Unit 3 Estimation of Brickwork in Single Storey Buildings Stone Masonry General Specifications of RCC Work
Unit 3 Estimation of Brickwork in Single Storey Buildings Stone Masonry General Specifications of RCC Work
Unit 3 Estimation of Brickwork in Single Storey Buildings Stone Masonry General Specifications of RCC Work
Brickwork in Single
UNIT 3 ESTIMATION OF BRICKWORK IN Storey Buildings
3.1 INTRODUCTION
The oldest man-made building block is the unbaked brick – and, it is still in use
inspite of the increasing use of cement concrete with or without reinforcement.
Bricks and the mortar to be used (foundations, walls, and now almost obsolete
practice of reinforced brickwork in roofs and stairs, etc.) shall be fully specified
(described) while measuring up the work. If any bond is specified (English,
Flemish, etc.) it shall be so stated.
General brickwork includes building in ends of beams, slabs, lintels, sills, trusses,
joints etc.; building in hold fasts etc.; preparing tops of existing walls for further
raising work to be carried out; leaving holes for pipes etc.; bedding wall plates,
lintels, sills, corrugated sheets, etc. in or on walls if not paid for separately; etc.
Footings (of foundations), plain copings (on compound or other exposed walls),
etc. also fall in the general category of brickwork.
Brickwork is generally measured in m3. However, one-brick-thick walls (and of
lesser thickness) shall be measured in m2 stating specifically the thickness of the
item. For a fraction of half brick wall thickness, occurring in architectural
embellishments shall be measured such as :
(a) up to ¼ brick – give actual measurements,
(b) more than ¼ brick – taken as a full half-brick thick.
Deductions in the quantity of brickwork shall be made for lintels, doors,
windows, etc. But, no deductions on additions shall be made for the following
features done in the work : 73
Estimating and (a) a dissimilar material (say, beams, lintels, etc.) measuring up to
Quantity Surveying-I
0.10 m2 in section,
(b) cement concrete blocks used for fixing hold fasts and holding down
bolts,
(c) wall plates, bed plates, bearing of slabs etc., where thickness does not
exceed 10.00 cm, and the bearing does not extend over the full wall
thickness, and
(d) iron fixtures, i.e. wall ties, pipes up to 30 cm dia, and hold fasts for
doors and windows.
Pillars and columns are to be measured in m3, and to be fully described –
rectangular, polygonal; curved (in plan); or any special shape.
All circular brickwork, above 6.0 m radius, shall be included in the general
brickwork. But, all brickwork, circular in plan and radius not exceeding 6.0 m is
measured separately, and shall include all cutting and waste, etc.
At certain places it is a practice to lay the damp proof courses of bricks too – laid
on edge. All such work shall be measured in m2, stating its thickness. Vertical and
horizontal DPC shall be measured separately.
As a common classification, brick masonry (or even stone masonry) shall have
following categories (to be paid for accordingly – as the height form GL
increases, and labour to lift the brick too increases) :
(a) brickwork in foundations (footings, etc.),
(b) brickwork in plinth below GL and above GL, and
(c) brickwork in superstructure – work in each floor measured separately.
Scaffolding for ordinary works is not measured and paid for separately but is
included in the rates for brickwork (BW).
Rounded or splayed sides of walls are considered as rectangular, and those very
dimensions are employed for computing quantities. As for other, such items,
dimensions shall be measured to the nearest 0.01 m (i.e. 0.1 cm) areas shall be
worked up to the nearest 0.01 m2; and the cubic contents shall be worked up to
the nearest 0.01 m3.
For bricks of nominal size (22.9 × 11.4 × 7.6 cm), the half-brick size is taken as
11.4 cm, for bricks of nominal size (25.4 × 12.7 × 7.6 cm), the half-brick size is
12.70 cm; and for model bricks of 20 × 10 × 10 cm, the half-brick size is 10.0 cm.
Hence, for different brick sizes, wall thickness given in table below is taken into
account :
Wall Size as Multiple of Thickness of Brick Wall (cm)
Brick Size For Brick Size
20 × 10 × 10 cm 22.9 × 11.4 × 7.6 cm
One-brick wall 20.0 22.90
1½ - brick wall 30.0 34.30
2-brick wall 40.0 45.70
2½ - brick wall 50.0 57.10
3 - brick wall 60.0 68.60
74
Estimation of
Objectives Brickwork in Single
After studying this unit, you should be able to Storey Buildings
C B
4 3 Centre
Line
12 20 10 11
24 23
16 15
8 7
H G
b1
b2
b3
l1
b4
E F
5 6
13 14
21 22
17 18
9 10
1 2
D A
b4
Superstructure
DPC
d4 Masonry (Plinth)
G L
b3 d3
Footing
Depth of Excavation
b2 d2
Foundation Concrete d1
b1
(b) Section
Figure 3.1 : A Simple Rectangular Trench Plan of a Building
and Section of Wall-cum-Foundation
76
It is obvious that with the decrease in the thickness of walls of a room, (i.e. Estimation of
Brickwork in Single
proceeding up from the first footing towards the superstructure) the length of a Storey Buildings
long wall decreases, whereas the length of a short wall increases in accordance
with the breadth (or, thickness as it is generally designated). At the plinth level,
the length of long wall = the length of the room (wall to wall, i.e. inner dimension
plus twice the wall thickness; and the length of short wall = width of the room
(inner dimension). If the thickness of the walls is different, the dimensions are
reckoned accordingly.
Example 3.1
A 20 cm brick wall (of a 4.8 × 3.30 m hut, having one door opening
1.5 × 2.5 m) has directly a beam built on a 30 cm thick plinth which goes
20 cm below ground level and remaining 50 cm above ground. Under this
plinth there lie two footings – 40 cm, and 60 cm thick (i.e., wide),
respectively, while their respective heights are 10 cm and 20 cm. The LC is
100 cm wide and 20 cm deep.
All this brickwork has been erected on LC 1.0 m thick (i.e., wide) and
20 cm deep.
