 mils
of inorganic zinc primer and topcoated in accordance with Work Package requirements.
6.4.3 Exterior riser plugs for shoreside connections shall be color-coded as follows:
•= Fresh water: Blue (Fed Std Color 15123)
•= Firemain: Gloss Red (Fed Std Color 11105)
•= JP-5: Purple (Fed Std Color 17142)
•= Steam: Haze Gray (Fed Std Color 26270)
•= Fuel: Haze Gray (Fed Std Color 26270)
•= Sewage: Gold (Fed Std Color 17043)
•= Lube oil: Striped Yellow (Fed Std Color 13538) and Gloss Black (Fed Std Color
17038)
6.5.1 Firemains shall be painted to match surrounding compartment or deck colors, and
stenciled in red to read "FIREMAIN" with an arrow indicating direction of flow. Firemains running
through the bilge and painted red shall be stenciled to read "FIREMAIN" in a contrasting color with an
arrow indicating direction of flow. All valve bodies and handles, fire cabinets and associated fittings
shall be painted or trimmed with Gloss Red (Fed Std Color 11105).
6.5.2 Carbon dioxide (CO2) piping , nozzles, valves, and control handles shall be painted
Gloss Red (Fed Std Color 11105), with white stenciling "CO2" and a white arrow indicating direction of
flow. This includes nozzles, valves, and control handles.
GTR No. 7
GENERAL PAINTING
6.5.3 For MSC ships without permanent washdown systems, washdown systems
brackets for chemical, biological, and radiological (CBR) defense shall be painted International
Orange (Fed Std Color 12197).
6.5.4 Halon piping shall be painted to match surrounding compartment or deck colors
and stenciled in Red to read "HALON" with an arrow indicating direction of flow. Nozzles, valves, and
handles shall be painted Gloss Red (Fed Std Color 11105).
Wireways, electric cabling, stuffing tubes, and similar electrical fittings shall be painted to
match surrounding compartment surfaces. Where cabling runs in bilges, it shall be painted White
(Fed Std Color 17875).
Weather doors to decontamination stations shall be painted Haze Gray, (Fed Std Color
26270). Door dogs shall be Gloss Black (Fed Std Color 17038).
Deck appurtenances such as deck lockers, handrails, ladders, and padeyes shall
be painted to match the surrounding area.
GTR No. 7
GENERAL PAINTING
Table 7.1 specifies the colors to be used for bulkheads, overheads and decks for various
spaces and Table 7.2 provides the Federal Standard Color Numbers for the colors used by MSC.
GTR No. 7
GENERAL PAINTING
Table 7.1. Interior Color Codes (Numbers Indicate FED-STD-595 Colors) (Cont.)
GTR No. 7
GENERAL PAINTING
GTR No. 21
JOINER WORK
1.0 ABSTRACT
This Item establishes general requirements for joiner work design, material, and
construction.
2.0 REFERENCES
2.1 American Society for Testing and Materials (ASTM), F1178, Standard Specification
for Enameling System, Baking, Metal Joiner Work and Furniture.
3.0 GENERAL
3.1 Materials and installation methods shall provide a finished appearance compatible
with the surroundings and blending with the decor.
3.2 Joiner work shall not be installed until main piping, cables, and vent ducts are
installed and their interference with the joiner work ascertained. Joiner work shall be designed
and installed to eliminate sharp edges.
3.3 Support for heavy items located against joiner bulkheads shall be provided with
strength members other than the bulkhead panel. Heavy items shall be through bolted to the
independent strength member.
3.4 Raceways shall be the same color as the surrounding ceiling and joiner panels for
concealing items including but not limited to pipe, electric cable, and fiber optic cable runs.
These raceways shall be easily removable to permit inspection, maintenance, repair, or
replacement of the concealed items.
4.2 Materials
4.2.1 Channel and mounting hardware shall be obtained from the same
manufacturer. Channel and mounting hardware shall be manufacturer’s standard stock items.
Screws shall be self-tapping and spaced closely enough to prevent panel rattling. Joiner
material and hardware shall be removable, color coordinated, and selected for ease of
maintenance. To the maximum extent possible, bulkhead, ceiling, and lining fasteners shall be
concealed. When joiner installation materials are exposed they shall be corrosion resistant and
GTR No. 21
JOINER WORK
have a baked enamel finish in accordance with Reference 2.1. Other joiner securing materials
and deck mounted tracking shall be corrosion resistant and painted to match the surrounding
area.
4.2.2 Joiner bulkheads and liners shall be installed to existing bulkheads to give a
finished appearance. Liners shall be installed as close as possible to the existing bulkhead,
without removing stiffener insulation. Veneers on hard core systems shall be High Pressure
Plastic Laminate (HPPL) and veneers on soft core systems shall be PVC foil coated steel.
4.3 When installing joiner material in spaces without a ceiling, install 18 gage sheet
metal flashing between the top of each joiner panel and the deckhead.
5.0 CEILINGS
Ceilings shall be treated galvanized steel or aluminum panels with beveled edges. Ceiling
panels shall be perforated, except in wet and sanitary spaces where panels shall be non-
perforated. Ceilings in galley/scullery areas shall be 20 USSG, AISI 304 stainless steel
construction with satin finish.
5.1 Fasteners
All ceiling fasteners shall be non-corrosive and colored to match the ceiling.
5.2 Insulation
GTR No. 22
1.0 ABSTRACT
2.0 REFERENCES
2.1 American Society of Testing and Materials (ASTM), F 683, Standard Practice for
Selection and Application of Thermal Insulation for Piping and Machinery.
2.2 Society of Naval Architects and Marine Engineers (SNAME), Technical and
Research Bulletin No. 4-7, Thermal Insulation Report.
2.3 Society of Naval Architects and Marine Engineers (SNAME), Technical and
Research Bulletin 3-37, Design Guide For Shipboard Noise Control.
3.0 DEFINITIONS
3.1 Thermal Insulation. Thermal insulation is installed to minimize heat transfer from or
to a surface that is hotter or colder than the surrounding atmosphere.
3.1.1 Hot Surface Insulation. Hot surface insulation is a type of thermal insulation
installed to external surfaces which are 52oC (125oF) or higher to protect personnel and limit
heat transfer.
3.1.3 Cold Fluids Insulation. Cold fluids insulation is a type of thermal insulation
installed to external surfaces of components conveying cold fluids such as refrigerant and brine
or chilled water to limit heat absorption by the chilled fluid and to prevent ice formation on the
surfaces.
3.3 Fastenings - Fastenings include hooks, wire, pins, retaining clips, and adhesive to
secure insulation and lagging.
GTR No. 22
3.4 Reusable Covers - Reusable covers are machinery and piping insulation and lagging
materials or pads which can be removed and easily reinstalled without damage.
3.6 Unheated spaces - Compartments in which there are no provisions for raising the
space's ambient temperature.
4.0 GENERAL
4.1 Insulation installations shall comply with References 2.1 through 2.3 and Table 22-1.
4.3 Red tint lagging shall be used to indicate asbestos free insulation.
5.0 INSTALLATION
5.1 General
5.1.1 Insulation installations include but are not limited to installing lagging,
securing fasteners, painting, sealing, and performing all work necessary to provide a finished
appearance.
5.1.2 When welding or flame cutting, insulation and lagging near the hot work shall
be removed. Insulation shall not be installed until paint has been touched up on disturbed
areas.
If insulation is installed in more than one layer, the insulation layers shall be
staggered against the preceding layer. Each layer shall be joined with adhesives in accordance
with manufacturers' recommendations.
GTR No. 22
6.1.2 Studs shall be installed to support the insulation not more than 300 mm (12
in) between staggered centers and not more than 75 mm (3 in) from the edge of the insulation.
6.1.3 Tape seams with at least 25 mm (1 in) overlap on both pieces of insulation.
6.2 Thickness
The type and thickness of insulation required shall be based upon HVAC, thermal,
and acoustic requirements. Thermal insulation requirements shall be calculated using
Reference 2.2.
6.3 Location
6.3.1 Where insulation is required in living, working, and public spaces that have a
common boundary with heat producing spaces, they shall be insulated on the heated side.
Where steel lined bulkheads are fitted, the insulation shall be installed between the liner and the
steel. Insulation that is installed between heated and unheated spaces, on exterior bulkheads
and decks, and on shell plating, shall be installed on the interior and/or heated side.
6.3.2 Where insulation is required in double wall construction, the insulation shall
be installed within the void space.
6.3.3 Where insulation is required in chill and freeze boxes, it shall be installed on
the exterior (single wall construction) or within the void space (double wall construction).
Insulation shall be installed on the interior of refrigerated cargo holds and other refrigerated
spaces. Insulation installed in refrigerated cargo holds must meet additional structural criteria
as denoted in the work specification.
GTR No. 22
6.3.5 When machinery spaces are insulated, insulation shall be installed no lower
than the lowest grating level above the bilge.
6.4 Insulation For Tank Bulkheads That Are Common Boundaries With Work Areas
Thermal insulation shall be installed on all common bulkheads between tanks and
work spaces and between tanks and storage spaces on the work space or storage space side.
6.6 Material
Insulation shall be lagged with fibrous glass cloth or painted canvas and/or
contained within a joiner bulkhead. All insulation shall have a continuous vapor barrier applied
on the heated side of the insulation before lagging. Stainless steel sheathing shall be used for
exterior applications or in damp environments and shall be sealed at all joints and fasteners.
Sheathing metal shall be 1.59 mm (No. 16 USSG) for vertical installations and 0.87 mm (No. 20
USSG) for horizontal installations.
Thermal pipe insulation and lagging shall be installed in accordance with Reference 2.1.
Insulation lagging, and removable covers installed over valves, fittings, machinery, and
equipment, and bent pipe, shall be installed according to Reference 2.1.
9.1 Before applying lagging, insulation exposed to the weather or to undue moisture
shall be protected with 6 mm (0.25 in) weather resistant insulation, reinforced with hardware
cloth and secured with No. 16 WG copper wire. Cracks or openings in the continuity of the
completed insulation and lagging shall be avoided.
GTR No. 22
9.2 Insulation and lagging subject to mechanical injury shall be protected by 6 mm (0.25
in) checkered plates and heavy angles.
9.3 Where insulation may be subject to damage (e.g. mechanical or fluid) the insulation
shall be sheathed with perforated aluminum, corrosion resistant steel, or galvanized sheet
metal.
Thermal and acoustic insulation shall be secured with adhesive. The adhesive shall
be compatible with the insulated surface. Insulation on rectangular ducts whose length or width
exceeds 300 mm (24 in) shall be further secured with metal clips or pins.
GTR No. 22
GTR No. 23
PIPING
1.0 ABSTRACT
This Item establishes the requirements for piping design, installation, and fabrication.
2.0 REFERENCES
2.1 American Society for Testing and Materials (ASTM), F 708, Practice for Design and
Installation of Rigid Pipe Hangers.
2.2 American Society for Testing and Materials (ASTM), F1155, Standard Practice for
Selection and Application of Piping System Materials.
2.3 American Society for Testing and Materials (ASTM), F1138, Specification for Spray
Shields for Mechanical Joints.
2.4 American Society for Testing and Materials (ASTM), F994, Specification for Design
and Installation of Overboard Discharge Hull Penetration Connections.
2.5 American Society for Testing and Materials (ASTM), F1386, Standard Guide for
Construction of a Sounding Tube and Striker Plate for Tank Sounding.
2.6 American Society for Testing and Materials (ASTM), F1139, Specification for Steam
Traps and Drains.
3.0 GENERAL
3.1.1 Piping systems shall have flexible joints, support points, expansion loops,
and equipment connections to accommodate ship movement, thermal expansion, vibration, and
changes in trim and stability.
3.1.2 Where orifices are installed, they shall be installed at flanged joints.
3.1.3 Backing rings shall be used unless open root welds are specified. The
Contractor shall provide calculations which show that backing rings do not cause flow
restrictions.
3.1.4 Piping installation shall permit passage along walkways and ladderways,
access for equipment operation and maintenance, and access to doors, soft patches, and other
openings. Where required, if it is impractical for piping to be clear of access plates, cutout
GTR No. 23
PIPING
valves shall be installed on both sides of the opening to allow for piping section removal. Piping
inside of tanks shall be clear of access holes and have enough clearance to permit sludge
removal from tank bottom.
3.1.5 Piping shall be installed directly with a minimum number of bends, flanges,
and joints. Piping shall be installed taking into account piping accessibility and maintenance.
3.1.9 Fittings, valves, and traps shall be installed so that piping may be completely
drained. Drains shall be installed on low points that are not self-draining.
3.2.1 Piping shall not be installed where it may be used for a step or grabrail.
3.2.2 Nonferrous piping shall not directly contact the ship's hull.
GTR No. 23
PIPING
j. CHTs.
k. Magazines.
l. Refrigerated spaces.
m. Medical spaces.
n. Chart rooms.
o. Generator rooms.
p. Battery lockers and battery charging stations.
q. Electronic spaces.
r. Dry cargo holds.
s. Food preparation spaces.
t. Mess rooms.
Piping through these spaces shall have all joints welded or brazed.
3.2.4 Mitered joints or fittings shall not be used. Lateral joints shall not be used
unless pre-manufactured.
3.2.5 Galvanized piping shall not be used in potable water and AFFF systems.
3.2.6 Fiberglass or plastic piping, tubing, valves, and in-line fittings shall not be
used for potable water systems.
3.2.7 Piping conveying flammable media shall be routed to avoid being located
over hot surfaces, unless adequately shielded, and shall be located at least 450 mm (18 in)
from high temperature steam lines.
3.2.8 The use of cocks instead of valves shall not be permitted without specific
approval of MSCREP, except in gage lines.
3.2.9 Backing rings shall not be used where it causes flow restrictions.
3.3 Materials
3.3.1 Repaired or replaced piping shall as a minimum be the same as the material
schedule of the existing system. If installing a new system, piping material shall comply with
Reference 2.2.
3.3.2 The radius of ferrous piping bends shall not be less than 5 pipe diameters.
The radius of non-ferrous piping and tubing bends shall not be less than 3 pipe diameters.
Tubing shall not be thinned below the minimum wall thickness.
4.1 Pipe sleeves penetrating watertight or fire zone boundaries shall be fitted with
GTR No. 23
PIPING
Schedule 80 pipe sleeves. Pipe sleeves shall extend 150 mm (6 in) on either side of the
boundary.
4.2 Pipe sleeves required in wet spaces shall be Schedule 80 and shall extend 150 mm
(6 in) above and 25 mm (1 in) below the plating. Pipes shall be continuously welded to the
sleeve on both sides.
Flange shields shall be located on piping flanges and bolted valve bonnets and flanges.
Shields shall meet the requirements of Reference 2.3. Shields shall be installed on:
5.1 Fuel lines in main and auxiliary machinery spaces where a source of ignition exists.
5.2 Lube and hydraulic oil piping if the flange is within 4.6 meters (15 ft) of electrical
equipment, a hot surface, or other source of ignition.
5.3 Flanges near any surface with a temperature exceeding 204 oC (400 oF).
5.4 Fuel and lube oil strainers subject to pump discharge pressure.
6.2 Check valves, automatic nonreturn valves, and scupper valves shall be installed so
that they open and close in a fore and aft direction and so that the flapper and hinge pin can be
easily removed or replaced.
6.3 Overboard plumbing, sewage, refrigerated space, and interior deck discharge drains
shall be installed above the load waterline and shall discharge overboard by gravity. Hull
penetrations shall comply with Reference 2.4.
6.4 Deck drains shall be installed to prevent water from standing on the decks for all trim
and list conditions which could be expected at sea or in port.
6.5 Interior deck drains shall have a trap with an integral or built in bell baffle to seal pipe
odors. Where a drain trap is required, it shall be installed with an area at least twice that of the
drain pipe. The drain shall have a brass, stainless steel, or reinforced plastic strainer plate.
Strainers shall be secured and flush with the deck.
6.6 Coamings are required around equipment which may leak or spill oil under normal
operating and maintenance conditions, a drain shall be installed. Drains shall run to an oily
waste tank.
GTR No. 23
PIPING
6.8.1 Where nonreturn valves are required, they shall be installed on plumbing
fixture drainpipes or deck drains which combine with other drains at higher elevation to prevent
back flooding during roll and pitch conditions.
6.8.2 Soil drains from water closets and urinals shall be independent of other
drains and shall be piped into mains.
6.8.3 Plumbing drain vents shall be installed to vent to the weather deck. Anti-
syphonic valves shall not be used.
6.8.4 Any check valves required for plumbing system shall be the full flow type.
Where required, house top deck drains shall be at least 38 mm (1.5 in) in diameter.
Scupper drain pipes on each lower deck shall be increased by 13 mm (0.5 in) in diameter over
that of the deck above, with a 75 mm (3 in) maximum. Drains from decks above shall lead to
gutterways adjacent to scuppers.
7.1 Vent, sounding, and overflow piping that penetrates tank tops, flats, or decks shall
be fitted with schedule 80 sleeves if the piping is subject to damage from physical abuse or
from corrosion due to standing water. The sleeves shall be continuously welded on both sides
of the plating. Sleeves shall extend 150 mm (6 in) above and 25 mm (1 in) below the plating.
Piping shall be continuously welded to the sleeve at top and bottom.
7.2.1 Overflow and vent terminals above the weather deck shall terminate close to
the bulwark or deck house side with gooseneck fittings that do not interfere with equipment,
cargo, boat handling, and embarkation operations. Vents from sewage tanks and waterclosets
shall not terminate near portholes, doorways, normal working areas, or any location where
fumes could enter the deck house. Fuel oil vents, sounding tube terminals, and fueling
connections shall not terminate within living spaces.
7.2.2 Where required, vent terminal screens shall be monel or CRES and
removable.
7.2.3 Flanged takedown connections shall be installed in overflow and vent lines to
permit fitting of blanks to isolate tanks for individual tank air testing or as required.
GTR No. 23
PIPING
7.2.4 Watercloset, lavatory, and sinks vents which terminate on the exterior of the
deckhouse shall have a horizontal one half round pipe welded to the side of the house to
prevent wind from blowing down the vent. The internal sectional area of the half round pipe
shall be equal to the area of the vent, and the length shall be four times the diameter of the
vent.
7.3.1 Sounding tubes and striker plates shall be installed in accordance with
Reference 2.5. Sounding tubes shall be at least 38 mm (1.5 in) in diameter except for fuel oil
tanks, which shall be at least 50 mm (2 in) in diameter. Holes shall be drilled along the length
of the tube in accordance with Reference 2.5.
7.3.3 Where flanged takedown joints are required, they shall be installed at the
bottom of the sounding tube in accordance with Reference 2.5.
7.3.4 Where sounding tubes terminate flush with the deck, flush brass deck plugs
shall be installed on the sounding tubes. Where sounding tubes which do not terminate flush
with the deck, a self closing gate valve shall be installed in an accessible location on the
sounding tubes.