Draw the cross-section of the wall and the foundation (to an enlarged scale)
and also the trench plan, superimposed with the plan for footings, plinth and
wall.
Calculate the following items of work by Long- and Short-wall method (as
well as by centre line method) :
(a) Earthwork in excavation,
(b) LC in foundation,
(c) Brickwork in first two footings,
(d) Masonry in the plinth,
(e) Masonry in superstructure.
Take the height of the hut form the plinth = 3.5 m.
Solution
[Note : The student shall draw the figures: section and plan as asked for
and check the dimensions therewith as worked out in this solution.]
The following Table presents the quantification of the required items by
Long- and Short-wall procedure :
Quantification of Items
Sl. No. Items No. Dimensions Quantity Remarks
L B H/D
(m) (m) (m) (m3)
1. Earthwork in
excavation
(b) LC in Foundation
Sl. No. L B H Quantity
(m) (m) (m) (m3)
0.20
(or 11.9 × = 3.4 – this mode of calculation being most common
0.70
for reasons given earlier).
(c) Masonry (BW) in Two Footings
Sl. No. L B H Quantity
(m) (m) (m) (m3)
1st footing
2nd footing
Total 2.72 m3
Bearing
Clear Span
of Opening
Lintels over openings (doors, windows, cup boards) may consist of RCC, or
RB work, or wood (as in earlier times), or simple bricks placed in
transverse direction to the bricks of the wall – unit of quantification is m3.
These items are paid for separately, and are to be deducted from the gross
quantity of masonry. In the absence of data about the bearing of lintel (on
either side),
l (the length of the lintel) is calculated as :
l = Clear Span + 2t
where, the value of 2t should, at least, be taken as 12 cm. Thus, the cubic
80 content of the lintel, Q, is given as :
Q = l × t × (Thickness of wall) Estimation of
Brickwork in Single
Similarly, for rectangular openings (doors, windows, cup boards), Storey Buildings
b
In the case of segmental arch openings, with rise, r,
2
Deduction = (b × h × Wall thickness) + ( × b × r × Wall thickness)
3
Segmental Arch
2
where, × l × r is an approximate estimation, but usefully adopted in
3
practice.
For a small semi-circular arch opening,
3
Deductions = [b × h × Wall thickness] + ( × b × r × Wall thickness)
4
where, b = 2r
r = (b/2)
Semi-circular Arch
81
Estimating and Elliptical Arches are Considered as Semi-circular for Purposes of
Quantity Surveying-I
Deductions
However, large arches are dealt with on the basis of rigorous mathematical
formulae.
As pointed out in the general specifications, partition walls (that are not
1
load bearing) that may be 10 cm or 12 cm thick, are designated as -brick
2
walls (or brick on − edge walls). The quantities are calculated in m or,
2
This holds good only if the width (thickness) and depth of concrete is
uniform throughout. For non-uniform dimensions, computation can be
made by parts.
(b) Inside White Washing (or Distempering of Walls and Ceiling)
Its quantity (m2) shall be the same as for inside plastering of walls and
ceiling.
(c) Outside Colour Washing
Its quantity (m2) shall be the same as for outside plastering or
pointing.
(d) Sand (or Cinder) Filling in Plinth
Its quantity (m3) =
Quantity of earth filling in plinth
× Required depth of sand filling 83
Depth of earth filling
Estimating and
Quantity Surveying-I 3.3 GENERAL SPECIFICATIONS FOR
BRICKWORK – WALLS AND ARCHES
Brickwork is designated as 1st, 2nd, or 3rd class brickwork according to the quality
of the bricks and/or mortar used in the construction of this masonry. Thus,
specifying the mortar (say, 1 : 4 cement, sand, etc.) with which the work is built,
is an essential part of its designation.
Before any brickwork is begun to be constructed, soaking of bricks is the first
step. This is of importance in the case of brickwork to be done in cement mortar,
or composite lime mortar (other than C and D categories of lime mortar –
eminently hydraulic lime is taken as class A category of lime; class C lime is
known as fat lime, etc.). Bricks shall be adequately soaked in stacks, before use,
and shall be profusely sprayed with clean water at regular intervals for a period of
not less than six hours. However, in compliance with the strict old theoretical
principles, they shall be immersed for 24 hours in a clean water body (tank, etc.).
Bricks shall be placed in the tank or pit by hand, one at a time, and not thrown or
tipped in. This procedure is meant to fill the pores of the brick so that it does not
absorb the moisture of the mortar and thus allowing it to set properly and gain the
intended strength. Tests have indicated that practically bricks absorb no further
water after 15 minutes to one hour soaking in a pit. Bricks to be used with mud
mortar, need not be soaked. It may be pointed out that kacha bricks built in mud
mortar form very strong wall till it remain dry.
Bricks are laid generally in English bond with if frogs upwards if nothing else is
specified. Half or cut bricks are not to be used except to complete the bond in a
given course, closers is in such situations shall be done to the required size to be
expressly used near the ends of a wall.
Wherever there is exposed brickwork, it is important to use only selected bricks
as specified, because such parts of the work form the face of the work which
demands a neat, decent look (façade).
Each brick shall be set with both bed and vertical joints filled with mortar, and
bricks bedded in and set home (in position) by gentle tapping with the handle of
the trowel or wooden mallet. Simple lipping with mortar at the edges shall not be
permitted. All horizontal joints shall be parallel, and, unless otherwise specified,
truly level. Vertical joints in alternate courses shall come directly over one
another. All brickwork shall be taken up truly plumb and each brick mason (i.e.,
brick layer) shall be provided with a plumb bob and a straight edge.
A layer of mortar shall be spread over the full width covering a suitable length of
the lower course. The inside face of a freshly laid brick shall be buttered with
mortar before its adjacent brick is laid and pressed against it. On the completion
of a course, all vertical joints shall be fully filled from the top with mortar. No
portion of work shall be left (while building up) more than one meter below the
rest of the work.
Thickness of joints shall not exceed 1.0 cm in a brickwork. All the face joints
shall be raked to a minimum depth of 15 mm by the raking tool during the
progress of work, when the mortar is still green – it helps provide a proper key
for the plaster or pointing to be done. Where pointing/plastering is not required to
be done, the joints shall be struck flush and finished at the time of laying. The
face of brickwork must be cleaned on the very day the work is laid – also, all
mortar droppings shall be removed promptly.
84
It is to be emphasized that for any face work, bricks shall be selected for trueness Estimation of
Brickwork in Single
of edges, shape and colour – these shall not be chipped or stained during the Storey Buildings
progress of the work. Moreover, as is understood, bricks shall be laid as to give a
perfectly straight and vertical face to the wall as to be always tested with a
straight edge; and no chipping or rubbing of the faces will be permitted to remedy
any bed laying. Bricks shall be cut or grooved where required for shaping jambs
or fitting chowkats. Corners, where special bricks for the purpose are not
available, shall be made with cut bricks, five being used per corner. Rates can
include labour for this cutting of bricks and making of mitres, splays, etc., except
grooving to receive chowkats.
Holdfasts and similar fixtures shall be built in with the surrounding brickwork in
their correct positions in 1 : 3 cement mortars.
First Class BW
Only headers shall be left out to allow of a putlog (one of the short timbers
that support the flooring of a scaffold) to be inserted, and not more than one
brick shall be left out for each putlog. Under no circumstances shall putlog
holes be made in, or immediately under, or next to the imposts or
skewbacks of arches.
Brickwork laid in lime and/or cement mortar shall be protected during
construction from the effects of the sun, rain, and frost, by appropriate
covering if necessary, and shall be kept moist for a period of ten days. The
work shall be, as per theoretical considerations, left flooded at the end of
each day with 2.5 to 3.00 cam of water.
In buildings where specified (say, hospitals, etc.), cut or specially moulded
bricks shall be used at all angles (formed by the junction of two walls) to
give rounded corners. Similarly, wherever required, cut or moulded bricks
shall be used in joints, arches and projecting corners in order to avoid the
formation of sharp angles from the inside of such buildings.
Bed plates of 1 : 2 : 4 cement concrete (CC), or of stone shall be given
under all beams and joists – for stones 1 : 3 cement mortar (CM) shall be
used. Bed plates must be laid to the correct level (as per drawing/estimate)
packing up, if needed, with tiles or split bricks.
In first class BW, the size of bricks shall be specified. These are made from
good brick earth, free from saline deposits and shall be sand moulded.
These shall be thoroughly burnt without being vitrified; shall be of good
(reddish) colour, and be of regular and uniform shape and size, with sharp
and square rises and parallel faces. First class bricks must be homogeneous
in texture; and must emit a clear ringing sound when struck. These shall be
free from flaws, cracks, chips, stones, nodules of lime or kankar and other
blemishes. A first class brick shall not absorb more than 1/6th of its weight
of water after being soaked for one hour, and shall show no signs of
efflorescence on drying.
Second Class BW
Second class bricks shall be as well burnt as first class, or slightly over
burnt, but not vitrified in any part and must give a clear ringing sound when
struck. In second class bricks, slight irregularities in size, shape, or colour
will be accepted, but in no case if these render the courses irregular or
uneven when laid. Slight chips or flaws can be tolerated; but, must be free
85
Estimating and from lime or kankar nodules. They shall not absorb water more than 1/4th
Quantity Surveying-I
their weight after one hour’s immersion.
Second class brickwork shall differ from first class only in that it shall be
laid out with second class bricks. Specifications laid down for first class
brickwork (as detailed above) shall apply in toto, except that the select
bricks may not be used in face work. However, no cut brickwork shall be
executed with second class bricks.
Third Class BW
Third class bricks need not be so fully burnt (baked) as first class or second
class – however, they must be burnt to a reddish yellow colour throughout.
Any defects in uniformity or shape can be accepted till these blemishes do
not cause difficulty in obtaining uniform courses when laid.
Third class BW shall differ from first class brickwork, in that it shall be laid
with third class bricks. Under-mentioned modifications are applicable to the
specifications meant for first class brickwork :
(a) Brickwork laid in mud-mortar shall be protected during construction
from rain or from uneven drying.
(b) Third class brickwork shall not be laid in 1 : 3 cement mortar.
(c) Joints in third class brickwork shall be 1.25 to 1.30 cm thick : but, in
no case shall exceed 1.60 cm in thickness. The height of four courses
as laid (with four joints) shall not exceed by more than 5.0 cm, the
height of four bricks as piled dry one upon another.
(d) As the depth of courses is different from that in the case of first and
second class brickwork, third class brickwork shall not be used where
it has to bond with the brickwork of superior classes.
(e) No selection of bricks for face work shall be insisted upon.
(f) No cut brickwork shall be executed with third class bricks.
Bricks and Brick Tiles other than Classed Ones
Underburnt (or pilla) bricks shall not be used in the construction of
brickwork except in sundried brickwork. Bricks that are so much overburnt
as have gotten vitrified as distorted are known as jhama bricks, and are of
no use for exact work. However, these are broken up for ballast provided
the vitrified mass has not become porous or spongy in the process of being
overburnt.
Sundried bricks shall be made from the same kind of clay that will produce
good bricks on being properly burnt. These shall be sand moulded and shall
be uniform in size and regular in shape. If after drying, a few bricks (picked
up at random) from a batch break into more than two pieces on being
dropped on an even ground from a height of about 1.30 to 1.50 m, the batch
must be rejected as having beam moulded with too much sand. Batches of
bricks in which cracks appear on drying shall be rejected as having been
moulded with too little sand. Special care shall be taken that the earth used
for making sun-dried bricks is free from efflorescing salts and from all
traces of white ants. All sun-dried bricks shall be thoroughly dried before
86
use; and have to be protected from rain – sun dried brick walls are given a Estimation of
Brickwork in Single
facing of burnt bricks, or given a mud-phaska (mud + cut paddy grass Storey Buildings
leaves, i.e. straw) plaster (or even cement plaster). These walls stand very
well till no moisture goes into this masonry. These are laid in mud mortar.