Where required, valves not accessible for local operation shall have remote
operating gear such as mechanical operating gear or reach rods. Operating gear, terminating
on the open deck or in passageways, shall have boxes fitted with "open" and "closed"
indicators. Remote operators terminating in passageways shall be close to the bulkhead. Box
wrenches shall be capable of removing the deck box plug as well as operating the gear and
shall be mounted near the deck plug box. Remote operating gear, not terminating in deck
boxes, shall be fitted with hand wheels.
GTR No. 23
PIPING
a. Flexible shafting used for remote operation shall not exceed the
manufacturer's specified bend radius. Selection of material shall be used for components in
corrosive or submerged conditions.
3) Where included angles are less than 150 degrees gear boxes
shall be used. 90 degree gearboxes shall be used only for 90 degree changes of direction all
other angles shall be obtained using the 300 degree type variable angle gearbox. Gearboxes
shall not have universal joints connected directly to them to make up incremental angles.
6) Hangers shall be used to support the reach rod along its length.
The distance between hangers on straight runs of rod shall not exceed 10 feet. In addition
hangers shall be arranged close to universal joints to prevent deflection of the reach rod during
turning of the universal joint. On vertical runs the reach rod shall have a vertical thrust bearing
at the top to take the weight of the system off the deck penetration piece. All hangers shall have
a bearing included in them to reduce friction, all hangers will be attached to substantial
foundations welded to the ships structure to prevent deflection. Hangers in corrosive
environments or where used for submerged applications shall have grease grooves in the
bearing surface and be fitted with grease fittings for the application of grease.
GTR No. 23
PIPING
10. The diameter of the reach rod shall be selected using the
manufacturer’s data and is based on the torque requirements of the valve.
Alignment of the various components shall ensure that the included angles
for universal joints do not exceed those listed above. In addition gearboxes of the 300 degree
variable angle type shall be aligned by first finding the compound angle between the two
sections of reach rod and then setting the gearbox supports to this angle without inducing
stress into the housings. Slip joints must be set at the mid point of their full range of movement
to allow for ship deflection and thermal growth. Functional testing of components should be
made after completion of installation in the conditions that the system is expected to function in
when the ship is in service.
8.2.2 Flanged waster pieces shall be installed between ferrous and nonferrous
material. Waster pieces shall be at least 300 mm (1 ft) long and two schedules heavier than
the system design pressure would dictate. Waster pieces shall be accessible and capable of
being easily replaced. Waster pieces shall be installed inboard of shell valves.
GTR No. 23
PIPING
8.2.3 Valves
•= Where pressure does not exceed 2070 kPa (300 psi), and
•= Where steam lines are 50 mm (2 in) or less in diameter.
g. Gate and globe valve stem glands shall seal when the valve is open.
Globe and angle valves shall have seating surfaces which are regrindable.
i. Gate and butterfly valves shall not be used for throttling services.
Globe valves shall be installed to minimize flow turbulence and pressure drop and where
regulating flow is of primary concern.
j. Butterfly type valves shall be suitable for use with all types of flanges
and in locations requiring “shut-off” for joint “breakdown” for maintenance without interruption of
service to the rest of the system(s). The valves shall be flange or lug type, with fastening to
each mating flange, or be equipped with adjacent flanged spool piece connecting the
equipment or flanged joint.
GTR No. 23
PIPING
k. The use of butterfly valves in fuel oil systems shall be avoided except
where space constraints do not allow any other type. Only USCG Category “A” type valves are
allowed. USCG Category “A” type valves are not allowed as a positive shut-off valve.
The maximum fluid velocity for a system is determined by minimum required inlet
pressure of machinery and components under maximum flow conditions and the limitations on
inlet velocities of machinery and components. System design velocities shall be based on
Table 23-1.
GTR No. 23
PIPING
1,d
Table 23-1. Design Fluid Velocities for Piping
FLUID VELOCITY, fps
a
SERVICE Nominal Limit
Condensate pump suction 3
d
Condensate pump discharge 8
3 d
Condensate drains 1
.3 d
Hot-water suction 3
d
Hot-water discharge 8
3 d
Feedwater suction 4
1.3 d
Feedwater discharge 10
4 d
Cold freshwater suction 15
3 d
Cold freshwater discharge 20
5 d
Lube-oil service pump suction 4
d
Lube-oil discharge 6
2 d
Heavy-fuel service suction 4
d
Heavy-fuel service discharge 6
1.5 d
Heavy-fuel transfer suction 6
d
Heavy-fuel transfer discharge 15
2 d
Distillate-fuel suction 7
2 d
Distillate-fuel discharge 12
5 d
Hydraulic-oil suction 8
1.5 d
Hydraulic-oil discharge 20
8 d
b, c
Seawater suction 12
3 d
b, c
Seawater discharge 12
5 d
Steam, high pressure 200
50 d
Steam exhaust, 215 psig 250
75 d
Steam exhaust, high vacuum 330
75 d
Notes: 1 - Roy L. Harrington, ed., Marine Engineering (Jersey City, NJ: The Society of Naval Architects
and Marine Engineers, 1992), pg. 796.
a - d is the pipe internal diameter in inches.
b - 9 fps for galvanized steel pipe.
c - Seawater velocity in titanium and GRP piping may exceed these limits without detrimental
erosion; however, friction losses, turbulence, and noise may still be limiting factors.
d - For 9010 Cu Ni and for galvanized piping, max velocity = 8 fps.
GTR No. 24
MANUFACTURER’S REPRESENTATIVES
1.0 ABSTRACT
This Item establishes the requirements for manufacturer’s and authorized manufacturer’s
representatives.
3.2 Technical representatives who are not authorized by the manufacturer to perform
maintenance, repair, service, troubleshooting, installation, and modification on the equipment or
machinery specified in the work item shall have the following minimum qualifications:
3.2.1 At least five years' experience which includes formal training in a field service
organization as an authorized manufacturer's technical representative for the type of equipment
or systems being serviced, repaired, installed, modified, or relocated.
3.2.3 References from at least three different clients for whom service was
provided on the type of equipment or systems being serviced, repaired, installed, modified, or
relocated.
3.2.4 Ability to procure parts and access to manufacturer’s drawings for the
equipment or machinery specified in the work item.
4.0 REPORT
GTR No. 25
1.0 ABSTRACT
This Item establishes the general requirements for the design and construction of
structure and foundations.
2.0 REFERENCES
2.1 American Society for Testing and Materials (ASTM), F1053, Standard Guide for
Steel Hull Construction Tolerances.
2.2 Mil-Std-1399, Sect. 301A, Interface Standard for Shipboard Systems, Ship Motion
and Attitude.
3.0 GENERAL
ABS Grade steel suitable for the application shall be used to make structural installations,
repairs or modifications or to manufacture foundations. Interfaces between two steel surfaces
shall not be of dissimilar metals.
4.1 Projections, interferences, and obstructions shall be minimized to ensure that clear
and unobstructed use of the space is achieved. Structural members shall be part of steel
divisional bulkheads where possible. Steel bulkheads shall not be substituted for joiner
bulkheads to avoid using pillars and girders. New bulkheads and decks shall be fair without
buckles, kinks, or other irregularities in accordance with Reference 2.1.
4.2 Outside corners of interior steel bulkheads, in working spaces and wherever they
present a hazard to personnel, shall have a radius of at least 75 mm (3 in).
5.0 COAMINGS
5.1 Coamings around new deck openings for vertical access, including openings in
trunks not protected by hatch covers, shall be at least 100 mm (4 in) high.
5.2 Coamings around stair and ladder companionways shall be 75 mm (3 in) above the
plating or deck covering and 75 mm (3 in) below the plating and shall be cut flush in way of
inclined ladders and stairs to avoid a tripping hazard.
GTR No. 25
5.3 Coamings around new and modified weather decks which surround deckhouses
shall be at least 75 mm (3 in) high.
5.4 Watertight coamings around joiner bulkheads surrounding wet spaces, including but
not limited to showers, decontamination stations, deck gear lockers, galleys, toilets, and
laundries shall be 150 mm (6 in.).
6.0 FOUNDATIONS
6.1 All new foundations shall provide complete support against static, dynamic, vertical,
and racking loads independent of the casing, frame, bedplate, or other parts of the supported
unit. Foundations shall be installed to provide support against loads due to ship motion which
shall be estimated using Reference 2.2. Foundations for electronic equipment shall have a
natural frequency of at least 10 Hz. The foundations supporting heat producing units shall be
designed to limit thermal stresses to allowable levels. Foundation construction shall permit
access for cleaning, maintenance, and equipment operation. Unless otherwise specified, the
allowable bending stress shall not exceed 124,000 kPa (9 tons/sq. in.), and the shearing stress
shall not exceed 0.6 times the allowable bending stress.
6.2 Foundations shall be installed so that the equipment mounting surfaces are parallel
or normal to the ship's baseline.
6.3 Auxiliary machinery shall be secured to foundations without the use of collision and
shifting chocks.
GTR No. 26
1.0 ABSTRACT
This Item establishes the general requirements for preparing interior decks and applying
deck coverings.
2.0 REFERENCES
2.1 National Shipbuilding Research Program (NSRP) 0354, The Standard Practice
for the Selection and Application of Marine Deck Coverings.
2.2 American Society for Testing and Materials (ASTM), D178, Specification for
Rubber Insulated Matting.
3.0 GENERAL
3.1 Deck covering shall not be installed until all required testing for watertightness and
all fastening of machinery, equipment, furniture, etc. has been completed. Deck covering shall
not be painted to hide stains and discolorations.
3.2 Deck covering appropriate for the service shall be selected from Reference 2.1.
4.1 Deck covering shall not be installed under built-in furniture, but shall scribe and fit it
up to sub-bases. The Contractor shall not install deck coverings over other deck
appurtenances, including but not limited to furniture tie downs and deck drains.
4.2 Coving shall be 100 mm (4 inch) high around the perimeter of newly floored spaces
and areas.
5.1 All tile of a particular style should come from a single manufacturer with the same
dye lot and date of manufacture.
5.2 Through pattern tiles - In through pattern tile, the pattern shall be distributed and
worked throughout the thickness of the tile. In mottled and marbleized tile, the marbleizing and
mottling shall be worked throughout the thickness of the tile.
5.3 Surface pattern tiles - The pattern need not extend through the entire thickness of
the tile, and may be decorated, embossed, or both. The appearance of the tile, when the
wearing layer has been removed to a depth of 0.25 mm (0.010-inch), shall compare favorably
for decoration with the tile's original appearance. The depressed areas of embossed tile shall
involve no more than one-third of the original, flat tile surface area prior to embossing as
GTR No. 26
measured on a full tile. On embossed tile, there shall be no depressed area into which a 16 mm
(0.625 in) diameter circle can be placed, except that this shall not apply to tiles that have an
overall embossed surface, such as brick, slate, or other textures.
5.4 Size - The tile shall be 230 by 230 mm (9 by 9 in) or 300 by 300 mm (12 by 12 in). A
tolerance of + 0.40 mm per 300 mm (0.016 in/ft) shall be permitted. All tiles in any one space
shall be of the same size. Vinyl plastic tile shall be 3 mm (0.125 in) thick. A tolerance of +
0.127 mm (0.005 in) shall be permitted.
5.5 Adhesive
5.5.2 The adhesive shall be free from grit, lumps, and skins and shall be suitable
for application with a trowel without heating or the addition of other ingredients.
6.0 TERRAZZO
6.1.1 The aggregate, including marble, shall be of a suitable size for application of
the deck covering in a 6 mm (0.25 in) thickness in one coat.
6.1.2 The adhesive shall be a water-based latex, free of all ingredients which may
negatively affect its serviceability or have a deleterious effect on metal or resilient deck
covering. The adhesive shall be free from grit, lumps, and skins and shall be suitable for
application with a trowel. The adhesive shall be suitable and effective for the purpose intended
without heating or the addition of other ingredients.
6.1.4 The terrazzo deck covering shall have continuous deck material to provide an
integrated base cove 100 mm (4 in) high along the bulkheads. Where the terrazzo ends in
open deck areas, it shall be feather-edged to the adjacent deck. The terrazzo after installation
shall be ground smooth to expose the binder, marble chips (aggregate), and sealer. The
surface of the finished terrazzo shall be of a uniform color.
6.2 Sealer
At least two coats of an approved sealer shall be applied to the finished terrazzo
allowing two hours between coats.
GTR No. 26
7.2 Rubber matting shall be gray, non-conductive, diamond tread. The matting shall be
made from a compound utilizing synthetic rubber, reclaimed rubber, polyvinyl chloride, a
copolymer of polyvinyl chloride and polyvinyl acetate, or a combination thereof. The use of
ingredients which would tend to emit objectionable odors in service are prohibited. Reclaimed
rubber shall be used to the maximum extent possible. The back side shall be finished with a
cloth fabric or a cloth imprint.
7.3 The mats shall be secured with cement except in way of removable floor plates or
gratings. Matting shall be installed with a minimum of seams. When rubber matting is required
in a space where another deck covering is also specified, the other deck covering shall be
installed outside the area of the rubber matting. Overlay shall be used to provide a smooth
transition between rubber matting and other deck covering. If rubber matting covers one-half or
more of the clear deck area of a space, the other covering shall be omitted and rubber matting
installed over the entire deck area of the space.
2
7.4 Rubber matting shall be rated for a minimum dielectric strength of 30,000 Volts/cm .
Its overall thickness shall be 4.5 mm (0.1875 in) minimum and its width shall be at least 1 meter
(3 ft).
Safety treads shall be of the fiberglass reinforced resin or metal abrasive insert type and
shall be weather resistant with a nonskid surface. Treads shall be located at the head and foot
of all inclined ladders, and shall cover each step on inclined ladders. Treads shall not be
installed where nonslip material such as rubber matting or grating is required or where nonslip
decking is required.
9.0 CARPET
Installed carpet shall be wool or man-made fiber (USCG Class A fire retardant) and be
bulkhead-to-bulkhead, and glued with a manufacturer's approved adhesive.
GTR No. 26
9.1.1 The carpet fiber shall be thoroughly scoured carpet type fiber which has
never been reclaimed from any woven, tufted, knitted, or felted product.
9.1.2 The backing material used in the construction of the primary backing of tufted
carpet shall be one customarily used and accepted by the trade.
9.1.3 The backing reinforcement shall be woven or knitted fabric weighing not less
than 170 g/sq. m (6.0 oz/sq. yd) or non-woven polypropylene weighing at least 100 g/sq. m (3.5
oz/sq. yd).
Carpet shall have attached rubber cushioning. The compound used in making the
cushioning shall be made from natural or synthetic latex or a mixture of natural and synthetic
lattices. The cushioning shall be free of objectionable odor and shall have a skin on the floor
side when affixed to the carpet. Rubber cushioning used under carpet shall meet the following
requirements:
9.2.2 The weight per square meter (sq. yd) shall be between 1.6 kg (3.50 lbs.) and
1.9 kg (4.25 lbs.).
9.2.3 The compressibility shall be between 2.3 kg (5 lbs.) and 4.1 kg (9 lbs.).
GTR No. 26
9.3 Seaming
9.4 Underlayment
Before the carpet is installed, the decks shall be faired with underlayment over
irregularities, including but not limited to weld seams, depressions, etc., to prevent high spots
and other irregularities from showing through the carpet and causing premature wear.
9.5 Installation
Carpet shall be fitted closely to the bulkhead, built-in furniture bases, and around
pipe and deck fixtures.
GTR No. 26
GTR No. 27
1.0 ABSTRACT
2.0 REFERENCES
2.1 Society of Naval Architects and Marine Engineers (SNAME) Technical and Research
Bulletin No. 4-16, Calculations for Merchant Ship Heating, Ventilation and Air Conditioning
Design.
2.2 Society of Naval Architects and Marine Engineers (SNAME) Technical and Research
Bulletin No. 4-7, Thermal Insulation Report.
2.3 HVAC Systems Duct Design, Sheet Metal and Air Conditioning Contractors National
Association, (SMACNA).
2.4 U.S. Public Health Service and MARAD's Joint Publication No. P 161019
"Ratproofing of Ships".
3.0 GENERAL
3.1 HVAC system design heating and cooling load calculations shall be based on
meeting the temperatures, relative humidity (RH) limits, and ventilation rates in Reference 2.1.
Heat transfer coefficients shall be based on Reference 2.2. Pressure drop calculations shall be
developed using Reference 2.3 as guidance.
3.2 HVAC systems shall include but not be limited to filters, fans, fan coil assemblies,
fan coil units, air filters, screens, duct work, steam preheaters, convection electric heaters,
cooling coils, electric and steam reheaters, unit heaters, sound attenuation boxes, silencers,
diffusers, terminals, closures, louvers, splitters, turn vanes, dampers (fire, diverting, and
balancing), thermostatic controls, drains, insulation (thermal and acoustic), vapor sealing and
lagging, label plates, operating instructions and all other items that are necessary for safe
system operation and satisfactory performance.
3.3 HVAC system design shall minimize compartment pressure with respect to
surrounding spaces and to the weather.
3.4 Odor producing spaces and spaces with toxic or explosive fumes and with Class A
bulkheads shall have a slight negative pressure of 0.06 kPa (0.25 in water) achieved by duct
design. Negative pressure in spaces with B or C Class bulkheads shall be achieved by natural
supply through louvered doors and/or mechanical exhaust.
GTR No. 27
3.5 System design shall eliminate condensation under design conditions for both heating
and cooling seasons.
3.6 Duct sections, cooling coils, and fan coil units shall not be installed over the following
types of equipment:
•= Computers.
•= Control panels.
•= Electronic equipment.
•= Generators.
•= Generator terminals.
•= Power distribution panels.
•= Switchboards.
•= Transformer terminals.
3.7 Where coils are installed, drains shall be installed at both ends of the pan. System
drains shall be designed for list conditions of up to 15 degrees.
o
3.8 Chilled water cooling coils (Navy Standard) shall be selected for use with 7 C (45
o
F) chilled water at a flow rate of 14 liters (3.6 gal)/minute/ton of refrigeration. All other cooling
coils shall be sized according to the manufacturer’s requirements.
3.9 Fan rooms used as plenums for air conditioning systems shall not be subject to a
positive pressure and shall be limited to no more than 0.12 kPa (0.5 in water) negative
pressure.
4.1 Steam preheaters shall be equipped with control valves or other mechanism to
prevent the coils (heating and cooling) from freezing.
4.2 Design Requirements
4.2.1 When duct bulbs are installed downstream of the coils, they shall be located
at least 2.4 meters (8 ft) from the discharge face of the controlled coil and away from splits or
branches. Duct bulbs shall be shielded from the effects of radiant heat.
GTR No. 27
4.2.2 Thermostats shall be bulkhead mounted about 1.5 m (5 ft) above the deck to
sense the return air temperature of the space or positioned so that they are not affected by
localized cold or heat sources. Thermostats shall regulate space temperature and read
temperature in degrees Fahrenheit.