Unless otherwise specified, two courses, underneath the roof (say, a pitched
roof) battens, and the jambs of doors and windows (to a depth of 23 cm)
shall be built in second class brickwork in mud. All roof beams shall also be
carried on piers of second class BW in mud for the full height of the wall.
Brick tiles (burnt) are used in roofing (over, say, RCC slab) or even
flooring.
Brick Ballast
Brick ballast shall be broken to the specified gauge, from first or second
class bricks or their bats or from dense overburnt bricks. No under-burnt
bricks or bats, nor jhama that has become spongy or porous in the process
of burning, shall be broken up for ballast.
Brick ballast is used as a flooring base (over the filled earth up to plinth
top) over which LC/CC etc. is laid to give the designed floor level and
finish.
Ballast shall be free from surkhi, leaves, straw, earth, sand or any other
foreign matter. To allow for loose stacking (before use, i.e., before
spreading over earth between plinth walls, and ramming to adequate
thickness), all stacks of ballast shall be paid as 30 cm for every 32.50 cm in
height.
Half-brick Wall Masonry
The work shall be done in the same way as other brickwork, except that all
the courses shall be laid with stretchers with staggered vertical joints. In
special cases (like half brick walls for water tanks, and long-length half
brick thick walls, etc.) sometimes reinforcement is provided to render the
work structurally stronger. Generally, two lengths of 6 mm bars are
provided at every third course. Reinforcement shall be clean from rust and
loose flakes – using a wire brush is quite adequate. The reinforcement is
placed quite straight on the mortar laid on the course under consideration.
For full embedment of the reinforcement, first half the quantity of mortar is
laid and then the rod is placed in position which is later covered with the
remaining half the quantity of mortar. This arrangement makes the joint
between the two courses stronger.
Such walls do serve as partition walls for WCs, baths, etc.
Length and height of this wall shall be measured correct to a cm. If it is to
be paid per m2 units, the area shall be calculated up to the line where the
half-brick masonry wall is joined to the main wall of one brick or greater
thickness – the measurements shall be taken for its clear length from the
face of the thicker wall. Reinforcement may be paid separately.
Brickwork in Arches
Arches shall not be commenced until the abutments (supporting structure
wall or joist) are built to their full width up to the level of the skew-backs.
Arch work shall be carried up evenly from both abutments; and as soon as
the arch is complete, the masonry is to be built up evenly on both sides to
the height of the crown so as to load the haunches.
87
Estimating and Before the building of an arch is begun, the abutments must be exactly at
Quantity Surveying-I
the same level and the skew-backs must be in place. Skew-backs shall be
formed of bricks correctly shaped to radiate truly from the centre of
curvature, and shall not be packed up with mortar or chips. Skew-backs are
not to be measured as part of the arch.
Centering shall be strong enough to bear the weight of the arch without
deflection. The surface of the centering shall be correctly struck to the
curvature of the soffit of the arch. Cost of centering is generally included in
the rate for arch work. Centering and shuttering shall also bear the live
loads that are likely to come upon it during its construction. Shuttering shall
be tightened with hard wood wedges or sand boxes to allow these to be
eased without any jerks being transmitted to the arch. The sequence of
easing the shuttering is to be planned before hand. Shuttering shall be struck
(gradual lowering of the centres) within 48 hours of the completion of the
arch but before 24 hours – this shall be done after the spandrel has been
filled in and the arch is loaded. A common schedule of striking the centers
that can be followed is outlined as under :
Specifications for brickwork (as outlined earlier) shall also apply to the
brickwork in arches. Arch work shall comprise masonry for both gauged as
well as plain arches – in gauged arches, cut or moulded bricks shall be
used; and, in plain arches uncut bricks are used. Defects in dressing of
bricks shall not be covered up by any extravagant use of mortar, nor the use
of chips, etc. shall be allowed.
The length of the arch shall be measured as the mean of the extrados and
intrados of the arch correct to a cm. Generally, the thickness of the arch
shall be measured in multiples of half brick. For arches exceeding 6.0 m in
span, extra payment shall be made for additional cost of centering, strutting,
bolting, wedging, easing, striking and its removal.
Corbelling, Copings, Cornices, Strings, etc.
All corbelling, brick copings, cornices, strings, eaves bricks, window sills,
drip courses and chimney stacks shall consist of first class brickwork laid in
lime and/or cement mortar as specified in the design. Vertical joints in each
case shall not exceed 3.0 to 4.0 mm in thickness. Bricks when laid flat in
such courses shall either be altogether without frogs or with frogs at one
end so as not to show, either on top or from below, when the bricks are in
position.
88
Corbelling, commonly, shall be effected by ¼-brick projections for ordinary Estimation of
Brickwork in Single
work and 1/8 × brick projections where great strength is required. Storey Buildings
Corbelling shall be measured by the actual cubic contents, and shall be paid
for at ordinary rates for the class of brickwork executed.
All the cornices shall be in accordance with the drawings, and accurately in
line with straight and parallel faces. All exposed cornices shall be
weathered and rendered on top in 1 : 3 cement mortar, and throated
underneath.
Brick cornices, if intended to be pointed, shall be made with specially
moulded bricks or bricks cut and rubbed so as to give mouldings true to
drawings. The profile shall be checked constantly during construction with
a sheet iron template. Cornices, if required to be palstered, shall have bricks
that are roughtly cut.
Cornices shall be measured and paid for by a linear rate.
For copings, unless otherwise specified, the top courses of all plinths,
parapets, steps, etc. shall be built in brick on edge. Coping shall be
measured by actual cubic contents.
String courses shall be made in bricks laid flat (or on edge) consisting of
one or more courses as required. This work is paid for in cubic contents.