5.1.1 Air velocities of HVAC systems and their components shall comply with Table
27-1.
5.1.2 Maximum air velocity at head end of berths shall not exceed 0.1778 m/s (35
FPM); elsewhere, velocity shall not exceed 0.254 m/s (50 FPM).
5.1.3 Decibel readings shall be limited to 55 decibels for living and office spaces,
and 70 decibels for passageways based on measurements taken three feet away from the
terminal.
5.2.1 Trunks, ducts, covers, louvers, and other HVAC items exposed to the
weather, shall be at least 3.2 mm (0.125 in) steel plate and shall be watertight.
5.2.2 Vertical trunks or ducts subject to damage shall be at least 3.2 mm (0.125 in)
thick.
5.2.3 Built in trunk construction shall not be used for ducts that have a cross
section of less than 0.09 sq. meter (1 sq. ft).
5.2.4 Ducts shall be airtight. Duct seams shall be constructed by any of the
following methods:
•= Riveted seams sealed with hot solder or fire resistant high velocity duct
sealer.
•= Welded, hooked seams and laps.
•= Spot welded on 25 mm (1 in) centers with external seams and joints
sealed by a 25 mm (1 in) wide strip of duct sealer.
5.2.5 Ducts shall be airtight before applying duct insulation. All other ducting shall
be made of hot dipped galvanized sheet steel. The minimum thickness of the material shall be
determined by the diameter of round ducts or the greatest dimension of rectangular ducts as
follows:
GTR No. 27
5.3.1 Access holes with bolted plate covers shall be provided as follows:
GTR No. 27
5.4.2 Duct joints shall be installed where duct section removal is required for
access to piping, cabling, and other equipment. Duct joints may be flanged, clamp type, or
sleeve type and sealed with duct sealer and tape. Flanged connections or flanged spools shall
be installed if the duct is installed in the weather or in machinery spaces.
5.4.3 Elbows in ducts and trunks shall be at least one half the standard throat
radius. When the throat radius is less than the one half standard, baffles and concentric turning
vanes shall be installed to provide quiet operation. Small radius turning vanes shall not be used
in elbows unless structural considerations require using miter throat radii. Turning vanes or
grids shall be installed to achieve uniform air flow to registers, grills, and diffusers.
5.4.4 Converging transition pieces shall have a taper which does not exceed 20
degrees on a side. Diverging transition pieces which have a taper that exceeds 10 degrees,
shall have splitters fitted to reduce the expansion angle to less than 10 degrees.
6.1 Damper and register linkages, bearings, pins, shafts, and similar working parts shall
be bronze.
6.2.1 Diffuser terminals shall be used in air conditioned spaces. Supply terminals
in working and machinery spaces shall have integral or separate throttling dampers for
manually controlling the volume of air flow.
6.2.2 Terminals shall be installed so that they properly ventilate the space served.
Diffusers shall be equipped with adjustable equalizing deflectors within the neck of the diffusers
to provide uniform terminal throat velocities and internal means for adjusting the discharge. The
thickness of material used for cones and orifices shall be at least No. 22 USSG (0.8 mm).
Other sheet steel parts shall be at least No. 20 USSG (0.9 mm). Heavier gages of material
shall be required when aluminum alloy is used. The air flow rate handled by each terminal shall
not exceed 14 cu meters (500 cu ft)/minute. Air terminals shall conform to the following
requirements:
b. Ventilating hoods and canopies shall terminate flush with the deckhead
and shall be screened. Pipes, cables, air ducts, and similar features over tops of hoods shall
be grouped so that spaces or pockets, inaccessible for inspection, are not formed. If such
spaces are formed, they shall be closed completely with sheet metal of No. 18 USSG (1.2 mm),
GTR No. 27
6.2.3 If register and diffuser parts are not furnished with a prime coat of paint, they
shall be hot dipped galvanized or cadmium plated to prevent corrosion before painting. Lever
operators, multilouver blades, and similar parts shall be zinc or cadmium plated. Connecting
bars, bearings, rivets, springs, washers, nuts and similar parts shall be made of bronze.
Turning surfaces shall be bronze on bronze.
6.2.4 13 mm (0.5 in) wire mesh screens or return air diffusers shall be installed on
return air terminals.
6.3.1 Diffuser terminals shall be installed flush with the ceiling panels in air
conditioned spaces. The air flow handled by each diffuser shall not exceed 10 cu meters (350
cu ft)/minute. The diffuser decibel rating shall not exceed 50 on the A scale.
6.3.2 Diffuser terminals serving air conditioned spaces shall be constructed so that
moisture cannot be formed on the cones.
6.3.3 Balancing dampers, when built into diffuser terminals or installed adjacent to
terminal inlets, shall be opposed acting and single group operated, equalizing the air flow over
the terminal and throttling air flow. After the system is balanced, dampers shall be tack welded
to secure the dampers permanently in the balanced position.
6.3.4 Balancing dampers fitted with position type indicators shall be used in splitter
ducting where required. After the system is balanced, dampers shall be tack welded to secure
the dampers permanently in the balanced position.
GTR No. 27
Fire dampers shall be constructed and installed in accordance with USCG rules.
They shall have an indicator showing damper position. They shall have a combined adjusting
and locking device located for accessibility and visibility. Damper control shall be from fully
open to fully closed.
6.5.1 Weather intakes shall be the self draining air lift type to prevent water and
spray from entering during washdown, rough seas, or inclement weather.
6.5.2 Weather openings shall be designed to minimize the effects of wind velocity
and weather, and have watertight covers as required by ABS.
6.5.3 Covers for weather openings shall be rattleproof when secured in the open
position.
7.0 RATPROOFING
7.1 HVAC system ratproofing shall be accomplished in accordance with Reference 2.4
to enable the ship to maintain its Deratization Exemption Certificate and Certificate of Sanitary
Construction.
7.2 Ratproofing shall not be accomplished if ducts are within ratproof double bulkheads
or deckheads or in fan rooms which have ratproof boundaries and doors marked "KEEP
CLOSED."
7.3 In cargo spaces, the ratproofing material shall be at least the next heavier even
numbered gauge than the space sheathing.
7.4 Natural supply and exhaust openings shall be ratproofed. Ratproofing shall be
installed for ventilation systems which serve a single space on the end which is most effective in
preventing rat harborage. Ducts extending from the weather deck directly to the cargo holds,
GTR No. 27
engine room, and boiler rooms, with no horizontal extensions, do not require ratproofing at
either end.
TABLE 27-1
GTR No. 27
GTR No. 28
1.0 ABSTRACT
This Item establishes the minimum requirements for ship's electrical and electronics
systems.
2.0 REFERENCES
2.1 IEEE Standard 45, Recommended Practice for Electric Installations on Shipboard.
2.2 National Electrical Manufacturers Association, NEMA 250, Enclosures for Electrical
Equipment (1000 volts maximum).
2.4 MIL-STD-1680 (Series) (SH), Installation Criteria for Shipboard Secure Electrical
Information Processing Systems. (Confidential-Used when applicable)
2.6 MIL-C-176 (Series), Cables, RF, Flexible and Semi-rigid, General Specifications for.
2.8 DOD-STD-1399 (NAVY), Interface Standard for Shipboard Systems, Section 300A.
2.9 MIL-STD-1310 (Series) (SH), Shipboard Bonding, Grounding, and Other Techniques
for Electromagnetic Compatibility and Safety.
3.1 Installations shall comply with the requirements of Reference 2.1 unless otherwise
noted.
3.2 Equipment which depends upon forced ventilation for cooling must be provided with
an imbedded temperature device that will initiate an alarm to indicate that the internal
temperature of the equipment has risen above design limits.
GTR No. 28
4.1.1 Power consuming equipment shall operate within 5% of rated voltage and
3% of rated frequency in accordance with Table 28-1. Unless otherwise specified, 60 Hz power
shall be Type 1 and 400 Hz power shall be Type 2. To ensure power quality and reduce
harmonic effects, physical and electrical isolation should be provided between electronic
systems and power systems which supply large numbers of solid state devices, or significantly
sized solid state motor controllers.
4.1.2 Source power for electronic equipment shall be Type 1 per Table 28-1.
4.2 Enclosures
4.2.1 Connection boxes, outlet boxes, junction boxes, and similar devices and
fixtures exposed to the weather, condensation, or excessive dampness shall comply with
Reference 2.2. Steel enclosures may be used in dry locations.
4.2.3 Any penetration into an enclosure shall not affect the degree of protection of
the enclosure.
4.2.4 Enclosures, foundations, and base plates shall not be made of wood or
materials with a flame point below 1000 °F.
GTR No. 28
External wires for electrical equipment (except motors and lighting fixtures) shall
have terminal boards or blocks. Terminal boards are not required in motor terminal boxes. The
leads shall be equipped with lugs for direct connection to lugs on ship cables and provide
adequate contact, low voltage drop, low temperature rise, and mechanical strength to resist
pullout and withstand shipboard vibration. For motors, lighting fixtures, and vital electrical
equipment crimp type connectors shall be used that conform to Reference 2.3. Connections
shall be wrapped in insulating tape. All connections shall be made within an enclosure.
5.1 Supply power (voltage, phase, frequency) shall be from a switchboard, load center,
or distribution panel and shall comply with Reference 2.1 and Table 28-1.
5.2 The power distribution system, lighting distribution system, interior communications,
and electronics distribution systems shall be maintained as separate distribution systems fed
from the ship service generator and emergency generator switchboards.
5.3 Weather deck and cargo hold floodlights permanently installed above the deck may
operate at 440 volts.
6.1 Electronic equipment shall be arranged and installed to comply with Reference 2.1
or 2.4 for secure communications.
6.2 On the navigation bridge (pilothouse), equipment shall be grouped into navigation,
maneuvering, communication, and monitoring functions. Communication equipment shall be
located as high in the vessel as practicable.
7.1 General
7.1.2 Only low smoke cable complying with Reference 2.1 shall be used.
7.1.3 Special cable or conductor types, such as coaxial cables, shielded twisted
pairs, and antenna connections shall be used as recommended by equipment manufacturers.
7.1.4 Portable cords shall have two current carrying conductors and one ground
GTR No. 28
conductor and shall be heavy duty rubber jacketed except where used for small appliances that
contain heating elements. For these applications, a heat and flame resistant portable cord shall
be used. The minimum size of conductors for portable cords shall be No. 16 AWG and meet
the requirements of Reference 2.5. Portable cords shall not be used for permanent
installations.
7.1.5 Connectors exposed to the weather shall be suitable for the installation and
be wrapped with plastic electrical tape at least 38 mm (1.5 in) beyond the connector. The
connector shall be covered with a durable weather tight jacket of the heat shrink or cold shrink
type. Before installing connectors, threaded sections shall be coated with an anti-seize
compound if permitted by the manufacturer.
7.1.6 Cable armor shall be electrically and mechanically grounded to the metal hull
at the supply end of final sub-circuits and grounded to the metal hull at each end for other
circuits. Single conductor AC cables shall have their armor grounded at the midpoint only.
Armor may not be used as the system or safety ground.
7.1.7 Power cables wherever practical shall be installed in a single bank. Where
double banking is unavoidable, cable current values are to be derated by 80%. Bunching of
cables is not permitted.
7.1.9 Electronic and RF cables shall be installed to obtain the best possible
operation and to reduce losses and interference in accordance with References 2.1, 2.4, 2.6,
2.7, 2.8, and 2.9.
7.1.10 Fiber optic cable shall be of type four (4) fiber, (OFNP) rated Plenum, Fiber
Optic Breakout cable and comply with Reference 2.1.
7.2.1 Cable runs shall be direct and installed according to References 2.1, 2.4, and
2.6.
7.2.2 Cables shall be kept at least 1 meter (3 ft) from surfaces dissipating extreme
heat. Where it is not possible to avoid installing cables near heat dissipating surfaces, heat
insulating barriers shall be used. Cables shall not be installed adjacent to piping or other
apparatus which may leak or drip condensation. If such proximity is unavoidable, the cables
shall be mechanically shielded. Cables should not be located in cargo tanks, ballast tanks, fuel
tanks, or water tanks except to supply equipment specifically designed for such locations and
whose functions require it to be installed in the tank. Cable installation in refrigerated spaces or
hazardous spaces is not permitted unless no other routing is possible. Cable installation in
refrigerated spaces, where unavoidable, shall be stepped away from the flat surfaces and shall
GTR No. 28
never be installed behind or within the insulation. Cables shall be installed in existing
cableways to the maximum extent practicable.
7.2.3 Cable runs shall not be exposed to the weather unless weather exposure is
unavoidable. Cables for fixtures and equipment located in the weather shall be installed on the
inside surface of house structures and other structures that support the fixtures.
7.2.5 Cable runs shall keep external magnetic fields to a minimum and shall be
protected from excessive external magnetic fields in accordance with References 2.1, 2.6, and
2.7. Cable runs shall be continuous between outlet boxes, connection boxes, switchboards,
and panelboards. Where a box or wiring device is not grounded to the ship's structure by its
mounting arrangement, a separate grounding conductor grounded at the panelboard shall be
installed.
7.2.6 Circuits containing nonlinear currents, such as thyrister drive cables, shall be
separated from other circuits according to Reference 2.1. Low level signal and control cables
and wires shall not be run in the cableways or wire bundles containing other cables and wires.
Wireways with cables carrying nonlinear currents shall be separated by 1 meter (3 ft) from
those containing other cables.
a. Cable size for communications circuits shall allow for possible future
system expansion. At least 10% additional wires or circuits, based on the actual number of
conductors used, shall be provided in IC cables that have five or more conductors. Four
conductor IC cables shall have at least one spare conductor.
b. Voltage drop for interior communication circuits shall not exceed 5%.
GTR No. 28
8.0 PANELBOARDS
Distribution panelboards shall comply with Reference 2.1 requirements and shall be the
circuit breaker type with at least 50 ampere frame size circuit breakers. Distribution panelboard
buses shall be three phase. Drip proof cabinet fronts for panel boards shall have one hinged
door for access to the circuit breaker handles. Dead front distribution panels shall be used.
Circuit breakers used in local distribution panelboards shall be the commercial marine
molded case type, quick make, quick break, with inverse time tripping characteristics on
overloads and an instantaneous trip device for short circuits.
10.0 MOTORS
Motors rated over 1/4 horsepower shall be AC squirrel cage induction type, designed for
the ship’s distribution system, typically 440 volts, 3 phase, 60 hertz, and continuous duty. Small
appliances and fractional horsepower motors less than 1/4 horsepower shall operate on 115
volts AC. Motors shall be single speed unless the application of driven equipment requires a
two speed motor. Two speed motors shall be the two winding type. Motors shall be equipped
with sealed antifriction bearings to meet thrust and radial load requirements. Fractional
horsepower motors, less than 1/4 horsepower may be equipped with sleeve bearings. Shaft
seals on the above motors shall be of the nonrubbing labyrinth type. Round frame motors shall
be provided for axial flow and propeller fans. No type of silicone varnish, compound, rubber,
grease, laminate, or binder shall be used in enclosed DC motors or enclosed AC motors that
have collector rings within the motor enclosure.
11.0 ANTENNAS
11.1 Antennas should be mounted as high as practicable. Radar antennas and satellite
system antennas shall be positioned to minimize shadowing. Antennas shall be physically
separated to reduce electrical interaction and to avoid physical contact due to antenna
deflection caused by ice loading, wind or sea conditions.
11.2 RF cable installation shall comply with Reference 2.6. All hardware used to secure
antennas and couplers shall be stainless steel.
Motor controllers shall have nonresettable hour-meters. Motor controllers shall be across
the line magnetic type. Controllers shall have integral disconnect circuit breakers. Whenever
several motors are installed in close proximity to one another, their controllers shall be grouped
on a bulkhead or framework at an accessible location near the motors, or a motor control center
shall be used. Heaters shall be installed for motors with insulation resistance monitors and
GTR No. 28
motor controllers located in the weather. The heater circuits shall be interlocked with motor
control circuits to prevent moisture condensation when the motors and controllers are
deenergized.
All equipment bonding and grounding shall be in accordance with Reference 2.9. This
includes but is not limited to:
•= Work benches
•= Machinery and equipment
•= Exterior doors, hatches, ladders and stairs
•= Metal handrails
•= Exterior vent hood covers, access covers, and soft patches
•= Antennas, waveguides, and cables
•= Rigging and load lifting davits
GTR No. 28
TABLE 28-1
VOLTAGE
(a) Nominal User Voltage 460 or 460 or 460, 115 or
115 volts rms 115 volts rms 115/200 volts
rms
(f) Voltage Spike (peak value, includes ±2500 volts ±2500 volts ±2500 volts
fundamental) (460 V sys) (460 V sys) (460 V sys)
±1000 volts ±1000 volts ±1000 volts
(115 V sys) (115 V sys) (115 V sys)
WAVEFORM (VOLTAGE)
(i) Maximum Total Harmonic Distortion 5% 5% 3%
(j) Maximum Single Harmonic 3% 3% 2%
(k) Maximum Deviation Factor 5% 5% 5%
GTR No. 28
FREQUENCY
(l) Nominal Frequency 60 Hz 400 Hz 400 Hz or
60 Hz
EMERGENCY CONDITIONS
(r) Frequency Excursion -100 to + -100 to + -100 to +
12% 12% 12%
GTR No. 28
GTR No. 29
IDENTIFYING MARKINGS
1.0 ABSTRACT
This Item establishes the requirements for identifying markings. Identifying markings are
labels, notices, certificates, instruction plates, warning signs, documents, and other indications
required for space and item identification and unit operation.
2.0 REFERENCES
2.1 American Society for Testing and Materials (ASTM), F992, Standard Specification
for Valve Label Plates.
2.2 IEEE Standard 45, Recommended Practice for Electric Installations on Shipboard
3.0 GENERAL
3.1 All Contractor and Government furnished equipment, machinery, doors, furniture,
rigging, and systems shall have identifying markings. Identifying markings and documents for
display shall be framed. Identifying markings shall be in English.
3.2 Identifying markings and other documents shall be protected during the availability.
Two or more similarly named spaces shall be designated by the space name
followed by a number, as follows:
4.2.1 Numbers shall be assigned consecutively (such as Radar room No. 1, Radar
room No. 2), starting with No. 1, by applying the following rules in the order given:
•= From top, down
•= From forward, aft
•= From starboard to port.
4.2.2 The forward bulkhead of a space shall be used for designating a space's
longitudinal location within the ship. After the numbers are assigned, modifications which add
additional spaces which would fall within a number group already assigned shall be assigned
the number of the space immediately preceding it, followed by the letter "A" (for example, an
additional radar room occurring between Radar Room No. 2 and Radar Room No. 3 shall be
designated Radar Room No. 2A). If a space number precedes the space numbered 1, it shall
be assigned the number 1 preceded by the letter "A" (such as Radar Room No. A1). If
GTR No. 29
IDENTIFYING MARKINGS
AUDITORIUM
CHAPLAIN'S STATEROOM (CHAPL SR)
CHIEF ENGINEER'S OFFICE (CH ENGR OFC)
CHIEF ENGINEER'S STATEROOM (CH ENGR SR)
CHIEF STEWARD'S STATEROOM (CH STW SR)
COMMANDING OFFICER'S MILITARY DEPARTMENT
CABIN (CO MIL DEPT CAB)
CHIEF PETTY OFFICER'S MESSROOM (CPO MESS RM)
CREW'S BERTHING (CR BERTH)
CREW'S DAY ROOM (CR DAY RM)
CREW'S LIBRARY (CR LBRY)
CREW'S MESSROOM (CR MESS RM)
CREW'S PANTRY (CR PAN)
DUTY MESSROOM (DUTY MESS RM)
ENLISTED MEN'S LOUNGE (EM LOUNGE)
ENLISTED MEN'S MESSROOM (EM MESS RM)
1st ASST. ENGINEER'S STATEROOM (1st ASST ENGR SR)
1st OFFICER'S STATEROOM (1st OFF SR)
GYMNASIUM (GYM)
LIBRARY
LOUNGE
MASTER'S CABIN (MA CAB)
MASTER'S STATEROOM (MA SR)
OFFICERS' LOUNGE (OFF LOUNGE)
OFFICER’S MESSROOM (OFF MESS RM)
PASSENGER’S STATEROOM (PASS SR)
PILOT'S SEA CABIN (PLT SEA CAB)
PANTRY (PAN)
PETTY OFFICER’S MESSROOM (P O MESS RM)
GTR No. 29
IDENTIFYING MARKINGS
BAKERY (BAK)
CREW'S SCULLERY (CR SCLY)
DAIRY
FISH
FRUIT & VEGETABLE (FRT & VEG)
MAIN GALLEY (MN GALY)
MEAT
MILK
SCULLERY (SCLY)
THAW ROOM (THW RM)
VEGETABLE PREPARATION ROOM (VEG PREP RM)
GTR No. 29
IDENTIFYING MARKINGS
GTR No. 29
IDENTIFYING MARKINGS
GTR No. 29
IDENTIFYING MARKINGS
4.3.8 Shops
GTR No. 29
IDENTIFYING MARKINGS
BARBER SHOP
CLEANING GEAR LOCKER (CG LKR)
CREW LAUNDRY (CR LAU)
DUMBWAITER (DW)
GARBAGE DISPOSAL ROOM (GBG DSPL RM)
INCINERATOR ROOM (INCIN RM)
LAUNDRY (LAU)
LAUNDRY ISSUE ROOM (LAU ISS RM)
LAUNDRY RECEIVING ROOM (LAU RCVG RM)
MOTION PICTURE PROJECTION ROOM (PROJTN RM)
OFFICER'S LAUNDRY (OFF LAU)
GTR No. 29
IDENTIFYING MARKINGS
BATHROOM
CREW'S SHOWER (CR SH)
CREW'S WASHROOM (CR WR)
DECONTAMINATION STATION (DECONTN STA)
ENGINEER'S SHOWER (ENGR SH)
ENGINEER'S WASHROOM (ENGR WR)
MEN'S BATH
MEN'S SHOWER (MEN’S SH)
MEN'S WASHROOM (MEN’S WR)
SHOWER
STEWARD'S SHOWER (STW SH)
STEWARD'S WASHROOM (STW WR)
TOILET (T)
TOILET AND SHOWER (T & S)
TRANSIENT OFFICERS' SHOWER (TRANSIENT OFF SH)
TRANSIENT OFFICERS' TOILET (TRANSIENT OFF T)
TRANSIENT OFFICERS' WASHROOM (TRANSIENT OFF WR)
WOMEN'S SHOWER (WOMEN’S SH)
WOMEN'S WASHROOM (WOMEN’S WR)
GTR No. 29
IDENTIFYING MARKINGS
The MSC fleet contains special project ships with spaces used for unusual
purposes. It is not possible to specify how each space shall be named. If space names or
abbreviations are not included in the above list, the spaces CAN be identified by their function
using recognizable abbreviations to shorten the label's length to a reasonable size. Since ships'
personnel need to quickly orient themselves to shipboard arrangements, compartments may be
identified in general terms such as:
5.1 Purpose
5.3 Subdivisions
Separate compartment numbers are not required for areas within large spaces if
their function is identical to that of the major space.
GTR No. 29
IDENTIFYING MARKINGS
The Main Deck shall always be assigned number 1. The first horizontal
division below the Main deck shall be assigned number 2. The second horizontal division below
the Main deck shall be assigned number 3, etc. Where a compartment extends down to the
tank tops or shell plating, the deck number assigned to the lowest horizontal division shall be
used. The first horizontal division above the Main Deck shall be assigned number 01. The
second horizontal division shall be assigned number 02, etc. The deck number becomes the
first part of the compartment number.
When the centerline of the ship passes through the compartment, the
number 0 shall be assigned to the compartment. Compartments located completely to
starboard of centerline shall be given odd numbers. Those located completely to port of
centerline shall be given even numbers. Where two or more compartments have the same
deck and frame numbers and are entirely starboard or entirely port of centerline, they shall have
consecutively higher odd or even numbers, numbering from the centerline outboard. In this
case, the first compartment outboard of the centerline to starboard shall be 1, the second
compartment 3, etc. Similarly, the first compartment outboard of the centerline to port shall be
2, the second 4, etc. Cases may arise in which the centerline of the ship passes through more
than one compartment, all of which have the same forward bulkhead number. In this case, the
compartment with the forward bulkhead through which the ship's centerline passes shall carry
the number 0, and the others shall carry the numbers 01, 02, 03, etc. These numbers
indicating relation to the centerline shall become the third part of the compartment number.
GTR No. 29
IDENTIFYING MARKINGS
5.4.4 Example
3-75-4
6.1 General
6.1.1 Items including but not limited to furniture, fans, motors, rooms, doors,
hatches, manholes, and warning lights shall have labels, notices, warning signs, and other
identifying markings. Identifying markings shall be:
•= Plastic, or
•= Engraved on metal.
6.1.2 Plastic label plates and instruction plates shall be constructed of laminated
phenolic having a black exterior and a white center. Engraving shall be a 90 degree maximum
included angle of sufficient depth to expose the white center.
6.1.3 Label plates shall be attached with stainless steel screws or approved
adhesives. Aluminum plates shall be insulated to prevent contact with dissimilar materials.
6.2.1 Staterooms shall have labels affixed on the doorframe centered above the
GTR No. 29
IDENTIFYING MARKINGS
door or on the bulkhead on the exterior knob side of each stateroom door 1.6 meters (5.25 ft)
above the deck. They shall be 50 mm (2 in) high and 3.2 mm (0.125 in) maximum thickness.
The stateroom labels shall not be attached to the door.
6.2.2 Officer and crew staterooms shall have label plates according to section 6.3,
designating room occupancy ratings on the first line and the compartment number on the
second line.
6.3.1 Spaces not required to be labeled elsewhere in this GTR shall have
identification plates at least 25 mm (1 in) wide. In general, letters shall be 13 mm (0.5 in) high.
If plates are brass, they shall be 1.3 mm (0.05 in) thick, the characters shall be engraved 0.5
mm (0.02 in) deep and filled with black engraver wax. If designating flammable material
storage, the wax shall be red.
6.3.2 The inscription on the identification plate shall give the compartment name
on the first line and the compartment number on the second line. For example:
Deck Stores
4-14-2
Portable furniture shall have small embossed metal or plastic plates secured in an
inconspicuous place or adhesive barcoded identification tags marked with deck and space in
which it belongs.
6.5.1 Special purpose doors, such as watertight doors, fire doors in main vertical
zone bulkheads, or stairway enclosures (except from individual rooms, such as staterooms, fan
rooms, lockers), and weather doors required to be closed for chemical, biological, and
radiological (CBR) washdown purposes, shall have an etched label plate marked at the center
on both sides in characters 3 mm (0.5 in) high, designating the type of door and deck, frame,
and location number. If stencils are used, letters and figures shall be at least 25 mm (1 in)
high. For example:
WTD 3-24-2
If the identification number cannot be seen with the door open, marking shall be on the frame or
immediately adjacent to the door. Watertight door remote control stations shall be marked in
GTR No. 29
IDENTIFYING MARKINGS
the same manner, and the direction of operation of the level or wheel to open and close the
door shall be conspicuously marked.
6.5.2 If a hatch, scuttle, or manhole cover hinges against a bulkhead, the label
plates shall be located on the bulkhead just above the hinged up position of the cover, so that
the label can be read with the cover in the open or the closed position. If a hatch, scuttle, or
manhole cover does not hinge against a bulkhead (i.e., hinged 180o to open or close), the label
plates shall be fitted on the top and the bottom of the cover, 150 mm (6 in) from the cover's
edge, on the side opposite the hinges. Hatch, deck scuttle, and manhole labels shall indicate
the compartments served by the hatch, scuttle, or manhole. For example:
6.5.3 Scuttles in doors and hatches shall be assigned the same number as the
door or hatch in which they are located. Both sides of the scuttle shall be labeled to name the
compartment to which it provides passage.
6.5.4 Portable hatch covers shall have markings to indicate the deck and hatch to
which they belong and their position. Covers that are interchangeable are not required to have
position markings.
6.5.5 The weather side of the door to decontamination stations shall have a label
with 75 mm (3 in) black letter stenciling "DECONTAMINATION STATION ENTRANCE". The
interior side of the same door shall be stenciled "EXIT TO WEATHER". Interior doors to
decontamination stations shall be painted to match surrounding area, with the stenciled
captions "DECONTAMINATION STATION ENTRANCE/EXIT TO INTERIOR".
GTR No. 29
IDENTIFYING MARKINGS
6.6.1 Label plates for access openings serving a number of compartments shall
indicate compartments served. The name and number of the first compartment shall be highest
on the label, and the compartments entered from the first compartment shall be listed under the
first compartment's label and indented.
6.6.2 The topmost hatch and the highest point of trunk entry through a door shall
have a label with the names and numbers of the compartments for which access is provided.
The hatch or closure labels for closures below these topmost closures shall indicate the closure
number and the name and number of the compartment below.
6.6.3 If there is more than one door or opening from a trunk on one level, the doors
providing access to other compartments on that level or lower levels shall have labels with 6
mm (0.25 in) letters, "TO COMPT" and list compartments entered via that door. The
compartment shall be grouped by levels and shall be separated by double vertical spacing
between groups of compartments on different levels.
6.6.4 Stairwell landing labels shall show the deck level on the first line and list the
compartments served below.
6.6.5 Access panels and openings in joiner work and overheads for access to
components including but not limited to piping cleanout connections, wiring, ducts, vents,
piping, air conditioning controls, filters, heaters, valves, ducting access plates, and other such
items shall have labels clearly identifying the concealed equipment.
TO BOATS
6.7.2 Signs near embarkation deck exits shall be similar to the above, and shall
indicate the boat stations nearest the exit. For example:
TO BOAT STATIONS
Nos. 1, 3, 5
GTR No. 29
IDENTIFYING MARKINGS
6.7.3 Each lifeboat station shall have a sign with 75 mm (3 in) letters located on
the deck beams or suspended athwartship from the overhead at each lifeboat station reading,
"LIFEBOAT STATION NO. 1," 2," 3," etc. If there is insufficient head room or no overhead
structure at a boat station, a sign shall be permanently installed where it shall be readily seen.
6.8.1 At regular intervals frames shall have identifying label plates spaced every 7
meters (24 ft) on weather decks, hangar decks, and in compartments over 7 meters (24 ft) in
fore and aft length.
6.8.2 On weather decks, or decks where there are no overhead beams, frame
number label plates shall be located on bulwarks, superstructure, or other structure.
6.8.3 Frame labels on long stretches of deck without erections (except helicopter
platforms) shall have labels plates 63 mm (2.5 in) high with only frame numbers (i.e. without the
word "frame").
6.9.1 Bulkhead label plates shall be located at the midwidth of the compartment
indicating the type and frame location of the bulkhead. If a compartment or hold is more than
one deck in height, the plates shall be about 1.7 meters (5.5 ft) above the deck. Bulkhead plate
letters shall be 50 mm (2 in) high. Examples are: WT BHD 123 or MVZ BHD 54.
6.9.2 Each major transverse bulkhead shall have a label on the centerline at each
deck and on both sides to indicate its type and frame location.
6.9.3 Watertight (WT) bulkheads shall have labels for the full vertical extent of the
bulkhead including those in the superstructure and where passageways intersect the bulkhead.
6.9.4 Nonwatertight (NWT) bulkheads shall have labels if they extend the full beam
of the ship or if the NWT bulkhead label replaces a frame label.
6.9.5 Bulkhead label plates are not necessary in tanks, voids, or on nonstructural,
wire mesh, or similar bulkheads.
GTR No. 29
IDENTIFYING MARKINGS
6.10.1 Ventilating, heating, and air conditioning system labels shall identify their
function and location. Major components shall be identified and labels shall indicate the
compartment numbers of spaces served.
6.10.2 The system number shall be the location number of the fan for mechanical
systems and the location number of the weather opening for natural systems.
6.10.3 The function of each system shall be identified by prefixing the system
number with the word SUPPLY, EXHAUST, or RECIRCULATING. Natural exhaust or supply
systems shall be identified as NAT. EXHAUST or NAT. SUPPLY. Air conditioned spaces do
not require additional labeling, but the letters AC may prefix the system name. On small labels,
the letters S or E may be used for SUPPLY or EXHAUST.
6.10.4 Fans shall have label plates located adjacent to or on the fan showing the
system name and number, followed by the words "SERVES COMPT" and the compartment
numbers. Next to this label or on the same label, the system major components shall be
named and location given. These components are:
6.10.5 Components shall have a label plate secured on or next to the component.
Labels for components in system branches serving only a portion of the system compartments
shall list the compartments served by the component and the component name, location, and
system name and number.
6.10.6 Natural ventilation systems shall have the system label posted next to the
weather opening. The label shall contain information similar to that required for mechanical
systems.
6.10.7 Weather openings serving fan rooms, plenum chambers, or exhaust systems
shall be labeled by function, such as INTAKE or DISCHARGE followed by location number. On
the following lines, the compartment (i.e., fan room) and ventilation systems served shall be
listed by name and number. Compartments served by the systems shall not be listed. Where
GTR No. 29
IDENTIFYING MARKINGS
adjacent openings serve the same fan room, only one label is required. Closures for weather
openings shall be marked with the opening number only if necessary for identification.
6.10.9 Ventilation terminals in a space shall have labels showing the system initial
and number. Where several terminals of one system serve one space, only one label placed in
a conspicuous location is needed.
6.10.10 Equipment installed for heating and cooling which is not part of a ducted
system, such as convectors, unit heaters, gravity type cooling coils, etc. shall have labels
naming and locating the equipment.
6.10.11 The following are examples of ventilating, heating, and air conditioning
labeling:
INTAKE 02-77-1
SERVES FAN ROOM 02-73-0
SUPPLY 02-76-1
SUPPLY 02-78-1
CONTROLLER 02-74-2
REMOTE CONT. FC. RM. 02-53-0
PHR 01-90-2
CC 01-89-2
FIRE DAMPER 01-91-2
AC DAMPER 01-75-2
GTR No. 29
IDENTIFYING MARKINGS
PHR 02-95-2
SUPPLY 02-76-2
SERVES 02-65-0
RHR 01-78-1
SUPPLY 02-76-2
SERVES 01-76-1, 01-76-2
f. Label identifying the remote control station and the controller serving
ventilation system SUPPLY 02-76-2:
6.11.1 Piping shall be identified with stenciled lettering, using contrasting stencil
paint to indicate the contents. Lettering shall be 32 mm (1.25 in) high, except on small pipe
sizes (under 50 mm (2 in) diameter) on which lettering shall be reduced proportionally to
present a good appearance. Flow direction shall be indicated by arrows.
6.11.2 Overflows and vent terminals shall have marked labels of engraved brass
plates indicating the tank or space served.
6.11.3 Sounding tube label plates shall be located in an easily readable position on
an adjacent bulkhead for tubes terminating on the deck plates or attached to the self closing
valve.
GTR No. 29
IDENTIFYING MARKINGS
6.12.1 The control cabinets or spaces containing valves or manifolds for the various
fire extinguishing systems shall be distinctly marked in conspicuous red letters at least 50 mm
(2 in) high - "STEAM FIRE APPARATUS," "CARBON DIOXIDE FIRE APPARATUS," "FOAM
FIRE APPARATUS," OR "WATER SPRAY FIRE APPARATUS," as appropriate.
6.12.2 Firemain cut out valves shall be numbered by deck, frame and side on a
metal plate, with 50 mm (2 in) high red letters. Plates shall be located adjacent to valve where
clearly visible from the deck:
FMCOV
3-120-1
6.12.3 Shore connections for firemain system shall have a label plate with 50 mm (2
in) high letters:
6.12.4 The branch line valves of fire extinguishing systems shall have plain and
permanent markings indicating the spaces served.
Each fire hydrant shall be identified in red letters and figures at least 50 mm (2 in)
high "FIRE STATION" followed by the station number. Example:
The number identifies the deck, frame, and location of the Fire Station. Hoses not stowed in
the open or behind glass where they can be readily seen, shall be identified so that they can be
readily seen from a distance.
Valves, closing appliances, and other mechanisms required for damage control
purposes, shall be conspicuously marked with letters at least 25 mm (1 in) high identifying the
control and the direction of operation. Indication shall be provided to show whether the control
is open or closed.
GTR No. 29
IDENTIFYING MARKINGS
The aft end of the ship shall have a propeller warning sign fastened port and
starboard to the deck handrails or bulwark above the propeller or propellers. Signs shall be
wood or plastic. Each sign shall read "DANGER-PROPELLER-KEEP CLEAR" in block letters.
Signs shall have white background with black letters except that the word "DANGER" shall be
red. The minimum area of each sign shall be 1 sq. meter (1 sq. yard) with lettering at least 150
mm (6 in) high.
Manual alarm boxes shall be clearly and permanently marked "IN CASE OF FIRE
BREAK GLASS." Existing boxes not marked with the same or equivalent wording, shall be
labeled on the box or adjacent bulkhead in 13 mm (0.5 in) high letters "IN CASE OF FIRE
BREAK GLASS." Manual alarm boxes shall have red numbers at least 13 mm (0.5 in) high
labeled on the adjacent bulkhead indicating the zone number.
6.17 Fire Detecting and Manual Alarm, Automatic Sprinkler, and Smoke Detecting Alarm
Bells
The fire detecting and manual alarm, automatic sprinkler, and smoke detecting
alarm bells in the engine room shall be labeled with at least 25 mm (1 in) red lettering indicating
"FIRE ALARM," "SPRINKLER ALARM," OR "SMOKE DETECTING ALARM," as appropriate.