Eaves brick shall be laid flat with a projection of 7.5 cm with a chamfer on
the upper edge. Eaves bricks are generally laid in 1 : 3 cement mortar –
these are paid by a linear rate.
Window sills shall be made of bricks laid on edge on a tile creasing to keep
the joints in line, and will extend to 7.50 cm beyond the opening on either
side. The bricks shall project 7.5 cm from the outer face of the wall.
Window sills are laid in 1 : 3 cement mortar. Sills shall be paid by a linear
rate.
Drip courses, when formed of flat bricks, shall follow the same
specifications and are paid for at the same rate as eaves bricks. Sometimes
these are built in brick on edge.
Bricks on edge are also laid in flooring and small, minor partitions – and are
paid for in m2 measure.
General specifications about buildings that categorise them into classes (1st, 2nd,
3rd; or ‘A’, ‘B’, ‘C’ or ‘D’) also help in evaluating a given properly (this may not
be a very exact evaluation) that is required to be sold/purchased, compensated for
by the insurance agencies/or by the government in case of rioting, etc. It may be
noted that there could be as diverse types of classification as the contents of
specifications that can be framed. UP PWD has developed some important
standard specifications for residential buildings, in order to classify them as :
class ‘A’; class ‘B’; class ‘C’; and class ‘D’ – a summary of this is presented as
under, giving an idea about the different ways in which things can be grouped. It
is an expert eye of a practising engineer that sees through this maze of
words/phrases and recognizes the fact that all the points of view discern the same
thing after all.
Class ‘A’ Building
Its foundation concrete shall have its ballast comprising fully burnt or over
burnt bricks (known as chatka in and around Delhi) of 40 mm size with
91
Estimating and 1 : 6 (cement : sand), or 1 : 2 (white lime : surkhi); in both these mixes the
Quantity Surveying-I
proportion of kanaka (ballast) being 1.5.
Its plinth shall be filled by earth (i.e., below the flooring). DPC shall be
2.00 cm thick with 1 : 2 (cement : coarse sand) mortar having 5% water
proofing compound by weight of cement.
Footing and plinth shall be built in 1st class BW in kankar lime or 1: 6
cement mortar – or it shall have hard burnt brickwork in kankar lime or 1: 6
cement mortar.
Superstructure shall be in 1st class bricks in kankar lime or 1: 6 cement
mortar. Its 12.5 cm walls shall be in 1st class bricks in 1: 3 (cement, coarse
sand) with reinforcement in place if it is self-supporting.
Lintels shall consist of 1 : 2 : 4 RCC, or reinforced 1st class BW, in 1 : 3
(cement : coarse sand ) mortar.
Roofs (both in single or double storey) shall comprise RCC or Jack arches,
or RC hollow tiles, or RB slab. Terracing shall be 11 cm concrete in LM
(kankar lime) or 1 : 2 (whitelime : surkhi) mortar.
All balconies shall be of RCC.
Class ‘A’ buildings shall have granolithic floors in drawing, bed and bath
rooms, while passages and kitchens shall have coloured cement floor – with
WCs having white glazed tiled floor and dado. 2.5 cm CC shall be laid over
7.5 cm LC floor – in all rooms and verandah.
Granolithic 90.0 cm dado shall be provided in bath rooms. In bed, drawing,
and dining rooms there shall be granolithic 25 cm skirting. In kitchen and
pantry there shall be cement dado (1 : 3) 90.0 cm high. And, there shall be
no cement skirting in any room in this class of building.
Rain water pipes of CI or AC pipes shall be provided.
Chowkats (frames) of doors and windows of class ‘A’ buildings shall be of
CP teak wood, while their shutters shall be of CP teak/P and G plyboarding.
Wire gauze doors shall be provided in all outer doors of main rooms,
kitchen and pantry; while for all windows and ventilators wire gauze
shutters shall also be there.
Spar varnish (2 coats) shall be given on all wood work. Plastering of
1 : 1 : 6, cement : whitelime : local sand, shall be applied on all walls
(inside and outside).
Distempering shall be done in all the main rooms up to a height of 3.30 m.
Inside finishing shall comprise three coats of white washing, while outside
finishing shall consist of buff colour washing (or painting as specified).
RCC sun shades shall be given over all doors and windows that are exposed
to rains.
Sanitary items in class ‘A’ buildings shall be provided, such as :
(a) Porcelain bath tub in two bath rooms.
(b) Procelain WC in all WCs (with one Indian type).
92
(c) Wash basins in bath rooms and side, verandah adjacent to Estimation of
Brickwork in Single
dining rooms. Storey Buildings
Door fittings shall be of iron; while no hot water boilers shall be provided.
Fire place; and hot case-cum-shelf shall be provided as in class ‘A’.
Class ‘C’ and ‘D’ Buildings
Foundation concrete, plinth filling, DPC, and footing-cum-plinth shall
follow specifications as for class ‘A’.
Superstructure for class ‘C’ as per class ‘A’, while for class ‘D’ it shall be
as per class ‘B’.
There shall be no 12.5 cm walls at all.
Lintels and roofs (single or double storey) shall be as per class ‘A’.
Balconies for class ‘C’ shall be of RCC, while there are no balconies for
class ‘D’. Terracing for both shall be as per class ‘A’.
In place of rain water pipes, class ‘C’ shall have spouts; and class ‘D’ too
shall have spouts if necessary.
These buildings shall have no granolithic floors, white glazed tiled floor
and dado, or coloured cement floors; nor shall have granolithic 90 cm dado
or granolithic 23 cm skirting. Both the classes shall have 2.5 cm CC over
7.5 cm LC floor as in class ‘A’.
Both shall have cement dado (1 : 3) 90 cm high in kitchen, bath rooms and
WCs. However cement skirting shall be there in the dining rooms of class
‘C’, while in class ‘D’ it shall be provided wherever floors may have to be
washed.
Chowkats of doors and windows shall be of sal wood (as in class ‘B’);
while door and window shutters for class ‘C’ shall comprise sal (or
shisham) with P and G 5-ply panels, and for class ‘D’ it shall be country
wood (battened).
For both classes : wire gauze doors shall be provided in kitchen, and in
window of the kitchen; and ordinary painting (3 coats) shall be given for
wood work.
94
Plastering shall be same as for class ‘A’. There shall be no distempering, Estimation of
Brickwork in Single
chick supports, or curtain pelmets. Storey Buildings
Finishing (outside) shall be as for class ‘A’ and for inside it shall be 3 coats
of white wash.
Plinth protection for class ‘C’ shall be 13 cm of kankar (or brick ballast),
rammed to 7.5 cm, and shall be 90 cm wide : while there will be no plinth
protection for class ‘D’.
RCC sun-shades shall be over all doors and windows that are exposed to
rains. Door fittings shall be of iron.
Rest no sanitary items shall be there in these two classes of buildings.
No hot water boiler, fire place, or hot case-cum-shelf shall be provided.
Servants’ quarters (in all 8 units, 4-units in ground floor + 4 units in first
floor) were proposed to be built (Figure 3.2). The Figure presents the
half-plan (at ground-floor level – plan being symmetrical about the centre
line as shown) of the complex.
The work could not be completed. Only the ground floor (4 units) were in
place, that too without baths, latrines, etc. (to be constructed at the back as
indicated); moreover, no stairs could be built in the well earmarked for the
purpose. The whole ground floor construction (incomplete in itself, though)
was topped with an RCC (1 : 2 : 4) roof slab 15 cm thick. Hard murran
filling was done everywhere.
[Note : Verandah gap as well as stair case gap is 2.3 m high with respect to
DPC top.]
Develop the trench plan of the structure. Also estimate the following
quantities (for 4 units) :
(a) Earthwork in excavation in hard soil.
(b) Hard Murram filling.
(c) Brickwork (BW) first-class in :
(i) plinth (below and above ground level), CM (1 : 6) –
including steps.
(ii) superstructure in CM (1 : 4).
(Note : Partition walls are to be paid cubic-content
wise.)
(d) Stone rubble soling in foundations, including hand packing.
(e) Cement concrete (1 : 4 : 8) in foundations.
95
Estimating and
Quantity Surveying-I
Figure 3.2 : Half Plan of 8-unit Servants Quarters (At Ground Floor) – Example 3.2
96
RCC (1 : 2 : 4) Roof Slab 15 cm Thick Estimation of
Brickwork in Single
Storey Buildings
Brick Masonry
3.50 m
30 cm
30 cm
Hard Murram Filling
35 cm 70 cm
GL
0.64 m 15 cm
50 m
0.66 m
0.84 m 0.85 m
0.30 cm CC
0.5 m (1 : 4 : 8) CC
53 cm 0.5 m Rubble Soling
1.10 m
9.0 m 0.65 m
1.95 m
+ + + + + + + + + + + + + + + + + + + +
2.6 m +
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+ 2.6 m
+ + + + + + + + + + + + + + + + + + + +
+ + + + + + + + + + + + + + + + + + + +
3.25 m
3.25 m
0.75 m
1.1 mm
(all
(all around)
around)
0.65 m 3.9 m
5.0 m 8.5 m
9.0 m
2.6 m
Figure 3.4 : Trench Plan of Servants Quarters – Example 3.2 – Walls Clubbed together
while Estimating Quantities are filled with different Markings (Symbol)
97
Estimating and Bill of Quantities – Example 3.2
Quantity Surveying-I
Sl. No Measurements
No. Description Quantity Total
L B H/D 3
(m) (m) (m) (m )
99
Estimating and (iii) 2 3.7 0.64 0.85 4.03
Quantity Surveying-I
1 6.76 0.64 0.85 3.68
(iv) 4 10.74 0.64 0.85 23.37
(v) 4 3.06 0.64 0.85 6.66
[1.3 + 0.16 = 1.46; and 0.85 –0.30 = 0.55; and 00.5 + 0.1 = 0.60]
[Note: If the rate of payment for this partition wall is as per area, the quantity would be
equal to 1.45 × 3.5 = 5.08 m2.]
100
Estimation of
No. L B H/D Quantity
Brickwork in Single
Deductions Storey Buildings
Masonry Work
h = Rise of Arch = r
t
r
Clean Span
t
Segmental Arch
When a semi-circular arch (subtending an angle of π radians (180o) at the
centre of the corresponding circle) is cut short – Figure 3.6 – on either side
so that the segment ABCD subtends an angle (θ) that is less than 180o, at
the centre, we get a segmental arch. Its span DC is, obviously, less than the
diameter of the parent circle. Therefore, the cubic content of masonry
contained in this segmental arch (which is b units long – perpendicular to
paper) is given by :
⎡ ⎛ 1 ⎞⎤ θ
Q = ⎢ 2π ⎜ t + ⎟ ⎥ × × [t × b] . . . (3.2)
⎣ ⎝ 2 ⎠ ⎦ 360o
⎡ ⎛ 1 ⎞⎤ θ
where, ⎢ 2π ⎜ t + ⎟ ⎥ × × [t × b] gives the mean (central) length (i.e.,
⎣ ⎝ 2 ⎠ ⎦ 360o
along the mean circumferential path) of the arch.
102
Estimation of
Masonry Brickwork in Single
Storey Buildings
E Steel Joist
B
A
l = Span t
D C
F
Arch
r CC Filling
EF = h = Rise of Arch
θ (in Degree)
⎡ l t⎤ θ
and Q = 2π ⎢ + ⎥ × (t × b) . . . (3.4)
⎣ 2 sin (θ / 2) 2 ⎦ 360
Example 3.3
Work out the quantity of masonry work (brick) for the following cases :
(a) A segmental arch of clear span = 2.75 m, and rise of 0.6 m. Take the
thickness of arch ring as 45 cm, and wall thickness = 50 cm.