Where alarms on the bridge or in the fire control station are part of an easily identifiable alarm
cabinet, the bells shall be identified by at least 25 mm (1 in) red lettering.
Alarms indicating ventilation loss in spaces specially suited for vehicles, shall be
marked with a conspicuous sign in at least 25 mm (1 in) high letters indicating "VENTILATION
FAILURE IN VEHICULAR SPACE."
6.19.1 Supervised patrol clocks or key stations shall be numbered with plates of 25
mm (1 in) high letters. For example: "KEY STA 8, RTA."
GTR No. 29
IDENTIFYING MARKINGS
6.19.2 Lockers or spaces containing equipment for the use of emergency personnel
shall be marked in 50 mm (2 in) high red letters: "DAMAGE CONTROL LOCKER #".
6.19.4 Portable fire extinguishers shall be marked with the stowage location number
at least 13 mm (0.5 in) high. Example: "FE 3-24-2" indicates the fire extinguisher is on the
third deck, port side, at Frame 24. Photoluminescent markers indicating "Fire Extinguisher"
shall be placed by each extinguisher.
6.19.5 Emergency lights shall be marked with a letter "E" at least 13 mm (0.5 in)
high, next to the light.
6.19.6 Firehoses and axes shall be marked with the ship's name in 25 mm (1 in)
high letters.
6.19.8 Magazine van and magazine chest labels shall be 75 mm (3 in) block type
lettering. Letters shall be red or white, whichever provides the better contrast against the
background. On small chests, the label size may be reduced to that consistent with the size of
the chest so that the inscription may be placed entirely on the side or top.
MAGAZINE
KEEP OPEN LIGHTS AND FIRE AWAY
KEEP DOOR CLOSED
MAGAZINE CHEST
KEEP OPEN LIGHTS AND FIRE AWAY
GTR No. 29
IDENTIFYING MARKINGS
d. Magazine vans except portable magazine vans shall bear the additional
statements on each side:
MAGAZINE
WARNING
DO NOT LIFT WITH CONTENTS
6.19.9 Damage control markings not designated in this GTR shall be stenciled in 13
mm (0.5 in) minimum letters and numbers at eye level (1.7 meters (5.5 ft) above the deck).
6.20 Access doors to chemical and scientific laboratories on Oceanographic Vessels shall
be labeled "CHEMICAL LABORATORY," or "SCIENTIFIC LABORATORY," as applicable.
Special systems, fittings, and appliances shall be marked identifying its function,
location, or other special requirement.
6.21.1 Gasoline systems, foam fire extinguishing systems, and elevators shall have
instruction plates with descriptions of valve, system, and appliance function and operation.
Lettering shall be 13 mm (0.5 in) high red letters and figures.
6.21.2 Tank air escapes shall have a label plate identifying the tank by name and its
number. For example:
GTR No. 29
IDENTIFYING MARKINGS
6-110-1
This identifies a vent whose terminus is located at 03-112-1 serving tank number 6-110-1. This
plate shall be located on or next to the vent at each deck level through which it passes.
6.21.3 Refrigerated spaces shall have a label plate located near the breather plugs
where fitted. Label plates shall read in 6.3 mm (0.25 in) letters:
6.21.5 Doors to air conditioned areas from weather, heat producing spaces, and
ventilated spaces, shall have a label plate on the upper halves of both sides of the door and
read:
WARNING
AIR CONDITIONED BOUNDARY
KEEP DOOR CLOSED
6.21.6 The main access to spaces containing escape scuttles that are required to
be unlocked shall have a label plate. The label plate shall read:
Steering stations shall have a label plate with 13 mm (0.5 in) high letters and
suitable arrows on the wheel or device, or in other position to be in the helmsman's line of
vision, indicating the direction the wheel or device must be turned for "right rudder" and for "left
rudder."
Instructions and system schematic drawings shall be posted in the steering room
providing the steps to switch over steering gear power pumps, line up and operate emergency
hand pumps, engage the trick wheel, rig block and tackle, or perform any other normal or
emergency mode of steering gear operation. Instructions shall have letters at least 13 mm (0.5
in) high and identify key valves, clutches, and links required for changeover. Key valves shall
be identified on schematics and identified by label plates on the steering gear equipment.
GTR No. 29
IDENTIFYING MARKINGS
6.24 Life Preservers, Ring Life Buoys, and Other Buoyant Apparatus
Life preservers, ring life buoys, and other buoyant apparatus shall be marked.
6.25 Decals
Decals, due to their poor durability and susceptibility to being painted over, shall not
be used for permanent markings. However, since they are readily renewed, they may be used
for general warning and instruction signs. Examples are:
NO SMOKING
or
WASH HANDS BEFORE LEAVING
Fuel jettison racks shall have labels clearly identifying the releasing mechanism.
Cargo gear, cranes, and lifting apparatus shall have labels clearly identifying the
Safe Working Load and date tested.
6.28 Valves
Valves shall have labels in accordance with Reference 2.1 unless other valve
labeling requirements are stated in this GTR.
Machinery space lifting gear, fixtures, and securements, including but not limited to
permanently installed hoists, trolley systems, machinery lifting fixtures, padeyes, tie down rings,
etc., shall have a CRES label plate attached stating the Safe Working Load and date tested.
GTR No. 29
IDENTIFYING MARKINGS
Bulkhead mounted spares shall have a clearly marked placard affixed adjacent to
the location of the spare part. The placard shall identify the part’s name, NSN, part number,
manufacturer, and the APL and equipment nomenclature.
Exit signs posted along escape routes and at exits shall have photolumeniscent
properties.
Spaces or equipment where eye injury can occur shall have eye hazard warning
signs posted in the space and on or adjacent to the equipment.
All members of the crew shall have a berth card describing emergency duties and a
duty station. The cards shall be index sized cards mounted in an aluminum frame adjacent to
the berth.
7.1 General
Newly installed equipment shall have safety precautions, operating instructions, and
other notices for newly installed equipment and machinery.
7.1.1 Operating instructions shall list the steps for starting, operating, and securing
equipment, a component, or a system. Operating instructions shall include as a minimum
maintenance instructions, lubricating charts, piping and wiring diagrams, and the location of
important switches and controls not mounted on or near the equipment or the equipment's
control point. Detailed preventive maintenance routines shall not be included.
GTR No. 29
IDENTIFYING MARKINGS
7.1.2 Safety precautions shall provide operation and handling guidance for
equipment, components, systems, or material which present a hazard to ship's security or
personnel safety. Safety precautions shall be combined with operating instructions on a single
placard. Some cases shall require individual danger, caution, directional, or informational
signs.
7.1.3 Ship's certificates, officers' licenses, stability letters, other notices required to
be displayed, and miscellaneous interior mounted instructions shall be displayed in CRES or
aluminum frames. Frames shall be glazed with a hinged front and lock, and be compatible with
the surroundings. Glass or Plexiglas face shall be 3 mm (0.125 in) thick and shall be used to
display instructions. If one frame displays more than one document, the frame's construction
shall permit the individual document replacement without affecting the display of others in the
same frame.
7.2 Fabrication
7.2.1 The print shall be clear and simple with proportionally larger print for titles
and paragraph headings. Lettering shall be black, except safety precautions and warning signs
which shall have red headings.
7.2.2 Operating instructions and safety precautions shall be 200 mm (8 in) x 260
mm (10.5 in). Smaller or larger sizes, preferably 200 mm (8 in) x 130 mm (5.25 in) or 400 mm
(16 in) x 260 mm (10.5 in) may be used when suitable for proper display.
7.3 Mounting
GTR No. 29
IDENTIFYING MARKINGS
7.3.1 Direct mounting to bulkheads or other surfaces with stainless steel screws or
adhesives. Aluminum plates shall be insulated to prevent contact with dissimilar materials.
7.3.2 Standard card holders 200 mm (8 in) x 270 mm (10.5 in), or 200 mm (8 in) x
130 mm (5.25 in), or 400 mm (16 in) x 270 mm (10.5 in).
7.3.3 Multiple hinged leaf card holders where it would be impractical to make
separate displays.
7.3.4 Glass faced metal frames for ship's certificates and licenses.
Personnel hazards, such as low structural beams, high hatch coamings, and other
"strike against, stumbling, tripping, and equipment hazards," shall be painted with alternate
bands of Black (Fed Std Color #27038), and Brilliant Yellow (Fed Std Color #13538). Band
stripes shall be from 38 mm to 100 mm (1.5 in to 4 in) wide, depending upon size of the area to
be painted (small areas shall have narrow stripe widths). On interior stairways, Brilliant Yellow
shall be applied on top and bottom risers. Cargo hold ladder handrails shall be painted solid
yellow from the deck up 1.8 meters (6 ft) minimum and from the top down 0.3 meter (1 ft)
minimum. Top and bottom ladder rungs shall be painted solid yellow. Self adhesive vinyl film
backed safety tape may be used.
Work boats, rescue boats, and utility boats shall have markings in accordance with
the following standards:
8.3.1 The ship name shall be plainly marked or painted on each side of the bow in
letters at least 75 mm (3 in) high.
8.3.2 The boats shall be numbered from forward to aft with odd numbers assigned
to boats on the starboard side and even numbers assigned to boats on the port side.
GTR No. 29
IDENTIFYING MARKINGS
Distinctive markings of damage control lockers and the equipment stowed therein is
necessary to identify and avoid misplacement or misuse of equipment. In order that the
identifying paint markings for all damage control lockers and equipment in MSC ships shall be
standardized, the following markings are prescribed:
8.4.1 The inner and outer sides of damage control locker doors shall be painted
international orange (Fed Std Color #12197). The outer side of Damage Control Lockers No. 1,
2, and 3 shall have one, two, or three black stripes, respectively, 25 mm (1 in) wide painted
under the door label, the same length as the label.
8.4.2 Handles or other parts of tools and other equipment stowed in damage
control lockers shall be painted international orange (Fed Std Color #12197) and marked with
one, two, or three black stripes to indicate whether the tools or equipment belong to Damage
Control Locker 1, 2, and 3 respectively. Ships having only one repair locker shall omit the black
stripe on door and equipment.
The ship's official number and net tonnage shall be marked permanently on the
ship's main beam according to U.S. Customs Regulations.
The underwater hull shall have markings and labels in accordance with the standards
listed in the following sections.
Hull markings (including draft marks, oil tight and watertight bulkhead identification,
frame numbers, Plimsoll marks, bulbous bow, and bow thruster markings) shall be reapplied on
repainted or replaced hull steel. If the underwater hull is repainted, hull marking paint shall be
reapplied. Markings shall be painted black above the upper limit of the boottopping and white
below. Hull markings shall be outlined by a weld bead.
When the underwater hull around the Plimsoll mark is repainted, the Plimsoll mark
GTR No. 29
IDENTIFYING MARKINGS
shall be repainted. Plimsoll marks shall be painted white. Plimsoll marks shall not be changed
unless a new Load Line Certificate is issued by the American Bureau of Shipping.
New hull markings shall be outlined with weld beads and shall be Black (Fed Std
Color #27038) unless otherwise indicated.
On ships longer than 61 m (200 ft), except Naval Fleet Auxiliary Ships, the
ship's name shall appear on both the bow and stern in lettering 380 mm (15 in) and 48 mm
(1.875 in) nominal thickness. Above the name shall be captioned "US NAVAL SHIP" in letters
254 mm (10 in) high and 32 mm (1.25 in) thick. At the bow, this caption shall be spaced 150
mm (6 in) above the ship's name. At the stern, this caption shall be spaced 600 mm (2 ft)
above the name.
Naval Fleet Auxiliary Ships longer than 61 m (200 ft) shall have stern
markings identical to those in paragraph 9.3.1 above, but no name or caption on the bow.
Instead, bows shall have Navy hull numbers (white with black shadowing).
Ships shorter than 61 m (200 ft) shall have name or hull number appearing
on both the bow and stern in letters 300 mm (12 in) high and 50 mm (2 in) thick. Above this
shall be the caption "US NAVAL SHIP" in letters 225 mm (9 in) high and 32 mm (1.25 in) thick.
At the bow and stern , this caption shall be spaced 300 mm (12 in) above the ship's name.
Ships shall have draft marks on the port and starboard sides at the bow,
GTR No. 29
IDENTIFYING MARKINGS
amidships, and stern. Numbers shall be Arabic 150 mm (6 in) high and spaced 150 mm (6 in)
vertically). The bottom of the number shall coincide with the draft it represents. These marks
shall extend 0.9 m (3 ft) above the boottopping at the bow and stern, and 2 m (6 ft) above the
boottopping amidships. Numbers above the boottopping shall be black. Numbers within and
below the boottopping shall be an antifoulant of the same type (but contrasting color) as the
underwater hull coating. All marks shall extend in a vertical line perpendicular to the baseline.
Bow marks shall not follow the rake of the stem.
10.1 Electrical equipment shall have labels in accordance with the following paragraphs.
In addition, special precautions or maintenance and operating instructions shall be on a
separate plate attached to the equipment in a visible location. Equipment connected to more
than one electrical power source such as connection boxes, switches, motor controllers, and
similar electric enclosures or units shall be identified with a visible red warning plate.
10.2 Switchboard and distribution panel buses shall be marked in a readily visible location
with their polarity or phase identification. Color coding of installed conductors shall be
consistent. Black, white, and red are reserved for phases A, B, and C respectively and for
conductors 1, 2, and 3 of multiconductor cables. Synthetic tubing marked with the conductor
identification shall be used at conductor ends where colors are not indicated. Terminal blocks
and strips in the ship's interior communications, exterior communications, and ship's navigating
aid systems shall be numbered to comply with the cable color code indicated in Reference 2.2.
Designations and labels shall match designations on drawings. Wire markers shall match the
elementary wiring diagrams, wiring tables, or other MSCREP approved wire numbering
scheme.
Electrical circuits, switchboards, and distribution and control equipment shall have
markings in accordance with the following standards:
GTR No. 29
IDENTIFYING MARKINGS
10.3.1 Switchboards.
GTR No. 29
IDENTIFYING MARKINGS
•= P-404 indicates feeder cable No. 4 for 480 volt power service
•= L-105 indicates feeder cable No. 5 for 120 volt lighting service
panel.
f. Control cabling shall be prefixed with the letter "K", followed by two or
three letters that identify the system suffixed with numerals starting with "1" For example, K-
1DG10 indicates a control circuit (K), diesel generator control circuit (DG), the tenth cable in the
circuit (10).
Installed, modified, and relocated cable shall have stamped aluminum strip
cable tags in the following locations:
10.3.4 Each panel, junction, or distribution box supplying isolated receptacle circuits
shall be inscribed as follows:
CAUTION
DO NOT CONNECT ADDITIONAL FIXTURES
OR RECEPTACLES TO THIS CIRCUIT
11.0 NAMEBOARDS
Ships shall have port and starboard nameboards constructed of varnished teak. Lettering
shall nominally be 300 mm (12 in) high and 48 mm (1.875 in) wide. The letters and border shall
be painted gold using commercial paint.
JUSTIFICATION:
JUSTIFICATION:
REVISION SHEET
CONTENTS
SECTION SHEET
1. INTRODUCTION...........................................................................................................................5
1.1 Summary .............................................................................................................................5
1.2 Changes to MSC Work Item Preparation Guide .................................................................5
3. GENERAL .....................................................................................................................................6
3.1 Introduction ..........................................................................................................................6
3.1.1 Work Item Content .................................................................................................6
3.1.2 Ambiguities .............................................................................................................6
3.2 Figures.................................................................................................................................6
3.3 General Technical Requirement (GTR)/Regulatory Requirements.....................................7
3.4 Writing .................................................................................................................................7
3.5 Regulatory Body Approvals .................................................................................................8
3.6 Guidance Level....................................................................................................................8
3.7 Calculations .........................................................................................................................8
3.8 Salient Features...................................................................................................................8
3.9 Cut Sheets ...........................................................................................................................8
3.10 Other....................................................................................................................................9
3.11 Work Package Amendments and Work Item Modification..................................................9
3.12 Work Item Quality Control...................................................................................................10
3.13 Disclaimer..........................................................................................................................10
4. SPECIFIC GUIDANCE................................................................................................................10
4.1 Header ...............................................................................................................................10
4.2 Footer ................................................................................................................................11
4.3 Work Item Articles .............................................................................................................11
1.0 ABSTRACT ...............................................................................................................11
2.0 REFERENCES/ENCLOSURES ................................................................................12
General......................................................................................................................12
Reference/Enclosure Format ....................................................................................12
References as Interfaces ..........................................................................................13
3.0 ITEM LOCATION/DESCRIPTION.............................................................................13
3.1 Location/Quantity...............................................................................................14
3.1.1 Location ...................................................................................................14
3.1.2 Quantity ...................................................................................................14
3.2 Item Description/Manufacturer's Data...............................................................14
Bill of Materials ..................................................................................................14
Disclaimer for Quantities and Type of Material in Bill of Materials ....................15
Description of Equipment/Systems ...................................................................15
4.0 GOVERNMENT FURNISHED EQUIPMENT/MATERIAL/SERVICES ......................15
Paint as Government Furnished Material (GFM) ......................................................16
5.0 NOTES ......................................................................................................................16
Required Work Item Notes........................................................................................17
Standardized Space Numbering Note .......................................................................17
CONTENTS (Cont.)
SECTION SHEET
1. INTRODUCTION
1.1 Summary. This document provides guidance for the preparation of MSC Work Items. MSC
work items are contractual documents and therefore must be carefully written to avoid errors/conflicts. The
guidance provided includes specifics on the organization, content and format of work items prepared for
MSC. Examples are provided showing a standardized work item format, required tasking statements and
completed work items. Additionally, comments are provided on the approach to writing the technical content,
on usage of standard language and phraseology, and on which articles of a work item are always used and
which are rarely used. The purpose of this document is to standardize the MSC work item format and the
presentation of the technical content and tasking, and to provide an easy-to-use reference document for
those developing MSC work items.
1.2 Changes to MSC Work Item Preparation Guide. It is expected that this document will be dynamic.
Any omissions, discrepancies, or suggestions for improvements to this document shall be forwarded to COMSC N7
using the Feedback Form at the end of this Guide. All feedback will be retained and thoroughly evaluated for
incorporation into subsequent revisions to the Guide. Originators will be advised of action on their proposed change.
2.1 Work Item Copies. There should only be one version (master) of a work item maintained in the
electronic files. Otherwise, it becomes difficult for someone other than the author to identify the correct file.
This single master file must be maintained so it can be easily located if the author is unavailable due to
illness, travel, etc. When changes are made to an item, the existing master should be replaced with the
changed item. There is generally no need to save old versions of work items. If for some reason the old
version must be saved, it should be put in a separate subdirectory named "OLD".
2.2 Saving Work Items. There should be a standard convention for saving work items. The work
items for a particular ship should be saved in an appropriate subdirectory. The file should be given the name
of the ship and the work item number followed by .DOC. For example, Work Item 515 for AFS 6 would be
saved as X:\MSC\WIS\AFS-6\515.DOC. If this work item is revised and the author desires to save the old
version, the old version could be saved as X:\MSC\WIS\AFS-6\AFS6-OLD\515-XXXX.DOC, where XXXX
represents the month and day the item was saved to the old file. The date at the top of the work item must
be updated every time the work item is modified. For multi-ship solicitations, separate files of work items
should be maintained for each ship, even though they are similar or identical. After the work item has been
delivered to MSC, it should be filed in a delivery file and no further changes made unless directed by MSC.
See Section 3.11 for guidance on amendments to work items.
3. GENERAL
3.1 Introduction. Work items are the contractual vehicle for tasking a shipyard to do work. A work
item is an integral part of a contract describing specific work to be accomplished. It is not a stand alone
document. It relies on the other components of the contract to fully state the requirements. These other
parts include, but are not limited to, FARs, CDRLs, GTR, drawings, ABS/USCG/USPHS regs., POA&M,
NAVSEA MSRA, etc. The work items are usually provided in Section J of the contract as an attachment.
The other parts of Section J include the CDRL, TMCR, ILS, and PTD. The GTR is usually invoked by Section
C. Collectively, all items in the contract, including the 000 items, M&R work items, and CIVMOD work items,
must form a consistent, integrated work package which is unambiguous and enforceable.
A work item is used to convey to the Contractor a clear understanding of the work necessary to
achieve a desired result. This will allow the Contractor to accurately bid, plan and execute the work in an
efficient and effective manner. The work item provides "tasking" to the Contractor. The associated drawings
that are developed along with the work item are provided to the Contractor as "guidance".
3.1.1 Work Item Content. A work item provides a contractual tasking statement for
installations, modifications, removals, etc. The work item will generally reference a drawing or a figure. A
work item may state, "Install system 'x' using References 2.1, 2.2, and 2.3 as guidance", where References
2.1, 2.2, and 2.3 are guidance drawings. As much information as possible should be put on drawings. No
additional taskings should be put in the drawing or general notes. When using a drawing to supplement a
work item, make reference to the drawing and include only such additional wording as is required to integrate
the drawing and the work item. Do not attempt to describe in the work item the work defined by the drawing
(or figure). It will not only be redundant but it may lead to errors. All tasking, along with the equipment salient
characteristics, should be included in the work item. Technical description which does not lend itself well to a
drawing should be included in the work item. The work item and its referenced drawings should tell the
shipyard clearly, unambiguously and succinctly what is to be accomplished. All work items in a package for a
specific ship must be consistent in format, wording, and level of detail for similar items.
3.1.2 Ambiguities. Ambiguities must be avoided when writing work items. The most
frequently encountered reason for Contractor claims against the Government are alleged ambiguities in work
items. In general ambiguities are read against the drafter, i.e. the Government. The legal principle called the
"Rule of Ambiguities" was stated by the Court of Claims as follows:
"Where one of the parties to a contract draws the document and uses
therein language which is susceptible to more than one meaning, and
the intention of the parties does not otherwise appear, the meaning will
be given the document which is more favorable to the party who did not
draw it. This rule is especially applicable to Government contracts
where the Contractor has nothing to say as to its provisions."
3.2 Figures. Drawings are critical to most work items and are generally preferred over figures. The
use of drawings ensures that the information is properly stored and easily retrieved for future use. Figures
attached to work items are not assigned numbers, and may not be kept in the central MSC filing system.
Figures are used only when the amount of information to be conveyed is considerably less than the amount
required to fill a drawing. If more than three or four figure sheets are needed to describe the work for an item,
create a new guidance drawing.
Drawings shall be developed in accordance with MSC Standard Drawing 303-7080803; Military
Sealift Command Computer Aided Designed (CAD) Drawing Standard. Figures shall be developd in
AUTOCAD. If a figure is developed for a work item, the figure should be saved to an appropriate sketch file.
When the work item is reviewed, the figure should be converted to a ".PLT" file and inserted into the work
item. This will allow the figure to become a permanent part of the work item and not a separate attachment.
Each work item figure shall have the words "FOR GUIDANCE ONLY" in all caps centered above the figure
and shall contain sufficient legends, notes, symbol lists, etc. to ensure that the figure is clearly understood.
3.3 General Technical Requirement (GTR)/Regulatory Requirements. The GTR sets technical
standards on how various work should be accomplished and is referenced in the contract. The GTR does
not automatically task the Contractor. It must be invoked, or "triggered", by the use of key operative words or
phrases in the work item. Complete understanding of the GTR is critical to successfully and efficiently
develop, review and interpret a work item. All involved in writing and reviewing work items must know what is
in the GTR and what GTR’s apply to each work item; work items must not repeat information stated in the
GTR.
Similarly, the applicable regulatory body requirements must not be repeated in a work item.
Before drafting an item, make sure that the regulatory body requirements which apply are known and avoid
conflicts or duplications in the work item.
•= Incorrect format (per this Guide), spelling (use a spell checker for each work item), grammar,
and punctuation
•= Unfamiliar or inconsistent abbreviations
•= No page numbers or incorrect page numbers (incl. figures in the page count)
•= Inconsistent quantities and units
•= Use of undefined words or phrases (e.g. fabricate and install, new).
Avoid "umbrella" phrases. The use of phrases such as "to suit", "as necessary", "as required",
"as needed", and "as directed by" should not be depended upon to ensure that work will be performed by the
Contractor. These phrases are often the result of a writer not knowing what is needed. The writer cannot
expect Contractors to satisfy requirements which are not clear.
Redundancy is detrimental to clarity. Do not include anything that is not absolutely necessary to
describe the required work. The work item's wording should be as concise as possible without impact on
clarity. Each requirement should stand by itself and should not be repeated in subsequent paragraphs.
In general, a period should be used only after a complete sentence. Phrases or single words are
not to be followed by a period.
Use active voice, e.g. "Perform the work using Reference 2.1 as guidance." Appendix A contains
a listing of active verbs and their MSC definitions for use when tasking work in the work item.
When referring to a specific ship compartment, state the compartment name with first letters
capitalized followed by the compartment number in parentheses, "Sewage Pump Room (4-19-5-E)", for
example. When referring to a space without using an assigned name, state the function (uncapitalized) and
the compartment number without parentheses, i.e. "fuel tank 5-144-0-F".
3.5 Regulatory Body Approvals. At the time of actual installation, all regulatory body approvals are
needed. This is typically the shipyard's responsibility. The work item author's responsibility is to obtain ABS
approval at the guidance level and to have ABS perform USCG consultative review at the guidance level.
This is required before the final item is incorporated into a work package. Work items requiring ABS approval
shall include the term, ABS, at the end of the title (see Section 4.1).
3.6 Guidance Level. Work items are performance oriented; the shipyard determines how to do the
work. Enough guidance is provided by MSC to bring forth any critical information that the shipyard needs to
know. The shipyard is responsible for shipchecking all aspects of the work item. The burden is on the
shipyard to provide a fully designed, approved and functional system. However, the drafter of a work
item/guidance drawing must ensure that the design conceptually shown will work. For that reason, validation
shipchecks by the guidance drawing drafter may be required.
The Contractor is responsible for design and implementation of a fully functional system, for
compliance with all applicable GTRs, for overcoming interferences not shown on the contract guidance
drawings but which would be visible on a reasonable shipcheck or should be anticipated by a competent
shipyard, for overcoming variations between actual ship conditions and those shown on the guidance
drawings to the extent they would be visible on a reasonable shipcheck or should be anticipated and would
amount to necessary implementing detail, and, finally, for omissions of details from the work package that are
necessary to fulfill the intent of the specifications. For the design approach conceptually presented on the
guidance drawings, MSC is responsible for the accuracy of parametric data shown on the guidance drawings
and that the specified equipment and materials satisfy cognizant regulatory body requirements. Parametric
data includes, but is not limited to, flow rates, amperage rates, linear measurements, etc.
3.7 Calculations. All design calculations must be clearly documented and maintained by the
cognizant engineers in design notebooks, along with appropriate notes on the design approach, assumptions
and resolutions of key issues. The calculations shall be submitted to MSC when the work items are
delivered.
3.8 Salient Features. When specifying equipment, MSC cannot sole source to a specific vendor
(absent written justification and approval). Identify the preferred equipment item (Brand Name or Equal) and
list the salient features which will define the minimum requirements should the shipyard proposes another
item meeting "form, fit and function". Say "Install pump and motor, Worthington Model 3LR-9, or equal", and
then list the salient features required such as 250 GPM at 50 ft., bronze body, monel shaft and impeller, and
mechanical seals, for example. State the salient features unambiguously. See Section 4.3, Article 7.0,
Salient Characteristics, for more details on how to list salient features.
3.9 Cut Sheets. For every item of preferred equipment called out in a work item, a "cut sheet" from
an up-to-date version of the manufacturer's equipment catalog shall be copied by the cognizant engineer.
These cut sheets, along with point-of-contact information (including company name, address, telephone
number and name of contact) and lead time information, shall be submitted to MSC when the work items are
delivered. Where a vendor's item is particularly complex or forms a major part of a system (e.g. MSD plant),
the system diagram should be sent to the vendor for review.
3.10 Other. Do not duplicate information on the drawing and in the work item. This can lead to
conflicting information. Get as much information as you can out of the work item and onto the drawing.
Define acceptance criteria. Avoid statements such as "To the satisfaction of the MSCREP", "In
accordance with good marine practice" or "To the maximum extent possible".
For Category B items only, the total quantity required may be included in the work item so that
the Contractor can provide "unit price" bids.
Pipe sizes and power cable sizes shall be shown, or, if no drawings or figures are used, called
out in Article 7.0 of the work item.
Do not tell the shipyard to make "temporary access" or how to remove something. The work item
author's responsibility is to ensure that it can be done. The shipyard is responsible for providing a finished
product.
Do not call out the same item in two places in the work package, e.g. callouts for the same
thermostat by both the HVAC and electrical work items; the shipyard may include the price twice in their bid.
Understand the terms "Install" "Remove", "Replace", “Temporarily Remove”, and "Relocate" as
defined by General Requirements Item No. 001 (see Appendix A).
Use commercial marine standards for requirements, acceptance, materials, etc. whenever
possible. Avoid the use of MIL-SPECS/STDS.
When you have completed a work item, ask yourself the following questions:
3.11 Work Package Amendments and Work Item Modification. After a work item has been
developed, reviewed and "completed" and issued for bids, it sometimes becomes necessary to modify it, e.g.
to incorporate updated information or to reflect changes made to another, but related, portion of the work
package. The work item revisions are highlighted by vertical bars in the right hand margin, placed in way of
the text changes. Every page of the modified work item has an amendment number typed at the bottom to
indicate to which amended work package it belongs. Last, the date on the work item header is changed to
the delivery date of the amended work package. Note that an amended work item only indicates (by the
margin bars) changes from the previous version of the work item. Thus a work item which has been
amended several times will not identify all of the changes made since the original version.
When modifying an existing work item that has been previously submitted to MSC, be sure that
you are working from the same version of the file as the previous submittal to MSC. Verify with the MSC
TPOC that the work item was not subsequently modified internally by MSC. If the item has been previously
issued to a shipyard by MSC for bidding, it is imperative that only approved changes (as directed by the MSC
TPOC) be made to the file of that version issued to the shipyard. If in doubt about the version of an item that
requires change, verify with the TPOC which is the correct version.
3.12 Work Item Quality Control. Sample work item quality control process documentation is
provided. The process should begin when a cognizant engineer begins work on a task or sub-task. Two
forms are recommended for use to document this process: the Technical Documentation Deliverable -
Quality Control Route Sheet, and the Work Item Format and Guidelines Checklist. Sample copies of both
forms are located in Appendix C.
The quality control route sheet and the checklist should be attached to each work item as it is
started and checked off and initialed, as appropriate, as it progresses to completion. The project engineer
and the program manager should sign off on all work items before submittal to MSC, in addition to
draftspersons, designers and engineers, as appropriate. This sign-off process applies to preliminary versions
of work items as well as later versions. Each work item shall be transmitted by letter. Copies of the
completed route sheet, check list and transmittal letter, along with the work item itself, should be maintained
by the LOE Contract Administrator.
3.13 Disclaimer. Each preliminary work item, figure, table and drawing (all pages and sheets) must
be stamped with the disclaimer that it is a preliminary item and not to be used for bidding purposes. This
should be done prior to making copies for distribution. Final deliverable work items, figures, tables and
drawings do not get this stamp.
4. SPECIFIC GUIDANCE
This section provides specific guidance for each of the articles in the standard work item outline.
Appendix D is the MSC Standard Format for Work Items with explanatory notes. Appendix E is a sample
work item containing examples of an enclosure, a table and a figure. The work item is not ment to be
technically correct, but is designed to show various format examples which are used within a work item.
Appendix F is an example of the work item format with format guidance in each section. Use these examples
for help in getting started. The font type for work items is Courier 12 point and work items have one inch
page margins all around. Tab settings for work items are 0.5 in., 1.0 in., 1.38 in., 1.75 in., 2.13 in., and 2.5 in.
Appendix G is an outline, or template, for a work item.
4.1 Header. The header should be as shown in the work item example, Appendix F, or the
sample/template, Appendix G. Header margins are one inch and the font is 12 point Courier bold. All letters
are in caps except the month and the word "Category" which are in both upper and lower case. For the
ship's name and hull designation, use center justification. The formats for the ship name and hull designation
are as follows:
• The SHIP NAME is of the form USNS HAYES, USNS WATERS, etc.
• The (HULL DESIGNATION) is of the form (T-AG 195), (T-AGS 45), etc.
For the remaining header lines, use right justification with a center tab at 3.25 inches and a right tab at the
right margin, or 6.5 inches. Remember to have one blank line at the end of the header. This will ensure at
least one blank line will separate the header from the text of the work item on all pages.
The header SECTION TITLE is taken from the section titles in the MSC Standard Work Package
Index, a copy of which is contained in Appendix H. The index generally follows the SWBS breakdown except
in the areas of HVAC, Drydocking and UNREP Gear. The header SECTION TITLE is the Appendix H title
listed for Section 000, 100, 200, 300, 400, 500, 600, 700, 800, 900, or 1000. For example, the SECTION
TITLE for an item installing a new structural bulkhead would be HULL STRUCTURE. The SECTION TITLE
for an item installing a ventilation supply fan would be HVAC.
The RFP NUMBER is the MSC number for the solicitation and will be provided by the MSC
TPOC. An example of the correct format is "RFP NO. N62387-96-R-3001". If the number is unknown, then
X's can be substituted in preliminary work items.
During the development and review period prior to the Reading Session Review, the header
DATE should be the current date, automatically printed to the work item. This is accomplished by selecting
the Insert/Date and Time function in Microsoft Word and selecting the date format of DAY MONTH, YEAR.
Thus, the work item with the latest date will always be the current version of the work item. After review
comments and changes are incorporated into the work item, the DATE should be changed to reflect the
delivery date of the work package. This date will be provided by the MSC TPOC for each project.
The ITEM NUMBER will be assigned by the MSC TPOC. The first digit is the one-digit level
section number for the work; see Appendix H. For example, the first digit for a Hull Structure item is "1". The
second two digits are consecutive numbers for items on a given program. Always include the first digit. If the
rest of the number is unknown, then "XX" can be substituted for the last two digits for preliminary items.
The CATEGORY is usually "A", which identifies items where the scope of work is well defined
and biddable. CATEGORY "B" items are those for which the scope of work is usually defined on a "per unit"
basis such as steel renewal or pipe replacement. The MSC TPOC will provide project specific guidance if an
item is to be CATEGORY "B".
The names and initials at the top should always be LOE Company Initials/AUTHOR'S LAST
NAME/MSC TPOC'S INITIALS, e.g. JJMA/BEAUBIEN/WFZ.
The TITLE is the title of the task to be performed: INSTALL FIRE PUMP, or REPLACE
BULKHEAD 87. At the end of the title include in parentheses any applicable TRANSALT, BASELINE, or
INSURV Card numbers. If the work being tasked by the work item requires ABS approval and/or inspection,
include in parentheses the term, ABS, at the end of the title.
4.2 Footer. The footer is as shown on the sample/template. The work item number and page
number are centered (center justification) in the footer. Work item footer margins are 0.7 inch.
4.3 Work Item Sections. This section addresses individual article numbers as they appear in the
work item.
• 1.0 ABSTRACT
This article provides a clear, concise description of the work to be done. It must NOT
be written to task the Contractor. For example, "This item describes the installation of a new potable water
system". Do not use a tasking statement such as "Install a new potable water system". Do not give space
names, quantities, or locations. Just describe what the item is accomplishing. One sentence is usually
sufficient.
• 2.0 REFERENCES/ENCLOSURES
MSC is responsible for ensuring that all references are either sent out with the work
package or are otherwise readily available to the Contractors. Therefore, do not list a reference unless you
know that it is available. Do not list the CFR, ABS or other regulatory body rules as references. These are
covered by the contract boiler plate. Note: There may be instances within Article 7.0 where you specifically
cite a regulation. For example, "Install in the Chartroom a Global Positioning System meeting 49 CFR
162.116.".
If the list of reference drawings and their revisions will be provided as a J Attachment to
the RFP, then DO NOT identify the drawing revision when writing out the reference, e.g. do not write "Rev A",
for example. This is to avoid having to check and update all the work item references as drawing revisions
are made.
Do not reference COMSCINSTs with the exception of the GTR. These are normally
internal to MSC and should not be used to place an obligation on the Contractor. You can excerpt from them
and attach as figures, work the excerpts into Article 7.0 of the work item, or create a drawing.
References are numbered starting with 2.1 (or 2.1.1 if enclosures are also used) in the
order that they are cited in Article 7.0 of the work item. Enclosures, if used, are listed separately following the
references and are numbered consecutively starting with "2.2.1". Enclosure titles contain the work item
number followed by a hyphen and the enclosure number (e.g.101-1, 101-2, etc.). For example, if there are
five references and one enclosure for Work Item 111, the title for the enclosure would be "2.2.1 Enclosure
111-1, List of Pertinent Information". Where cited in the work item, refer to the enclosure as, "using
Enclosure 2.2.1 as guidance". Enclosures must be attached to the work item.
The format for listing references when no enclosures are contained in the work item is
as follows:
2.0 REFERENCES
The format for listing both references and enclosures in a work item is as follows:
2.0 REFERENCES/ENCLOSURES
2.1 References
2.2 Enclosures
References as Interfaces. References are also used to flag the interfaces between
the work being tasked in a particular work item and related work being tasked by other work items and their
reference drawings. To ensure that the work items collectively effect a complete job, drawings defining
related work necessary to properly execute the subject removal, modification/relocation, or installation shall
also be listed in Article 2.0 and cited in Article 7.0 in the appropriate removals, modifications/relocations or
installations paragraph. This defines the interfaces between the specific work item and other applicable
work items. For example, a work item installing a new system requiring potable water, waste drains, air
conditioning and electricity would reference drawings showing the existing system removal and new system
installation, as well as the drawings defining the interfaces with related work: potable water system
installation, soil and waste drain installation, HVAC system installation, and the as-converted electrical one-
line diagram.