(b) A semi-circular arch of clear span = 3.0 m; and thickness of arch ring
50 cm; and wall thickness = 50 cm, and
(c) A 70o segmental arch whose clear span (i.e. opening) is 2.5 m. Take
the thickness of the arch ring as 50 cm, and wall thickness as 30 cm. 103
Estimating and Solution
Quantity Surveying-I
(a) Here, with reference to Eq. (3.3), we have :
l = 2.75 m; t = 0.45 m; b = 0.50 m and, h = 0.6 m
⎡ 2 2 ⎤
⎢8 × ⎛ 2.75 + 0.45 ⎞ ⎛ 0.45 ⎞ ⎥
⎜ ⎟ + ⎜ 0.6 + ⎟ − (2.75 + 0.45)
⎢ ⎝ 2 ⎠ ⎝ 2 ⎠ ⎥
∴Q = ⎢ ⎥ × 0.45 × 0.50
⎢ 3 ⎥
⎢ ⎥
⎣ ⎦
⎡ 8 × (2.56 + 0.680) − 3.20 ⎤
=⎢ ⎥ × 0.225
⎢⎣ 3 ⎥⎦
14.4 − 3.2
= × 0.225
3
= 0.84 m3
⎛l t⎞
Q=π⎜ + ⎟×t×b
⎝2 2⎠
⎛ 3 0.5 ⎞
=π ⎜ + ⎟ × 0.5 × 0.5
⎝2 2 ⎠
= 1.37 m3
⎡ 2.5 0.5 ⎤ 70
Q = 2π ⎢ + ⎥ × 0.5 × 0.3
⎢⎣ 2 sin 35o 2 ⎥ 360
⎦
⎡ 2.5 ⎤
or, Q = 2π ⎢ + 0.25⎥ × 0.029
⎣1.147 ⎦
= 2 π [2.43] ×0.029
= 0.443 m3.
Mazdoor 14 Nos
Bhisti 3 Nos
Tools and Plants
(sundries, etc.) LS
Formwork LS
Scaffolding LS
(d) For 10 m3 of First Class Brickwork in Jack Arches in 1 : 3 cement
and coarse sand mortar :
Materials
Bricks 5000 Nos
Cement (0.75 m3) 22.5 bags
Coarse sand 2.25 m3
Labour
Mistri 0.6 Nos
Mason 21 Nos
Beldar 15 Nos
Mazdoor 23 Nos
Bhisti 2 Nos
Tools and plants
(sundries etc.) LS
Centering and shuttering LS
Scaffolding LS
(e) For 10 m3 of Second Class Brickwork in mud mortar in
superstructure :
Materials
Bricks (2nd Class) 5000 Nos
Loamy soil (or any other suitable soil) 4.0 m3
Labour
Mistri 0.3 Nos
Mason 8.0 Nos
Beldar 7.0 Nos
Mazdoor 1.0 Nos
Bhisti 1.0 No
Sundries (Tools and Plants, etc.) LS
Scaffolding LS
(f) For 10 m3 of Third Class Brickwork in superstructure in mud
mortar :
Materials 107
Estimating and Bricks (3rd Class) 5000 Nos
Quantity Surveying-I
Loamy (or other, suitable ) soil 4.0 m3
Labour
Same as for item (a).
Example 3.4
What are the materials and labour component required for the following
items of work :
(a) 10 m3 coursed rubble stone masonry in superstructure in 1 : 6
cement-sand mortar, and
(b) 10 m3of random rubble stone masonry in superstructure in 1 : 6
cement-sand mortar.
Solution
Men and Materials Required Per 10 m3
Sl. Particulars Materials Labour
111
Estimating and No. Stone Cement Sand Mistri Mason Beldar Mazdoor Bhisti
Quantity Surveying-I (Including
Wastage)
(a) Coursed
Rubble Stone
Masonry in 0.6 m3 3.6
superstructure, 12.5 m3 0.5 16 16 8 1.5
= 18 bags m3
in 1 : 6 cement
and sand
mortar
(For complete rate analysis, add LS amount for scaffolding, T and P and sundries)
(b) Random
Rubble Stone
Masonry in 0.7 m3 4.2
12.5 m3 0.5 11 11 11 1.5
superstructure = 21 bags m3
in 1 : 6 cement
sand mortar
(For complete rate analysis, add LS amount for scaffolding, T and P and sundries)
SAQ 1
(a) With reference to the motor garage [Example 2.3 and Figure 2.3],
estimate the following quantities;
(i) First class BW in plinth and foundation, in 1 : 6 cement mortar,
and
(ii) First class BW in lime mortar, in superstructure.
By both centre-line method, and Long and Short-wall method.
Assume the following data :
(i) Window (W) size – 1.2 × 1.0 (height) m
(ii) Almirah (A) size – 1.0 × 1.2 (height) m
(b) Figure 3.7 gives the centre-line plan of a residential quarter for an
overseer working in Public Works Department of a State in India.
Compute the quantities of the following items of work, after
developing the double line plan (above plinth level) of the structure:
(i) Brick Masonry work in superstructure, in 1 : 4 CM.
(ii) RCC (1 : 2 : 4) in roof slab, and lintels. Due to the possibility of
first floor being constructed over the ground floor, there are no
projections of the roof slab over the walls. Roof slabs at 3 m
height go into full wall thickness.
Following specifications are applicable:
(i) Height of main rooms from DPC upwards = 4.0 m.
(ii) Height of verandah, passage, kitchen, store, bath, and
WC = 3.00 m.
(iii) Thickness of walls above the plinth level = 20 cm.
(iv) Sizes
Doors, D – 1 × 2.1 m
Windows, W1 – 2 × 1.5 m (it is a double shutter window)
Windows W2 – 1 ×1.5 m (a single shutter window)
(v) Thickness of RCC roof slab = 15 cm
Thickness of lintels over doors and windows = 10 cm
112 Bearing of lintels on either side = 10 cm
Calculate the above mentioned brick masonry by centre-line as well Estimation of
Brickwork in Single
as Long- and Short-wall methods. Storey Buildings
Also draw (to scale) :
(a) Front elevation,
(b) Side elevation of right and left side, separately,
(c) Back elevation, and
(d) One sectional elevation.