Drawings can be referenced in more than one work items. For example, an Electrical
One-Line Diagram may be referenced in several work items.
This article must always have two paragraphs, "3.1 Location/Quantity" and "3.2 Item
Description/Manufacturer's Data".
3.1 Location/Quantity. This paragraph must always have two parts, "3.1.1
Location" and "3.1.2 Quantity".
3.1.1 Location.
a. List the general areas where the work will be performed. The primary
purpose is to allow the shipyard to understand the scope of work involved. If work is to be done in a tank or
specific compartment, then it should be identified by name and number; see Section 3.4.
b. If there is only one location, list it directly after the title: "3.1.1
Location: Emergency Diesel Generator Room (2-XXX-X)".
c. If there is more than one location where the work is being performed,
use the term "Various", such as "3.1.1 Locations: Various". If the locations are not shown in the reference
drawing, or there is no reference drawing, the locations must be stated in the appropriate paragraph of
Article 7.0, Statement of Work Required.
Disclaimer for Quantities and Type of Material in Bill of Materials. The bill of
materials is an estimate of the required material for that work item and does not contain such items as
fasteners, consumables, connectors, fittings, etc. Paragraph 3.2.2 shall follow the bill of materials stating the
quantities provided in the bill of materials is an estimate only and that certain consumables have been
omitted. Wording and format for Paragraph 3.2.2 is as follows: (Note: The listing of consumable material
shall be tailored for each specific work item.)
This article is used to list anything to be provided by the Government. If there is nothing
being provided by the Government, the title is followed by "None" placed on the same line after "SERVICES:".
The Contractor generally supplies all equipment, material, services and information except in unusual
circumstances. If the Government is providing equipment, or material, or services, or information, then all the
Paragraphs, 4.1 through 4.4, must be included even if one or more of them are "None".
For example, if the Government is providing a pump as GFE, list it as "One ABC Co.
Feed Pump, Model 3342". Do not list every piece of material such as valves, piping, gages, etc. If such
detail is needed, it should be provided as text within Article 7.0, in a figure or enclosure, or in a referenced
drawing. An example follows:
If there is more than one item for a sub-heading, use 4.1.1, 4.1.2, etc.
mentioned in Article 7.0. Verify the availability and scheduling of the specified services.
4.2.4 Thinner
a. 10 Gallons Amercoat 65
Notes: (1) Thinner is for spray viscosity control only, not for equipment
clean-up.
• 5.0 NOTES
In general, only state here relevant information about the item which does not fit
elsewhere in the work item format. Do not task in the notes. Thus, do not use the term "shall". Do not say
that the item should be worked in conjunction with specific work items. We do not want to tell the shipyards
how to do their job. However, if the tasked work is supported by the work of another work item or if the work
item supports work being tasked in anther work item, then a statement that this work item supports or is
supported by that work item. In this instance use the title of the other work item and not the work item
number. For example, “Structural modifications necessary to support HSL Davit Installation are installed in
accordance with the HSL Sideport Installation Work Item”.
If there is more than one note, use sub-headings: 5.1, 5.2, etc.
Required Work Item Notes. Every work item shall include two notes, numbered 5.1
and 5.2, to provide the specific GTR used in the work item tasking and the specific “000” Work Items
applicable to the work item. These notes are to assist shops and subcontractors in determining all applicable
requirements These required notes with sample GTR and “000” Work Items are as follows.
5.0 NOTES
5.1 The contractor and all subcontractors, regardless of tier must consult the
General Technical Requirements (GTR) to determine applicability to this work item. In
performance of this work item, the contractor and all subcontractors regardless of tier
must comply with the requirements of all applicable GTR’s including but not limited to
GTR’s 1 through 7, 22, 23, 24, 28, and 29.
5.2 The contractor and all subcontractors, regardless of tier are advised to
review other work items under this contract, including but not limited to Work items 009,
010, and 015, to determine their effect on the work required under this work item. Many
of the definitions relating to performance of this work item are found in Work Item 001.
Note, if there are no GTRs numbered 20 or higher which apply to a work item,
Paragraph 5.1 shall read as follows:
5.1 The contractor and all subcontractors regardless of tier shall consult the
General Technical Requirements (GTRs) to determine applicability to this work item. In
performance of this work item, the contractor and all subcontractors regardless of tier
must comply with the requirements of all applicable GTRs including but not limited to
GTRs 1 through 7.
Standardized Space Numbering Note. When the work is tasked in a specific space
(i.e. Crew Living Space, 1-118-1-L) and spaces are being relocated, redesignated, and/or renumbered
throughout the ship, the contractor/sub-contractors/shops need to know if the space name and number for
the tasked work is an existing or new space name and number. This information is provided in a note using
the following standardized wording: “Existing compartment names and numbers are used for the removals
work. New compartment names and numbers are used for the modification and installation work.”. This note
is to be included in the work item only when required.
This article should contain any quality assurance requirements which are beyond the
normal requirements of ABS, the GTR, etc. If there are additional QA requirements, Paragraphs 6.1 through
6.3 must all be included. State material certification requirements in Paragraph 6.1. Specify exceptional
requirements for personnel qualifications (e.g. welder qualifications) or process certifications beyond those
detailed in the GTR in Paragraph 6.2. Paragraph 6.3 is used to specify requirements for conducting/reporting
inspections and tests beyond the GTR and regulatory body requirements.
General. All biddable work must be tasked in Article 7.0. All ten paragraphs at the two
digit level are always included (7.1, 7.2, etc.). These paragraphs are as follows:
•= 7.1 Arrangements/Outfitting
•= 7.2 Structural
•= 7.3 Mechanical/Fluids
•= 7.4 Electrical
•= 7.5 Electronics
•= 7.6 Preparation of Drawings/Documentation
•= 7.7 Inspection/Test
•= 7.8 Painting
•= 7.9 Marking
•= 7.10 Manufacturer’s Representative
It is essential that the paragraphs be technically correct and that all work necessary to
satisfy the Government be described.
Identify known or suspected long lead time CFE/CFM and advise the MSC TPOC.
Tasking Statements. Each tasking paragraph should begin with an active verb such
as "Install", "Remove", "Relocate", etc. There are very specific definitions for these verbs which are provided
in General Requirements Item No. 001. These are included in Appendix A for information. All work item
writers must review, understand, and use these definitions.
When using the term "Remove", DO NOT list ancillary removals such as associated
foundations and cabling. They are taken care of by the MSC definition of "Remove".
If an item is being removed and a new one of similar form, fit, and function is being
installed in its place, use "Replace" rather than "Remove" and "Install". If a new item is “similar” but requires
additional piping, wiring, foundations, etc., then "Remove" and "Install" should be used.
When using "Install", DO NOT list the removal or relocation of any interferences. They
are taken care of by the MSC definition of "Install". If there is a reference drawing, use a tasking statement of
this form: "Install the refrigeration monitoring system using Reference 2.1 as guidance." This is all that needs
to be said. If there is also a power hook-up and a reference drawing has been developed, the tasking
statement should read: "Install the refrigeration monitoring system using References 2.1 and 2.2 as
guidance," where Reference 2.2 is the as-converted electrical one-line diagram. Make sure the required
power interface is shown on the one-line. (See Section 4.3 of this Guide, Work Item Article 2.0, References
as Interfaces for more information on references in the work item.)
Task the shipyard to do the work on the drawings with simple tasking statements. It is
not necessary to tell the shipyard to install each of the components, cabling, support, services, etc. These
elements are all shown on the referenced drawings and/or included in the shipyards requirement to provide a
fully functional installation.
Salient Characteristics. When installing an item of CFE/CFM, always tell the shipyard
what to install, provide the "Brand Name or Equal" for the preferred equipment, and list the salient
characteristics. The make and model number of the preferred equipment must always be followed by the
words "or equal". It is essential to state the salient technical characteristics of the equipment, as discussed in
Section 3.8 of this Guide. The salient characteristics must either be listed in tabular form on the reference
drawing or listed in the work item using bulletized format. The salient characteristics define the performance
and other technical features which a proposed alternative equipment item must possess in order to be judged
"equal" to the preferred make and model. An example of specifying the installation of a piece of equipment
and identifying its salient characteristics in bulletized format follows:
"Install a safe, Mosler Model No. 1234 or equal, in the Master's Stateroom, using
Reference 2.1 as guidance, with the following salient characteristics:
Do not use the phrase "as directed by the MSCREP", it is acceptable to say "The exact
location shall be approved by the MSCREP." Always use the term "MSCREP" when referring to the MSC on-
site staff.
Tables and Figures. Where a paragraph would contain repetitive tasking statements,
turn them into a table or tables. A prime example is the furnishings for staterooms and offices. Another
example is the equipment in shops. Tables may be cited in Article 7.0 of the work item or included in a
drawing. If cited in the work item, the table numbers are based on the work item number. For example,
tables contained in Work Item 101 are identified as Table 101-1, Table 101-2, etc. Depending on the length
of the table, tables are placed in the work item immediately following the tasking statement or at the end of
the work item. Tables at the end of the work item receive consecutive page numbers as part of the work
item. These tables must have the same header data as the body of the work item. The desired table format
is attached; see Appendix I.
Any Figures that have been prepared must also be cited in Article 7.0 and be placed at
the end of the work item. As with tables, figure numbers are based on the work item number, e.g. Figure
201-1, Figure 201-2, etc. Figures receive consecutive page numbers as part of the work item and must
contain the same header information as the body of the work item. The desired figure format is attached; see
Appendix J. Figures must be prepared using AutoCAD and must be imported into the work item file (see
Section 3.2). Figures must contain the notation "FOR GUIDANCE ONLY" in all caps centered above the
figure. Figures must also contain sufficient legends, notes, symbol lists, etc. to ensure that the figure is
clearly understood.
Referencing. Always use the words: "...using Reference 2.1 as guidance" not "... in
accordance with Reference 2.1", or "...as shown on Reference 2.1".
7.2 Structure
Installations
7.2 Structure
Installations
(c) Two tasking paragraphs (removals and relocations) with one or more tasks in a
paragraph:
7.2 Structure
7.2.1 Removals
7.2.2 Relocations
Use bullets or letters to list items in tasking statements within the tasking paragraph.
The number of fire dampers shall be minimized by using heavier gauge sheet metal
ducting where allowed by the regulatory bodies.
Paragraph 7.6 "Preparation of Drawings". There are three types of drawings that
one deals with in work items: Contract Guidance, Working, and Selected Record. These three drawing
types are defined in MSC Standrad Drawing No. 803-7080803.
Contract Guidance Drawings. Contract Guidance Drawings are provided by MSC with
the work items to the bidding shipyards. They are drawings which show the work to be accomplished and are
for guidance only. They disclose the basic technical information and performance requirements necessary
for a Contractor to complete the detailed design required to develop and produce a working drawing.
Working Drawings. Working Drawings are developed by the shipyard so that the
purchasing department can order the proper quantities of material, the regulatory bodies and MSC can
approve the proposed installation, the shipyard shops can install the system, and finally, MSC can be given
an as-built copy for its records. There is no intent for MSC to revise these drawings at a later date to reflect
subsequent modifications to the ship.
The Contractor shall prepare Working Drawings in CAD format, scaled to Size F (.71
meter X 1.01 meter (28 in x 40 in)) in accordance with MSC Standard Drawing 7080803, necessary for
accomplishing the work required by the Work Package. The level of detail (as defined in American Society of
Mechanical Engineers (ASME), Y14.24M, Types and Applications of Engineering Drawings) for working
drawings shall be as follows:
b. Arrangement drawings
d. Assembly drawings.
e. Installation drawings.
g. Layout drawings.
h. Electrical/Electronic diagrams.
The final revision of the working drawings are "as-built" drawings and reflect the
condition of all areas covered by the Work Package upon ship redelivery.
Selected Record Drawings. Selected Record Drawings (SRDs) are drawings which are
ship specific and are periodically updated throughout the life of the ship so that they reflect the current ship
configuration. The primary purpose of SRDs is to provide Masters, Administrative Commanders and
Contract Operators of MSC Force ships an accurate description of the ship as presently configured to permit
safe and efficient operation. SRDs are also used by shore personnel responsible for ship support,
maintenance, and modernizations.
The SRDs typically include the general arrangement drawing with profiles, capacity
plan, docking plan, machinery arrangement, HVAC diagrammatic and equipment list, electrical distribution
one-line diagram, IC block diagram, tank capacity tables, fire control plan, damage control display plan, and
all piping diagrams, as well as other analyses, plans and diagrams.
The MSC requirements for SRDs are stated in COMSCINST 9000.1, "Preparation,
Maintenance and Distribution of Selected Record Plans and Booklets for MSC Ships (USNS)", and MSC
Standard Drawing 803-7079667, "Preparation of Selected Record Drawings (SRDs) for USNS Ships".
Tasking Working Drawings in Paragraph 7.6. Use Paragraph 7.6 to task the shipyard to
produce only those working drawings necessary for MSC project office personnel to ensure that the shipyard
will install a fully functional installation. Do not attempt to list all of the working drawings which the shipyard
might choose to develop.
If more than one drawing is tasked, use the statement, "Prepare working drawings to
accomplish all work required by this item. Drawings as a minimum shall include: ", followed by a list of the
necessary drawings. For example:
It is important to always use the phrase "working drawings" because it invokes the
appropriate CDRL. Without this phrase there is no applicable CDRL.
Do not include Selected Record Drawings (SRDs) in this paragraph unless specifically
directed to do so by the Project Engineer. MSC may need to obtain a shipbuilder-produced drawing which is
an SRD sooner than they will get the SRDs. If so, the drawing must be stated as a work item deliverable in
Paragraph 7.6.
If there are no specific working drawing requirements, follow the title with "None
additional".
If both Inspections and Tests are required, use the following format:
7.7 Inspection/Test
7.7.1 Inspections
a.
b.
7.7.2 Tests
a.
b.
If there are no inspection or testing requirements, follow the title with "None additional".
Paragraph 7.8 "Painting". The standard words for painting are: "Paint all new and
modified surfaces to match surrounding surfaces." This should appear word for word in virtually all work
items.
If there are special requirements for painting, they should be called out here, e.g.
requirements for specialty coating systems such as flame spray, Devcon, etc.
For exterior paint, MSC has a painting contractor who will provide the paint as GFM.
Therefore, an estimate of the required coverage in square feet must be provided to the MSC TPOC who will
get the paint contractor to provide information on the type and quantity of paint he will supply. This paint type
and quantity must be listed as GFM in Article 4.0. Paint for other special applications, such as potable water
and MSD tanks, may also be specified as GFM. When providing paint as GFM, a specific tasking statement
is required and is shown in the example below as Paragraph 7.8.2:
7.8 Painting
7.8.2 Blast to near white and paint all new exterior surfaces with the
following approved paint system, as provided in paragraph 4.2:
If there are no painting requirements, follow the title with "None additional".
Paragraph 7.9 "Marking". Virtually all work items should include the following
standard words for markings: "Install name plates, notices, and markings for all new and modified systems
(or areas)." This statement will also obtain cable tags.
List any additional special label, hazard, and warning plates or markings here.
If there are no marking requirements, follow the title with "None additional".
Always use the term "authorized" when requiring a technical representative but never
for a manufacturer's representative. A manufacturer's representative is authorized by definition since he or
she is an employee of the manufacturer and use of the term "authorized" is redundant. A technical
representative, on the other hand, is independent from the manufacturer and is not an employee of the
manufacturer. Therefore, if the services of a technical representative are required, it is very important that
the "tech rep" be authorized by the manufacturer to represent him in order to ensure the proper qualifications.
If the term "authorized technical representative" is not used, the necessary qualifications for any contractor
furnished (CF) tech rep must be provided.
Sources for CF tech reps must also be provided. Required services must be quantified,
along with the required duration, e.g. pierside testing, sea trials, etc., so that they can be bid. Support for the
installation and testing of a particular system sufficiently quantifies the required support. If the required
services cannot be quantified, estimate the required hours and use words like "Provide 600 hours of service
from an authorized technical representative." State that CF tech rep reports shall be submitted to the
MSCREP.
Put any additional design or special requirements in this article. These requirements
would be above and beyond those invoked for the entire package through the "000" items containing the
general requirements. If there are no special requirements for this article, then the title shall be followed by
"None additional".
MSC DEFINITIONS
1. Administrative Contracting Officer - identifies the MSC Contracting officer at the Contractor's
facility.
2. Article - means a separately numbered part of a work item of the Work Package. Articles in
different items may bear the same number; hence, to identify an article completely, the item of which it is a
part must be specified.
3. As-original - means a condition meeting the original system and manufacturer's design.
4. CFE and CFM - identify Contractor Furnished Equipment and Material and are used
interchangeably.
6. COMSCLANT or COMSCPAC - identifies the Area Commander, Military Sealift Command, Atlantic
or Pacific.
7. Contracting Officer - identifies the Commanding Officer Military Sealift Command, Central
Technical Activity.
8. Contractor - identifies the shipyard holding the prime contract for the work specified in the Work
Package.
9. Delivery. The term "delivery" is the correct contractual term for the point in time when the
Contractor accepts the ship into his custody. The point where the ship is "delivered" is stated in the
Delivery, Care, Redelivery item as it is dependent on steaming, towing, etc.
10. Detach or Disconnect - means to disconnect attachments to the unit to enable the unit to be
moved. Attachment points shall be tagged, identified, blanked, and protected to facilitate reinstallation.
Work items do not necessarily identify interferences, and the Contractor is responsible for the
identification and resolution of interferences affecting a detachment and subsequent movement.
12. General Technical Requirements (GTRs) - defines the standards of performance for work being
performed by Contractors.
13. GFE and GFM - Identify Government Furnished Equipment and Material and are used
interchangeably.
a. When new material or equipment is not specified by type, the material or equipment shall be
identical to the existing. When "install" is used with reference to GFE, all conditions of the above definition
except the requirement to provide the piece of equipment are applicable.
b. Work items do not necessarily identify interferences and the Contractor is responsible for the
identification and resolution of interferences affecting the installation by temporarily removing, reinstalling,
or relocating interferences. The Contractor shall temporarily remove, permanently relocate, alter, and
reroute all interferences, including, but not limited to, ductwork, piping, wireways, fixtures, insulation, joiner
linings, equipment, furniture, etc., to facilitate finished fully operational installations and modifications
covered by the Work Package. In the event that piping, ductwork, equipment, linings, etc. must be
temporarily removed to facilitate installation of new or modified work, the Contractor shall subsequently
reinstall same in an "as original" condition. This includes but is not limited to painting of steel, restoring
floor coverings and joiner work, painting, replacing items and equipment removed for access, plugging
wiring and pipe penetrations, and restoring all other disturbed areas to match the surrounding areas.