8.8 m
W2 W2 W2
D 1.4 m
8.1 m 3.7 m
7.3 m
D
D D 20 × 20 cm
pillar
Room 1
W1 3.37 × 3.7 m Verandah
3.0 m
W1 D
W2 W2 W2 0.8 m
0.9 m
W1 20 cm
0.8 m
1.2 m
Store 1.3 m WC
1.7 m 1.7 m Bath
D
1.4 m
1.0 m
D
1.9 m
D
Room 2
D Passage
2.8 m
4.2 m 3.5 m
Kitchen
2.3 m
4.10 m
W2
D
8.3 m W1
7.5 m
0.7 m
D 1.2 m
D D
W1 Room 1 Verandah
3.5 × 3.5 m
Pillar
5.1 m 20 × 20 cm
D 3.0 m
9.0 m
W1
113
Estimating and
Quantity Surveying-I 3.9 SUMMARY
Brickwork (masonry) is one of the major items of work in a building –
foundations, superstructure, and arches (wherever incorporated) – and its
quantification calls for a clear headed understanding of plan, elevation, and
sections of a building. Thickness, i.e. width of BW varies from foundation
courses (of different widths, as is generally the case) up to the superstructure
(exposed walls, i.e. above the ground/plinth level).
Centre-line method, as well as Long- and Short-wall methods can be employed to
estimate the quantity of BW – the former method being effective where
uniformity of foundation and wall thickness is prevailing. As explained elsewhere
also, in Long- and Short-wall methods the lengths of long wall keep decreasing,
and while of short walls keep increasing as one proceeds upwards from the
bottom of the excavation trench and the width (thickness) of courses go on
decreasing.
Every kind of brickwork has to be constructed according to the relevant
specifications. Buildings fall into various classes, depending, among other things,
on the class of bricks and the richness of the mortar used.
Stone masonry has its own specifications but its quantity is also expressed in
cubical contents (m3) as in any brickwork. Its length, breadth, and height have to
be measured for computing the contents.
(b) Double-line plan, above the plinth level (say, at window level) is
shown in Figure 3.8; calculations, explaining its various dimensions,
are given below (for the student, to apply his/her mind to) in order the
student correlates the same with the plan layout :
1 7.3 + 0.2 = 7.5 12 1 + 0.2 = 1.2
2 8.8 + 0.2 = 9.0 13 2.1 – 0.2 = 1.9
3 8.1 + 0.2 = 8.3 14 1.4 –0.2 = 1.2
4 0.8 + 0.2 = 1.0 15 3.0 –0.2 = 2.8
115
Estimating and Sl. Description No Measurements Quantity
Quantity Surveying-I No. (m3)
L B H/D
(m) (m) (m)
(1) BW in superstructure in
1 : 4 CM
4-m high walls
Main Room 1
Long Wall 2 3.90 0.20 4.0 6.24
Short wall 2 3.5 0.20 4.0 5.60
Main Room 2
Long Wall 2 4.5 0.20 4.0 7.2
Short Wall 2 3.5 0.20 4.0 5.6
Total of 4-m high walls = 24.64 m3
3-m high walls
(i) Store + Bath
Long Walls (dotted) 2 3.2 0.2 3.0 3.84
Short Walls (plain) 3 1.7 0.2 3.0 3.06
(ii) Kitchen
Short Walls (hatched) 2 2.3 0.2 3.0 2.76
(iii) WC
Long Wall inner (triangles) 1 1.5 0.2 3.0 0.90
Outer (triangles) 1 0.8 0.20 3.0 0.48
Short walls (plain) 2 0.8 0.2 3.0 0.96
(iv) Passage
Outer Wall 1 0.9 0.2 3.0 0.54
(v) Verandah wall 1 1.2 0.2 3.0 0.72
(excepting the portion
considered under Room 2)
(vi) Pillars 2 0.2 0.2 3.0 0.24
Total of 3-m high walls 1350 m3
Grand Total of Item 1 38.14 m3
Deductions
Door openings, D 9 1.0 0.2 2.10 3.78
Window openings, W1 4 2.0 0.2 1.5 2.40
W2 4 1.0 0.2 1.5 1.20
Lintels
D 9 1.2 0.2 0.10 0.22
W1 4 2.2 0.2 0.10 0.18
W2 4 1.2 0.2 0.10 ≈ 0.1
Roof slab going into 4-m
high walls at 3-m height
Room 1 1 3.90 0.2 0.15 0.12
1 3.7 0.2 0.15 0.11
(3.5 + 0.4 = 3.90; 3.5 + 0.2 = 3.7)
Room 2 1 3.90 0.2 0.15 0.12
1 4.3 0.2 0.15 0.13
(4.1 + 0.2 = 4.3)
Total Deductions = 8.36 m3
Net BW in superstructure 38.14
116
(−) 8.36 Estimation of
Brickwork in Single
29.78 m3 Storey Buildings
(2) RCC (1 : 2 : 4) in roof slab
and lintels in
(i) Room 1 1 3.9 3.9 0.15 2.28
Room 2 1 4.5 3.9 0.15 2.63
(ii) Over store, bath,
kitchen, part of 1 5.3 4.6 0.15 3.66
passage, and WC
(2.8 + 0.2 + 0.2 + 1.9 + 0.2 = 5.3 ; Associated passage ⇒ 2.3 + 0.2 + 1.7 + 0.2 +
0.2 = 4.6 ; or, 4.2 + 0.2 + 0.2 = 4.6)
Rest of the passage 1 1.6 0.5 0.15 0.12
(1.2 + 0.2 + 0.2 = 1.6)
Verandah 1 3.2 (= 3 5.3 0.15 2.54
+ 0.2) (=5.1
+
0.2)
Add lintels (as calculated
under item (1))
D 0.22
W1 0.18
W2 0.10
Total RCC(1 : 2 : 4) = 11.73 m3
118