Disturbed coatings shall be repaired.
15. Interference - means any objects(s), equipment(s), or component(s) that must be temporarily
removed and reinstalled, relocated, modified, or designed around to facilitate the installation of new or
modified equipment or systems.
16. Labor and Materials - means labor, materials, plant facilities, supervision services, equipment, and
any other resources required to accomplish the specified work.
17. Manifests - are the official shipping document forms originated and signed by the generators,
transporters, and operators of the hazardous waste disposal facility as required by Federal, state, or local
regulations.
19. MSC Representative (MSCREP) - identifies the technical representative of the MSC Contracting
Officer at the contractor's facility.
20. MSCREP approval - indicates only that the general method of construction and detailing as
presented by the Contractor appear to be satisfactory and will not relieve the Contractor of the
responsibility of any error.
22. None additional or None - means that there are no additional requirements beyond those
contained in the GTRs and Work Items 001 to 099. Where specific requirements are set forth in Articles
6.0, 7.0 or 8.0 of a work item, such requirements are in addition to those requirements listed in the GTRs
and Work Items 001 to 099.
23. Or equal - means that components or equipment shall be equivalent in terms of performance (flow
rate, pressure, heat transfer characteristics, etc.), services required (power, cooling water, HVAC, etc.),
compatibility with interrelated systems and arrangements, and supportability over the service life of the
components or equipment. In the case of component or equipment substitution for those components or
equipment noted on the Contract Guidance Drawings or in the Work Package, the Contractor shall submit
a written request delineating the design and performance data on both the specified and substituted piece
of equipment for MSCREP approval and if approved, the Contractor shall take full contractual and
technical responsibility for ensuring installation of components or equipment or both and compatibility with
the interrelated systems.
24. Redelivery. The term "redelivery" means the point in time that the Master/MSCREP accepts the
ship back from the Contractor by signing the DD 250.
25. Refurbish - means to temporarily remove, disassemble, clean, inspect, and submit an as-found
condition report; further, upon approval of the MSCREP, the contractor shall lubricate, reassemble the
unit, equipment or system, set and adjust in accordance with manufacturer's specifications, test the unit,
equipment, or system to demonstrate proper function to the manufacturer's specifications, and submit an
as-released condition report. The reinstalled refurbished unit, equipment, or system shall be fully
operational and complete in all aspects. New screws, bolts, nuts, washers, gaskets, packing, pins, keys,
"o"-rings, and shims shall be used when reassembling and reinstalling the unit, equipment or system.
Additional information concerning the location of equipment refurbishment, special processes to be used
in the refurbishment, and additional parts to be replaced during refurbishment shall be as specified in the
individual work items.
26. Reinstall - means that the Contractor shall provide labor and material to install a piece of
equipment, material, or system after the equipment, material, or system was temporarily removed,
relocated, modified, or refurbished. The requirements of an installation as set forth in paragraphs 14.,
14.a, and 14.b above with regard to completeness, operation, testing, the identification and resolution of
interferences, etc. also apply to a reinstallation.
27. Relocate - means to provide labor and materials to detach the unit, equipment, or system and to
reinstall the same unit, equipment, or system at a new or modified location. The requirements of an
installation as set forth in paragraphs 14, 14.a, and 14.b above with regard to completeness, operation,
testing, the identification and resolution of interferences, etc. also apply to a relocation.
28. Remove or Ripout - means to provide labor and materials to disconnect, detach, and transfer the
unit, equipment, materials, or system in its entirety off the ship as specified in the GTR. Supports, stuffing
tubes, collars, and other appurtenances shall be removed by burning, chipping, or cutting when a Work
Item requires machinery, piping, wiring, ducting, structure, outfitting, joiner, or equipment removal. Areas
effected by removals/ripouts shall be restored as set forth in paragraph 14.b.
a. When the Work Package requires the removal of machinery, piping, wiring, ducting, structure,
outfitting, joiner, or equipment removal, supports, stuffing tubes, collars, or other appurtenances by
burning, chipping, or cutting, stubs, rough spots, and other surface irregularities shall be ground smooth
and flush with adjacent surfaces. Once tasked work in the affected area is complete, the areas affected
by the removal shall be restored to the condition before the removal action. This includes but is not limited
to painting of steel, restoring floor coverings and joiner work, painting, replacing items and equipment
removed for access, plugging wiring and pipe penetrations, and restoring all other disturbed areas to
match the surrounding areas. Disturbed coatings shall be repaired to match the surrounding area.
b. After removing the machinery, piping, wiring, ducting, structure, outfitting, joiner, or equipment
removal, supports, stuffing tubes, collars, or other appurtenances, watertight and firezone boundaries shall
be reestablished. Holes in oil tight, watertight, and gas tight boundaries and structural bulkheads shall be
blanked with flush inserts providing structural integrity and tightness equal to that which they replace.
c. When the electrical wiring requiring removal joins a circuit not being removed (i.e. at a
junction box), the electrical wiring or cable shall be entirely removed to the junction point. All other
attachments including but not limited to fasteners, supports, and brackets shall be entirely removed.
When electric cable is designated for removal, it shall be physically and electrically traced to the power
source and the circuit deenergized before removing the cable. When cable is removed from multiple
cable runs, the remaining cables shall be bound and strapped.
29. Replace or Renew - means to remove the unit, equipment, or systems including interferences, and
to install a new unit, equipment, or system which is either identical to or equal to that which was removed;
the installation shall include but not be limited to any hook-ups, supports, and adapters which are required
to effect a finished fully operational installation complete in all aspects.
30. Restore - means to perform those processes (i.e. weld build-up, chrome plate, machine, grind, lap,
non-destructive test, etc.) which are required to return a component to the manufacturer's specifications
regarding dimensions, tolerances, angles, surface finish, and clearances.
31. Section - means a major part of the Work Package and shall include a group of related work items.
32. Specification - means either a single work item or a complete set of work items.
33. Tag out - means a procedure to both notify personnel that tagged-out equipment, components, or
systems are either isolated or not in a normal operating condition and to prevent injury to personnel,
improper operation, or damage to the tagged-out equipment, components, or systems.
34. Temporary Installation or Temporarily Install - means to provide labor and materials to install the
unit, material, equipment or system to completely provide the function described in the individual Work
Item, and to remove the same unit, material, equipment or system prior to redelivery of vessel or as
required to satisfactorily meet the requirements of the individual Work Item. All of the requirements of an
installation and a removal set forth in paragraphs 14, 14.a, 14.b and 28 above with regard to
completeness, operation, testing, the identification and resolution of interferences, disconnection,
detachment and transfer of the unit, material, equipment or system in its entirety off the ship as specified
in the GTR apply to a temporary installation and subsequent removal.
35. Temporary Removal or Temporarily Remove - mean to provide labor and materials to disconnect
and move the unit, equipment, or system from its initial location, and to reinstall the same unit, equipment,
or system either in the same location or elsewhere on the ship as described in the Work Package. All the
requirements of an installation as set forth in paragraphs 14, 14.a, and 14.b above with regard to
completeness, operation, testing, the identification and resolution of interferences, etc. also apply to a
temporary removal and reinstallation.
36. Work item or item - means a separately numbered part of the Work Package describing a discrete
portion of the work to be accomplished.
37. Work Package - means the entire written portion of the contract including the Master Ship Repair
Agreement, the contract provisions, work items, and the GTRs.
1. ORIGINATOR
2. WORD PROCESSING
3. TECHNICAL EDITOR
4. COG. ENGINEER
5. SR. ENGINEER
6. SUP. ENG.-NAVARCH
8 SUP. ENG.-ELEC/ELEX
9. MANAGER
10. DIRECTOR
(Ship's Name)
(Hull Designation)
1.0 ABSTRACT
1.1 (8)
2.0 REFERENCES/ENCLOSURES
2.1 (9)
(Ship's Name)
(Hull Designation)
1.1 (8)
2.0 REFERENCES
2.1 (9)
(NOTE: When the alternate format is used for repair Work Items, this article is to be written in a
time- phased sequence. The last two items in this article are to be entitled Manufacturer's
Representative and Preparation of Drawings; if neither is required, enter "None".)
NOTES
(1) Section Title from MSC Standard Work Package Index Sections (e.g., HULL STRUCTURE)
(2) x01 to x99 of any section; Obtain the x number from the Standard Work Package Index (e.g.,
HULL STRUCTURE is 100. Pumps are found in Section 500, MACHINERY, AUXILIARY
SYSTEMS of the Index, etc.)
(7) Title of discrete task (e.g., Modify Living Spaces 03 Level, Relocate Entertainment System
(TransAlt T-AO-428), or Repair Main Feed Pump). Indicate, when applicable, TransAlt No., V/R,
CASREP, sponsor request, etc., in the title
(8) Provide a brief overview of what is to be done, identifying the purpose or objective of the work
item. Do not use "intent" in the text.
(9) List the primary drawings, specifications, manuals and other documents necessary for doing the
work (e.g., a. Drawing, T-AO (STD)-570-4840203, "Fueling at Sea Stations - Arr & Dets"). Listed
references must be addressed in the body of the item; do not list any reference which is not cited
elsewhere in the work item; do not repeat herein references which are cited in the references
listed (e.g., the references which are listed on referenced drawing T-AO (STD)-570-4840203,
"Fueling at Sea Stations - Arr & Dets", would not be added to the list of references herein). If
none, enter "None".
(10) a. Identify the location in Vessel where the work will be performed (deck, compartment
number, frame, port or starboard, etc.).
b. Identify the number of units, compartments, extent of system, etc. involved. Having an
established location for the numbers involved will assist many people who need to know the
extent of the work package without having to search for it.
(11) Provide any pertinent data to describe the equipment being worked (e.g., MFR, model, size,
capacity, CID, etc.). If none, enter "None". This section may be used as bill of material.
(12) List equipment, material, and services to be supplied by the Government. If none, enter "None".
(13) Include pertinent explanatory information that does not lend itself to inclusion in the General
Requirements Section. Notes shall not place a work requirement on the Contractor.
(14) Specify requirements for certification of material called out in Article 7.0 (e.g., "Contractor shall
provide written certification that material used in salt water piping system is 70-30 CuNi.").
(15) Specify exceptional requirements for personnel qualifications (e.g., welder's qualifications) which
are beyond those detailed in the General Technical Requirement.
(16) Specify requirements for conducting/reporting inspections and tests; identify and refer to
test/inspection procedures/requirements/acceptance criteria established by regulatory bodies
(e.g., "Tests shall be conducted in accordance with written procedure previously approved by
MSC representative.").
(17) All work to be accomplished under this Work Package item must be addressed within Article 7.0
STATEMENT OF WORK. Other sections of the item contain general requirements, performance
standards, and notes, but no work statements. Articles 6.0, 7.0 and 8.0 contain Contractor
requirements; all other sections contain information and guidance to assist the Contractor, but the
Contractor is not bound by them.
(18) Specify work to be accomplished. A normal logical time sequence within the trade or component
is to be used.
(19) List drawings to be deleted, marked up, updated or new drawings to be prepared.
(20) Specify inspections and tests to be performed, when they are to be performed, who shall be
notified to witness, etc.
(23) Indicate if manufacturer's representative is required, what will be expected from him, who is to pay
for his services, etc.
(24) Since the MSC General Technical Requirements (GTR) are to be invoked in the first work item of
every Work Package, this section is to be used only when a technical requirement is not covered
in the GTR. Do not repeat requirements identified elsewhere in the work item or conditions
addressed in the Master Agreement for Repair and Alteration of Vessels (i.e., firewatch,
cleanliness, paint touch-up).
GENERAL NOTES (the following instructions apply for all Work Package items):
• All eight (8) categories shall be listed for each Work Package item. Where information or
data is not applicable to a particular category, the word "None" shall be entered under that
category.
• Information or data for categories 1.0, 3.1, and 7.0, is mandatory for all Work Package
items.
• The heading, down to and including Item Title, shall be included on each page of the Work
Package item.
• Pages shall be numbered at the bottom center of the page using item number-sheet
number format (e.g., 402-1, 402-2, 402-3, 403-1).
The procedures described above organize the work requirements according to shops or technical
areas and will generally be used when developing MSC Work Package items. When developing
work items for a repair contract, however, the Preparing Activity may select to organize the work
requirements according to a time-phased sequence. The time-phased approach shall not be
used for major alterations or installations. Selection of this option (for repair contracts only) will
result in the following modifications to the procedures outlined above:
These may be incorporated under Article 7.0 of the work item. In this case, "Refer to
Article 7.0" should be entered.
The subsections shall follow the natural order of work to be performed (e.g., 7.1
Disconnect Piping; 7.2 Removal to Shop; 7.3 Inspection; 7.4 Repair; 7.5 Installations; 7.6
Painting; 7.7 Testing). the last two items of Article 7.0 shall be Manufacturer's
Representative and Preparation of Drawings; if the repair contract will not require the
assistance of a manufacturer's representative or the preparation of drawings, "None" shall
be entered under these last two items. Note that the subsections of Article 7.0 are
renumbered when using the time-phased approach for repair.
Section Title
a. ADMINISTRATIVE
c. DOCUMENTATION REQUIREMENTS
1. Manufacturer's Representatives
2. Vendor Drawings
3. Spare Parts
f. TESTING REQUIREMENTS
1. Stability Tests
2. Dock Trials
3. Sea Trials
4. Sponsor Equipment Tests
5. Helicopter Platform Test
Section Title
300 ELECTRICAL
Section Title
1. Lube Oil
2. Diesel Support Systems
3. Turbine Support Systems
4. Operating Fluids
5. Spare Parts
e. Interior Communications
1. Sound-Powered Phone
2. Switchboards for I.C. Systems
3. Telephone Systems
4. Announcing Systems
Section Title
f. Exterior Communications
1. Underwater Systems
2. Visual and Audible Systems
3. Telemetry Systems
4. TTY and Facsimile Systems
5. Security Equipment Systems
g. Sonar Systems
Section Title
a. Hull Fittings
b. Boats, Boat Stowage and Handling (Zodiak, Monark, Whaleboat, but not
Lifeboat)
c. Boats, Boat Handling and Stowage Systems
Section Title
A. Unrep Gear - Hydraulic Pumps and Motors, Winches (Steam Elect. and
Elect/Hydr), Sliding Pad Eyes, Control Stations and Light Boxes
OVERFLOW, VENT AND FUEL OIL TANK REGULATOR VALVE MODS (ABS)
1.0 ABSTRACT
2.0 REFERENCES/ENCLOSURES
2.1 References
2.2 Enclosures
3.1 Location/Quantity
OVERFLOW, VENT AND FUEL OIL TANK REGULATOR VALVE MODS (ABS)
5.0 NOTES
OVERFLOW, VENT AND FUEL OIL TANK REGULATOR VALVE MODS (ABS)
5.3 New compartment names and numbers are used for the
installation and modification work.
7.3 Mechanical/Fluids
7.3.1 Removals
Table 501-1
TANK NUMBER
Port Fuel Oil Settling Tank (6-208-2)
Port Fuel Oil Settling Tank (6-211-2)
Stbd Fuel Oil Settling Tank (6-208-1)
Stbd Fuel Oil Settling Tank (6-211-1)
Fuel Oil Tank (8-227-2)
Fuel Oil Tank (8-227-1)
Fuel Oil Tank (8-246-2)
501-3
OVERFLOW, VENT AND FUEL OIL TANK REGULATOR VALVE MODS (ABS)
7.3.2 Installations
•= Temperature Regulator
•= Thermo sensing unit, with sensing line
•= Size to suit
•= Stainless Steel
• Paddle type
• Single pole double throw
• 316 SS construction
OVERFLOW, VENT AND FUEL OIL TANK REGULATOR VALVE MODS (ABS)
7.4 Electrical
Installations
• Buna N Float
• Normally Open
• SPST Switch
• 316 SS material for wetted parts
501-5
OVERFLOW, VENT AND FUEL OIL TANK REGULATOR VALVE MODS (ABS)
7.7 Inspection/Test
7.8 Painting
7.9 Marking
OVERFLOW, VENT AND FUEL OIL TANK REGULATOR VALVE MODS (ABS)
Figure 501-1
501-7
ENCL 501-1
PAGE 1 of 1
OVERFLOW, VENT AND FUEL OIL TANK REGULATOR VALVE MODS (ABS)
2.0 REFERENCES
--(If the work item has both references and Enclosures, then
use this format:)--
2.0 REFERENCES/ENCLOSURES
2.1 References
2.2 Enclosure
3.1 Location/Quantity
XXX-1
PC No. QTY
Description
X YDescription of material
(Large items, cabling,
piping, and tubing.
Fastners, consummables,
connectors, fittings,
etc., are not included.)
--(Bill of material to be provided on all work items when a
drawing does not accompany tasked worked.)--
XXX-2
5.0 NOTES
--(If there are no notes, the term “None “ is placed here. Use
this section for relevant information which does not have a
home elsewhere. Do not use the word "shall". "Shall" is a
tasking word and belongs in Article 7.0. Do not use "Notes" to
specify a work requirement, but only to provide information.
If there is more than one note, use sub-headings as follows:
5.1, 5.2, etc.)--
XXX-3
7.1 Arrangements/Outfitting
--(Use this format if there are at least two of Removals,
Modifications/Relocations, or Installations. Use only those
sub-headings which have action.)--
7.1.1 Removals
XXX-4
7.1.2 Relocations
--(Use this format when only one action listed for a sub-
heading.)--
Relocate RST using Reference 2.1.2 as
guidance.
7.2 Structural
--(Use this format when only one sub-heading of the three sub-
headings, Removals, Modifications/Relocations, or
Installations, has action, i.e. Removals but no
Modifications/Relocations or Installations.)--
7.3 Mechanical/Fluids
Installations
XXX-5
• Compartment X-XXX-X-X
• Compartment X-XXX-X-X
7.4 Electrical
--Example showing removals, modifications, and installations
with salient characteristics.--
7.4.1 Removals
7.4.2 Modifications
7.4.3 Installations
--(Use bullets or numbers to list items under sub-items as
follows:)--
XXX-6
(2) Controller:
• Disconnect switch
• Appropriate NEMA size starters, non-
reversing, magnetic, 450 VAC
• Local pushbutton operators and
indicator lights as required
7.5 Electronics
7.5.1 Removals
7.5.2 Modifications/Relocations
7.5.3 Installations
7.6.1
7.6.2
XXX-7
7.7 Inspection/Test
--(List the appropriate test as it is titled in the GTR)--
--(If both Inspections and Tests are required, then use this
format)--
7.7.1 Inspections
a.
b.
7.7.2 Tests
a.
b.
7.8 Painting
7.9 Marking
XXX-8
XXX-9
Table XXX-1
TABLE TITLE
Figure XXX-1
JUSTIFICATION:
JUSTIFICATION: